Deck 10: Project Scheduling: Lagging, crashing, and Activity Networks

ملء الشاشة (f)
exit full mode
سؤال
Gantt charts cannot depict float.
استخدم زر المسافة أو
up arrow
down arrow
لقلب البطاقة.
سؤال
The most common type of logical sequencing between tasks is the ________ relationship.
سؤال
________ represent one of the first attempts to develop a network diagram that orders project activities by baseline calendar dates.
سؤال
In an actual project,one means of crashing critical path activities would be to perform at a lower level of quality.
سؤال
The critical path may not contain a dummy activity.
سؤال
In order to accelerate completion of a project,the manager must crash critical path activities.
سؤال
Quite often the marginal gains in employee productivity decrease dramatically with the increased use of overtime.
سؤال
Networks are adaptable and useful for all scheduling challenges that an organization faces.
سؤال
Most activity estimations using PERT methods lead to overly optimistic activity duration estimates.
سؤال
The logical relationship between the start and finish of one activity and the start and finish of another activity is the ________.
سؤال
Gantt charts can display early start or late start logic.
سؤال
Finish to start lags are the same as additional activity slack.
سؤال
The least common type of lag relationship occurs when a successor's finish is dependent upon a predecessor's start.
سؤال
Most project management software employs AOA diagramming
سؤال
For large projects,network diagrams are more useful if they are completely detailed.
سؤال
Start-to-start lags are becoming increasingly used as a means to accelerate projects through a process known as ________.
سؤال
AOA is a more useful technique than AON if the project is complex and has many significant milestones.
سؤال
A(n)________ relationship is appropriate where two or more linked activities must be completed before a successor is begun.
سؤال
Dummy activities are used in AOA networks to indicate the existence of precedent relationships between activities and their event nodes.
سؤال
Brook's Law states that the typical crashing decision to add more resources to an activity only delays the activity further.
سؤال
Each individual bar on a Gantt chart represents a(n)________.
سؤال
Activities A and B have a finish to finish relationship and early start and finish times as shown.What is the result of incorporating a 4-day lag between activities C and B? <strong>Activities A and B have a finish to finish relationship and early start and finish times as shown.What is the result of incorporating a 4-day lag between activities C and B?  </strong> A)The early finish for A increases to 31. B)The early start time for A increases to 24. C)The early finish time for B increases to 31. D)The early start time for D falls to 23. <div style=padding-top: 35px>

A)The early finish for A increases to 31.
B)The early start time for A increases to 24.
C)The early finish time for B increases to 31.
D)The early start time for D falls to 23.
سؤال
The three principal methods for accelerating project activities are to change the ________,________,and ________ of the project resources.
سؤال
In analyzing crash options for project activities,each activity has a slope that is calculated as the ________ divided by the ________.
سؤال
The most common type of logical sequencing between tasks is referred to as the:

A)finish to start relationship.
B)finish to finish relationship.
C)start to start relationship.
D)start to finish relationship.
سؤال
An activity of duration zero whose sole purpose is to maintain network logic is a(n)________.
سؤال
Use the Gantt chart and the activity list to determine which resource is used the least. <strong>Use the Gantt chart and the activity list to determine which resource is used the least.    </strong> A)Resource 1 B)Resource 3 C)Resource 4 D)Resource 2 <div style=padding-top: 35px> <strong>Use the Gantt chart and the activity list to determine which resource is used the least.    </strong> A)Resource 1 B)Resource 3 C)Resource 4 D)Resource 2 <div style=padding-top: 35px>

A)Resource 1
B)Resource 3
C)Resource 4
D)Resource 2
سؤال
The horizontal axis for a Gantt chart is ________.
سؤال
The process of accelerating a project is referred to as ________.
سؤال
Which statement about this Gantt chart is best? <strong>Which statement about this Gantt chart is best?  </strong> A)Activity a has a duration that could be as short as 1 day and as long as 10. B)Activity b probably has activity a as a predecessor. C)No progress has been made on activity c. D)Activity d is the longest activity. <div style=padding-top: 35px>

A)Activity a has a duration that could be as short as 1 day and as long as 10.
B)Activity b probably has activity a as a predecessor.
C)No progress has been made on activity c.
D)Activity d is the longest activity.
سؤال
PERT analysis is based on ________ estimates,which,if unreasonably determined,can lead to inaccurate and misleading project schedules.
سؤال
The primary drawback with ________ occurs when the project is very complex,with numerous paths through the model.
سؤال
If a project is extraordinarily complex,rather than showing every possible path through the network and every activity sequence,a(n)________ that shows only the key subroutines or network paths can be created.
سؤال
Use the Gantt chart and the activity list to determine when resource 5 is free. <strong>Use the Gantt chart and the activity list to determine when resource 5 is free.    </strong> A)between 0 and 15 B)between 15 and 30 C)between 30 and 45 D)between 45 and 60 <div style=padding-top: 35px> <strong>Use the Gantt chart and the activity list to determine when resource 5 is free.    </strong> A)between 0 and 15 B)between 15 and 30 C)between 30 and 45 D)between 45 and 60 <div style=padding-top: 35px>

A)between 0 and 15
B)between 15 and 30
C)between 30 and 45
D)between 45 and 60
سؤال
Consider the Gantt chart shown below where the time scale is in minutes and all activities are performed on an early start basis.How much slack is available in The Great Hair Washing project? <strong>Consider the Gantt chart shown below where the time scale is in minutes and all activities are performed on an early start basis.How much slack is available in The Great Hair Washing project?  </strong> A)10 minutes B)15 minutes C)0 minutes D)5 minutes <div style=padding-top: 35px>

A)10 minutes
B)15 minutes
C)0 minutes
D)5 minutes
سؤال
What is the early start time for activity C if it has the start to start relationship shown? <strong>What is the early start time for activity C if it has the start to start relationship shown?  </strong> A)day 20 B)day 25 C)day 27 D)day 29 <div style=padding-top: 35px>

A)day 20
B)day 25
C)day 27
D)day 29
سؤال
The two primary drawbacks to the use of overtime as a means of crashing a product are the ________ and the ________.
سؤال
A finish to start lag delay is usually shown:

A)as an added value in the predecessor's activity time.
B)on the line adjoining the two activity nodes.
C)as an added value in the predecessors early start time.
D)as a subtracted value in the follower's early finish time.
سؤال
Use the Gantt chart and the activity list to determine when resource 2 is free. <strong>Use the Gantt chart and the activity list to determine when resource 2 is free.    </strong> A)between 0 and 15 B)between 15 and 30 C)between 30 and 45 D)between 45 and 60 <div style=padding-top: 35px> <strong>Use the Gantt chart and the activity list to determine when resource 2 is free.    </strong> A)between 0 and 15 B)between 15 and 30 C)between 30 and 45 D)between 45 and 60 <div style=padding-top: 35px>

A)between 0 and 15
B)between 15 and 30
C)between 30 and 45
D)between 45 and 60
سؤال
Activity X has the start to finish relationship shown with activity Y and both have early start and finish times as shown.Which statement is best? <strong>Activity X has the start to finish relationship shown with activity Y and both have early start and finish times as shown.Which statement is best?  </strong> A)a < d B)a < c C)b < c D)d < a <div style=padding-top: 35px>

A)a < d
B)a < c
C)b < c
D)d < a
سؤال
Which of these approaches will NOT accelerate the completion of a project?

A)Improve the productivity of existing project resources.
B)Increase the bureaucratic oversight.
C)Improve the working method.
D)Increase the quantity of personnel and equipment.
سؤال
A 14-week construction activity requires a crane that rents for $1,000 per week and a crew of general laborers that costs $5,000 per week.In order to complete this activity within 10 weeks,you must hire additional general laborers at a cost of $2,000 per week.What is the slope for this activity?

A)$0 per week
B)$1,000 per week
C)$2,000 per week
D)$6,000 per week
سؤال
Use the Gantt chart and activity list to determine which resource has the greatest continual use. <strong>Use the Gantt chart and activity list to determine which resource has the greatest continual use.    </strong> A)Resource 4 B)Resource 2 C)Resource 3 D)Resource 5 <div style=padding-top: 35px> <strong>Use the Gantt chart and activity list to determine which resource has the greatest continual use.    </strong> A)Resource 4 B)Resource 2 C)Resource 3 D)Resource 5 <div style=padding-top: 35px>

A)Resource 4
B)Resource 2
C)Resource 3
D)Resource 5
سؤال
One reason for crashing a project is:

A)the project has slipped behind schedule.
B)that the initial schedule may be too pessimistic.
C)market needs change and the project is not in demand any more.
D)there are no repercussions for delivering the project late.
سؤال
Use the Gantt chart and activity list to determine which resource has the greatest continual use. <strong>Use the Gantt chart and activity list to determine which resource has the greatest continual use.    </strong> A)Resource 3 B)Resource 1 C)Resource 2 D)Resource 4 <div style=padding-top: 35px> <strong>Use the Gantt chart and activity list to determine which resource has the greatest continual use.    </strong> A)Resource 3 B)Resource 1 C)Resource 2 D)Resource 4 <div style=padding-top: 35px>

A)Resource 3
B)Resource 1
C)Resource 2
D)Resource 4
سؤال
Use the Gantt chart and the activity list to determine which resource is free for use in another project before the others. <strong>Use the Gantt chart and the activity list to determine which resource is free for use in another project before the others.    </strong> A)Resource 4 B)Resource 3 C)Resource 1 D)Resource 2 <div style=padding-top: 35px> <strong>Use the Gantt chart and the activity list to determine which resource is free for use in another project before the others.    </strong> A)Resource 4 B)Resource 3 C)Resource 1 D)Resource 2 <div style=padding-top: 35px>

A)Resource 4
B)Resource 3
C)Resource 1
D)Resource 2
سؤال
Use the Gantt chart and activity list to determine which resource is used the most. <strong>Use the Gantt chart and activity list to determine which resource is used the most.    </strong> A)Resource 4 B)Resource 2 C)Resource 1 D)Resource 5 <div style=padding-top: 35px> <strong>Use the Gantt chart and activity list to determine which resource is used the most.    </strong> A)Resource 4 B)Resource 2 C)Resource 1 D)Resource 5 <div style=padding-top: 35px>

A)Resource 4
B)Resource 2
C)Resource 1
D)Resource 5
سؤال
An activity performed by a subcontractor is scheduled for 20 weeks at an anticipated cost of $100,000.Due to slippage on the critical path you need to reduce this activity by three weeks.If the subcontractor informs you that the activity can be completed in 15 weeks for $200,000,what is the slope for the activity?

A)$20,000 per week
B)$33,333 per week
C)$5,000 per week
D)$13,333 per week
سؤال
A basic Gantt chart:

A)clearly displays early and late start and finish times for all activities.
B)cannot be used to track the project's progress.
C)permits scheduling resources well before they are needed.
D)shows dummy activities to preserve network logic.
سؤال
Use the Gantt chart and activity list to determine which resource is used the most. <strong>Use the Gantt chart and activity list to determine which resource is used the most.    </strong> A)Resource 1 B)Resource 2 C)Resource 4 D)Resource 5 <div style=padding-top: 35px> <strong>Use the Gantt chart and activity list to determine which resource is used the most.    </strong> A)Resource 1 B)Resource 2 C)Resource 4 D)Resource 5 <div style=padding-top: 35px>

A)Resource 1
B)Resource 2
C)Resource 4
D)Resource 5
سؤال
Given the cost information in the table,what is the cheapest activity to crash on a per week basis? <strong>Given the cost information in the table,what is the cheapest activity to crash on a per week basis?  </strong> A)Activity A B)Activity B C)Activity C D)Activity D <div style=padding-top: 35px>

A)Activity A
B)Activity B
C)Activity C
D)Activity D
سؤال
The process of accelerating a project is referred to as:

A)streamlining.
B)expediting.
C)rushing.
D)crashing.
سؤال
Use the Gantt chart and activity list to determine which resource is used the least. <strong>Use the Gantt chart and activity list to determine which resource is used the least.    </strong> A)Resource 1 B)Resource 2 C)Resource 4 D)Resource 5 <div style=padding-top: 35px> <strong>Use the Gantt chart and activity list to determine which resource is used the least.    </strong> A)Resource 1 B)Resource 2 C)Resource 4 D)Resource 5 <div style=padding-top: 35px>

A)Resource 1
B)Resource 2
C)Resource 4
D)Resource 5
سؤال
Use the Gantt chart and the activity list to determine which resource is needed earliest in this project. <strong>Use the Gantt chart and the activity list to determine which resource is needed earliest in this project.    </strong> A)Resource 2 B)Resource 3 C)Resource 1 D)Resource 4 <div style=padding-top: 35px> <strong>Use the Gantt chart and the activity list to determine which resource is needed earliest in this project.    </strong> A)Resource 2 B)Resource 3 C)Resource 1 D)Resource 4 <div style=padding-top: 35px>

A)Resource 2
B)Resource 3
C)Resource 1
D)Resource 4
سؤال
Use the Gantt chart and activity list to determine when resource 3 is free. <strong>Use the Gantt chart and activity list to determine when resource 3 is free.    </strong> A)between 0 and 10 B)between 10 and 20 C)between 20 and 30 D)between 30 and 40 <div style=padding-top: 35px> <strong>Use the Gantt chart and activity list to determine when resource 3 is free.    </strong> A)between 0 and 10 B)between 10 and 20 C)between 20 and 30 D)between 30 and 40 <div style=padding-top: 35px>

A)between 0 and 10
B)between 10 and 20
C)between 20 and 30
D)between 30 and 40
سؤال
If an activity's cost is plotted against its duration on axes with zeros at the origin:

A)the slope of the line is positive because it costs more to finish an activity more quickly.
B)the slope of the line is negative because a shorter activity costs less than a longer one.
C)the slope of the line is negative because it costs more to finish an activity more quickly.
D)the slope of the line is positive because a longer activity costs more than a shorter one.
سؤال
Use the Gantt chart and activity list to determine which resource is released from this project for use in another project the earliest. <strong>Use the Gantt chart and activity list to determine which resource is released from this project for use in another project the earliest.    </strong> A)Resource 2 B)Resource 4 C)Resource 1 D)Resource 3 <div style=padding-top: 35px> <strong>Use the Gantt chart and activity list to determine which resource is released from this project for use in another project the earliest.    </strong> A)Resource 2 B)Resource 4 C)Resource 1 D)Resource 3 <div style=padding-top: 35px>

A)Resource 2
B)Resource 4
C)Resource 1
D)Resource 3
سؤال
The most common method for shortening activity durations involves the decision to:

A)eliminate bureaucracy.
B)alter the technology used in the activity.
C)assign more senior personnel to the activity.
D)increase project resources.
سؤال
Use the Gantt chart and the activity list to determine which resource is used the most. <strong>Use the Gantt chart and the activity list to determine which resource is used the most.    </strong> A)Resource 4 B)Resource 3 C)Resource 1 D)Resource 2 <div style=padding-top: 35px> <strong>Use the Gantt chart and the activity list to determine which resource is used the most.    </strong> A)Resource 4 B)Resource 3 C)Resource 1 D)Resource 2 <div style=padding-top: 35px>

A)Resource 4
B)Resource 3
C)Resource 1
D)Resource 2
سؤال
Use the Gantt chart and activity list to determine which resource is used the least. <strong>Use the Gantt chart and activity list to determine which resource is used the least.    </strong> A)Resource 4 B)Resource 2 C)Resource 1 D)Resource 3 <div style=padding-top: 35px> <strong>Use the Gantt chart and activity list to determine which resource is used the least.    </strong> A)Resource 4 B)Resource 2 C)Resource 1 D)Resource 3 <div style=padding-top: 35px>

A)Resource 4
B)Resource 2
C)Resource 1
D)Resource 3
سؤال
A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the total cost for completing this project in 50 days? <strong>A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the total cost for completing this project in 50 days?  </strong> A)$253,000 B)$237,000 C)$216,000 D)$207,000 <div style=padding-top: 35px>

A)$253,000
B)$237,000
C)$216,000
D)$207,000
سؤال
What is the late finish for activity D in the network shown in the diagram? <strong>What is the late finish for activity D in the network shown in the diagram?  </strong> A)15 B)16 C)17 D)18 <div style=padding-top: 35px>

A)15
B)16
C)17
D)18
سؤال
An activity on an arrow network:

A)cannot have more arrows than nodes.
B)cannot have more nodes than arrows.
C)has one more node than arrows.
D)has one more arrow than nodes.
سؤال
Use the information in the table (all times are in days)to determine the lowest extra cost for an 18-day project. <strong>Use the information in the table (all times are in days)to determine the lowest extra cost for an 18-day project.  </strong> A)$380 B)$400 C)$420 D)$440 <div style=padding-top: 35px>

A)$380
B)$400
C)$420
D)$440
سؤال
It costs $75 per day for each day that a construction crew is on site.The project manager determines that most activities can be crashed and has listed the crashing costs next to the minimum time for each activity.Use this information to determine the lowest cost for this project.All times given are in days. <strong>It costs $75 per day for each day that a construction crew is on site.The project manager determines that most activities can be crashed and has listed the crashing costs next to the minimum time for each activity.Use this information to determine the lowest cost for this project.All times given are in days.  </strong> A)$1,800 B)$1,770 C)$1,700 D)$1,630 <div style=padding-top: 35px>

A)$1,800
B)$1,770
C)$1,700
D)$1,630
سؤال
A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $250 per week for every week the project extends beyond 50 weeks.What is the cost of the least expensive project possible? <strong>A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $250 per week for every week the project extends beyond 50 weeks.What is the cost of the least expensive project possible?  </strong> A)$18,100 B)$19,350 C)$17,416.67 D)$16,110 <div style=padding-top: 35px>

A)$18,100
B)$19,350
C)$17,416.67
D)$16,110
سؤال
A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $5,000 per week for every week the project extends beyond 45 weeks.What is the lowest total cost for completing this project? <strong>A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $5,000 per week for every week the project extends beyond 45 weeks.What is the lowest total cost for completing this project?  </strong> A)$222,667 B)$217,000 C)$222,000 D)$208,000 <div style=padding-top: 35px>

A)$222,667
B)$217,000
C)$222,000
D)$208,000
سؤال
Dummy activities have a duration equal to the:

A)slack on the critical path.
B)length of the predecessor.
C)length of the successor.
D)lag needed to preserve network logic.
سؤال
A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the lowest total cost for completing this project in 45 days? <strong>A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the lowest total cost for completing this project in 45 days?  </strong> A)$222,667 B)$243,675 C)$258,333 D)$272,500 <div style=padding-top: 35px>

A)$222,667
B)$243,675
C)$258,333
D)$272,500
سؤال
The critical path of this network is: <strong>The critical path of this network is:  </strong> A)14. B)15. C)12. D)13. <div style=padding-top: 35px>

A)14.
B)15.
C)12.
D)13.
سؤال
Use the information in the table (all times are in days)to determine the lowest extra cost for a 20-day project. <strong>Use the information in the table (all times are in days)to determine the lowest extra cost for a 20-day project.  </strong> A)$200 B)$130 C)$120 D)$100 <div style=padding-top: 35px>

A)$200
B)$130
C)$120
D)$100
سؤال
The fastest completion time for this project is: <strong>The fastest completion time for this project is:  </strong> A)14. B)15. C)16. D)17. <div style=padding-top: 35px>

A)14.
B)15.
C)16.
D)17.
سؤال
A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $250 per week for every week the project extends beyond 50 weeks.What is the duration of the least expensive project possible? <strong>A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $250 per week for every week the project extends beyond 50 weeks.What is the duration of the least expensive project possible?  </strong> A)60 weeks B)57 weeks C)53 weeks D)50 weeks <div style=padding-top: 35px>

A)60 weeks
B)57 weeks
C)53 weeks
D)50 weeks
سؤال
The AOA network described by this table needs: <strong>The AOA network described by this table needs:  </strong> A)zero dummy activities. B)one dummy activity. C)two dummy activities. D)three dummy activities. <div style=padding-top: 35px>

A)zero dummy activities.
B)one dummy activity.
C)two dummy activities.
D)three dummy activities.
سؤال
The AOA network described by this table needs: <strong>The AOA network described by this table needs:  </strong> A)zero dummy activities. B)one dummy activity. C)two dummy activities. D)three dummy activities. <div style=padding-top: 35px>

A)zero dummy activities.
B)one dummy activity.
C)two dummy activities.
D)three dummy activities.
سؤال
A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the lowest total cost for completing this project in 55 weeks? <strong>A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the lowest total cost for completing this project in 55 weeks?  </strong> A)$16,950 B)$15,000 C)$16,350 D)$15,350 <div style=padding-top: 35px>

A)$16,950
B)$15,000
C)$16,350
D)$15,350
سؤال
What information is NOT included in the nodes for an AOA network?

A)label
B)early start time
C)late finish time
D)early finish time
سؤال
Use the information in the table (all times are in days)to determine the lowest cost minimum completion time? <strong>Use the information in the table (all times are in days)to determine the lowest cost minimum completion time?  </strong> A)$1,040 B)$1,020 C)$740 D)$720 <div style=padding-top: 35px>

A)$1,040
B)$1,020
C)$740
D)$720
سؤال
A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $6,000 per week for every week the project extends beyond 40 weeks.What is the lowest total cost for completing this project? <strong>A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $6,000 per week for every week the project extends beyond 40 weeks.What is the lowest total cost for completing this project?  </strong> A)$234,000 B)$255,600 C)$248,333 D)$252,000 <div style=padding-top: 35px>

A)$234,000
B)$255,600
C)$248,333
D)$252,000
سؤال
A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the lowest total cost for completing this project in 40 days? <strong>A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the lowest total cost for completing this project in 40 days?  </strong> A)$242,667 B)$255,600 C)$263,333 D)$272,500 <div style=padding-top: 35px>

A)$242,667
B)$255,600
C)$263,333
D)$272,500
فتح الحزمة
قم بالتسجيل لفتح البطاقات في هذه المجموعة!
Unlock Deck
Unlock Deck
1/110
auto play flashcards
العب
simple tutorial
ملء الشاشة (f)
exit full mode
Deck 10: Project Scheduling: Lagging, crashing, and Activity Networks
1
Gantt charts cannot depict float.
False
2
The most common type of logical sequencing between tasks is the ________ relationship.
finish to start
3
________ represent one of the first attempts to develop a network diagram that orders project activities by baseline calendar dates.
Gantt charts
4
In an actual project,one means of crashing critical path activities would be to perform at a lower level of quality.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
5
The critical path may not contain a dummy activity.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
6
In order to accelerate completion of a project,the manager must crash critical path activities.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
7
Quite often the marginal gains in employee productivity decrease dramatically with the increased use of overtime.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
8
Networks are adaptable and useful for all scheduling challenges that an organization faces.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
9
Most activity estimations using PERT methods lead to overly optimistic activity duration estimates.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
10
The logical relationship between the start and finish of one activity and the start and finish of another activity is the ________.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
11
Gantt charts can display early start or late start logic.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
12
Finish to start lags are the same as additional activity slack.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
13
The least common type of lag relationship occurs when a successor's finish is dependent upon a predecessor's start.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
14
Most project management software employs AOA diagramming
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
15
For large projects,network diagrams are more useful if they are completely detailed.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
16
Start-to-start lags are becoming increasingly used as a means to accelerate projects through a process known as ________.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
17
AOA is a more useful technique than AON if the project is complex and has many significant milestones.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
18
A(n)________ relationship is appropriate where two or more linked activities must be completed before a successor is begun.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
19
Dummy activities are used in AOA networks to indicate the existence of precedent relationships between activities and their event nodes.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
20
Brook's Law states that the typical crashing decision to add more resources to an activity only delays the activity further.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
21
Each individual bar on a Gantt chart represents a(n)________.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
22
Activities A and B have a finish to finish relationship and early start and finish times as shown.What is the result of incorporating a 4-day lag between activities C and B? <strong>Activities A and B have a finish to finish relationship and early start and finish times as shown.What is the result of incorporating a 4-day lag between activities C and B?  </strong> A)The early finish for A increases to 31. B)The early start time for A increases to 24. C)The early finish time for B increases to 31. D)The early start time for D falls to 23.

A)The early finish for A increases to 31.
B)The early start time for A increases to 24.
C)The early finish time for B increases to 31.
D)The early start time for D falls to 23.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
23
The three principal methods for accelerating project activities are to change the ________,________,and ________ of the project resources.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
24
In analyzing crash options for project activities,each activity has a slope that is calculated as the ________ divided by the ________.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
25
The most common type of logical sequencing between tasks is referred to as the:

A)finish to start relationship.
B)finish to finish relationship.
C)start to start relationship.
D)start to finish relationship.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
26
An activity of duration zero whose sole purpose is to maintain network logic is a(n)________.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
27
Use the Gantt chart and the activity list to determine which resource is used the least. <strong>Use the Gantt chart and the activity list to determine which resource is used the least.    </strong> A)Resource 1 B)Resource 3 C)Resource 4 D)Resource 2 <strong>Use the Gantt chart and the activity list to determine which resource is used the least.    </strong> A)Resource 1 B)Resource 3 C)Resource 4 D)Resource 2

A)Resource 1
B)Resource 3
C)Resource 4
D)Resource 2
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
28
The horizontal axis for a Gantt chart is ________.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
29
The process of accelerating a project is referred to as ________.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
30
Which statement about this Gantt chart is best? <strong>Which statement about this Gantt chart is best?  </strong> A)Activity a has a duration that could be as short as 1 day and as long as 10. B)Activity b probably has activity a as a predecessor. C)No progress has been made on activity c. D)Activity d is the longest activity.

A)Activity a has a duration that could be as short as 1 day and as long as 10.
B)Activity b probably has activity a as a predecessor.
C)No progress has been made on activity c.
D)Activity d is the longest activity.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
31
PERT analysis is based on ________ estimates,which,if unreasonably determined,can lead to inaccurate and misleading project schedules.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
32
The primary drawback with ________ occurs when the project is very complex,with numerous paths through the model.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
33
If a project is extraordinarily complex,rather than showing every possible path through the network and every activity sequence,a(n)________ that shows only the key subroutines or network paths can be created.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
34
Use the Gantt chart and the activity list to determine when resource 5 is free. <strong>Use the Gantt chart and the activity list to determine when resource 5 is free.    </strong> A)between 0 and 15 B)between 15 and 30 C)between 30 and 45 D)between 45 and 60 <strong>Use the Gantt chart and the activity list to determine when resource 5 is free.    </strong> A)between 0 and 15 B)between 15 and 30 C)between 30 and 45 D)between 45 and 60

A)between 0 and 15
B)between 15 and 30
C)between 30 and 45
D)between 45 and 60
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
35
Consider the Gantt chart shown below where the time scale is in minutes and all activities are performed on an early start basis.How much slack is available in The Great Hair Washing project? <strong>Consider the Gantt chart shown below where the time scale is in minutes and all activities are performed on an early start basis.How much slack is available in The Great Hair Washing project?  </strong> A)10 minutes B)15 minutes C)0 minutes D)5 minutes

A)10 minutes
B)15 minutes
C)0 minutes
D)5 minutes
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
36
What is the early start time for activity C if it has the start to start relationship shown? <strong>What is the early start time for activity C if it has the start to start relationship shown?  </strong> A)day 20 B)day 25 C)day 27 D)day 29

A)day 20
B)day 25
C)day 27
D)day 29
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
37
The two primary drawbacks to the use of overtime as a means of crashing a product are the ________ and the ________.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
38
A finish to start lag delay is usually shown:

A)as an added value in the predecessor's activity time.
B)on the line adjoining the two activity nodes.
C)as an added value in the predecessors early start time.
D)as a subtracted value in the follower's early finish time.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
39
Use the Gantt chart and the activity list to determine when resource 2 is free. <strong>Use the Gantt chart and the activity list to determine when resource 2 is free.    </strong> A)between 0 and 15 B)between 15 and 30 C)between 30 and 45 D)between 45 and 60 <strong>Use the Gantt chart and the activity list to determine when resource 2 is free.    </strong> A)between 0 and 15 B)between 15 and 30 C)between 30 and 45 D)between 45 and 60

A)between 0 and 15
B)between 15 and 30
C)between 30 and 45
D)between 45 and 60
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
40
Activity X has the start to finish relationship shown with activity Y and both have early start and finish times as shown.Which statement is best? <strong>Activity X has the start to finish relationship shown with activity Y and both have early start and finish times as shown.Which statement is best?  </strong> A)a < d B)a < c C)b < c D)d < a

A)a < d
B)a < c
C)b < c
D)d < a
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
41
Which of these approaches will NOT accelerate the completion of a project?

A)Improve the productivity of existing project resources.
B)Increase the bureaucratic oversight.
C)Improve the working method.
D)Increase the quantity of personnel and equipment.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
42
A 14-week construction activity requires a crane that rents for $1,000 per week and a crew of general laborers that costs $5,000 per week.In order to complete this activity within 10 weeks,you must hire additional general laborers at a cost of $2,000 per week.What is the slope for this activity?

A)$0 per week
B)$1,000 per week
C)$2,000 per week
D)$6,000 per week
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
43
Use the Gantt chart and activity list to determine which resource has the greatest continual use. <strong>Use the Gantt chart and activity list to determine which resource has the greatest continual use.    </strong> A)Resource 4 B)Resource 2 C)Resource 3 D)Resource 5 <strong>Use the Gantt chart and activity list to determine which resource has the greatest continual use.    </strong> A)Resource 4 B)Resource 2 C)Resource 3 D)Resource 5

A)Resource 4
B)Resource 2
C)Resource 3
D)Resource 5
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
44
One reason for crashing a project is:

A)the project has slipped behind schedule.
B)that the initial schedule may be too pessimistic.
C)market needs change and the project is not in demand any more.
D)there are no repercussions for delivering the project late.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
45
Use the Gantt chart and activity list to determine which resource has the greatest continual use. <strong>Use the Gantt chart and activity list to determine which resource has the greatest continual use.    </strong> A)Resource 3 B)Resource 1 C)Resource 2 D)Resource 4 <strong>Use the Gantt chart and activity list to determine which resource has the greatest continual use.    </strong> A)Resource 3 B)Resource 1 C)Resource 2 D)Resource 4

A)Resource 3
B)Resource 1
C)Resource 2
D)Resource 4
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
46
Use the Gantt chart and the activity list to determine which resource is free for use in another project before the others. <strong>Use the Gantt chart and the activity list to determine which resource is free for use in another project before the others.    </strong> A)Resource 4 B)Resource 3 C)Resource 1 D)Resource 2 <strong>Use the Gantt chart and the activity list to determine which resource is free for use in another project before the others.    </strong> A)Resource 4 B)Resource 3 C)Resource 1 D)Resource 2

A)Resource 4
B)Resource 3
C)Resource 1
D)Resource 2
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
47
Use the Gantt chart and activity list to determine which resource is used the most. <strong>Use the Gantt chart and activity list to determine which resource is used the most.    </strong> A)Resource 4 B)Resource 2 C)Resource 1 D)Resource 5 <strong>Use the Gantt chart and activity list to determine which resource is used the most.    </strong> A)Resource 4 B)Resource 2 C)Resource 1 D)Resource 5

A)Resource 4
B)Resource 2
C)Resource 1
D)Resource 5
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
48
An activity performed by a subcontractor is scheduled for 20 weeks at an anticipated cost of $100,000.Due to slippage on the critical path you need to reduce this activity by three weeks.If the subcontractor informs you that the activity can be completed in 15 weeks for $200,000,what is the slope for the activity?

A)$20,000 per week
B)$33,333 per week
C)$5,000 per week
D)$13,333 per week
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
49
A basic Gantt chart:

A)clearly displays early and late start and finish times for all activities.
B)cannot be used to track the project's progress.
C)permits scheduling resources well before they are needed.
D)shows dummy activities to preserve network logic.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
50
Use the Gantt chart and activity list to determine which resource is used the most. <strong>Use the Gantt chart and activity list to determine which resource is used the most.    </strong> A)Resource 1 B)Resource 2 C)Resource 4 D)Resource 5 <strong>Use the Gantt chart and activity list to determine which resource is used the most.    </strong> A)Resource 1 B)Resource 2 C)Resource 4 D)Resource 5

A)Resource 1
B)Resource 2
C)Resource 4
D)Resource 5
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
51
Given the cost information in the table,what is the cheapest activity to crash on a per week basis? <strong>Given the cost information in the table,what is the cheapest activity to crash on a per week basis?  </strong> A)Activity A B)Activity B C)Activity C D)Activity D

A)Activity A
B)Activity B
C)Activity C
D)Activity D
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
52
The process of accelerating a project is referred to as:

A)streamlining.
B)expediting.
C)rushing.
D)crashing.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
53
Use the Gantt chart and activity list to determine which resource is used the least. <strong>Use the Gantt chart and activity list to determine which resource is used the least.    </strong> A)Resource 1 B)Resource 2 C)Resource 4 D)Resource 5 <strong>Use the Gantt chart and activity list to determine which resource is used the least.    </strong> A)Resource 1 B)Resource 2 C)Resource 4 D)Resource 5

A)Resource 1
B)Resource 2
C)Resource 4
D)Resource 5
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
54
Use the Gantt chart and the activity list to determine which resource is needed earliest in this project. <strong>Use the Gantt chart and the activity list to determine which resource is needed earliest in this project.    </strong> A)Resource 2 B)Resource 3 C)Resource 1 D)Resource 4 <strong>Use the Gantt chart and the activity list to determine which resource is needed earliest in this project.    </strong> A)Resource 2 B)Resource 3 C)Resource 1 D)Resource 4

A)Resource 2
B)Resource 3
C)Resource 1
D)Resource 4
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
55
Use the Gantt chart and activity list to determine when resource 3 is free. <strong>Use the Gantt chart and activity list to determine when resource 3 is free.    </strong> A)between 0 and 10 B)between 10 and 20 C)between 20 and 30 D)between 30 and 40 <strong>Use the Gantt chart and activity list to determine when resource 3 is free.    </strong> A)between 0 and 10 B)between 10 and 20 C)between 20 and 30 D)between 30 and 40

A)between 0 and 10
B)between 10 and 20
C)between 20 and 30
D)between 30 and 40
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
56
If an activity's cost is plotted against its duration on axes with zeros at the origin:

A)the slope of the line is positive because it costs more to finish an activity more quickly.
B)the slope of the line is negative because a shorter activity costs less than a longer one.
C)the slope of the line is negative because it costs more to finish an activity more quickly.
D)the slope of the line is positive because a longer activity costs more than a shorter one.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
57
Use the Gantt chart and activity list to determine which resource is released from this project for use in another project the earliest. <strong>Use the Gantt chart and activity list to determine which resource is released from this project for use in another project the earliest.    </strong> A)Resource 2 B)Resource 4 C)Resource 1 D)Resource 3 <strong>Use the Gantt chart and activity list to determine which resource is released from this project for use in another project the earliest.    </strong> A)Resource 2 B)Resource 4 C)Resource 1 D)Resource 3

A)Resource 2
B)Resource 4
C)Resource 1
D)Resource 3
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
58
The most common method for shortening activity durations involves the decision to:

A)eliminate bureaucracy.
B)alter the technology used in the activity.
C)assign more senior personnel to the activity.
D)increase project resources.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
59
Use the Gantt chart and the activity list to determine which resource is used the most. <strong>Use the Gantt chart and the activity list to determine which resource is used the most.    </strong> A)Resource 4 B)Resource 3 C)Resource 1 D)Resource 2 <strong>Use the Gantt chart and the activity list to determine which resource is used the most.    </strong> A)Resource 4 B)Resource 3 C)Resource 1 D)Resource 2

A)Resource 4
B)Resource 3
C)Resource 1
D)Resource 2
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
60
Use the Gantt chart and activity list to determine which resource is used the least. <strong>Use the Gantt chart and activity list to determine which resource is used the least.    </strong> A)Resource 4 B)Resource 2 C)Resource 1 D)Resource 3 <strong>Use the Gantt chart and activity list to determine which resource is used the least.    </strong> A)Resource 4 B)Resource 2 C)Resource 1 D)Resource 3

A)Resource 4
B)Resource 2
C)Resource 1
D)Resource 3
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
61
A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the total cost for completing this project in 50 days? <strong>A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the total cost for completing this project in 50 days?  </strong> A)$253,000 B)$237,000 C)$216,000 D)$207,000

A)$253,000
B)$237,000
C)$216,000
D)$207,000
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
62
What is the late finish for activity D in the network shown in the diagram? <strong>What is the late finish for activity D in the network shown in the diagram?  </strong> A)15 B)16 C)17 D)18

A)15
B)16
C)17
D)18
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
63
An activity on an arrow network:

A)cannot have more arrows than nodes.
B)cannot have more nodes than arrows.
C)has one more node than arrows.
D)has one more arrow than nodes.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
64
Use the information in the table (all times are in days)to determine the lowest extra cost for an 18-day project. <strong>Use the information in the table (all times are in days)to determine the lowest extra cost for an 18-day project.  </strong> A)$380 B)$400 C)$420 D)$440

A)$380
B)$400
C)$420
D)$440
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
65
It costs $75 per day for each day that a construction crew is on site.The project manager determines that most activities can be crashed and has listed the crashing costs next to the minimum time for each activity.Use this information to determine the lowest cost for this project.All times given are in days. <strong>It costs $75 per day for each day that a construction crew is on site.The project manager determines that most activities can be crashed and has listed the crashing costs next to the minimum time for each activity.Use this information to determine the lowest cost for this project.All times given are in days.  </strong> A)$1,800 B)$1,770 C)$1,700 D)$1,630

A)$1,800
B)$1,770
C)$1,700
D)$1,630
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
66
A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $250 per week for every week the project extends beyond 50 weeks.What is the cost of the least expensive project possible? <strong>A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $250 per week for every week the project extends beyond 50 weeks.What is the cost of the least expensive project possible?  </strong> A)$18,100 B)$19,350 C)$17,416.67 D)$16,110

A)$18,100
B)$19,350
C)$17,416.67
D)$16,110
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
67
A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $5,000 per week for every week the project extends beyond 45 weeks.What is the lowest total cost for completing this project? <strong>A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $5,000 per week for every week the project extends beyond 45 weeks.What is the lowest total cost for completing this project?  </strong> A)$222,667 B)$217,000 C)$222,000 D)$208,000

A)$222,667
B)$217,000
C)$222,000
D)$208,000
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
68
Dummy activities have a duration equal to the:

A)slack on the critical path.
B)length of the predecessor.
C)length of the successor.
D)lag needed to preserve network logic.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
69
A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the lowest total cost for completing this project in 45 days? <strong>A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the lowest total cost for completing this project in 45 days?  </strong> A)$222,667 B)$243,675 C)$258,333 D)$272,500

A)$222,667
B)$243,675
C)$258,333
D)$272,500
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
70
The critical path of this network is: <strong>The critical path of this network is:  </strong> A)14. B)15. C)12. D)13.

A)14.
B)15.
C)12.
D)13.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
71
Use the information in the table (all times are in days)to determine the lowest extra cost for a 20-day project. <strong>Use the information in the table (all times are in days)to determine the lowest extra cost for a 20-day project.  </strong> A)$200 B)$130 C)$120 D)$100

A)$200
B)$130
C)$120
D)$100
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
72
The fastest completion time for this project is: <strong>The fastest completion time for this project is:  </strong> A)14. B)15. C)16. D)17.

A)14.
B)15.
C)16.
D)17.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
73
A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $250 per week for every week the project extends beyond 50 weeks.What is the duration of the least expensive project possible? <strong>A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $250 per week for every week the project extends beyond 50 weeks.What is the duration of the least expensive project possible?  </strong> A)60 weeks B)57 weeks C)53 weeks D)50 weeks

A)60 weeks
B)57 weeks
C)53 weeks
D)50 weeks
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
74
The AOA network described by this table needs: <strong>The AOA network described by this table needs:  </strong> A)zero dummy activities. B)one dummy activity. C)two dummy activities. D)three dummy activities.

A)zero dummy activities.
B)one dummy activity.
C)two dummy activities.
D)three dummy activities.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
75
The AOA network described by this table needs: <strong>The AOA network described by this table needs:  </strong> A)zero dummy activities. B)one dummy activity. C)two dummy activities. D)three dummy activities.

A)zero dummy activities.
B)one dummy activity.
C)two dummy activities.
D)three dummy activities.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
76
A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the lowest total cost for completing this project in 55 weeks? <strong>A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the lowest total cost for completing this project in 55 weeks?  </strong> A)$16,950 B)$15,000 C)$16,350 D)$15,350

A)$16,950
B)$15,000
C)$16,350
D)$15,350
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
77
What information is NOT included in the nodes for an AOA network?

A)label
B)early start time
C)late finish time
D)early finish time
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
78
Use the information in the table (all times are in days)to determine the lowest cost minimum completion time? <strong>Use the information in the table (all times are in days)to determine the lowest cost minimum completion time?  </strong> A)$1,040 B)$1,020 C)$740 D)$720

A)$1,040
B)$1,020
C)$740
D)$720
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
79
A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $6,000 per week for every week the project extends beyond 40 weeks.What is the lowest total cost for completing this project? <strong>A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $6,000 per week for every week the project extends beyond 40 weeks.What is the lowest total cost for completing this project?  </strong> A)$234,000 B)$255,600 C)$248,333 D)$252,000

A)$234,000
B)$255,600
C)$248,333
D)$252,000
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
80
A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the lowest total cost for completing this project in 40 days? <strong>A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the lowest total cost for completing this project in 40 days?  </strong> A)$242,667 B)$255,600 C)$263,333 D)$272,500

A)$242,667
B)$255,600
C)$263,333
D)$272,500
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.
فتح الحزمة
k this deck
locked card icon
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 110 في هذه المجموعة.