Deck 12: Resource Management

ملء الشاشة (f)
exit full mode
سؤال
Splitting activities refers to:

A) Assigning the work to two or more workers.
B) Assigning the work to two or more days.
C) Starting an activity, interrupting it to use a resource elsewhere, and then returning to work on the activity.
D) Breaking each non-critical activity into two or more components and subdividing the resources they use by a similar divisor.
استخدم زر المسافة أو
up arrow
down arrow
لقلب البطاقة.
سؤال
Which of the following would NOT typically be displayed in a resource loading table?

A) The project team members
B) The tasks the project team members have been assigned
C) The time the activities are expected to take
D) The expenses allocated to the activities
سؤال
A resource loading form can be generated once you have developed:

A) The activity network and productivity profile.
B) The work breakdown structure and the project budget.
C) The activity network and the work breakdown structure.
D) The project budget and the productivity profile.
سؤال
A resource loading chart displays:

A) The amount of time needed as a function of resource limits.
B) The amount of resources required as a function of time.
C) The amount of time needed as a function of money.
D) The amount of resources needed as a function of money.
سؤال
The assistant professor frantically prepared his tenure and promotion dossier for the personnel committee.The deadline loomed and he had several other things to accomplish - deadlines for papers and key correspondence that demanded replies.By his reckoning,he probably didn't have enough toner,paper,or computing time available to accomplish all that he had left to do.His project is unfortunately:

A) Time constrained.
B) Resource constrained.
C) Mix-constrained.
D) Personally constrained.
سؤال
The independent axis of a resource loading chart is in units of:

A) Nothing - it is simply relative magnitude.
B) Resources.
C) Time.
D) Workers/people.
سؤال
A resource loading form is also known as a(n):

A) Load schedule.
B) Resource usage calendar.
C) Activity resource schedule.
D) Network resource profile.
سؤال
Use the resource loading table to determine which of the Yaki sisters is over-allocated. <strong>Use the resource loading table to determine which of the Yaki sisters is over-allocated.  </strong> A) Suki B) Terri C) both D) Can't be determined from the information provided. <div style=padding-top: 35px>

A) Suki
B) Terri
C) both
D) Can't be determined from the information provided.
سؤال
The best method for establishing the existence of resource conflicts across project activities uses resource-loading charts.
سؤال
A project that must be finished by December 31st is:

A) Time-constrained.
B) Resource-constrained.
C) Mix-constrained.
D) Capacity-constrained.
سؤال
The One Shovel Construction Company is hired by the City of Edmond to lay sewer pipe from the east end of town to the west end of town using their single shovel to dig the trench.While the crew would like to begin at both ends simultaneously and have a dramatic ceremony when both ends meet,they find themselves with a bit of a:

A) Time constraint.
B) Resource constraint.
C) Mixed constraint.
D) Partial network.
سؤال
In addition to identifying overallocation of people,a resource usage table can also be used to identify overallocation of:

A) Tasks.
B) Managers.
C) Money.
D) Resources.
سؤال
The BEST method for establishing the existence of resource conflicts across project activities uses:

A) Gantt charts.
B) Network diagrams.
C) Pareto diagrams.
D) Resource loading charts.
سؤال
What information is usually provided on a resource-usage calendar?

A) The tasks, the precedence requirements, and the money per unit time needed to reduce them.
B) The personnel, their hourly wage or salary, and the number of hours per week they are available.
C) The personnel, their responsibility for certain tasks, and the number of hours per week they are available.
D) The tasks, the people and equipment available, and the ownership and reporting relationships among them.
سؤال
Placing resources on a detailed schedule of tasks is referred to as:

A) Placing.
B) Rectifying.
C) Loading.
D) Dragging.
سؤال
In general,when constructing a resource loading chart,one should avoid:

A) Splitting the activities.
B) Obeying the pre-established precedence requirements for the activities.
C) Identifying the slack for each activity.
D) Changing the duration of the activities.
سؤال
The amounts of individual resources that a schedule requires during specific time periods is referred to as the resource's:

A) Loading.
B) Capacity.
C) Constraint.
D) Drag.
سؤال
In a resource constrained project,the work must be finished by a certain time,or date,as efficiently as possible.
سؤال
There is,for almost all projects,usually a dominant constraint that serves as the final arbiter of project decisions.
سؤال
What are the three types of constraints that projects face; provide examples and suggest ways to address these constraints?
سؤال
<strong>  Use this resource load chart to determine which activity uses the greatest number of resources.</strong> A) Activity A B) Activity B C) Activity C D) Activity D <div style=padding-top: 35px>
Use this resource load chart to determine which activity uses the greatest number of resources.

A) Activity A
B) Activity B
C) Activity C
D) Activity D
سؤال
Consider the project that is neatly summarized in this table.What are the top two priority activities when using the smallest duration leveling heuristic? <strong>Consider the project that is neatly summarized in this table.What are the top two priority activities when using the smallest duration leveling heuristic?  </strong> A) B and C B) A and B C) C and E D) A and E <div style=padding-top: 35px>

A) B and C
B) A and B
C) C and E
D) A and E
سؤال
Resource loading charts are used to display the amount of resources required as a function of time on a graph.
سؤال
All that is needed to create a resource loading calendar is the work breakdown structure and the activity network.
سؤال
Consider the project that is neatly summarized in this table.What are the top priority activity when using the most successors leveling heuristic? <strong>Consider the project that is neatly summarized in this table.What are the top priority activity when using the most successors leveling heuristic?  </strong> A) A B) B C) C D) D <div style=padding-top: 35px>

A) A
B) B
C) C
D) D
سؤال
<strong>  Use this resource load chart to determine which activity is the longest in duration.</strong> A) Activity A B) Activity B C) Activity C D) Activity D <div style=padding-top: 35px>
Use this resource load chart to determine which activity is the longest in duration.

A) Activity A
B) Activity B
C) Activity C
D) Activity D
سؤال
Consider the project that is neatly summarized in this table.What are the lowest priority activities when using the smallest amount of slack leveling heuristic? <strong>Consider the project that is neatly summarized in this table.What are the lowest priority activities when using the smallest amount of slack leveling heuristic?  </strong> A) A and B B) C and E C) A and D D) B and D <div style=padding-top: 35px>

A) A and B
B) C and E
C) A and D
D) B and D
سؤال
Consider the project that is neatly summarized in this table.What are the highest priority activities when using the most resources required leveling heuristic? <strong>Consider the project that is neatly summarized in this table.What are the highest priority activities when using the most resources required leveling heuristic?  </strong> A) E and B B) C and E C) C and D D) B and D <div style=padding-top: 35px>

A) E and B
B) C and E
C) C and D
D) B and D
سؤال
Create a resource loading chart for the project described by this network. Create a resource loading chart for the project described by this network.  <div style=padding-top: 35px>
سؤال
<strong>  The project represented by this resource load chart has a maximum limit of 6 units of resource activity in any day.Which activity could be split to help the project team finish on time and meet the resource cap?</strong> A) Activity A B) Activities B and C C) Activities D and E D) Activity E and F <div style=padding-top: 35px>
The project represented by this resource load chart has a maximum limit of 6 units of resource activity in any day.Which activity could be split to help the project team finish on time and meet the resource cap?

A) Activity A
B) Activities B and C
C) Activities D and E
D) Activity E and F
سؤال
<strong>  Use this resource load chart to determine which activity uses the fewest resources.</strong> A) Activity A B) Activity B C) Activity C D) Activity D <div style=padding-top: 35px>
Use this resource load chart to determine which activity uses the fewest resources.

A) Activity A
B) Activity B
C) Activity C
D) Activity D
سؤال
Create a resource loading chart using early start times for the project described by this table. Create a resource loading chart using early start times for the project described by this table.  <div style=padding-top: 35px>
سؤال
It's resource leveling time at Satriale's Pork Store and management is pondering four possibilities for task splitting.Which of these activities would be the worst candidate for splitting?

A) Silvio's task, which requires several workers
B) Paulie's task, which is the most expensive
C) Richie's task, which has high start up costs
D) Ralph's task, which is the least expensiv
سؤال
The resource usage table tells us the project team members,their assigned tasks,and the time each task is expected to take.
سؤال
Use this activity precedence table to create a resource loading profile.Activity lengths are given in days and an 8-hour day is assumed. Use this activity precedence table to create a resource loading profile.Activity lengths are given in days and an 8-hour day is assumed.  <div style=padding-top: 35px>
سؤال
Which of these statements about resource management is BEST?

A) A mathematically optimal solution is almost always attainable and should be pursued.
B) The project manager should level resources as to maximize fluctuations from time period to time period.
C) A common approach to analyzing resource-leveling problems is to apply heuristics.
D) Resource management is usually a univariate, combinatorial problem.
سؤال
The process that addresses the complex challenges of project constraints is known as:

A) TOC.
B) Resource leveling.
C) Constraint scheduling.
D) Resource scheduling.
سؤال
Use this resource loading chart and the information in the table to fill in the rest of the table as completely as possible.All activities in the chart are shown with early start times. Use this resource loading chart and the information in the table to fill in the rest of the table as completely as possible.All activities in the chart are shown with early start times.    <div style=padding-top: 35px> Use this resource loading chart and the information in the table to fill in the rest of the table as completely as possible.All activities in the chart are shown with early start times.    <div style=padding-top: 35px>
سؤال
<strong>  The project represented by this resource load chart has a maximum limit of 6 units of resource activity in any day.The first activities that are strong candidates for shifting are:</strong> A) Activity A B) Activities B and C C) Activities D and E D) Activity E and F <div style=padding-top: 35px>
The project represented by this resource load chart has a maximum limit of 6 units of resource activity in any day.The first activities that are strong candidates for shifting are:

A) Activity A
B) Activities B and C
C) Activities D and E
D) Activity E and F
سؤال
If an activity can be split,only the functional portion of the original activity needs to be accomplished for the project to be fully completed.
سؤال
Use the project described in the table to determine the total resources required for activity D if a worker is expected to work half-time (four hours per day)on this project. <strong>Use the project described in the table to determine the total resources required for activity D if a worker is expected to work half-time (four hours per day)on this project.  </strong> A) 6 hours B) 40 hours C) 24 hours D) 48 hours <div style=padding-top: 35px>

A) 6 hours
B) 40 hours
C) 24 hours
D) 48 hours
سؤال
Use the project described in the table to determine the total resources required for this project during week 1 if a worker is expected to devote half-time (four hours per day)to this project.Assume that the project work is conducted on a 5-day-per-week basis. <strong>Use the project described in the table to determine the total resources required for this project during week 1 if a worker is expected to devote half-time (four hours per day)to this project.Assume that the project work is conducted on a 5-day-per-week basis.  </strong> A) 40 hours B) 20 hours C) 28 hours D) 36 hours <div style=padding-top: 35px>

A) 40 hours
B) 20 hours
C) 28 hours
D) 36 hours
سؤال
A project consisting of six activities is shown in the table.If the project manager decides to operate on an early start schedule,which of these days has the highest resource requirements? <strong>A project consisting of six activities is shown in the table.If the project manager decides to operate on an early start schedule,which of these days has the highest resource requirements?  </strong> A) Day 5 B) Day 10 C) Day 15 D) Day 20 <div style=padding-top: 35px>

A) Day 5
B) Day 10
C) Day 15
D) Day 20
سؤال
A project consisting of six activities is shown in the table.If the project manager decides to operate on an early start schedule,which of these days has the lowest resource requirements? <strong>A project consisting of six activities is shown in the table.If the project manager decides to operate on an early start schedule,which of these days has the lowest resource requirements?  </strong> A) Day 15 B) Day 19 C) Day 24 D) Day 29 <div style=padding-top: 35px>

A) Day 15
B) Day 19
C) Day 24
D) Day 29
سؤال
The project described in the table uses the same resource for activities A,B,C,and D.Which activity gets first use of this resource if we assign the resource based on the activity with the lowest activity identification number? <strong>The project described in the table uses the same resource for activities A,B,C,and D.Which activity gets first use of this resource if we assign the resource based on the activity with the lowest activity identification number?  </strong> A) Activity A B) Activity B C) Activity C D) Activity D <div style=padding-top: 35px>

A) Activity A
B) Activity B
C) Activity C
D) Activity D
سؤال
The project described in the table uses the same resource for activities A,B,C,and D.Which activity gets first use of this resource if we assign the resource based on the activity with the greatest number of successor tasks? <strong>The project described in the table uses the same resource for activities A,B,C,and D.Which activity gets first use of this resource if we assign the resource based on the activity with the greatest number of successor tasks?  </strong> A) Activity A B) Activity B C) Activity C D) Activity D <div style=padding-top: 35px>

A) Activity A
B) Activity B
C) Activity C
D) Activity D
سؤال
Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.Which week has the highest resource usage? <strong>Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.Which week has the highest resource usage?  </strong> A) Week 6 B) Week 2 C) Week 4 D) Week 3 <div style=padding-top: 35px>

A) Week 6
B) Week 2
C) Week 4
D) Week 3
سؤال
A project consisting of six activities is shown in the table.If the project manager decides to operate on a late start schedule,which of these days has the highest resource requirements? <strong>A project consisting of six activities is shown in the table.If the project manager decides to operate on a late start schedule,which of these days has the highest resource requirements?  </strong> A) Day 21 B) Day 18 C) Day 24 D) Day 15 <div style=padding-top: 35px>

A) Day 21
B) Day 18
C) Day 24
D) Day 15
سؤال
Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.Which week has the lowest resource usage? <strong>Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.Which week has the lowest resource usage?  </strong> A) Week 3 B) Week 2 C) Week 9 D) Week 8 <div style=padding-top: 35px>

A) Week 3
B) Week 2
C) Week 9
D) Week 8
سؤال
Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.What is the total resource requirement for the project? <strong>Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.What is the total resource requirement for the project?  </strong> A) 365 hours B) 335 hours C) 320 hours D) 310 hours <div style=padding-top: 35px>

A) 365 hours
B) 335 hours
C) 320 hours
D) 310 hours
سؤال
Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.Which week has the lowest resource usage? <strong>Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.Which week has the lowest resource usage?  </strong> A) Week 6 B) Week 2 C) Week 4 D) Week 3 <div style=padding-top: 35px>

A) Week 6
B) Week 2
C) Week 4
D) Week 3
سؤال
Use the project described in the table to determine the total resources required for this project on day 10 if a worker is expected to devote half-time (four hours per day)to this project.Assume that the project work is conducted on a 5-day-per-week basis. <strong>Use the project described in the table to determine the total resources required for this project on day 10 if a worker is expected to devote half-time (four hours per day)to this project.Assume that the project work is conducted on a 5-day-per-week basis.  </strong> A) 5 hours B) 10 hours C) 4 hours D) 8 hours <div style=padding-top: 35px>

A) 5 hours
B) 10 hours
C) 4 hours
D) 8 hours
سؤال
Use the project described in the table to determine the total resources required for this project if a worker is expected to devote half-time (four hours per day)to this project. <strong>Use the project described in the table to determine the total resources required for this project if a worker is expected to devote half-time (four hours per day)to this project.  </strong> A) 36 hours B) 40 hours C) 64 hours D) 128 hours <div style=padding-top: 35px>

A) 36 hours
B) 40 hours
C) 64 hours
D) 128 hours
سؤال
Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.Which week has the highest resource usage? <strong>Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.Which week has the highest resource usage?  </strong> A) Week 4 B) Week 5 C) Week 6 D) Week 7 <div style=padding-top: 35px>

A) Week 4
B) Week 5
C) Week 6
D) Week 7
سؤال
Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.What is the total resource requirement for activity G? <strong>Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.What is the total resource requirement for activity G?  </strong> A) 22 hours B) 88 hours C) 44 hours D) 132 hours <div style=padding-top: 35px>

A) 22 hours
B) 88 hours
C) 44 hours
D) 132 hours
سؤال
Use the project described in the table to determine the total resources required for this project on day 2 if a worker is expected to devote half-time (four hours per day)to this project. <strong>Use the project described in the table to determine the total resources required for this project on day 2 if a worker is expected to devote half-time (four hours per day)to this project.  </strong> A) 4 hours B) 2 hours C) 8 hours D) 6 hours <div style=padding-top: 35px>

A) 4 hours
B) 2 hours
C) 8 hours
D) 6 hours
سؤال
The project described in the table uses the same resource for activities A,B,C,and D.Which activity gets first use of this resource if we assign the resource based on the activity with the shortest duration? <strong>The project described in the table uses the same resource for activities A,B,C,and D.Which activity gets first use of this resource if we assign the resource based on the activity with the shortest duration?  </strong> A) Activity A B) Activity B C) Activity C D) Activity D <div style=padding-top: 35px>

A) Activity A
B) Activity B
C) Activity C
D) Activity D
سؤال
A project consisting of six activities is shown in the table.If the project manager decides to operate on a late start schedule,which of these days has the lowest resource requirements? <strong>A project consisting of six activities is shown in the table.If the project manager decides to operate on a late start schedule,which of these days has the lowest resource requirements?  </strong> A) Day 21 B) Day 18 C) Day 24 D) Day 15 <div style=padding-top: 35px>

A) Day 21
B) Day 18
C) Day 24
D) Day 15
سؤال
The project described in the table uses the same resource for activities A,B,C,and D.Which activity gets first use of this resource if we assign the resource based on the activity with the smallest amount of slack? <strong>The project described in the table uses the same resource for activities A,B,C,and D.Which activity gets first use of this resource if we assign the resource based on the activity with the smallest amount of slack?  </strong> A) Activity A B) Activity B C) Activity C D) Activity D <div style=padding-top: 35px>

A) Activity A
B) Activity B
C) Activity C
D) Activity D
سؤال
Use the project described in the table to determine the total resources required for this project during week 2 if a worker is expected to devote half-time (four hours per day)to this project.Assume that the project work is conducted on a 5-day-per-week basis. <strong>Use the project described in the table to determine the total resources required for this project during week 2 if a worker is expected to devote half-time (four hours per day)to this project.Assume that the project work is conducted on a 5-day-per-week basis.  </strong> A) 30 hours B) 20 hours C) 40 hours D) 36 hours <div style=padding-top: 35px>

A) 30 hours
B) 20 hours
C) 40 hours
D) 36 hours
سؤال
A project consisting of six activities is shown in the table.The project manager must achieve the lowest possible maximum resource requirement while adhering to a 34-day deadline.The lowest possible peak resource demand occurs: <strong>A project consisting of six activities is shown in the table.The project manager must achieve the lowest possible maximum resource requirement while adhering to a 34-day deadline.The lowest possible peak resource demand occurs:  </strong> A) On days 19 through 20 for an early start schedule. B) On days 17 through 20 for a late start schedule. C) On days 13 through 18 for an early start schedule. D) On days 21 through 22 for a late start schedule. <div style=padding-top: 35px>

A) On days 19 through 20 for an early start schedule.
B) On days 17 through 20 for a late start schedule.
C) On days 13 through 18 for an early start schedule.
D) On days 21 through 22 for a late start schedule.
سؤال
A project consists of six activities (all times are given in days).Provide the range of days during which resource usage is highest and the range of days during which resource usage is lowest using an early start schedule.
A project consists of six activities (all times are given in days).Provide the range of days during which resource usage is highest and the range of days during which resource usage is lowest using an early start schedule.  <div style=padding-top: 35px>
سؤال
A project consists of eleven activities (all times are given in days)and has worker requirements as indicated in the table.Assume that all six workers employed by this organization are generalists and are able to work on any of the tasks.What is the fastest the project can be completed? <strong>A project consists of eleven activities (all times are given in days)and has worker requirements as indicated in the table.Assume that all six workers employed by this organization are generalists and are able to work on any of the tasks.What is the fastest the project can be completed?  </strong> A) 54 days B) 56 days C) 58 days D) 60 days <div style=padding-top: 35px>

A) 54 days
B) 56 days
C) 58 days
D) 60 days
سؤال
A project consists of six activities (all times are given in days).Provide the range of days during which resource usage is highest and the range of days during which resource usage is lowest using a late start schedule.
A project consists of six activities (all times are given in days).Provide the range of days during which resource usage is highest and the range of days during which resource usage is lowest using a late start schedule.  <div style=padding-top: 35px>
سؤال
A project consists of eleven activities (all times are given in days)and has worker requirements as indicated in the table.Assume that all four workers employed by this organization are generalists and are able to work on any of the tasks.What day does activity K start under a leveled project with the four worker limitation? <strong>A project consists of eleven activities (all times are given in days)and has worker requirements as indicated in the table.Assume that all four workers employed by this organization are generalists and are able to work on any of the tasks.What day does activity K start under a leveled project with the four worker limitation?  </strong> A) Day 56 B) Day 57 C) Day 58 D) Day 59 <div style=padding-top: 35px>

A) Day 56
B) Day 57
C) Day 58
D) Day 59
سؤال
If resources have been over-allocated,the loading table must be reconfigured to eliminate resource contention points.The project manager can focus solely on the original point of contention since the activities in a project are separate entities.
سؤال
The idea behind resource leveling is to avoid huge swings in utilization of labor and equipment.
سؤال
A project consists of eleven activities (all times are given in days)and has worker requirements as indicated in the table.Assume that all four workers employed by this organization are generalists and are able to work on any of the tasks.What day does activity H start under a leveled project with the four worker limitation? <strong>A project consists of eleven activities (all times are given in days)and has worker requirements as indicated in the table.Assume that all four workers employed by this organization are generalists and are able to work on any of the tasks.What day does activity H start under a leveled project with the four worker limitation?  </strong> A) Day 27 B) Day 28 C) Day 29 D) Day 30 <div style=padding-top: 35px>

A) Day 27
B) Day 28
C) Day 29
D) Day 30
سؤال
A project consists of eleven activities (all times are given in days)and has worker requirements as indicated in the table.Assume that all four workers employed by this organization are generalists and are able to work on any of the tasks.What day does activity C start under a leveled project with the four worker limitation? <strong>A project consists of eleven activities (all times are given in days)and has worker requirements as indicated in the table.Assume that all four workers employed by this organization are generalists and are able to work on any of the tasks.What day does activity C start under a leveled project with the four worker limitation?  </strong> A) Day 13 B) Day 15 C) Day 17 D) Day 19 <div style=padding-top: 35px>

A) Day 13
B) Day 15
C) Day 17
D) Day 19
سؤال
What are any four heuristics for prioritizing resource allocation to activities? Why would a project manager choose one above another?
سؤال
Because resource management is typically a multivariate,combinatorial problem (i.e.,one that is characterized by multiple solutions involving literally dozens,hundreds,or even thousands of activity variables)truly correct answers are not possible.
سؤال
A project consists of eleven activities (all times are given in days)and has worker requirements as indicated in the table.Assume that all four workers employed by this organization are generalists.What schedule is attainable if the number of workers is not an issue? What is the fastest the project can be completed while constrained by the four worker limitation?
A project consists of eleven activities (all times are given in days)and has worker requirements as indicated in the table.Assume that all four workers employed by this organization are generalists.What schedule is attainable if the number of workers is not an issue? What is the fastest the project can be completed while constrained by the four worker limitation?  <div style=padding-top: 35px>
سؤال
A project consists of eleven activities (all times are given in days)and has worker requirements as indicated in the table.Assume that all four workers employed by this organization are generalists and are able to work on any of the tasks.What is the first day where this project exceeds the four worker maximum? <strong>A project consists of eleven activities (all times are given in days)and has worker requirements as indicated in the table.Assume that all four workers employed by this organization are generalists and are able to work on any of the tasks.What is the first day where this project exceeds the four worker maximum?  </strong> A) Day 10 B) Day 11 C) Day 12 D) Day 13 <div style=padding-top: 35px>

A) Day 10
B) Day 11
C) Day 12
D) Day 13
سؤال
A resource loading table is created through identifying the project activities and the resources required for completion and applying this information to the project schedule baseline.
سؤال
A project consists of eleven activities (all times are given in days)and has worker requirements as indicated in the table.Assume that all four workers employed by this organization are generalists and are able to work on any of the tasks.What is the fastest the project can be completed while constrained by the four worker limitation? <strong>A project consists of eleven activities (all times are given in days)and has worker requirements as indicated in the table.Assume that all four workers employed by this organization are generalists and are able to work on any of the tasks.What is the fastest the project can be completed while constrained by the four worker limitation?  </strong> A) 68 days B) 70 days C) 66 days D) 72 days <div style=padding-top: 35px>

A) 68 days
B) 70 days
C) 66 days
D) 72 days
سؤال
The first step in the resource leveling process is to create the resource loading table.
سؤال
Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.If the project manager is told that the total number of hours per week cannot exceed 48,what is the first week that some resource leveling must occur? <strong>Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.If the project manager is told that the total number of hours per week cannot exceed 48,what is the first week that some resource leveling must occur?  </strong> A) Week 2 B) Week 6 C) Week 4 D) Week 5 <div style=padding-top: 35px>

A) Week 2
B) Week 6
C) Week 4
D) Week 5
سؤال
A project consisting of six activities is represented in the resource loading table shown below.There is a limit of 12 hours' time spent on this project for any given day.What activities are involved in the first resource problem in this schedule? <strong>A project consisting of six activities is represented in the resource loading table shown below.There is a limit of 12 hours' time spent on this project for any given day.What activities are involved in the first resource problem in this schedule?  </strong> A) Activities A, B, and C B) Activities B, C, and D C) Activities C, D, and E D) Activities D, E, and F <div style=padding-top: 35px>

A) Activities A, B, and C
B) Activities B, C, and D
C) Activities C, D, and E
D) Activities D, E, and F
سؤال
This resource loading table shows the requirements for a five-task project that has a 42-day duration.The table is designed to reflect an early start schedule.Activity D has only one predecessor and activities C and E have two each.What differences exist between this table and the late start resource table?
This resource loading table shows the requirements for a five-task project that has a 42-day duration.The table is designed to reflect an early start schedule.Activity D has only one predecessor and activities C and E have two each.What differences exist between this table and the late start resource table?  <div style=padding-top: 35px>
سؤال
A project consisting of six activities is represented in the resource loading table shown below.There is a limit of 12 hours' time spent on this project for any given day.Which activity should be left alone if at all possible in the adjustment process among the candidates? <strong>A project consisting of six activities is represented in the resource loading table shown below.There is a limit of 12 hours' time spent on this project for any given day.Which activity should be left alone if at all possible in the adjustment process among the candidates?  </strong> A) Activity B B) Activity C C) Activity F D) Activity E <div style=padding-top: 35px>

A) Activity B
B) Activity C
C) Activity F
D) Activity E
فتح الحزمة
قم بالتسجيل لفتح البطاقات في هذه المجموعة!
Unlock Deck
Unlock Deck
1/99
auto play flashcards
العب
simple tutorial
ملء الشاشة (f)
exit full mode
Deck 12: Resource Management
1
Splitting activities refers to:

A) Assigning the work to two or more workers.
B) Assigning the work to two or more days.
C) Starting an activity, interrupting it to use a resource elsewhere, and then returning to work on the activity.
D) Breaking each non-critical activity into two or more components and subdividing the resources they use by a similar divisor.
C
2
Which of the following would NOT typically be displayed in a resource loading table?

A) The project team members
B) The tasks the project team members have been assigned
C) The time the activities are expected to take
D) The expenses allocated to the activities
D
3
A resource loading form can be generated once you have developed:

A) The activity network and productivity profile.
B) The work breakdown structure and the project budget.
C) The activity network and the work breakdown structure.
D) The project budget and the productivity profile.
C
4
A resource loading chart displays:

A) The amount of time needed as a function of resource limits.
B) The amount of resources required as a function of time.
C) The amount of time needed as a function of money.
D) The amount of resources needed as a function of money.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
5
The assistant professor frantically prepared his tenure and promotion dossier for the personnel committee.The deadline loomed and he had several other things to accomplish - deadlines for papers and key correspondence that demanded replies.By his reckoning,he probably didn't have enough toner,paper,or computing time available to accomplish all that he had left to do.His project is unfortunately:

A) Time constrained.
B) Resource constrained.
C) Mix-constrained.
D) Personally constrained.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
6
The independent axis of a resource loading chart is in units of:

A) Nothing - it is simply relative magnitude.
B) Resources.
C) Time.
D) Workers/people.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
7
A resource loading form is also known as a(n):

A) Load schedule.
B) Resource usage calendar.
C) Activity resource schedule.
D) Network resource profile.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
8
Use the resource loading table to determine which of the Yaki sisters is over-allocated. <strong>Use the resource loading table to determine which of the Yaki sisters is over-allocated.  </strong> A) Suki B) Terri C) both D) Can't be determined from the information provided.

A) Suki
B) Terri
C) both
D) Can't be determined from the information provided.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
9
The best method for establishing the existence of resource conflicts across project activities uses resource-loading charts.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
10
A project that must be finished by December 31st is:

A) Time-constrained.
B) Resource-constrained.
C) Mix-constrained.
D) Capacity-constrained.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
11
The One Shovel Construction Company is hired by the City of Edmond to lay sewer pipe from the east end of town to the west end of town using their single shovel to dig the trench.While the crew would like to begin at both ends simultaneously and have a dramatic ceremony when both ends meet,they find themselves with a bit of a:

A) Time constraint.
B) Resource constraint.
C) Mixed constraint.
D) Partial network.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
12
In addition to identifying overallocation of people,a resource usage table can also be used to identify overallocation of:

A) Tasks.
B) Managers.
C) Money.
D) Resources.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
13
The BEST method for establishing the existence of resource conflicts across project activities uses:

A) Gantt charts.
B) Network diagrams.
C) Pareto diagrams.
D) Resource loading charts.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
14
What information is usually provided on a resource-usage calendar?

A) The tasks, the precedence requirements, and the money per unit time needed to reduce them.
B) The personnel, their hourly wage or salary, and the number of hours per week they are available.
C) The personnel, their responsibility for certain tasks, and the number of hours per week they are available.
D) The tasks, the people and equipment available, and the ownership and reporting relationships among them.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
15
Placing resources on a detailed schedule of tasks is referred to as:

A) Placing.
B) Rectifying.
C) Loading.
D) Dragging.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
16
In general,when constructing a resource loading chart,one should avoid:

A) Splitting the activities.
B) Obeying the pre-established precedence requirements for the activities.
C) Identifying the slack for each activity.
D) Changing the duration of the activities.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
17
The amounts of individual resources that a schedule requires during specific time periods is referred to as the resource's:

A) Loading.
B) Capacity.
C) Constraint.
D) Drag.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
18
In a resource constrained project,the work must be finished by a certain time,or date,as efficiently as possible.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
19
There is,for almost all projects,usually a dominant constraint that serves as the final arbiter of project decisions.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
20
What are the three types of constraints that projects face; provide examples and suggest ways to address these constraints?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
21
<strong>  Use this resource load chart to determine which activity uses the greatest number of resources.</strong> A) Activity A B) Activity B C) Activity C D) Activity D
Use this resource load chart to determine which activity uses the greatest number of resources.

A) Activity A
B) Activity B
C) Activity C
D) Activity D
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
22
Consider the project that is neatly summarized in this table.What are the top two priority activities when using the smallest duration leveling heuristic? <strong>Consider the project that is neatly summarized in this table.What are the top two priority activities when using the smallest duration leveling heuristic?  </strong> A) B and C B) A and B C) C and E D) A and E

A) B and C
B) A and B
C) C and E
D) A and E
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
23
Resource loading charts are used to display the amount of resources required as a function of time on a graph.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
24
All that is needed to create a resource loading calendar is the work breakdown structure and the activity network.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
25
Consider the project that is neatly summarized in this table.What are the top priority activity when using the most successors leveling heuristic? <strong>Consider the project that is neatly summarized in this table.What are the top priority activity when using the most successors leveling heuristic?  </strong> A) A B) B C) C D) D

A) A
B) B
C) C
D) D
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
26
<strong>  Use this resource load chart to determine which activity is the longest in duration.</strong> A) Activity A B) Activity B C) Activity C D) Activity D
Use this resource load chart to determine which activity is the longest in duration.

A) Activity A
B) Activity B
C) Activity C
D) Activity D
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
27
Consider the project that is neatly summarized in this table.What are the lowest priority activities when using the smallest amount of slack leveling heuristic? <strong>Consider the project that is neatly summarized in this table.What are the lowest priority activities when using the smallest amount of slack leveling heuristic?  </strong> A) A and B B) C and E C) A and D D) B and D

A) A and B
B) C and E
C) A and D
D) B and D
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
28
Consider the project that is neatly summarized in this table.What are the highest priority activities when using the most resources required leveling heuristic? <strong>Consider the project that is neatly summarized in this table.What are the highest priority activities when using the most resources required leveling heuristic?  </strong> A) E and B B) C and E C) C and D D) B and D

A) E and B
B) C and E
C) C and D
D) B and D
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
29
Create a resource loading chart for the project described by this network. Create a resource loading chart for the project described by this network.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
30
<strong>  The project represented by this resource load chart has a maximum limit of 6 units of resource activity in any day.Which activity could be split to help the project team finish on time and meet the resource cap?</strong> A) Activity A B) Activities B and C C) Activities D and E D) Activity E and F
The project represented by this resource load chart has a maximum limit of 6 units of resource activity in any day.Which activity could be split to help the project team finish on time and meet the resource cap?

A) Activity A
B) Activities B and C
C) Activities D and E
D) Activity E and F
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
31
<strong>  Use this resource load chart to determine which activity uses the fewest resources.</strong> A) Activity A B) Activity B C) Activity C D) Activity D
Use this resource load chart to determine which activity uses the fewest resources.

A) Activity A
B) Activity B
C) Activity C
D) Activity D
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
32
Create a resource loading chart using early start times for the project described by this table. Create a resource loading chart using early start times for the project described by this table.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
33
It's resource leveling time at Satriale's Pork Store and management is pondering four possibilities for task splitting.Which of these activities would be the worst candidate for splitting?

A) Silvio's task, which requires several workers
B) Paulie's task, which is the most expensive
C) Richie's task, which has high start up costs
D) Ralph's task, which is the least expensiv
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
34
The resource usage table tells us the project team members,their assigned tasks,and the time each task is expected to take.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
35
Use this activity precedence table to create a resource loading profile.Activity lengths are given in days and an 8-hour day is assumed. Use this activity precedence table to create a resource loading profile.Activity lengths are given in days and an 8-hour day is assumed.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
36
Which of these statements about resource management is BEST?

A) A mathematically optimal solution is almost always attainable and should be pursued.
B) The project manager should level resources as to maximize fluctuations from time period to time period.
C) A common approach to analyzing resource-leveling problems is to apply heuristics.
D) Resource management is usually a univariate, combinatorial problem.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
37
The process that addresses the complex challenges of project constraints is known as:

A) TOC.
B) Resource leveling.
C) Constraint scheduling.
D) Resource scheduling.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
38
Use this resource loading chart and the information in the table to fill in the rest of the table as completely as possible.All activities in the chart are shown with early start times. Use this resource loading chart and the information in the table to fill in the rest of the table as completely as possible.All activities in the chart are shown with early start times.    Use this resource loading chart and the information in the table to fill in the rest of the table as completely as possible.All activities in the chart are shown with early start times.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
39
<strong>  The project represented by this resource load chart has a maximum limit of 6 units of resource activity in any day.The first activities that are strong candidates for shifting are:</strong> A) Activity A B) Activities B and C C) Activities D and E D) Activity E and F
The project represented by this resource load chart has a maximum limit of 6 units of resource activity in any day.The first activities that are strong candidates for shifting are:

A) Activity A
B) Activities B and C
C) Activities D and E
D) Activity E and F
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
40
If an activity can be split,only the functional portion of the original activity needs to be accomplished for the project to be fully completed.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
41
Use the project described in the table to determine the total resources required for activity D if a worker is expected to work half-time (four hours per day)on this project. <strong>Use the project described in the table to determine the total resources required for activity D if a worker is expected to work half-time (four hours per day)on this project.  </strong> A) 6 hours B) 40 hours C) 24 hours D) 48 hours

A) 6 hours
B) 40 hours
C) 24 hours
D) 48 hours
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
42
Use the project described in the table to determine the total resources required for this project during week 1 if a worker is expected to devote half-time (four hours per day)to this project.Assume that the project work is conducted on a 5-day-per-week basis. <strong>Use the project described in the table to determine the total resources required for this project during week 1 if a worker is expected to devote half-time (four hours per day)to this project.Assume that the project work is conducted on a 5-day-per-week basis.  </strong> A) 40 hours B) 20 hours C) 28 hours D) 36 hours

A) 40 hours
B) 20 hours
C) 28 hours
D) 36 hours
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
43
A project consisting of six activities is shown in the table.If the project manager decides to operate on an early start schedule,which of these days has the highest resource requirements? <strong>A project consisting of six activities is shown in the table.If the project manager decides to operate on an early start schedule,which of these days has the highest resource requirements?  </strong> A) Day 5 B) Day 10 C) Day 15 D) Day 20

A) Day 5
B) Day 10
C) Day 15
D) Day 20
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
44
A project consisting of six activities is shown in the table.If the project manager decides to operate on an early start schedule,which of these days has the lowest resource requirements? <strong>A project consisting of six activities is shown in the table.If the project manager decides to operate on an early start schedule,which of these days has the lowest resource requirements?  </strong> A) Day 15 B) Day 19 C) Day 24 D) Day 29

A) Day 15
B) Day 19
C) Day 24
D) Day 29
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
45
The project described in the table uses the same resource for activities A,B,C,and D.Which activity gets first use of this resource if we assign the resource based on the activity with the lowest activity identification number? <strong>The project described in the table uses the same resource for activities A,B,C,and D.Which activity gets first use of this resource if we assign the resource based on the activity with the lowest activity identification number?  </strong> A) Activity A B) Activity B C) Activity C D) Activity D

A) Activity A
B) Activity B
C) Activity C
D) Activity D
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
46
The project described in the table uses the same resource for activities A,B,C,and D.Which activity gets first use of this resource if we assign the resource based on the activity with the greatest number of successor tasks? <strong>The project described in the table uses the same resource for activities A,B,C,and D.Which activity gets first use of this resource if we assign the resource based on the activity with the greatest number of successor tasks?  </strong> A) Activity A B) Activity B C) Activity C D) Activity D

A) Activity A
B) Activity B
C) Activity C
D) Activity D
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
47
Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.Which week has the highest resource usage? <strong>Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.Which week has the highest resource usage?  </strong> A) Week 6 B) Week 2 C) Week 4 D) Week 3

A) Week 6
B) Week 2
C) Week 4
D) Week 3
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
48
A project consisting of six activities is shown in the table.If the project manager decides to operate on a late start schedule,which of these days has the highest resource requirements? <strong>A project consisting of six activities is shown in the table.If the project manager decides to operate on a late start schedule,which of these days has the highest resource requirements?  </strong> A) Day 21 B) Day 18 C) Day 24 D) Day 15

A) Day 21
B) Day 18
C) Day 24
D) Day 15
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
49
Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.Which week has the lowest resource usage? <strong>Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.Which week has the lowest resource usage?  </strong> A) Week 3 B) Week 2 C) Week 9 D) Week 8

A) Week 3
B) Week 2
C) Week 9
D) Week 8
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
50
Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.What is the total resource requirement for the project? <strong>Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.What is the total resource requirement for the project?  </strong> A) 365 hours B) 335 hours C) 320 hours D) 310 hours

A) 365 hours
B) 335 hours
C) 320 hours
D) 310 hours
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
51
Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.Which week has the lowest resource usage? <strong>Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.Which week has the lowest resource usage?  </strong> A) Week 6 B) Week 2 C) Week 4 D) Week 3

A) Week 6
B) Week 2
C) Week 4
D) Week 3
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
52
Use the project described in the table to determine the total resources required for this project on day 10 if a worker is expected to devote half-time (four hours per day)to this project.Assume that the project work is conducted on a 5-day-per-week basis. <strong>Use the project described in the table to determine the total resources required for this project on day 10 if a worker is expected to devote half-time (four hours per day)to this project.Assume that the project work is conducted on a 5-day-per-week basis.  </strong> A) 5 hours B) 10 hours C) 4 hours D) 8 hours

A) 5 hours
B) 10 hours
C) 4 hours
D) 8 hours
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
53
Use the project described in the table to determine the total resources required for this project if a worker is expected to devote half-time (four hours per day)to this project. <strong>Use the project described in the table to determine the total resources required for this project if a worker is expected to devote half-time (four hours per day)to this project.  </strong> A) 36 hours B) 40 hours C) 64 hours D) 128 hours

A) 36 hours
B) 40 hours
C) 64 hours
D) 128 hours
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
54
Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.Which week has the highest resource usage? <strong>Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.Which week has the highest resource usage?  </strong> A) Week 4 B) Week 5 C) Week 6 D) Week 7

A) Week 4
B) Week 5
C) Week 6
D) Week 7
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
55
Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.What is the total resource requirement for activity G? <strong>Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.What is the total resource requirement for activity G?  </strong> A) 22 hours B) 88 hours C) 44 hours D) 132 hours

A) 22 hours
B) 88 hours
C) 44 hours
D) 132 hours
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
56
Use the project described in the table to determine the total resources required for this project on day 2 if a worker is expected to devote half-time (four hours per day)to this project. <strong>Use the project described in the table to determine the total resources required for this project on day 2 if a worker is expected to devote half-time (four hours per day)to this project.  </strong> A) 4 hours B) 2 hours C) 8 hours D) 6 hours

A) 4 hours
B) 2 hours
C) 8 hours
D) 6 hours
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
57
The project described in the table uses the same resource for activities A,B,C,and D.Which activity gets first use of this resource if we assign the resource based on the activity with the shortest duration? <strong>The project described in the table uses the same resource for activities A,B,C,and D.Which activity gets first use of this resource if we assign the resource based on the activity with the shortest duration?  </strong> A) Activity A B) Activity B C) Activity C D) Activity D

A) Activity A
B) Activity B
C) Activity C
D) Activity D
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
58
A project consisting of six activities is shown in the table.If the project manager decides to operate on a late start schedule,which of these days has the lowest resource requirements? <strong>A project consisting of six activities is shown in the table.If the project manager decides to operate on a late start schedule,which of these days has the lowest resource requirements?  </strong> A) Day 21 B) Day 18 C) Day 24 D) Day 15

A) Day 21
B) Day 18
C) Day 24
D) Day 15
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
59
The project described in the table uses the same resource for activities A,B,C,and D.Which activity gets first use of this resource if we assign the resource based on the activity with the smallest amount of slack? <strong>The project described in the table uses the same resource for activities A,B,C,and D.Which activity gets first use of this resource if we assign the resource based on the activity with the smallest amount of slack?  </strong> A) Activity A B) Activity B C) Activity C D) Activity D

A) Activity A
B) Activity B
C) Activity C
D) Activity D
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
60
Use the project described in the table to determine the total resources required for this project during week 2 if a worker is expected to devote half-time (four hours per day)to this project.Assume that the project work is conducted on a 5-day-per-week basis. <strong>Use the project described in the table to determine the total resources required for this project during week 2 if a worker is expected to devote half-time (four hours per day)to this project.Assume that the project work is conducted on a 5-day-per-week basis.  </strong> A) 30 hours B) 20 hours C) 40 hours D) 36 hours

A) 30 hours
B) 20 hours
C) 40 hours
D) 36 hours
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
61
A project consisting of six activities is shown in the table.The project manager must achieve the lowest possible maximum resource requirement while adhering to a 34-day deadline.The lowest possible peak resource demand occurs: <strong>A project consisting of six activities is shown in the table.The project manager must achieve the lowest possible maximum resource requirement while adhering to a 34-day deadline.The lowest possible peak resource demand occurs:  </strong> A) On days 19 through 20 for an early start schedule. B) On days 17 through 20 for a late start schedule. C) On days 13 through 18 for an early start schedule. D) On days 21 through 22 for a late start schedule.

A) On days 19 through 20 for an early start schedule.
B) On days 17 through 20 for a late start schedule.
C) On days 13 through 18 for an early start schedule.
D) On days 21 through 22 for a late start schedule.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
62
A project consists of six activities (all times are given in days).Provide the range of days during which resource usage is highest and the range of days during which resource usage is lowest using an early start schedule.
A project consists of six activities (all times are given in days).Provide the range of days during which resource usage is highest and the range of days during which resource usage is lowest using an early start schedule.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
63
A project consists of eleven activities (all times are given in days)and has worker requirements as indicated in the table.Assume that all six workers employed by this organization are generalists and are able to work on any of the tasks.What is the fastest the project can be completed? <strong>A project consists of eleven activities (all times are given in days)and has worker requirements as indicated in the table.Assume that all six workers employed by this organization are generalists and are able to work on any of the tasks.What is the fastest the project can be completed?  </strong> A) 54 days B) 56 days C) 58 days D) 60 days

A) 54 days
B) 56 days
C) 58 days
D) 60 days
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
64
A project consists of six activities (all times are given in days).Provide the range of days during which resource usage is highest and the range of days during which resource usage is lowest using a late start schedule.
A project consists of six activities (all times are given in days).Provide the range of days during which resource usage is highest and the range of days during which resource usage is lowest using a late start schedule.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
65
A project consists of eleven activities (all times are given in days)and has worker requirements as indicated in the table.Assume that all four workers employed by this organization are generalists and are able to work on any of the tasks.What day does activity K start under a leveled project with the four worker limitation? <strong>A project consists of eleven activities (all times are given in days)and has worker requirements as indicated in the table.Assume that all four workers employed by this organization are generalists and are able to work on any of the tasks.What day does activity K start under a leveled project with the four worker limitation?  </strong> A) Day 56 B) Day 57 C) Day 58 D) Day 59

A) Day 56
B) Day 57
C) Day 58
D) Day 59
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
66
If resources have been over-allocated,the loading table must be reconfigured to eliminate resource contention points.The project manager can focus solely on the original point of contention since the activities in a project are separate entities.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
67
The idea behind resource leveling is to avoid huge swings in utilization of labor and equipment.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
68
A project consists of eleven activities (all times are given in days)and has worker requirements as indicated in the table.Assume that all four workers employed by this organization are generalists and are able to work on any of the tasks.What day does activity H start under a leveled project with the four worker limitation? <strong>A project consists of eleven activities (all times are given in days)and has worker requirements as indicated in the table.Assume that all four workers employed by this organization are generalists and are able to work on any of the tasks.What day does activity H start under a leveled project with the four worker limitation?  </strong> A) Day 27 B) Day 28 C) Day 29 D) Day 30

A) Day 27
B) Day 28
C) Day 29
D) Day 30
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
69
A project consists of eleven activities (all times are given in days)and has worker requirements as indicated in the table.Assume that all four workers employed by this organization are generalists and are able to work on any of the tasks.What day does activity C start under a leveled project with the four worker limitation? <strong>A project consists of eleven activities (all times are given in days)and has worker requirements as indicated in the table.Assume that all four workers employed by this organization are generalists and are able to work on any of the tasks.What day does activity C start under a leveled project with the four worker limitation?  </strong> A) Day 13 B) Day 15 C) Day 17 D) Day 19

A) Day 13
B) Day 15
C) Day 17
D) Day 19
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
70
What are any four heuristics for prioritizing resource allocation to activities? Why would a project manager choose one above another?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
71
Because resource management is typically a multivariate,combinatorial problem (i.e.,one that is characterized by multiple solutions involving literally dozens,hundreds,or even thousands of activity variables)truly correct answers are not possible.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
72
A project consists of eleven activities (all times are given in days)and has worker requirements as indicated in the table.Assume that all four workers employed by this organization are generalists.What schedule is attainable if the number of workers is not an issue? What is the fastest the project can be completed while constrained by the four worker limitation?
A project consists of eleven activities (all times are given in days)and has worker requirements as indicated in the table.Assume that all four workers employed by this organization are generalists.What schedule is attainable if the number of workers is not an issue? What is the fastest the project can be completed while constrained by the four worker limitation?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
73
A project consists of eleven activities (all times are given in days)and has worker requirements as indicated in the table.Assume that all four workers employed by this organization are generalists and are able to work on any of the tasks.What is the first day where this project exceeds the four worker maximum? <strong>A project consists of eleven activities (all times are given in days)and has worker requirements as indicated in the table.Assume that all four workers employed by this organization are generalists and are able to work on any of the tasks.What is the first day where this project exceeds the four worker maximum?  </strong> A) Day 10 B) Day 11 C) Day 12 D) Day 13

A) Day 10
B) Day 11
C) Day 12
D) Day 13
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
74
A resource loading table is created through identifying the project activities and the resources required for completion and applying this information to the project schedule baseline.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
75
A project consists of eleven activities (all times are given in days)and has worker requirements as indicated in the table.Assume that all four workers employed by this organization are generalists and are able to work on any of the tasks.What is the fastest the project can be completed while constrained by the four worker limitation? <strong>A project consists of eleven activities (all times are given in days)and has worker requirements as indicated in the table.Assume that all four workers employed by this organization are generalists and are able to work on any of the tasks.What is the fastest the project can be completed while constrained by the four worker limitation?  </strong> A) 68 days B) 70 days C) 66 days D) 72 days

A) 68 days
B) 70 days
C) 66 days
D) 72 days
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
76
The first step in the resource leveling process is to create the resource loading table.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
77
Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.If the project manager is told that the total number of hours per week cannot exceed 48,what is the first week that some resource leveling must occur? <strong>Use the information in the table and assume that a worker is expected to devote half-time (four hours per day)to this project with work taking place on a 5-day-per-week basis.If the project manager is told that the total number of hours per week cannot exceed 48,what is the first week that some resource leveling must occur?  </strong> A) Week 2 B) Week 6 C) Week 4 D) Week 5

A) Week 2
B) Week 6
C) Week 4
D) Week 5
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
78
A project consisting of six activities is represented in the resource loading table shown below.There is a limit of 12 hours' time spent on this project for any given day.What activities are involved in the first resource problem in this schedule? <strong>A project consisting of six activities is represented in the resource loading table shown below.There is a limit of 12 hours' time spent on this project for any given day.What activities are involved in the first resource problem in this schedule?  </strong> A) Activities A, B, and C B) Activities B, C, and D C) Activities C, D, and E D) Activities D, E, and F

A) Activities A, B, and C
B) Activities B, C, and D
C) Activities C, D, and E
D) Activities D, E, and F
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
79
This resource loading table shows the requirements for a five-task project that has a 42-day duration.The table is designed to reflect an early start schedule.Activity D has only one predecessor and activities C and E have two each.What differences exist between this table and the late start resource table?
This resource loading table shows the requirements for a five-task project that has a 42-day duration.The table is designed to reflect an early start schedule.Activity D has only one predecessor and activities C and E have two each.What differences exist between this table and the late start resource table?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
80
A project consisting of six activities is represented in the resource loading table shown below.There is a limit of 12 hours' time spent on this project for any given day.Which activity should be left alone if at all possible in the adjustment process among the candidates? <strong>A project consisting of six activities is represented in the resource loading table shown below.There is a limit of 12 hours' time spent on this project for any given day.Which activity should be left alone if at all possible in the adjustment process among the candidates?  </strong> A) Activity B B) Activity C C) Activity F D) Activity E

A) Activity B
B) Activity C
C) Activity F
D) Activity E
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.
فتح الحزمة
k this deck
locked card icon
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 99 في هذه المجموعة.