Deck 9: Managing Project Risk

ملء الشاشة (f)
exit full mode
سؤال
The process of identifying risks to a project and documenting them is called:

A)risk documentation.
B)risk identification.
C)risk elaboration.
D)risk management.
استخدم زر المسافة أو
up arrow
down arrow
لقلب البطاقة.
سؤال
Risk is the process of monitoring identified risks for change and controlling those changes.

A)assessment
B)monitoring and control
C)execution
D)management
سؤال
are risks that remain after avoidance, transfer, or mitigation strategies have been applied.

A)Outstanding risks
B)Enduring risks
C)Remaining risks
D)Residual risks
سؤال
is a risk response strategy in which risks are simply accepted and contingency strategies are planned.

A)Risk acceptance
B)Risk contingency planning.
C)Risk adoption
D)Risk response
سؤال
During initiation, risk most often occurs in the stage.

A)project integration
B)project selection
C)project initiation
D)project evaluation
سؤال
The formal record listing all project risks, explaining the nature of the risk, and management of the risk is called:

A)risk register.
B)risk record.
C)risk list.
D)risk file.
سؤال
Which of the following is NOT a risk management process as identified by the PMBOK guide?

A)Risk management planning
B)Risk identification
C)Risk transference
D)Risk response planning
سؤال
Which of the following is NOT a decision technique used during quantitative risk analysis?

A)Setting realistic targets in terms of scope, cost, and schedule
B)Identifying the most problematic project requirements in terms of scope
C)Identifying the most salient risk in terms of the project
D)Risk quantification in terms of additional scheduling and cost needs
سؤال
A_________ is a documented plan for risk response.

A)risk response register
B)risk document
C)risk response plan
D)risk management plan
سؤال
Which of the following is NOT among the four types of risk specifically associated with IS projects?

A)Finding and assigning skilled personnel
B)Gaining user acceptance
C)Finishing on time and on budget
D)Ongoing changes in technology
سؤال
is a diagramming technique used to evaluate courses of action in terms of their potential cost and benefits relative to other courses of action.

A)Simulation
B)Decision tree analysis
C)Tornado analysis
D)EMV analysis
سؤال
is a risk response strategy in which steps are taken to mitigate risks.

A)Risk mitigation
B)Risk reduction
C)Risk avoidance
D)Risk minimization
سؤال
Risk is concerned with the consequences of the occurrence of a certain risk.

A)impact
B)strength
C)probability
D)likelihood
سؤال
is the analysis of the probability of occurrence and impact of risk on project objectives using numerical techniques.

A)Quantitative risk analysis
B)Probability/impact risk rating matrix
C)Impact/likelihood risk rating matrix
D)Qualitative risk analysis
سؤال
The assessment of the quality of the data used to assess risk is called:

A)project assumption testing.
B)risk data quality assessment.
C)risk assessment data testing.
D)risk data precision estimation.
سؤال
The overall plan used to outline risks and the strategies used to manage them is called:

A)risk response plan.
B)risk management plan.
C)risk baseline.
D)risk outline.
سؤال
is a risk response strategy designed to transfer risk to another party, often through the use of contracts.

A)Risk mitigation
B)Risk transference
C)Risk removal
D)Risk related contractual agreements
سؤال
Risk management planning meetings should be attended by:

A)senior managers.
B)stakeholders.
C)project team leaders.
D)all of the above.
سؤال
is a tool used to determine whether important technical milestones are being met.

A)Technical milestone measurement
B)Technical milestone review
C)Technical performance measurement
D)Technical performance review
سؤال
The process of developing methods for responding to project risks is called:

A)risk mitigation planning.
B)risk reaction planning.
C)risk response planning.
D)risk management.
سؤال
is a technique to examine the potential impact of specific risks to a project.

A)Decision tree analysis
B)Impact analysis
C)Risk analysis
D)Sensitivity analysis
سؤال
The most well- known simulation technique is called:

A)Bellagio analysis.
B)Monte Carlo analysis.
C)Monaco analysis.
D)Venetian analysis.
سؤال
All of the following are elements of a risk response plan EXCEPT:

A)a list of actions to be used to implement the risk response strategies.
B)the roles and responsibilities of any risk owners.
C)budget and schedule information in terms of risk response.
D)the roles and responsibilities of project stakeholders.
سؤال
Tornado analysis is a form of:

A)EMV analysis.
B)graphical analysis.
C)sensitivity analysis.
D)simulation.
سؤال
Changing industry standards are an example of:

A)external risks.
B)project management risks.
C)organizational risks.
D)technical, quality, or performance risks.
سؤال
The systematic approach to planning the risk management activities of a given project is called:

A)risk response planning.
B)risk mitigation planning.
C)risk management planning.
D)risk identification.
سؤال
Poor project planning is an example of:

A)project management risks.
B)technical, quality, or performance risks.
C)organizational risks.
D)external risks.
سؤال
is a statistical technique that captures the average value of potential projects by analyzing the likelihood of possible project outcomes as well as each outcome's financial consequences.

A)Simulation
B)EMV analysis
C)Decision tree analysis
D)Tornado analysis
سؤال
Events that serve as early warnings of risk are called:

A)actuators.
B)warnings.
C)triggers.
D)risk advisories.
سؤال
is a risk response strategy designed to avoid potential project risks.

A)Risk avoidance
B)Risk mitigation
C)Risk transference
D)Risk acceptance
سؤال
are risks resulting from the application of a risk response strategy.

A)Secondary risks
B)Resultant risks
C)Resulting risks
D)Derived risks
سؤال
is a technique used to perform what- if analyses to determine the impact of a given situation on a project objective.

A)EMV analysis
B)Tornado analysis
C)Simulation
D)Decision tree analysis
سؤال
are reviews designed to review existing risk activities and to monitor any changes to the project.

A)Project risk response audits
B)Periodic risk assessments
C)Project risk assessments
D)Periodic project risk reviews
سؤال
Inconsistent goals are an example of:

A)project management risks.
B)organizational risks.
C)external risks.
D)technical, quality, or performance risks.
سؤال
Risk management are used to provide organizational standards for project risk management.

A)schedules
B)matrices
C)templates
D)plans
سؤال
is a technique used to analyze project risk in terms of its probability of occurrence and its impact on project outcomes.

A)Probability/impact risk rating matrix
B)Impact/likelihood risk rating matrix
C)Qualitative risk analysis
D)Quantitative risk analysis
سؤال
is the establishment of probabilities regarding both the impact and the likelihood of specific risk occurrence.

A)Impact/likelihood analysis
B)Qualitative risk analysis
C)Probability/impact analysis
D)Quantitative risk analysis
سؤال
A technique used during qualitative risk analysis to test the assumptions made during risk identification is called:

A)risk assumption testing.
B)project assumption testing.
C)risk quality assessment.
D)project quality testing.
سؤال
The review of organizational information to aid during risk identification is called:

A)project file review.
B)risk review.
C)reviews of published information.
D)documentation review.
سؤال
Project team members responsible for specific risk activity decisions are called:

A)risk mitigators.
B)risk deciders.
C)risk managers.
D)risk owners.
سؤال
Periodic risk response audits are designed to evaluate the effectiveness of _________and risk owners.
سؤال
_________involves the establishment of probabilities regarding both the impact and the likelihood of specific risk occurrence.
سؤال
It is important to plan a risk management strategy that __________ the type of risk that may be encountered along with the importance of the project to the organization.
سؤال
_________is the process of developing methods for responding to risks.
سؤال
_________is a risk response strategy in which risks are simply accepted and contingency strategies are planned.
سؤال
The risk _________is a formal record listing all project risks, explaining the nature of the risk and management of the risk.
سؤال
Periodic project risk reviews are designed to review existing_________ and to monitor any changes to the project.
سؤال
are designed to evaluate the effectiveness of risk response strategies and risk owners.

A)Project risk response audits
B)Project risk assessments
C)Periodic project risk reviews
D)Periodic risk assessments
سؤال
A graphical depiction of EMV can be captured in a_________ .
سؤال
A __________ matrix is used analyze project risk in terms of its probability of occurrence and its impact on project outcomes.
سؤال
_________graphically represent potential problems while accounting for causal influences, time, and other relationships between project activities and outcomes.
سؤال
A _________is a documented plan for risk response.
سؤال
_________is a risk response strategy in which steps are taken to mitigate project risk.
سؤال
Legal events are an example of:

A)external risks.
B)technical, quality, or performance risks.
C)project management risks.
D)organizational risks.
سؤال
Risk _ is concerned with the likelihood that a certain risk will occur.

A)likelihood
B)probability
C)impact
D)strength
سؤال
Diagramming tools commonly used during risk identification include:

A)influence diagrams.
B)cause and effect diagrams.
C)system or process flow charts.
D)all of the above.
سؤال
Risk identification consists of identifying potential risks to a project and_________ .
سؤال
Project risk is an uncertain event or condition that, if it occurs, has a effect on a project objective.

A)positive or negative
B)negative
C)positive
D)devastating
سؤال
Conflicting priorities among users is an example of_________ .
سؤال
Information gathering techniques commonly used during risk identification include:

A)Delphi technique.
B)interviewing.
C)brainstorming.
D)all of the above.
سؤال
_________are those risks that remain after avoidance, transfer, or mitigation strategies have been applied.
سؤال
_________is used to test the assumptions made during risk identification.
سؤال
Risks associated with ongoing changes _________are unique to IS projects.
سؤال
_________is a term for any contracts for the purpose of risk transference during the project.
سؤال
_________depict the interrelations among project activities and can be used to help managers determine the risks associated with those interrelations.
سؤال
_________is a statistical technique that captures the average value of potential projects by analyzing the likelihood of possible project outcomes as well as each outcome's financial consequences.
سؤال
A tornado analysis shows, in descending order, which risk causes the_________ on some outcome.
سؤال
_________is a technique used to examine the potential impact of specific risks to a project.
سؤال
_________involves a systematic approach to planning the risk management activities of a given project.
سؤال
Project risk is an uncertain event or condition that, if it occurs, has a _________effect on a project objective.
سؤال
Tornado analysis is an example of a _________.
سؤال
Risk owners are project team members responsible for specific_________ .
سؤال
Environmental concerns are an example of _________.
سؤال
Changing industry standards are an example of __________ .
سؤال
_________are those risks resulting from the application of a risk response strategy.
سؤال
Risks associated with poor project planning are an example of_________ .
سؤال
_________are events that serve as early warnings of risks.
سؤال
_________is a strategy designed to avoid potential risks.
سؤال
Brainstorming, the Delphi technique, or interviewing are _________used during risk identification.
سؤال
Risk management _________are used to provide organizational standards for project risk management.
فتح الحزمة
قم بالتسجيل لفتح البطاقات في هذه المجموعة!
Unlock Deck
Unlock Deck
1/111
auto play flashcards
العب
simple tutorial
ملء الشاشة (f)
exit full mode
Deck 9: Managing Project Risk
1
The process of identifying risks to a project and documenting them is called:

A)risk documentation.
B)risk identification.
C)risk elaboration.
D)risk management.
B
2
Risk is the process of monitoring identified risks for change and controlling those changes.

A)assessment
B)monitoring and control
C)execution
D)management
B
3
are risks that remain after avoidance, transfer, or mitigation strategies have been applied.

A)Outstanding risks
B)Enduring risks
C)Remaining risks
D)Residual risks
D
4
is a risk response strategy in which risks are simply accepted and contingency strategies are planned.

A)Risk acceptance
B)Risk contingency planning.
C)Risk adoption
D)Risk response
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
5
During initiation, risk most often occurs in the stage.

A)project integration
B)project selection
C)project initiation
D)project evaluation
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
6
The formal record listing all project risks, explaining the nature of the risk, and management of the risk is called:

A)risk register.
B)risk record.
C)risk list.
D)risk file.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
7
Which of the following is NOT a risk management process as identified by the PMBOK guide?

A)Risk management planning
B)Risk identification
C)Risk transference
D)Risk response planning
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
8
Which of the following is NOT a decision technique used during quantitative risk analysis?

A)Setting realistic targets in terms of scope, cost, and schedule
B)Identifying the most problematic project requirements in terms of scope
C)Identifying the most salient risk in terms of the project
D)Risk quantification in terms of additional scheduling and cost needs
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
9
A_________ is a documented plan for risk response.

A)risk response register
B)risk document
C)risk response plan
D)risk management plan
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
10
Which of the following is NOT among the four types of risk specifically associated with IS projects?

A)Finding and assigning skilled personnel
B)Gaining user acceptance
C)Finishing on time and on budget
D)Ongoing changes in technology
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
11
is a diagramming technique used to evaluate courses of action in terms of their potential cost and benefits relative to other courses of action.

A)Simulation
B)Decision tree analysis
C)Tornado analysis
D)EMV analysis
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
12
is a risk response strategy in which steps are taken to mitigate risks.

A)Risk mitigation
B)Risk reduction
C)Risk avoidance
D)Risk minimization
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
13
Risk is concerned with the consequences of the occurrence of a certain risk.

A)impact
B)strength
C)probability
D)likelihood
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
14
is the analysis of the probability of occurrence and impact of risk on project objectives using numerical techniques.

A)Quantitative risk analysis
B)Probability/impact risk rating matrix
C)Impact/likelihood risk rating matrix
D)Qualitative risk analysis
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
15
The assessment of the quality of the data used to assess risk is called:

A)project assumption testing.
B)risk data quality assessment.
C)risk assessment data testing.
D)risk data precision estimation.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
16
The overall plan used to outline risks and the strategies used to manage them is called:

A)risk response plan.
B)risk management plan.
C)risk baseline.
D)risk outline.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
17
is a risk response strategy designed to transfer risk to another party, often through the use of contracts.

A)Risk mitigation
B)Risk transference
C)Risk removal
D)Risk related contractual agreements
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
18
Risk management planning meetings should be attended by:

A)senior managers.
B)stakeholders.
C)project team leaders.
D)all of the above.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
19
is a tool used to determine whether important technical milestones are being met.

A)Technical milestone measurement
B)Technical milestone review
C)Technical performance measurement
D)Technical performance review
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
20
The process of developing methods for responding to project risks is called:

A)risk mitigation planning.
B)risk reaction planning.
C)risk response planning.
D)risk management.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
21
is a technique to examine the potential impact of specific risks to a project.

A)Decision tree analysis
B)Impact analysis
C)Risk analysis
D)Sensitivity analysis
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
22
The most well- known simulation technique is called:

A)Bellagio analysis.
B)Monte Carlo analysis.
C)Monaco analysis.
D)Venetian analysis.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
23
All of the following are elements of a risk response plan EXCEPT:

A)a list of actions to be used to implement the risk response strategies.
B)the roles and responsibilities of any risk owners.
C)budget and schedule information in terms of risk response.
D)the roles and responsibilities of project stakeholders.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
24
Tornado analysis is a form of:

A)EMV analysis.
B)graphical analysis.
C)sensitivity analysis.
D)simulation.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
25
Changing industry standards are an example of:

A)external risks.
B)project management risks.
C)organizational risks.
D)technical, quality, or performance risks.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
26
The systematic approach to planning the risk management activities of a given project is called:

A)risk response planning.
B)risk mitigation planning.
C)risk management planning.
D)risk identification.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
27
Poor project planning is an example of:

A)project management risks.
B)technical, quality, or performance risks.
C)organizational risks.
D)external risks.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
28
is a statistical technique that captures the average value of potential projects by analyzing the likelihood of possible project outcomes as well as each outcome's financial consequences.

A)Simulation
B)EMV analysis
C)Decision tree analysis
D)Tornado analysis
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
29
Events that serve as early warnings of risk are called:

A)actuators.
B)warnings.
C)triggers.
D)risk advisories.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
30
is a risk response strategy designed to avoid potential project risks.

A)Risk avoidance
B)Risk mitigation
C)Risk transference
D)Risk acceptance
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
31
are risks resulting from the application of a risk response strategy.

A)Secondary risks
B)Resultant risks
C)Resulting risks
D)Derived risks
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
32
is a technique used to perform what- if analyses to determine the impact of a given situation on a project objective.

A)EMV analysis
B)Tornado analysis
C)Simulation
D)Decision tree analysis
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
33
are reviews designed to review existing risk activities and to monitor any changes to the project.

A)Project risk response audits
B)Periodic risk assessments
C)Project risk assessments
D)Periodic project risk reviews
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
34
Inconsistent goals are an example of:

A)project management risks.
B)organizational risks.
C)external risks.
D)technical, quality, or performance risks.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
35
Risk management are used to provide organizational standards for project risk management.

A)schedules
B)matrices
C)templates
D)plans
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
36
is a technique used to analyze project risk in terms of its probability of occurrence and its impact on project outcomes.

A)Probability/impact risk rating matrix
B)Impact/likelihood risk rating matrix
C)Qualitative risk analysis
D)Quantitative risk analysis
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
37
is the establishment of probabilities regarding both the impact and the likelihood of specific risk occurrence.

A)Impact/likelihood analysis
B)Qualitative risk analysis
C)Probability/impact analysis
D)Quantitative risk analysis
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
38
A technique used during qualitative risk analysis to test the assumptions made during risk identification is called:

A)risk assumption testing.
B)project assumption testing.
C)risk quality assessment.
D)project quality testing.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
39
The review of organizational information to aid during risk identification is called:

A)project file review.
B)risk review.
C)reviews of published information.
D)documentation review.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
40
Project team members responsible for specific risk activity decisions are called:

A)risk mitigators.
B)risk deciders.
C)risk managers.
D)risk owners.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
41
Periodic risk response audits are designed to evaluate the effectiveness of _________and risk owners.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
42
_________involves the establishment of probabilities regarding both the impact and the likelihood of specific risk occurrence.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
43
It is important to plan a risk management strategy that __________ the type of risk that may be encountered along with the importance of the project to the organization.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
44
_________is the process of developing methods for responding to risks.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
45
_________is a risk response strategy in which risks are simply accepted and contingency strategies are planned.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
46
The risk _________is a formal record listing all project risks, explaining the nature of the risk and management of the risk.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
47
Periodic project risk reviews are designed to review existing_________ and to monitor any changes to the project.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
48
are designed to evaluate the effectiveness of risk response strategies and risk owners.

A)Project risk response audits
B)Project risk assessments
C)Periodic project risk reviews
D)Periodic risk assessments
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
49
A graphical depiction of EMV can be captured in a_________ .
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
50
A __________ matrix is used analyze project risk in terms of its probability of occurrence and its impact on project outcomes.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
51
_________graphically represent potential problems while accounting for causal influences, time, and other relationships between project activities and outcomes.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
52
A _________is a documented plan for risk response.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
53
_________is a risk response strategy in which steps are taken to mitigate project risk.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
54
Legal events are an example of:

A)external risks.
B)technical, quality, or performance risks.
C)project management risks.
D)organizational risks.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
55
Risk _ is concerned with the likelihood that a certain risk will occur.

A)likelihood
B)probability
C)impact
D)strength
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
56
Diagramming tools commonly used during risk identification include:

A)influence diagrams.
B)cause and effect diagrams.
C)system or process flow charts.
D)all of the above.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
57
Risk identification consists of identifying potential risks to a project and_________ .
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
58
Project risk is an uncertain event or condition that, if it occurs, has a effect on a project objective.

A)positive or negative
B)negative
C)positive
D)devastating
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
59
Conflicting priorities among users is an example of_________ .
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
60
Information gathering techniques commonly used during risk identification include:

A)Delphi technique.
B)interviewing.
C)brainstorming.
D)all of the above.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
61
_________are those risks that remain after avoidance, transfer, or mitigation strategies have been applied.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
62
_________is used to test the assumptions made during risk identification.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
63
Risks associated with ongoing changes _________are unique to IS projects.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
64
_________is a term for any contracts for the purpose of risk transference during the project.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
65
_________depict the interrelations among project activities and can be used to help managers determine the risks associated with those interrelations.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
66
_________is a statistical technique that captures the average value of potential projects by analyzing the likelihood of possible project outcomes as well as each outcome's financial consequences.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
67
A tornado analysis shows, in descending order, which risk causes the_________ on some outcome.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
68
_________is a technique used to examine the potential impact of specific risks to a project.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
69
_________involves a systematic approach to planning the risk management activities of a given project.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
70
Project risk is an uncertain event or condition that, if it occurs, has a _________effect on a project objective.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
71
Tornado analysis is an example of a _________.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
72
Risk owners are project team members responsible for specific_________ .
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
73
Environmental concerns are an example of _________.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
74
Changing industry standards are an example of __________ .
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
75
_________are those risks resulting from the application of a risk response strategy.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
76
Risks associated with poor project planning are an example of_________ .
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
77
_________are events that serve as early warnings of risks.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
78
_________is a strategy designed to avoid potential risks.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
79
Brainstorming, the Delphi technique, or interviewing are _________used during risk identification.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 111 في هذه المجموعة.
فتح الحزمة
k this deck
80
Risk management _________are used to provide organizational standards for project risk management.