Deck 34: Project Scheduling
1
Approximately what percent of the project time line should be devoted to each of the activities listed below?
Planning ______
Analysis ______
Design ______
Coding ______
Testing ______
If you could expend more time in one activity,which would have the highest likelihood of improving software quality? Why?
Planning ______
Analysis ______
Design ______
Coding ______
Testing ______
If you could expend more time in one activity,which would have the highest likelihood of improving software quality? Why?
Planning 2-3%
Analysis 10-25%
Design 20-25%
Coding 15-20%
Testing 30-40%
Expend more time in design because design is the place where quality is built into a product.
Analysis 10-25%
Design 20-25%
Coding 15-20%
Testing 30-40%
Expend more time in design because design is the place where quality is built into a product.
2
What is "earned value analysis" as it relates to project scheduling?
Earned value is a measure of progress.It enables you to assess the "percent of completeness" of a project using quantitative analysis rather than rely on a gut feeling.
Final Exam Question
Final Exam Question
3
In software project scheduling work,what is a task (or activity)network?
A task network is a graphic representation depicting software engineering task dependencies and the workflow for a project.
4
List 3 principles for scheduling software projects.