Deck 11: Project Management

ملء الشاشة (f)
exit full mode
سؤال
One PERT/COST assumption is that money is spent at a constant rate over the time taken to complete an activity.
استخدم زر المسافة أو
up arrow
down arrow
لقلب البطاقة.
سؤال
A PERT/CPM network is a graphical display of a project that connects activities.
سؤال
In CPM, crashing an activity that is not on the critical path increases the cost of the project.
سؤال
Before drawing a PERT or CPM network, we must identify all activities and their predecessors.
سؤال
The identification of the project activities and their time, cost, resource requirements, predecessors, and person(s)responsible is called PERT planning.
سؤال
The optimistic time is the greatest amount of time that could be required to complete an activity.
سؤال
PERT is a deterministic analysis tool allowing for precise times of activities within a project.
سؤال
In PERT, the earliest start time for an activity is equal to the latest of the earliest finish times of all of its immediate predecessors.
سؤال
CPM was developed for use in managing projects about which we have good information about activity or task completion times.
سؤال
CPM is a probabilistic analysis of managing a project.
سؤال
The first step in planning and scheduling a project is to develop the work breakdown structure.
سؤال
PERT and CPM are quantitative analysis tools designed to schedule and control large projects.
سؤال
The longest time path through a PERT/CPM network is called the critical path.
سؤال
PERT stands for Probabilistic Evaluation and Review Technique.
سؤال
One of the most significant benefits of PERT is that it forces the project manager to sit down and plan the project in great detail-and thus come to an understanding of relationships between the activities.
سؤال
The three time estimates employed in PERT are optimistic time, average time, and pessimistic time.
سؤال
Given the assumptions in PERT, the probability that a project will be completed in less time than required by the activities on the critical path is approximately 50%.
سؤال
With PERT, we are able to calculate the probability of finishing the project within a specified time.
سؤال
Through the use of PERT/CPM, astute managers can derive flexibility by identifying noncritical activities and replanning, rescheduling, and reallocating resources such as personnel and finances.
سؤال
Given the variability of the activity completion times, the original critical path we identify in our PERT analysis may not always be the actual critical path as the project takes place.
سؤال
Once the crash cost per time period value is negative, no additional crashing should be performed.
سؤال
The critical path of a network is the

A)shortest time path through the network.
B)path with the fewest activities.
C)path with the most activities.
D)longest time path through the network.
سؤال
Gantt charts and PERT diagrams provide the same information, just in different formats.
سؤال
When crashing a project, all critical paths must be shortened by the same amount for activity duration reductions to be cost-effective.
سؤال
Given an activity's optimistic, most likely, and pessimistic time estimates of 4, 6, and 14 days respectively, compute the PERT expected activity time for this activity.

A)8
B)6
C)7
D)9
سؤال
Given an activity's optimistic, most likely, and pessimistic time estimates of 4, 14, and 18 days respectively, compute the PERT expected activity time for this activity.

A)14
B)12
C)11
D)13
سؤال
The value of work completed is computed by multiplying budgeted cost by the percent completion.
سؤال
CPM

A)assumes we do not know ahead of time what activities must be completed.
B)assumes that activity time estimates follow the normal probability distribution.
C)is a deterministic network technique that allows for project crashing.
D)is a network technique that allows three time estimates for each activity in a project.
سؤال
Gantt charts contain information about the time taken by each activity, but not about the sequential dependencies of the activities.
سؤال
The first step in planning and scheduling a project is to develop the

A)employee scheduling plan.
B)PERT/CPM network diagram.
C)critical path.
D)work breakdown structure.
سؤال
The expected time in PERT is

A)a weighted average of the most optimistic time, most pessimistic time, and four times the most likely time.
B)the modal time of a beta distribution.
C)a simple average of the most optimistic, most likely, and most pessimistic times.
D)the square root of the sum of the variances of the activities on the critical path.
سؤال
The activity crash cost is equal to the incremental cost of shortening the project.
سؤال
The activity difference is the actual duration of an activity less the planned duration of that same activity.
سؤال
Given an activity's optimistic, most likely, and pessimistic time estimates of 2, 5, and 14 days respectively, compute the PERT expected activity time for this activity.

A)6
B)7
C)9
D)5
سؤال
Budgets are computed using only ES times.
سؤال
PERT

A)assumes that we do not know ahead of time what activities must be completed.
B)assumes that activity time estimates follow the normal probability distribution.
C)is a network technique that uses three time estimates for each activity in a project.
D)is a deterministic network technique that allows for project crashing.
سؤال
For projects that have a daily fixed cost, it is not possible to reduce the overall duration once the cost of crashing exceeds the daily fixed cost.
سؤال
Slack time in a network is the

A)amount of time that an activity would take assuming very unfavorable conditions.
B)shortest amount of time that could be required to complete the activity.
C)amount of time that you would expect it would take to complete the activity.
D)amount of time that an activity can be delayed without delaying the entire project.
سؤال
Which of the following is not a concept associated with CPM?

A)normal time
B)probability
C)normal cost
D)crash cost
سؤال
In a PERT network, the earliest (activity)start time is the

A)earliest time that an activity can be finished without delaying the entire project.
B)latest time that an activity can be started without delaying the entire project.
C)earliest time that an activity can start without violation of precedence requirements.
D)latest time that an activity can be finished without delaying the entire project.
سؤال
Table 11-1
The following represents a project with known activity times.All times are in weeks.
<strong>Table 11-1 The following represents a project with known activity times.All times are in weeks.   Using the data in Table 11-1, what is the minimum possible time required for completing the project?</strong> A)8 B)14 C)25 D)10 <div style=padding-top: 35px>
Using the data in Table 11-1, what is the minimum possible time required for completing the project?

A)8
B)14
C)25
D)10
سؤال
Given an activity's optimistic, most likely, and pessimistic time estimates of 4, 12, and 18 days respectively, compute the PERT variance for this activity.

A)2.33
B)5.44
C)8.00
D)64.00
سؤال
Given the following small project, the critical path is ________ days. <strong>Given the following small project, the critical path is ________ days.  </strong> A)10 B)14 C)16 D)20 <div style=padding-top: 35px>

A)10
B)14
C)16
D)20
سؤال
Table 11-2
The following represents a project with four activities.All times are in weeks.
<strong>Table 11-2 The following represents a project with four activities.All times are in weeks.   According to Table 11-2, there are four activities in the project.Assume the normal distribution is appropriate to use to determine the probability of finishing by a particular time.If you wished to find the probability of finishing the project in 20 weeks or fewer, it would be necessary to find the variance and then the standard deviation to be used with the normal distribution.What variance would be used?</strong> A)2 B)4 C)8 D)12 <div style=padding-top: 35px>
According to Table 11-2, there are four activities in the project.Assume the normal distribution is appropriate to use to determine the probability of finishing by a particular time.If you wished to find the probability of finishing the project in 20 weeks or fewer, it would be necessary to find the variance and then the standard deviation to be used with the normal distribution.What variance would be used?

A)2
B)4
C)8
D)12
سؤال
Given the following small project, the critical path is ________ days. <strong>Given the following small project, the critical path is ________ days.  </strong> A)4 B)10 C)12 D)22 <div style=padding-top: 35px>

A)4
B)10
C)12
D)22
سؤال
Consider a project that has an expected completion time of 60 weeks and a standard deviation of five weeks.What is the probability that the project is finished in 70 weeks or fewer? (Round to two decimals.)

A)0.98
B)0.48
C)0.50
D)0.02
سؤال
Table 11-3
<strong>Table 11-3   According to Table 11-3, there are five activities in a PERT project.If the normal distribution were used to find the probability of finishing this project in 24 weeks or fewer, what mean and variance would be used?</strong> A)30 and 5.222 B)20 and 5.222 C)30 and 4.222 D)22.667 and 1.111 <div style=padding-top: 35px>
According to Table 11-3, there are five activities in a PERT project.If the normal distribution were used to find the probability of finishing this project in 24 weeks or fewer, what mean and variance would be used?

A)30 and 5.222
B)20 and 5.222
C)30 and 4.222
D)22.667 and 1.111
سؤال
In a PERT network, the latest (activity)start time is the

A)earliest time that an activity can be finished without delaying the entire project.
B)latest time that an activity can be started without delaying the entire project.
C)earliest time that an activity can start without violation of precedence requirements.
D)latest time that an activity can be finished without delaying the entire project.
سؤال
Your company is considering submitting a bid on a major project.You determine that the expected completion time is 100 weeks and the standard deviation is 10 weeks.It is assumed that the normal distribution applies.You wish to set the due date for the project such that there is an 85 percent chance that the project will be finished by this time.What due date should be set?

A)108.0
B)110.4
C)89.6
D)85.0
سؤال
Table 11-3
<strong>Table 11-3   According to Table 11-3, there are five activities in a PERT project.What is the variance of the critical path?</strong> A)5.222 B)4.222 C)1.222 D)1.111 <div style=padding-top: 35px>
According to Table 11-3, there are five activities in a PERT project.What is the variance of the critical path?

A)5.222
B)4.222
C)1.222
D)1.111
سؤال
Table 11-1
The following represents a project with known activity times.All times are in weeks.
<strong>Table 11-1 The following represents a project with known activity times.All times are in weeks.   Using the data in Table 11-1, compute the latest finish time for activity E.</strong> A)4 B)10 C)14 D)25 <div style=padding-top: 35px>
Using the data in Table 11-1, compute the latest finish time for activity E.

A)4
B)10
C)14
D)25
سؤال
Table 11-2
The following represents a project with four activities.All times are in weeks.
<strong>Table 11-2 The following represents a project with four activities.All times are in weeks.   According to Table 11-2, there are four activities in the project.Assume the normal distribution is appropriate to use to determine the probability of finishing by a particular time.What is the probability that the project is finished in 16 weeks or fewer? (Round to two decimals.)</strong> A)0.07 B)0.93 C)0.43 D)0.77 <div style=padding-top: 35px>
According to Table 11-2, there are four activities in the project.Assume the normal distribution is appropriate to use to determine the probability of finishing by a particular time.What is the probability that the project is finished in 16 weeks or fewer? (Round to two decimals.)

A)0.07
B)0.93
C)0.43
D)0.77
سؤال
Table 11-2
The following represents a project with four activities.All times are in weeks.
<strong>Table 11-2 The following represents a project with four activities.All times are in weeks.   According to the data in Table 11-2, what is the minimum expected completion time for the project?</strong> A)18 B)19 C)37 D)11 <div style=padding-top: 35px>
According to the data in Table 11-2, what is the minimum expected completion time for the project?

A)18
B)19
C)37
D)11
سؤال
The critical path of a network is the

A)path with the least variance.
B)path with zero slack.
C)path with the most activities.
D)path with the largest variance.
سؤال
Given an activity's optimistic, most likely, and pessimistic time estimates of 3, 5, and 15 days, respectively, compute the PERT standard deviation for this activity.

A)2
B)4
C)5
D)15
سؤال
Table 11-3
<strong>Table 11-3   According to Table 11-3, there are five activities in a PERT project.Which activities are on the critical path?</strong> A)A-C-E B)B-D C)A-B-C-D D)B-E <div style=padding-top: 35px>
According to Table 11-3, there are five activities in a PERT project.Which activities are on the critical path?

A)A-C-E
B)B-D
C)A-B-C-D
D)B-E
سؤال
Table 11-1
The following represents a project with known activity times.All times are in weeks.
<strong>Table 11-1 The following represents a project with known activity times.All times are in weeks.   According to Table 11-1, compute the slack time for activity D.</strong> A)0 B)5 C)3 D)6 <div style=padding-top: 35px>
According to Table 11-1, compute the slack time for activity D.

A)0
B)5
C)3
D)6
سؤال
Given an activity's optimistic, most likely, and pessimistic time estimates of 2, 10, and 20 days respectively, compute the PERT variance for this activity.

A)3
B)6
C)9
D)18
سؤال
Table 11-2
The following represents a project with four activities.All times are in weeks.
<strong>Table 11-2 The following represents a project with four activities.All times are in weeks.   According to the data in Table 11-2, what is the critical path?</strong> A)A-B B)A-C C)B-D D)A-B-C-D <div style=padding-top: 35px>
According to the data in Table 11-2, what is the critical path?

A)A-B
B)A-C
C)B-D
D)A-B-C-D
سؤال
Table 11-1
The following represents a project with known activity times.All times are in weeks.
<strong>Table 11-1 The following represents a project with known activity times.All times are in weeks.   Using the data in Table 11-1, what is the latest possible time that C may be started without delaying completion of the project?</strong> A)0 B)4 C)8 D)10 <div style=padding-top: 35px>
Using the data in Table 11-1, what is the latest possible time that C may be started without delaying completion of the project?

A)0
B)4
C)8
D)10
سؤال
Given an activity's optimistic, most likely, and pessimistic time estimates of 3, 5, and 13 days respectively, compute the expected time for this activity.

A)3
B)4
C)5
D)6
سؤال
The project described by: <strong>The project described by:   is best represented by which of the following networks?</strong> A)   B)   C)   D)   <div style=padding-top: 35px> is best represented by which of the following networks?

A)
<strong>The project described by:   is best represented by which of the following networks?</strong> A)   B)   C)   D)   <div style=padding-top: 35px>
B)
<strong>The project described by:   is best represented by which of the following networks?</strong> A)   B)   C)   D)   <div style=padding-top: 35px>
C)
<strong>The project described by:   is best represented by which of the following networks?</strong> A)   B)   C)   D)   <div style=padding-top: 35px>
D)
<strong>The project described by:   is best represented by which of the following networks?</strong> A)   B)   C)   D)   <div style=padding-top: 35px>
سؤال
Table 11-4
The following represents a project with known activity times.All times are in weeks.
<strong>Table 11-4 The following represents a project with known activity times.All times are in weeks.   Using the data in Table 11-4, what is the minimum possible time required for completing the project?</strong> A)8 B)12 C)18 D)10 <div style=padding-top: 35px>
Using the data in Table 11-4, what is the minimum possible time required for completing the project?

A)8
B)12
C)18
D)10
سؤال
The project described by <strong>The project described by   has a critical path length of:</strong> A)21 days. B)14 days. C)23 days. D)32 days. <div style=padding-top: 35px> has a critical path length of:

A)21 days.
B)14 days.
C)23 days.
D)32 days.
سؤال
CPM stands for

A)critical path management.
B)critical project management.
C)critical project method.
D)critical path method.
سؤال
The two common techniques for drawing PERT networks are

A)NOA and NRA.
B)AON and AOA.
C)GANTT and NOA.
D)ONA and OAO.
سؤال
Table 11-4
The following represents a project with known activity times.All times are in weeks.
<strong>Table 11-4 The following represents a project with known activity times.All times are in weeks.   Using the data in Table 11-4, what is the latest possible time that C may be started without delaying completion of the project?</strong> A)0 B)4 C)8 D)10 <div style=padding-top: 35px>
Using the data in Table 11-4, what is the latest possible time that C may be started without delaying completion of the project?

A)0
B)4
C)8
D)10
سؤال
Table 11-4
The following represents a project with known activity times.All times are in weeks.
<strong>Table 11-4 The following represents a project with known activity times.All times are in weeks.   Using the data in Table 11-4, determine the latest time activity A can be started without delaying the project completion.</strong> A)4 B)3 C)8 D)6 <div style=padding-top: 35px>
Using the data in Table 11-4, determine the latest time activity A can be started without delaying the project completion.

A)4
B)3
C)8
D)6
سؤال
Your company is considering submitting a bid on a major project.You determine that the expected completion time is 150 weeks and the standard deviation is 10 weeks.It is assumed that the normal distribution applies.You wish to set the due date for the project such that there is a 95 percent chance that the project will be finished by this time.What due date should be set?

A)108.0
B)160.4
C)166.5
D)135.0
سؤال
Consider a project that has an expected completion time of 50 weeks and a standard deviation of 9 weeks.What is the probability that the project is finished in 57 weeks or fewer? (Round to two decimals.)

A)0.68
B)0.78
C)0.22
D)0.32
سؤال
PERT stands for

A)probabilistic evaluation and review technique.
B)program evaluation and review technique.
C)probability of expected run times.
D)program of expected run times.
سؤال
Table 11-4
The following represents a project with known activity times.All times are in weeks.
<strong>Table 11-4 The following represents a project with known activity times.All times are in weeks.   Using the data in Table 11-4, compute the latest finish time for activity E.</strong> A)4 B)10 C)14 D)25 <div style=padding-top: 35px>
Using the data in Table 11-4, compute the latest finish time for activity E.

A)4
B)10
C)14
D)25
سؤال
In PERT, we assume that

A)the times to complete individual activities are known with certainty.
B)all activities are carried out by staff from our own organization.
C)the total cost of a project is independent of the time to complete the project.
D)the total time to complete all activities on the critical path is described by a normal distribution.
سؤال
Given an activity's optimistic, most likely, and pessimistic time estimates of 3, 7, and 11 days respectively, compute the expected time for this activity.

A)5
B)6
C)7
D)12
سؤال
The project described by: <strong>The project described by:   has a critical path of length of</strong> A)15 days. B)20 days. C)17 days. D)18 days. <div style=padding-top: 35px> has a critical path of length of

A)15 days.
B)20 days.
C)17 days.
D)18 days.
سؤال
Table 11-4
The following represents a project with known activity times.All times are in weeks.
<strong>Table 11-4 The following represents a project with known activity times.All times are in weeks.   Using the data in Table 11-4, determine the latest time activity A can be finished and not delay any activity?</strong> A)4 B)0 C)8 D)5 <div style=padding-top: 35px>
Using the data in Table 11-4, determine the latest time activity A can be finished and not delay any activity?

A)4
B)0
C)8
D)5
سؤال
In PERT analysis, the probability of the optimistic time occurring should be on the order of

A)1/3.
B)1/6.
C)1/10.
D)1/100.
سؤال
Given an activity's optimistic, most likely, and pessimistic time estimates of 1, 9, and 23 days respectively, compute the PERT expected activity time for this activity.

A)10
B)12
C)9
D)11
سؤال
Given an activity's optimistic, most likely, and pessimistic time estimates of 3, 6, and 9 days respectively, compute the PERT variance for this activity.

A)3
B)1
C)9
D)6
سؤال
Table 11-4
The following represents a project with known activity times.All times are in weeks.
<strong>Table 11-4 The following represents a project with known activity times.All times are in weeks.   Using the data in Table 11-4, compute the slack time for activity D.</strong> A)0 B)5 C)3 D)6 <div style=padding-top: 35px>
Using the data in Table 11-4, compute the slack time for activity D.

A)0
B)5
C)3
D)6
فتح الحزمة
قم بالتسجيل لفتح البطاقات في هذه المجموعة!
Unlock Deck
Unlock Deck
1/142
auto play flashcards
العب
simple tutorial
ملء الشاشة (f)
exit full mode
Deck 11: Project Management
1
One PERT/COST assumption is that money is spent at a constant rate over the time taken to complete an activity.
True
2
A PERT/CPM network is a graphical display of a project that connects activities.
True
3
In CPM, crashing an activity that is not on the critical path increases the cost of the project.
True
4
Before drawing a PERT or CPM network, we must identify all activities and their predecessors.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
5
The identification of the project activities and their time, cost, resource requirements, predecessors, and person(s)responsible is called PERT planning.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
6
The optimistic time is the greatest amount of time that could be required to complete an activity.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
7
PERT is a deterministic analysis tool allowing for precise times of activities within a project.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
8
In PERT, the earliest start time for an activity is equal to the latest of the earliest finish times of all of its immediate predecessors.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
9
CPM was developed for use in managing projects about which we have good information about activity or task completion times.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
10
CPM is a probabilistic analysis of managing a project.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
11
The first step in planning and scheduling a project is to develop the work breakdown structure.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
12
PERT and CPM are quantitative analysis tools designed to schedule and control large projects.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
13
The longest time path through a PERT/CPM network is called the critical path.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
14
PERT stands for Probabilistic Evaluation and Review Technique.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
15
One of the most significant benefits of PERT is that it forces the project manager to sit down and plan the project in great detail-and thus come to an understanding of relationships between the activities.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
16
The three time estimates employed in PERT are optimistic time, average time, and pessimistic time.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
17
Given the assumptions in PERT, the probability that a project will be completed in less time than required by the activities on the critical path is approximately 50%.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
18
With PERT, we are able to calculate the probability of finishing the project within a specified time.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
19
Through the use of PERT/CPM, astute managers can derive flexibility by identifying noncritical activities and replanning, rescheduling, and reallocating resources such as personnel and finances.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
20
Given the variability of the activity completion times, the original critical path we identify in our PERT analysis may not always be the actual critical path as the project takes place.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
21
Once the crash cost per time period value is negative, no additional crashing should be performed.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
22
The critical path of a network is the

A)shortest time path through the network.
B)path with the fewest activities.
C)path with the most activities.
D)longest time path through the network.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
23
Gantt charts and PERT diagrams provide the same information, just in different formats.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
24
When crashing a project, all critical paths must be shortened by the same amount for activity duration reductions to be cost-effective.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
25
Given an activity's optimistic, most likely, and pessimistic time estimates of 4, 6, and 14 days respectively, compute the PERT expected activity time for this activity.

A)8
B)6
C)7
D)9
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
26
Given an activity's optimistic, most likely, and pessimistic time estimates of 4, 14, and 18 days respectively, compute the PERT expected activity time for this activity.

A)14
B)12
C)11
D)13
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
27
The value of work completed is computed by multiplying budgeted cost by the percent completion.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
28
CPM

A)assumes we do not know ahead of time what activities must be completed.
B)assumes that activity time estimates follow the normal probability distribution.
C)is a deterministic network technique that allows for project crashing.
D)is a network technique that allows three time estimates for each activity in a project.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
29
Gantt charts contain information about the time taken by each activity, but not about the sequential dependencies of the activities.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
30
The first step in planning and scheduling a project is to develop the

A)employee scheduling plan.
B)PERT/CPM network diagram.
C)critical path.
D)work breakdown structure.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
31
The expected time in PERT is

A)a weighted average of the most optimistic time, most pessimistic time, and four times the most likely time.
B)the modal time of a beta distribution.
C)a simple average of the most optimistic, most likely, and most pessimistic times.
D)the square root of the sum of the variances of the activities on the critical path.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
32
The activity crash cost is equal to the incremental cost of shortening the project.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
33
The activity difference is the actual duration of an activity less the planned duration of that same activity.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
34
Given an activity's optimistic, most likely, and pessimistic time estimates of 2, 5, and 14 days respectively, compute the PERT expected activity time for this activity.

A)6
B)7
C)9
D)5
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
35
Budgets are computed using only ES times.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
36
PERT

A)assumes that we do not know ahead of time what activities must be completed.
B)assumes that activity time estimates follow the normal probability distribution.
C)is a network technique that uses three time estimates for each activity in a project.
D)is a deterministic network technique that allows for project crashing.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
37
For projects that have a daily fixed cost, it is not possible to reduce the overall duration once the cost of crashing exceeds the daily fixed cost.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
38
Slack time in a network is the

A)amount of time that an activity would take assuming very unfavorable conditions.
B)shortest amount of time that could be required to complete the activity.
C)amount of time that you would expect it would take to complete the activity.
D)amount of time that an activity can be delayed without delaying the entire project.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
39
Which of the following is not a concept associated with CPM?

A)normal time
B)probability
C)normal cost
D)crash cost
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
40
In a PERT network, the earliest (activity)start time is the

A)earliest time that an activity can be finished without delaying the entire project.
B)latest time that an activity can be started without delaying the entire project.
C)earliest time that an activity can start without violation of precedence requirements.
D)latest time that an activity can be finished without delaying the entire project.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
41
Table 11-1
The following represents a project with known activity times.All times are in weeks.
<strong>Table 11-1 The following represents a project with known activity times.All times are in weeks.   Using the data in Table 11-1, what is the minimum possible time required for completing the project?</strong> A)8 B)14 C)25 D)10
Using the data in Table 11-1, what is the minimum possible time required for completing the project?

A)8
B)14
C)25
D)10
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
42
Given an activity's optimistic, most likely, and pessimistic time estimates of 4, 12, and 18 days respectively, compute the PERT variance for this activity.

A)2.33
B)5.44
C)8.00
D)64.00
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
43
Given the following small project, the critical path is ________ days. <strong>Given the following small project, the critical path is ________ days.  </strong> A)10 B)14 C)16 D)20

A)10
B)14
C)16
D)20
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
44
Table 11-2
The following represents a project with four activities.All times are in weeks.
<strong>Table 11-2 The following represents a project with four activities.All times are in weeks.   According to Table 11-2, there are four activities in the project.Assume the normal distribution is appropriate to use to determine the probability of finishing by a particular time.If you wished to find the probability of finishing the project in 20 weeks or fewer, it would be necessary to find the variance and then the standard deviation to be used with the normal distribution.What variance would be used?</strong> A)2 B)4 C)8 D)12
According to Table 11-2, there are four activities in the project.Assume the normal distribution is appropriate to use to determine the probability of finishing by a particular time.If you wished to find the probability of finishing the project in 20 weeks or fewer, it would be necessary to find the variance and then the standard deviation to be used with the normal distribution.What variance would be used?

A)2
B)4
C)8
D)12
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
45
Given the following small project, the critical path is ________ days. <strong>Given the following small project, the critical path is ________ days.  </strong> A)4 B)10 C)12 D)22

A)4
B)10
C)12
D)22
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
46
Consider a project that has an expected completion time of 60 weeks and a standard deviation of five weeks.What is the probability that the project is finished in 70 weeks or fewer? (Round to two decimals.)

A)0.98
B)0.48
C)0.50
D)0.02
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
47
Table 11-3
<strong>Table 11-3   According to Table 11-3, there are five activities in a PERT project.If the normal distribution were used to find the probability of finishing this project in 24 weeks or fewer, what mean and variance would be used?</strong> A)30 and 5.222 B)20 and 5.222 C)30 and 4.222 D)22.667 and 1.111
According to Table 11-3, there are five activities in a PERT project.If the normal distribution were used to find the probability of finishing this project in 24 weeks or fewer, what mean and variance would be used?

A)30 and 5.222
B)20 and 5.222
C)30 and 4.222
D)22.667 and 1.111
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
48
In a PERT network, the latest (activity)start time is the

A)earliest time that an activity can be finished without delaying the entire project.
B)latest time that an activity can be started without delaying the entire project.
C)earliest time that an activity can start without violation of precedence requirements.
D)latest time that an activity can be finished without delaying the entire project.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
49
Your company is considering submitting a bid on a major project.You determine that the expected completion time is 100 weeks and the standard deviation is 10 weeks.It is assumed that the normal distribution applies.You wish to set the due date for the project such that there is an 85 percent chance that the project will be finished by this time.What due date should be set?

A)108.0
B)110.4
C)89.6
D)85.0
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
50
Table 11-3
<strong>Table 11-3   According to Table 11-3, there are five activities in a PERT project.What is the variance of the critical path?</strong> A)5.222 B)4.222 C)1.222 D)1.111
According to Table 11-3, there are five activities in a PERT project.What is the variance of the critical path?

A)5.222
B)4.222
C)1.222
D)1.111
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
51
Table 11-1
The following represents a project with known activity times.All times are in weeks.
<strong>Table 11-1 The following represents a project with known activity times.All times are in weeks.   Using the data in Table 11-1, compute the latest finish time for activity E.</strong> A)4 B)10 C)14 D)25
Using the data in Table 11-1, compute the latest finish time for activity E.

A)4
B)10
C)14
D)25
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
52
Table 11-2
The following represents a project with four activities.All times are in weeks.
<strong>Table 11-2 The following represents a project with four activities.All times are in weeks.   According to Table 11-2, there are four activities in the project.Assume the normal distribution is appropriate to use to determine the probability of finishing by a particular time.What is the probability that the project is finished in 16 weeks or fewer? (Round to two decimals.)</strong> A)0.07 B)0.93 C)0.43 D)0.77
According to Table 11-2, there are four activities in the project.Assume the normal distribution is appropriate to use to determine the probability of finishing by a particular time.What is the probability that the project is finished in 16 weeks or fewer? (Round to two decimals.)

A)0.07
B)0.93
C)0.43
D)0.77
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
53
Table 11-2
The following represents a project with four activities.All times are in weeks.
<strong>Table 11-2 The following represents a project with four activities.All times are in weeks.   According to the data in Table 11-2, what is the minimum expected completion time for the project?</strong> A)18 B)19 C)37 D)11
According to the data in Table 11-2, what is the minimum expected completion time for the project?

A)18
B)19
C)37
D)11
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
54
The critical path of a network is the

A)path with the least variance.
B)path with zero slack.
C)path with the most activities.
D)path with the largest variance.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
55
Given an activity's optimistic, most likely, and pessimistic time estimates of 3, 5, and 15 days, respectively, compute the PERT standard deviation for this activity.

A)2
B)4
C)5
D)15
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
56
Table 11-3
<strong>Table 11-3   According to Table 11-3, there are five activities in a PERT project.Which activities are on the critical path?</strong> A)A-C-E B)B-D C)A-B-C-D D)B-E
According to Table 11-3, there are five activities in a PERT project.Which activities are on the critical path?

A)A-C-E
B)B-D
C)A-B-C-D
D)B-E
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
57
Table 11-1
The following represents a project with known activity times.All times are in weeks.
<strong>Table 11-1 The following represents a project with known activity times.All times are in weeks.   According to Table 11-1, compute the slack time for activity D.</strong> A)0 B)5 C)3 D)6
According to Table 11-1, compute the slack time for activity D.

A)0
B)5
C)3
D)6
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
58
Given an activity's optimistic, most likely, and pessimistic time estimates of 2, 10, and 20 days respectively, compute the PERT variance for this activity.

A)3
B)6
C)9
D)18
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
59
Table 11-2
The following represents a project with four activities.All times are in weeks.
<strong>Table 11-2 The following represents a project with four activities.All times are in weeks.   According to the data in Table 11-2, what is the critical path?</strong> A)A-B B)A-C C)B-D D)A-B-C-D
According to the data in Table 11-2, what is the critical path?

A)A-B
B)A-C
C)B-D
D)A-B-C-D
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
60
Table 11-1
The following represents a project with known activity times.All times are in weeks.
<strong>Table 11-1 The following represents a project with known activity times.All times are in weeks.   Using the data in Table 11-1, what is the latest possible time that C may be started without delaying completion of the project?</strong> A)0 B)4 C)8 D)10
Using the data in Table 11-1, what is the latest possible time that C may be started without delaying completion of the project?

A)0
B)4
C)8
D)10
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
61
Given an activity's optimistic, most likely, and pessimistic time estimates of 3, 5, and 13 days respectively, compute the expected time for this activity.

A)3
B)4
C)5
D)6
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
62
The project described by: <strong>The project described by:   is best represented by which of the following networks?</strong> A)   B)   C)   D)   is best represented by which of the following networks?

A)
<strong>The project described by:   is best represented by which of the following networks?</strong> A)   B)   C)   D)
B)
<strong>The project described by:   is best represented by which of the following networks?</strong> A)   B)   C)   D)
C)
<strong>The project described by:   is best represented by which of the following networks?</strong> A)   B)   C)   D)
D)
<strong>The project described by:   is best represented by which of the following networks?</strong> A)   B)   C)   D)
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
63
Table 11-4
The following represents a project with known activity times.All times are in weeks.
<strong>Table 11-4 The following represents a project with known activity times.All times are in weeks.   Using the data in Table 11-4, what is the minimum possible time required for completing the project?</strong> A)8 B)12 C)18 D)10
Using the data in Table 11-4, what is the minimum possible time required for completing the project?

A)8
B)12
C)18
D)10
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
64
The project described by <strong>The project described by   has a critical path length of:</strong> A)21 days. B)14 days. C)23 days. D)32 days. has a critical path length of:

A)21 days.
B)14 days.
C)23 days.
D)32 days.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
65
CPM stands for

A)critical path management.
B)critical project management.
C)critical project method.
D)critical path method.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
66
The two common techniques for drawing PERT networks are

A)NOA and NRA.
B)AON and AOA.
C)GANTT and NOA.
D)ONA and OAO.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
67
Table 11-4
The following represents a project with known activity times.All times are in weeks.
<strong>Table 11-4 The following represents a project with known activity times.All times are in weeks.   Using the data in Table 11-4, what is the latest possible time that C may be started without delaying completion of the project?</strong> A)0 B)4 C)8 D)10
Using the data in Table 11-4, what is the latest possible time that C may be started without delaying completion of the project?

A)0
B)4
C)8
D)10
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
68
Table 11-4
The following represents a project with known activity times.All times are in weeks.
<strong>Table 11-4 The following represents a project with known activity times.All times are in weeks.   Using the data in Table 11-4, determine the latest time activity A can be started without delaying the project completion.</strong> A)4 B)3 C)8 D)6
Using the data in Table 11-4, determine the latest time activity A can be started without delaying the project completion.

A)4
B)3
C)8
D)6
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
69
Your company is considering submitting a bid on a major project.You determine that the expected completion time is 150 weeks and the standard deviation is 10 weeks.It is assumed that the normal distribution applies.You wish to set the due date for the project such that there is a 95 percent chance that the project will be finished by this time.What due date should be set?

A)108.0
B)160.4
C)166.5
D)135.0
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
70
Consider a project that has an expected completion time of 50 weeks and a standard deviation of 9 weeks.What is the probability that the project is finished in 57 weeks or fewer? (Round to two decimals.)

A)0.68
B)0.78
C)0.22
D)0.32
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
71
PERT stands for

A)probabilistic evaluation and review technique.
B)program evaluation and review technique.
C)probability of expected run times.
D)program of expected run times.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
72
Table 11-4
The following represents a project with known activity times.All times are in weeks.
<strong>Table 11-4 The following represents a project with known activity times.All times are in weeks.   Using the data in Table 11-4, compute the latest finish time for activity E.</strong> A)4 B)10 C)14 D)25
Using the data in Table 11-4, compute the latest finish time for activity E.

A)4
B)10
C)14
D)25
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
73
In PERT, we assume that

A)the times to complete individual activities are known with certainty.
B)all activities are carried out by staff from our own organization.
C)the total cost of a project is independent of the time to complete the project.
D)the total time to complete all activities on the critical path is described by a normal distribution.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
74
Given an activity's optimistic, most likely, and pessimistic time estimates of 3, 7, and 11 days respectively, compute the expected time for this activity.

A)5
B)6
C)7
D)12
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
75
The project described by: <strong>The project described by:   has a critical path of length of</strong> A)15 days. B)20 days. C)17 days. D)18 days. has a critical path of length of

A)15 days.
B)20 days.
C)17 days.
D)18 days.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
76
Table 11-4
The following represents a project with known activity times.All times are in weeks.
<strong>Table 11-4 The following represents a project with known activity times.All times are in weeks.   Using the data in Table 11-4, determine the latest time activity A can be finished and not delay any activity?</strong> A)4 B)0 C)8 D)5
Using the data in Table 11-4, determine the latest time activity A can be finished and not delay any activity?

A)4
B)0
C)8
D)5
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
77
In PERT analysis, the probability of the optimistic time occurring should be on the order of

A)1/3.
B)1/6.
C)1/10.
D)1/100.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
78
Given an activity's optimistic, most likely, and pessimistic time estimates of 1, 9, and 23 days respectively, compute the PERT expected activity time for this activity.

A)10
B)12
C)9
D)11
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
79
Given an activity's optimistic, most likely, and pessimistic time estimates of 3, 6, and 9 days respectively, compute the PERT variance for this activity.

A)3
B)1
C)9
D)6
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
80
Table 11-4
The following represents a project with known activity times.All times are in weeks.
<strong>Table 11-4 The following represents a project with known activity times.All times are in weeks.   Using the data in Table 11-4, compute the slack time for activity D.</strong> A)0 B)5 C)3 D)6
Using the data in Table 11-4, compute the slack time for activity D.

A)0
B)5
C)3
D)6
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.
فتح الحزمة
k this deck
locked card icon
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 142 في هذه المجموعة.