Deck 15: Project Management Online

ملء الشاشة (f)
exit full mode
سؤال
The longest path through a network is comprised of the ____ activities.

A) longest
B) essential
C) mandatory
D) critical
استخدم زر المسافة أو
up arrow
down arrow
لقلب البطاقة.
سؤال
If we are employing Activity-On-Arc (AOA) network design, the arcs in the network diagram represent

A) significance relationships.
B) precedence relationships.
C) tasks to complete.
D) task times.
سؤال
How many paths are there in the following project precedence network? <strong>How many paths are there in the following project precedence network?  </strong> A) 6 B) 7 C) 8 D) 9 <div style=padding-top: 35px>

A) 6
B) 7
C) 8
D) 9
سؤال
What is the latest finish time for activity D in the following diagram? <strong>What is the latest finish time for activity D in the following diagram?  </strong> A) 6 B) 13 C) 14 D) 15 <div style=padding-top: 35px>

A) 6
B) 13
C) 14
D) 15
سؤال
What is the earliest start time for activity D in the following diagram? <strong>What is the earliest start time for activity D in the following diagram?  </strong> A) 3 B) 4 C) 6 D) 7 <div style=padding-top: 35px>

A) 3
B) 4
C) 6
D) 7
سؤال
Which of the following correctly describes the focus of the Critical Path Method (CPM)?

A) To order activities in a project in terms of their completion time to facilitate scheduling of the activities.
B) To determine when a project should be completed and to schedule when each activity in the project must begin in order to keep the project on schedule.
C) To estimate the probability of completing a project by a given deadline when the time required to perform the activity is essentially a random variable.
D) To structure the activities of a project in order to eliminate or reduce critical dependencies among the activities.
سؤال
Non-critical activities are distinguished by the presence of

A) positive slack.
B) idle resources.
C) wasted time.
D) zero slack.
سؤال
If we are employing Activity-On-Node (AON) network design, the arcs in the network diagram represent

A) significance relationships.
B) precedence relationships.
C) tasks to complete.
D) task times.
سؤال
There are various similarities between the CPM and PERT methods. Which of the following is not one of those similarities?

A) Any project can be broken down into component activities that require different amounts of time.
B) Any project can be broken down into component activities that must be accomplished in a specific order.
C) Both techniques use the same method to calculate the time element of the activities in the project.
D) Both require a detailed network of the project that clearly indicates each of the main activities and the precedence relationship among the activities.
سؤال
What are the immediate successors of activity D in this network? <strong>What are the immediate successors of activity D in this network?  </strong> A) A, B, C B) B, C C) E, F D) E <div style=padding-top: 35px>

A) A, B, C
B) B, C
C) E, F
D) E
سؤال
What are the immediate predecessors of activity D in this network? <strong>What are the immediate predecessors of activity D in this network?  </strong> A) A, B, C B) B, C C) E, F D) E, G, H <div style=padding-top: 35px>

A) A, B, C
B) B, C
C) E, F
D) E, G, H
سؤال
Slack for activity I is computed as

A) LFTi ESTi
B) LSTi ESTi
C) ESTi LSTi
D) EFTi LFTi
سؤال
Which of the following correctly describes the focus of the Program Evaluation and Review Technique (PERT)?

A) To order activities in a project in terms of their completion time to facilitate scheduling of the activities.
B) To determine when a project should be completed and to schedule when each activity in the project must begin in order to keep the project on schedule.
C) To estimate the probability of completing a project by a given deadline when the time required to perform the activity is essentially a random variable.
D) To structure the activities of a project in order to eliminate or reduce critical dependencies among the activities.
سؤال
Which of the following definitions correctly defines the acronym, PERT?

A) Program Evaluation and Review Technique.
B) Process Evaluation and Review Technique.
C) Program Evaluation and Reduction Technique.
D) Program Explanation and Reduction Technique.
سؤال
The critical path is the ____ path throughout the network.

A) longest
B) most expensive
C) shortest
D) least expensive
سؤال
Activity-on-Arc (AOA) networks do not allow multiple arcs with common start and finish nodes. If this must be represented, how is an AOA network modified?

A) The network is redrawn into an Activity-on-Node network.
B) Connect the arcs to the node using an IFERROR() function.
C) Phantom (dummy) activity arcs are added.
D) Zero duration activity arcs are added.
سؤال
Critical activities are distinguished by the presence of

A) slack.
B) idle resources.
C) wasted time.
D) zero slack.
سؤال
What is the formula for the earliest finish time for activity i?

A) EFTi = ESTi + ti
B) EFTi = EFTj + tj
C) EFTi = EFTi1 + ti
D) EFTi = ESTi ti
سؤال
Which of the following is true regarding projects?

A) Projects can have a unique start activity and a unique finish activity.
B) Projects can have multiple start activities and a unique finish activity.
C) Projects can have multiple start and finish activities.
D) All of these are true regarding projects.
سؤال
The term "time zero" identifies

A) the start time for each activity.
B) the start time for the project.
C) midnight on each work day.
D) days with not wasted effort.
سؤال
Exhibit 15.1
The following questions employ the AON network and partial spreadsheet below.
 <strong>Exhibit 15.1 The following questions employ the AON network and partial spreadsheet below.    \begin{array}{|c|c|c|c|c|c|c|c|c|c|} \hline & \text { A } & \text { B } & \text { C } & \mathrm{D} & \mathrm{E} & \mathrm{F} & \mathrm{G} & \mathrm{H} & \mathrm{I} \\ \hline 1 & \text { Activity } & \text { Description } & \text { Predecessor } & \text { Time } & \text { EST } & \text { EFT } & \text { LST } & \text { LFT } & \text { Slack } \\ \hline 2 & \text { A } & \text { Activity A } & & 4 & 0 & 4 & 0 & 4 & \\ \hline 3 & \text { B } & \text { Activity B } & \text { A } & 3 & 4 & 7 & 4 & 7 & \\ \hline 4 & \text { C } & \text { Activity C } & \text { A } & 2 & 4 & 6 & 5 & 7 & \\ \hline 5 & \text { D } & \text { Activity D } & ? & 7 & ? & ? & ? & ? & \\ \hline 6 & \text { E } & \text { Activity E } & \text { D } & 1 & 14 & 15 & 15 & 16 & \\ \hline 7 & \text { F } & \text { Activity F } & \text { D } & 2 & 14 & 16 & 14 & 16 & \\ \hline 8 & \text { G } & \text { Activity G } & \text { E,F } & 3 & 16 & 19 & 16 & 19 & \\ \hline \end{array}    -Refer to Exhibit 15.1. What values are placed in cell C5 of the spreadsheet?</strong> A) E, F B) B C) C D) B, C <div style=padding-top: 35px>   A  B  C DEFGHI1 Activity  Description  Predecessor  Time  EST  EFT  LST  LFT  Slack 2 A  Activity A 404043 B  Activity B  A 347474 C  Activity C  A 246575 D  Activity D ?7????6 E  Activity E  D 1141515167 F  Activity F  D 2141614168 G  Activity G  E,F 316191619\begin{array}{|c|c|c|c|c|c|c|c|c|c|}\hline & \text { A } & \text { B } & \text { C } & \mathrm{D} & \mathrm{E} & \mathrm{F} & \mathrm{G} & \mathrm{H} & \mathrm{I} \\\hline 1 & \text { Activity } & \text { Description } & \text { Predecessor } & \text { Time } & \text { EST } & \text { EFT } & \text { LST } & \text { LFT } & \text { Slack } \\\hline 2 & \text { A } & \text { Activity A } & & 4 & 0 & 4 & 0 & 4 & \\\hline 3 & \text { B } & \text { Activity B } & \text { A } & 3 & 4 & 7 & 4 & 7 & \\\hline 4 & \text { C } & \text { Activity C } & \text { A } & 2 & 4 & 6 & 5 & 7 & \\\hline 5 & \text { D } & \text { Activity D } & ? & 7 & ? & ? & ? & ? & \\\hline 6 & \text { E } & \text { Activity E } & \text { D } & 1 & 14 & 15 & 15 & 16 & \\\hline 7 & \text { F } & \text { Activity F } & \text { D } & 2 & 14 & 16 & 14 & 16 & \\\hline 8 & \text { G } & \text { Activity G } & \text { E,F } & 3 & 16 & 19 & 16 & 19 & \\\hline\end{array}


-Refer to Exhibit 15.1. What values are placed in cell C5 of the spreadsheet?

A) E, F
B) B
C) C
D) B, C
سؤال
One of PERT's bold assumptions is that

A) individual activity times are independent of each other.
B) individual activity times are dependent of each other.
C) individual activity times are constant.
D) individual activity times can be added together.
سؤال
Exhibit 15.1
The following questions employ the AON network and partial spreadsheet below.
 <strong>Exhibit 15.1 The following questions employ the AON network and partial spreadsheet below.    \begin{array}{|c|c|c|c|c|c|c|c|c|c|} \hline & \text { A } & \text { B } & \text { C } & \mathrm{D} & \mathrm{E} & \mathrm{F} & \mathrm{G} & \mathrm{H} & \mathrm{I} \\ \hline 1 & \text { Activity } & \text { Description } & \text { Predecessor } & \text { Time } & \text { EST } & \text { EFT } & \text { LST } & \text { LFT } & \text { Slack } \\ \hline 2 & \text { A } & \text { Activity A } & & 4 & 0 & 4 & 0 & 4 & \\ \hline 3 & \text { B } & \text { Activity B } & \text { A } & 3 & 4 & 7 & 4 & 7 & \\ \hline 4 & \text { C } & \text { Activity C } & \text { A } & 2 & 4 & 6 & 5 & 7 & \\ \hline 5 & \text { D } & \text { Activity D } & ? & 7 & ? & ? & ? & ? & \\ \hline 6 & \text { E } & \text { Activity E } & \text { D } & 1 & 14 & 15 & 15 & 16 & \\ \hline 7 & \text { F } & \text { Activity F } & \text { D } & 2 & 14 & 16 & 14 & 16 & \\ \hline 8 & \text { G } & \text { Activity G } & \text { E,F } & 3 & 16 & 19 & 16 & 19 & \\ \hline \end{array}    -Refer to Exhibit 15.1. What array formula is placed in cell E5 to calculate the Earliest Start Time?</strong> A) E2 + D2 B) MAX(IF(ISERR(FIND($A$5:$A$17,C5)),0,$F$5:$F$17)) C) H2 <font face=symbol>?</font> D2 D) MIN(IF(ISNUMBER(FIND(A5,$C$2:$C$8)),$G$2:$G$8)) <div style=padding-top: 35px>   A  B  C DEFGHI1 Activity  Description  Predecessor  Time  EST  EFT  LST  LFT  Slack 2 A  Activity A 404043 B  Activity B  A 347474 C  Activity C  A 246575 D  Activity D ?7????6 E  Activity E  D 1141515167 F  Activity F  D 2141614168 G  Activity G  E,F 316191619\begin{array}{|c|c|c|c|c|c|c|c|c|c|}\hline & \text { A } & \text { B } & \text { C } & \mathrm{D} & \mathrm{E} & \mathrm{F} & \mathrm{G} & \mathrm{H} & \mathrm{I} \\\hline 1 & \text { Activity } & \text { Description } & \text { Predecessor } & \text { Time } & \text { EST } & \text { EFT } & \text { LST } & \text { LFT } & \text { Slack } \\\hline 2 & \text { A } & \text { Activity A } & & 4 & 0 & 4 & 0 & 4 & \\\hline 3 & \text { B } & \text { Activity B } & \text { A } & 3 & 4 & 7 & 4 & 7 & \\\hline 4 & \text { C } & \text { Activity C } & \text { A } & 2 & 4 & 6 & 5 & 7 & \\\hline 5 & \text { D } & \text { Activity D } & ? & 7 & ? & ? & ? & ? & \\\hline 6 & \text { E } & \text { Activity E } & \text { D } & 1 & 14 & 15 & 15 & 16 & \\\hline 7 & \text { F } & \text { Activity F } & \text { D } & 2 & 14 & 16 & 14 & 16 & \\\hline 8 & \text { G } & \text { Activity G } & \text { E,F } & 3 & 16 & 19 & 16 & 19 & \\\hline\end{array}


-Refer to Exhibit 15.1. What array formula is placed in cell E5 to calculate the Earliest Start Time?

A) E2 + D2
B) MAX(IF(ISERR(FIND($A$5:$A$17,C5)),0,$F$5:$F$17))
C) H2 ? D2
D) MIN(IF(ISNUMBER(FIND(A5,$C$2:$C$8)),$G$2:$G$8))
سؤال
The purpose of the backward pass in the Critical Path Method (CPM) technique is to

A) review each of the precedence relationships in the activity network.
B) calculate the slack time within each node on the activity network.
C) determine the earliest time each activity can start and finish.
D) determine the latest time each activity can start and finish.
سؤال
If the following project must be completed by day 18 at minimum cost how do we change the LP model? <strong>If the following project must be completed by day 18 at minimum cost how do we change the LP model?  </strong> A) Enter 18 in cell E14. B) Add a constraint that E14 <font face=symbol></font> 18. C) Make cell E14 the target cell. D) Add a constraint that E14 = 18. <div style=padding-top: 35px>

A) Enter 18 in cell E14.
B) Add a constraint that E14 18.
C) Make cell E14 the target cell.
D) Add a constraint that E14 = 18.
سؤال
Slack represents the amount of time by which an activity can be delayed without delaying the entire project, assuming that

A) all successor activities start at their earliest start times.
B) all predecessor activities start at their earliest start times.
C) immediate predecessor activities start at their earliest start times.
D) all predecessor activities start at their latest start times.
سؤال
Exhibit 15.1
The following questions employ the AON network and partial spreadsheet below.
 <strong>Exhibit 15.1 The following questions employ the AON network and partial spreadsheet below.    \begin{array}{|c|c|c|c|c|c|c|c|c|c|} \hline & \text { A } & \text { B } & \text { C } & \mathrm{D} & \mathrm{E} & \mathrm{F} & \mathrm{G} & \mathrm{H} & \mathrm{I} \\ \hline 1 & \text { Activity } & \text { Description } & \text { Predecessor } & \text { Time } & \text { EST } & \text { EFT } & \text { LST } & \text { LFT } & \text { Slack } \\ \hline 2 & \text { A } & \text { Activity A } & & 4 & 0 & 4 & 0 & 4 & \\ \hline 3 & \text { B } & \text { Activity B } & \text { A } & 3 & 4 & 7 & 4 & 7 & \\ \hline 4 & \text { C } & \text { Activity C } & \text { A } & 2 & 4 & 6 & 5 & 7 & \\ \hline 5 & \text { D } & \text { Activity D } & ? & 7 & ? & ? & ? & ? & \\ \hline 6 & \text { E } & \text { Activity E } & \text { D } & 1 & 14 & 15 & 15 & 16 & \\ \hline 7 & \text { F } & \text { Activity F } & \text { D } & 2 & 14 & 16 & 14 & 16 & \\ \hline 8 & \text { G } & \text { Activity G } & \text { E,F } & 3 & 16 & 19 & 16 & 19 & \\ \hline \end{array}    -Refer to Exhibit 15.1. What array formula is placed in cell H5 to calculate the Latest Finish Time?</strong> A) E2 + D2 B) MAX(IF(ISNUMBER(FIND($A$2:$A$8,C5)),$F$2:$F$8)) C) H2 <font face=symbol>?</font> D2 D) MIN(IF(ISERR(FIND(A5,$C$5:$C$17)),MAX($F$5:$F$17),$G$5:$G$17)) <div style=padding-top: 35px>   A  B  C DEFGHI1 Activity  Description  Predecessor  Time  EST  EFT  LST  LFT  Slack 2 A  Activity A 404043 B  Activity B  A 347474 C  Activity C  A 246575 D  Activity D ?7????6 E  Activity E  D 1141515167 F  Activity F  D 2141614168 G  Activity G  E,F 316191619\begin{array}{|c|c|c|c|c|c|c|c|c|c|}\hline & \text { A } & \text { B } & \text { C } & \mathrm{D} & \mathrm{E} & \mathrm{F} & \mathrm{G} & \mathrm{H} & \mathrm{I} \\\hline 1 & \text { Activity } & \text { Description } & \text { Predecessor } & \text { Time } & \text { EST } & \text { EFT } & \text { LST } & \text { LFT } & \text { Slack } \\\hline 2 & \text { A } & \text { Activity A } & & 4 & 0 & 4 & 0 & 4 & \\\hline 3 & \text { B } & \text { Activity B } & \text { A } & 3 & 4 & 7 & 4 & 7 & \\\hline 4 & \text { C } & \text { Activity C } & \text { A } & 2 & 4 & 6 & 5 & 7 & \\\hline 5 & \text { D } & \text { Activity D } & ? & 7 & ? & ? & ? & ? & \\\hline 6 & \text { E } & \text { Activity E } & \text { D } & 1 & 14 & 15 & 15 & 16 & \\\hline 7 & \text { F } & \text { Activity F } & \text { D } & 2 & 14 & 16 & 14 & 16 & \\\hline 8 & \text { G } & \text { Activity G } & \text { E,F } & 3 & 16 & 19 & 16 & 19 & \\\hline\end{array}


-Refer to Exhibit 15.1. What array formula is placed in cell H5 to calculate the Latest Finish Time?

A) E2 + D2
B) MAX(IF(ISNUMBER(FIND($A$2:$A$8,C5)),$F$2:$F$8))
C) H2 ? D2
D) MIN(IF(ISERR(FIND(A5,$C$5:$C$17)),MAX($F$5:$F$17),$G$5:$G$17))
سؤال
Which activities are critical in the following diagram? <strong>Which activities are critical in the following diagram?  </strong> A) A, C, D, F B) B, D, E C) A, C, D, E D) A, B, D, E, F <div style=padding-top: 35px>

A) A, C, D, F
B) B, D, E
C) A, C, D, E
D) A, B, D, E, F
سؤال
A strength of Gantt charts is that they

A) clearly portray precedence relationships.
B) model uncertainty in activity duration times.
C) provide a timeline-based, graphical view of when activities can begin and end.
D) clearly identifies the critical path.
سؤال
What formula should go in cell I5 of the following spreadsheet to compute Actual Time Between Starts? <strong>What formula should go in cell I5 of the following spreadsheet to compute Actual Time Between Starts?  </strong> A) =VLOOKUP(H5,$B$5:$D$11,3)-VLOOKUP(G5,$B$5:$D$11,3) B) =VLOOKUP(H5,$B$5:$D$11,2)-VLOOKUP(G5,$B$5:$D$11,2) C) =VLOOKUP(G5,$B$5:$D$11,3)-VLOOKUP(H5,$B$5:$D$11,3) D) =VLOOKUP(H5,$B$5:$D$11,3)-VLOOKUP(G5,$B$5:$D$11,3) <div style=padding-top: 35px>

A) =VLOOKUP(H5,$B$5:$D$11,3)-VLOOKUP(G5,$B$5:$D$11,3)
B) =VLOOKUP(H5,$B$5:$D$11,2)-VLOOKUP(G5,$B$5:$D$11,2)
C) =VLOOKUP(G5,$B$5:$D$11,3)-VLOOKUP(H5,$B$5:$D$11,3)
D) =VLOOKUP(H5,$B$5:$D$11,3)-VLOOKUP(G5,$B$5:$D$11,3)
سؤال
Which activities have slack in the following diagram? <strong>Which activities have slack in the following diagram?  </strong> A) A, C, D, F B) B, E C) A, C, D, E D) B, D, E <div style=padding-top: 35px>

A) A, C, D, F
B) B, E
C) A, C, D, E
D) B, D, E
سؤال
A company wants to use PERT to manage a project. They have developed the following spreadsheet for the problem. If The Risk Solver Platform (RSP) is used, what formula should go in cell F3 of the spreadsheet to compute the Activity Time when simulating a PERT analysis? <strong>A company wants to use PERT to manage a project. They have developed the following spreadsheet for the problem. If The Risk Solver Platform (RSP) is used, what formula should go in cell F3 of the spreadsheet to compute the Activity Time when simulating a PERT analysis?  </strong> A) =IF(E3<font face=symbol></font>(C3-E3)/(D3-B3),D3-SQRT((D3-B3)*(D3-C3)*(1-E3)),B3+SQRT((D3-E3)*(C3-B3)*E3)) B) =IF(E3<font face=symbol></font>(D3-B3)/(C3-E3),B3+SQRT((D3-E3)*(C3-B3)*E3),D3-SQRT((D3-B3)*(D3-C3)*(1-E3))) C) =IF(E3<font face=symbol></font>(C3-E3)/(D3-B3),B3-SQRT((D3-E3)*(C3-B3)*E3),D3+SQRT((D3-B3)*(D3-C3)*(1-E3))) D) =PsiTriangular(B3,C3,D3) <div style=padding-top: 35px>

A) =IF(E3(C3-E3)/(D3-B3),D3-SQRT((D3-B3)*(D3-C3)*(1-E3)),B3+SQRT((D3-E3)*(C3-B3)*E3))
B) =IF(E3(D3-B3)/(C3-E3),B3+SQRT((D3-E3)*(C3-B3)*E3),D3-SQRT((D3-B3)*(D3-C3)*(1-E3)))
C) =IF(E3(C3-E3)/(D3-B3),B3-SQRT((D3-E3)*(C3-B3)*E3),D3+SQRT((D3-B3)*(D3-C3)*(1-E3)))
D) =PsiTriangular(B3,C3,D3)
سؤال
Exhibit 15.2
The following questions employ the AON network and completed spreadsheet below.
 <strong>Exhibit 15.2 The following questions employ the AON network and completed spreadsheet below.    \begin{array}{|c|c|c|c|c|c|c|c|c|c|} \hline & \text { A } & \text { B } & \text { C } & \mathrm{D} & \mathrm{E} & \mathrm{F} & \mathrm{G} & \mathrm{H} & \mathrm{I} \\ \hline 1 & \text { Activity } & \text { Description } & \text { Predecessor } & \text { Time } & \text { EST } & \text { EFT } & \text { LST } & \text { LFT } & \text { Slack } \\ \hline 2 & \text { A } & \text { Activity A } & & 4 & 0 & 4 & 0 & 4 & 0 \\ \hline 3 & \text { B } & \text { Activity B } & \text { A } & 3 & 4 & 7 & 4 & 7 & 0 \\ \hline 4 & \text { C } & \text { Activity C } & \text { A } & 2 & 4 & 6 & 5 & 7 & 1 \\ \hline 5 & \text { D } & \text { Activity D } & \text { B,C } & 7 & 7 & 14 & 7 & 14 & 0 \\ \hline 6 & \text { E } & \text { Activity E } & \text { D } & 1 & 14 & 15 & 15 & 16 & 1 \\ \hline 7 & \text { F } & \text { Activity F } & \text { D } & 2 & 14 & 16 & 14 & 16 & 0 \\ \hline 8 & \text { G } & \text { Activity G } & \text { E,F } & 3 & 16 & 19 & 16 & 19 & 0 \\ \hline \end{array}    -Refer to Exhibit 15.2. Which of the following activities is not on the critical path for the network?</strong> A) Activity A B) Activity C C) Activity D D) Activity G <div style=padding-top: 35px>   A  B  C DEFGHI1 Activity  Description  Predecessor  Time  EST  EFT  LST  LFT  Slack 2 A  Activity A 4040403 B  Activity B  A 3474704 C  Activity C  A 2465715 D  Activity D  B,C 771471406 E  Activity E  D 11415151617 F  Activity F  D 21416141608 G  Activity G  E,F 3161916190\begin{array}{|c|c|c|c|c|c|c|c|c|c|}\hline & \text { A } & \text { B } & \text { C } & \mathrm{D} & \mathrm{E} & \mathrm{F} & \mathrm{G} & \mathrm{H} & \mathrm{I} \\\hline 1 & \text { Activity } & \text { Description } & \text { Predecessor } & \text { Time } & \text { EST } & \text { EFT } & \text { LST } & \text { LFT } & \text { Slack } \\\hline 2 & \text { A } & \text { Activity A } & & 4 & 0 & 4 & 0 & 4 & 0 \\\hline 3 & \text { B } & \text { Activity B } & \text { A } & 3 & 4 & 7 & 4 & 7 & 0 \\\hline 4 & \text { C } & \text { Activity C } & \text { A } & 2 & 4 & 6 & 5 & 7 & 1 \\\hline 5 & \text { D } & \text { Activity D } & \text { B,C } & 7 & 7 & 14 & 7 & 14 & 0 \\\hline 6 & \text { E } & \text { Activity E } & \text { D } & 1 & 14 & 15 & 15 & 16 & 1 \\\hline 7 & \text { F } & \text { Activity F } & \text { D } & 2 & 14 & 16 & 14 & 16 & 0 \\\hline 8 & \text { G } & \text { Activity G } & \text { E,F } & 3 & 16 & 19 & 16 & 19 & 0 \\\hline\end{array}


-Refer to Exhibit 15.2. Which of the following activities is not on the critical path for the network?

A) Activity A
B) Activity C
C) Activity D
D) Activity G
سؤال
Shortening the activity completion time is called

A) expediting
B) speeding
C) accelerating
D) crashing
سؤال
What formula should go in cell H3 of the following spreadsheet to compute Crash Cost Per Day? <strong>What formula should go in cell H3 of the following spreadsheet to compute Crash Cost Per Day?  </strong> A) =(C3-E3)/(F3-D3) B) =(F3-D3)/(C3-E3) C) =(F3)/(C3-E3) D) =(F3-D3)/(E3) <div style=padding-top: 35px>

A) =(C3-E3)/(F3-D3)
B) =(F3-D3)/(C3-E3)
C) =(F3)/(C3-E3)
D) =(F3-D3)/(E3)
سؤال
Exhibit 15.2
The following questions employ the AON network and completed spreadsheet below.
 <strong>Exhibit 15.2 The following questions employ the AON network and completed spreadsheet below.    \begin{array}{|c|c|c|c|c|c|c|c|c|c|} \hline & \text { A } & \text { B } & \text { C } & \mathrm{D} & \mathrm{E} & \mathrm{F} & \mathrm{G} & \mathrm{H} & \mathrm{I} \\ \hline 1 & \text { Activity } & \text { Description } & \text { Predecessor } & \text { Time } & \text { EST } & \text { EFT } & \text { LST } & \text { LFT } & \text { Slack } \\ \hline 2 & \text { A } & \text { Activity A } & & 4 & 0 & 4 & 0 & 4 & 0 \\ \hline 3 & \text { B } & \text { Activity B } & \text { A } & 3 & 4 & 7 & 4 & 7 & 0 \\ \hline 4 & \text { C } & \text { Activity C } & \text { A } & 2 & 4 & 6 & 5 & 7 & 1 \\ \hline 5 & \text { D } & \text { Activity D } & \text { B,C } & 7 & 7 & 14 & 7 & 14 & 0 \\ \hline 6 & \text { E } & \text { Activity E } & \text { D } & 1 & 14 & 15 & 15 & 16 & 1 \\ \hline 7 & \text { F } & \text { Activity F } & \text { D } & 2 & 14 & 16 & 14 & 16 & 0 \\ \hline 8 & \text { G } & \text { Activity G } & \text { E,F } & 3 & 16 & 19 & 16 & 19 & 0 \\ \hline \end{array}    -Refer to Exhibit 15.2. What formula is placed in cell G5 to calculate the Latest Start Time?</strong> A) H5 <font face=symbol>?</font> G5 B) F5 <font face=symbol>?</font> G5 C) H5 <font face=symbol>?</font> D5 D) F5 <font face=symbol>?</font> D5 <div style=padding-top: 35px>   A  B  C DEFGHI1 Activity  Description  Predecessor  Time  EST  EFT  LST  LFT  Slack 2 A  Activity A 4040403 B  Activity B  A 3474704 C  Activity C  A 2465715 D  Activity D  B,C 771471406 E  Activity E  D 11415151617 F  Activity F  D 21416141608 G  Activity G  E,F 3161916190\begin{array}{|c|c|c|c|c|c|c|c|c|c|}\hline & \text { A } & \text { B } & \text { C } & \mathrm{D} & \mathrm{E} & \mathrm{F} & \mathrm{G} & \mathrm{H} & \mathrm{I} \\\hline 1 & \text { Activity } & \text { Description } & \text { Predecessor } & \text { Time } & \text { EST } & \text { EFT } & \text { LST } & \text { LFT } & \text { Slack } \\\hline 2 & \text { A } & \text { Activity A } & & 4 & 0 & 4 & 0 & 4 & 0 \\\hline 3 & \text { B } & \text { Activity B } & \text { A } & 3 & 4 & 7 & 4 & 7 & 0 \\\hline 4 & \text { C } & \text { Activity C } & \text { A } & 2 & 4 & 6 & 5 & 7 & 1 \\\hline 5 & \text { D } & \text { Activity D } & \text { B,C } & 7 & 7 & 14 & 7 & 14 & 0 \\\hline 6 & \text { E } & \text { Activity E } & \text { D } & 1 & 14 & 15 & 15 & 16 & 1 \\\hline 7 & \text { F } & \text { Activity F } & \text { D } & 2 & 14 & 16 & 14 & 16 & 0 \\\hline 8 & \text { G } & \text { Activity G } & \text { E,F } & 3 & 16 & 19 & 16 & 19 & 0 \\\hline\end{array}


-Refer to Exhibit 15.2. What formula is placed in cell G5 to calculate the Latest Start Time?

A) H5 ? G5
B) F5 ? G5
C) H5 ? D5
D) F5 ? D5
سؤال
The purpose of the forward pass in the Critical Path Method (CPM) technique is to

A) review each of the precedence relationships in the activity network.
B) calculate the slack time within each node on the activity network.
C) determine the earliest time each activity can start and finish.
D) determine the latest time each activity can start and finish.
سؤال
A weakness of Gantt charts is that they do not explicitly

A) indicate activity times.
B) show precedence relationships.
C) show activity start times.
D) show activity finish times.
سؤال
In a PERT network the time required to complete a path is a(n)

A) constant
B) random variable
C) Poisson distributed variable
D) exponentially distributed variable
سؤال
The critical path in PERT analysis is the path with the

A) smallest variance.
B) longest expected completion time.
C) smallest number of tasks.
D) smallest variance and longest expected completion time.
سؤال
Exhibit 15.3
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Exhibit 15.3 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities:   Refer to Exhibit 15.3. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. Based on the data in the spreadsheet, which activities are on the critical path?  <div style=padding-top: 35px>
Refer to Exhibit 15.3. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. Based on the data in the spreadsheet, which activities are on the critical path?
Exhibit 15.3 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities:   Refer to Exhibit 15.3. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. Based on the data in the spreadsheet, which activities are on the critical path?  <div style=padding-top: 35px>
سؤال
Exhibit 15.4
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Exhibit 15.4 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities:   Refer to Exhibit 15.4. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells E2:E8 to calculate Earliest Start Times?  <div style=padding-top: 35px>
Refer to Exhibit 15.4. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells E2:E8 to calculate Earliest Start Times?
Exhibit 15.4 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities:   Refer to Exhibit 15.4. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells E2:E8 to calculate Earliest Start Times?  <div style=padding-top: 35px>
سؤال
A company wants to use PERT to manage a project. They have developed the following spreadsheet for the problem. What formula should go in cell F3 of the spreadsheet to compute the Activity Time when simulating a PERT analysis?
A company wants to use PERT to manage a project. They have developed the following spreadsheet for the problem. What formula should go in cell F3 of the spreadsheet to compute the Activity Time when simulating a PERT analysis?  <div style=padding-top: 35px>
سؤال
Exhibit 15.4
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Exhibit 15.4 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities:   Refer to Exhibit 15.4. Manually determine the earliest and latest start and finish times for each activity and the amount of slack for each activity. What is the critical path for the project and how long should it take to complete it?<div style=padding-top: 35px>
Refer to Exhibit 15.4. Manually determine the earliest and latest start and finish times for each activity and the amount of slack for each activity. What is the critical path for the project and how long should it take to complete it?
سؤال
Exhibit 15.4
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Exhibit 15.4 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities:   Refer to Exhibit 15.4. Draw the CPM network for this problem. Use AON notation.<div style=padding-top: 35px>
Refer to Exhibit 15.4. Draw the CPM network for this problem. Use AON notation.
سؤال
Exhibit 15.3
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Exhibit 15.3 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities:   Refer to Exhibit 15.3. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells H2:H8 to calculate Latest Finish Times?  <div style=padding-top: 35px>
Refer to Exhibit 15.3. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells H2:H8 to calculate Latest Finish Times?
Exhibit 15.3 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities:   Refer to Exhibit 15.3. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells H2:H8 to calculate Latest Finish Times?  <div style=padding-top: 35px>
سؤال
Exhibit 15.5
The following questions use the information below.
A company wants to crash a project and reduce the time required to complete it. They have developed the following table of activity costs and times and a spreadsheet to compute starting time for each activity.
Exhibit 15.5 The following questions use the information below. A company wants to crash a project and reduce the time required to complete it. They have developed the following table of activity costs and times and a spreadsheet to compute starting time for each activity.     Refer to Exhibit 15.5. What formula should go in cell H3 of the Costs spreadsheet to compute Crash Cost Per Day?<div style=padding-top: 35px> Exhibit 15.5 The following questions use the information below. A company wants to crash a project and reduce the time required to complete it. They have developed the following table of activity costs and times and a spreadsheet to compute starting time for each activity.     Refer to Exhibit 15.5. What formula should go in cell H3 of the Costs spreadsheet to compute Crash Cost Per Day?<div style=padding-top: 35px>
Refer to Exhibit 15.5. What formula should go in cell H3 of the Costs spreadsheet to compute Crash Cost Per Day?
سؤال
Exhibit 15.5
The following questions use the information below.
A company wants to crash a project and reduce the time required to complete it. They have developed the following table of activity costs and times and a spreadsheet to compute starting time for each activity.
Exhibit 15.5 The following questions use the information below. A company wants to crash a project and reduce the time required to complete it. They have developed the following table of activity costs and times and a spreadsheet to compute starting time for each activity.     Refer to Exhibit 15.5. What formula should go in cell I5 of the Model spreadsheet to compute Actual Time Between Starts?<div style=padding-top: 35px> Exhibit 15.5 The following questions use the information below. A company wants to crash a project and reduce the time required to complete it. They have developed the following table of activity costs and times and a spreadsheet to compute starting time for each activity.     Refer to Exhibit 15.5. What formula should go in cell I5 of the Model spreadsheet to compute Actual Time Between Starts?<div style=padding-top: 35px>
Refer to Exhibit 15.5. What formula should go in cell I5 of the Model spreadsheet to compute Actual Time Between Starts?
سؤال
Exhibit 15.6
The following questions use the information below.
Consider the CPM network for the following set of activities:
Exhibit 15.6 The following questions use the information below. Consider the CPM network for the following set of activities:   Refer to Exhibit 15.6. Is it necessary to draw an arc from the node for activity F to the node for activity I?<div style=padding-top: 35px>
Refer to Exhibit 15.6. Is it necessary to draw an arc from the node for activity F to the node for activity I?
سؤال
Exhibit 15.3
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Exhibit 15.3 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities:   Refer to Exhibit 15.3. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells E2:E8 to calculate Earliest Start Times?  <div style=padding-top: 35px>
Refer to Exhibit 15.3. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells E2:E8 to calculate Earliest Start Times?
Exhibit 15.3 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities:   Refer to Exhibit 15.3. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells E2:E8 to calculate Earliest Start Times?  <div style=padding-top: 35px>
سؤال
Exhibit 15.3
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Exhibit 15.3 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities:   Refer to Exhibit 15.3. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells F2:F8 to calculate Earliest Finish Times, G2:G8 to calculate Latest Start Times, and cells I2:I8 to calculate the Slack?  <div style=padding-top: 35px>
Refer to Exhibit 15.3. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells F2:F8 to calculate Earliest Finish Times, G2:G8 to calculate Latest Start Times, and cells I2:I8 to calculate the Slack?
Exhibit 15.3 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities:   Refer to Exhibit 15.3. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells F2:F8 to calculate Earliest Finish Times, G2:G8 to calculate Latest Start Times, and cells I2:I8 to calculate the Slack?  <div style=padding-top: 35px>
سؤال
Exhibit 15.4
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Exhibit 15.4 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities:   Refer to Exhibit 15.4. Identify each path through the network and its expected length.<div style=padding-top: 35px>
Refer to Exhibit 15.4. Identify each path through the network and its expected length.
سؤال
Exhibit 15.3
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Exhibit 15.3 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities:   Refer to Exhibit 15.3. Identify each path through the network and its expected length.<div style=padding-top: 35px>
Refer to Exhibit 15.3. Identify each path through the network and its expected length.
سؤال
Exhibit 15.3
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Exhibit 15.3 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities:   Refer to Exhibit 15.3. Draw the CPM network for this problem. Use AON notation.<div style=padding-top: 35px>
Refer to Exhibit 15.3. Draw the CPM network for this problem. Use AON notation.
سؤال
Exhibit 15.4
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Exhibit 15.4 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities:   Refer to Exhibit 15.4. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells F2:F8 to calculate Earliest Finish Times, G2:G8 to calculate Latest Start Times, and cells I2:I8 to calculate the Slack?  <div style=padding-top: 35px>
Refer to Exhibit 15.4. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells F2:F8 to calculate Earliest Finish Times, G2:G8 to calculate Latest Start Times, and cells I2:I8 to calculate the Slack?
Exhibit 15.4 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities:   Refer to Exhibit 15.4. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells F2:F8 to calculate Earliest Finish Times, G2:G8 to calculate Latest Start Times, and cells I2:I8 to calculate the Slack?  <div style=padding-top: 35px>
سؤال
Exhibit 15.3
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Exhibit 15.3 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities:   Refer to Exhibit 15.3. Manually determine the earliest and latest start and finish times for each activity and the amount of slack for each activity. What is the critical path for the project and how long should it take to complete it?<div style=padding-top: 35px>
Refer to Exhibit 15.3. Manually determine the earliest and latest start and finish times for each activity and the amount of slack for each activity. What is the critical path for the project and how long should it take to complete it?
سؤال
Exhibit 15.6
The following questions use the information below.
Consider the CPM network for the following set of activities:
Exhibit 15.6 The following questions use the information below. Consider the CPM network for the following set of activities:   Refer to Exhibit 15.6. Is it necessary to draw an arc from the node for activity A to the node for activity C?<div style=padding-top: 35px>
Refer to Exhibit 15.6. Is it necessary to draw an arc from the node for activity A to the node for activity C?
سؤال
Exhibit 15.4
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Exhibit 15.4 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities:   Refer to Exhibit 15.4. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. Based on the data in the spreadsheet, which activities are on the critical path?  <div style=padding-top: 35px>
Refer to Exhibit 15.4. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. Based on the data in the spreadsheet, which activities are on the critical path?
Exhibit 15.4 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities:   Refer to Exhibit 15.4. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. Based on the data in the spreadsheet, which activities are on the critical path?  <div style=padding-top: 35px>
سؤال
Exhibit 15.4
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Exhibit 15.4 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities:   Refer to Exhibit 15.4. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells H2:H8 to calculate Latest Finish Times?  <div style=padding-top: 35px>
Refer to Exhibit 15.4. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells H2:H8 to calculate Latest Finish Times?
Exhibit 15.4 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities:   Refer to Exhibit 15.4. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells H2:H8 to calculate Latest Finish Times?  <div style=padding-top: 35px>
سؤال
Exhibit 15.5
The following questions use the information below.
A company wants to crash a project and reduce the time required to complete it. They have developed the following table of activity costs and times and a spreadsheet to compute starting time for each activity.
Exhibit 15.5 The following questions use the information below. A company wants to crash a project and reduce the time required to complete it. They have developed the following table of activity costs and times and a spreadsheet to compute starting time for each activity.     Refer to Exhibit 15.5. If the following project must be completed by day 18 at minimum cost how do we change the LP model?<div style=padding-top: 35px> Exhibit 15.5 The following questions use the information below. A company wants to crash a project and reduce the time required to complete it. They have developed the following table of activity costs and times and a spreadsheet to compute starting time for each activity.     Refer to Exhibit 15.5. If the following project must be completed by day 18 at minimum cost how do we change the LP model?<div style=padding-top: 35px>
Refer to Exhibit 15.5. If the following project must be completed by day 18 at minimum cost how do we change the LP model?
سؤال
Exhibit 15.6
The following questions use the information below.
Consider the CPM network for the following set of activities:
Exhibit 15.6 The following questions use the information below. Consider the CPM network for the following set of activities:   Refer to Exhibit 15.6. Modify the table above by completing the following table. For column 3, list only the immediate predecessors for each activity.  <div style=padding-top: 35px>
Refer to Exhibit 15.6. Modify the table above by completing the following table. For column 3, list only the immediate predecessors for each activity.
Exhibit 15.6 The following questions use the information below. Consider the CPM network for the following set of activities:   Refer to Exhibit 15.6. Modify the table above by completing the following table. For column 3, list only the immediate predecessors for each activity.  <div style=padding-top: 35px>
فتح الحزمة
قم بالتسجيل لفتح البطاقات في هذه المجموعة!
Unlock Deck
Unlock Deck
1/61
auto play flashcards
العب
simple tutorial
ملء الشاشة (f)
exit full mode
Deck 15: Project Management Online
1
The longest path through a network is comprised of the ____ activities.

A) longest
B) essential
C) mandatory
D) critical
D
2
If we are employing Activity-On-Arc (AOA) network design, the arcs in the network diagram represent

A) significance relationships.
B) precedence relationships.
C) tasks to complete.
D) task times.
C
3
How many paths are there in the following project precedence network? <strong>How many paths are there in the following project precedence network?  </strong> A) 6 B) 7 C) 8 D) 9

A) 6
B) 7
C) 8
D) 9
D
4
What is the latest finish time for activity D in the following diagram? <strong>What is the latest finish time for activity D in the following diagram?  </strong> A) 6 B) 13 C) 14 D) 15

A) 6
B) 13
C) 14
D) 15
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
5
What is the earliest start time for activity D in the following diagram? <strong>What is the earliest start time for activity D in the following diagram?  </strong> A) 3 B) 4 C) 6 D) 7

A) 3
B) 4
C) 6
D) 7
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
6
Which of the following correctly describes the focus of the Critical Path Method (CPM)?

A) To order activities in a project in terms of their completion time to facilitate scheduling of the activities.
B) To determine when a project should be completed and to schedule when each activity in the project must begin in order to keep the project on schedule.
C) To estimate the probability of completing a project by a given deadline when the time required to perform the activity is essentially a random variable.
D) To structure the activities of a project in order to eliminate or reduce critical dependencies among the activities.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
7
Non-critical activities are distinguished by the presence of

A) positive slack.
B) idle resources.
C) wasted time.
D) zero slack.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
8
If we are employing Activity-On-Node (AON) network design, the arcs in the network diagram represent

A) significance relationships.
B) precedence relationships.
C) tasks to complete.
D) task times.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
9
There are various similarities between the CPM and PERT methods. Which of the following is not one of those similarities?

A) Any project can be broken down into component activities that require different amounts of time.
B) Any project can be broken down into component activities that must be accomplished in a specific order.
C) Both techniques use the same method to calculate the time element of the activities in the project.
D) Both require a detailed network of the project that clearly indicates each of the main activities and the precedence relationship among the activities.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
10
What are the immediate successors of activity D in this network? <strong>What are the immediate successors of activity D in this network?  </strong> A) A, B, C B) B, C C) E, F D) E

A) A, B, C
B) B, C
C) E, F
D) E
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
11
What are the immediate predecessors of activity D in this network? <strong>What are the immediate predecessors of activity D in this network?  </strong> A) A, B, C B) B, C C) E, F D) E, G, H

A) A, B, C
B) B, C
C) E, F
D) E, G, H
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
12
Slack for activity I is computed as

A) LFTi ESTi
B) LSTi ESTi
C) ESTi LSTi
D) EFTi LFTi
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
13
Which of the following correctly describes the focus of the Program Evaluation and Review Technique (PERT)?

A) To order activities in a project in terms of their completion time to facilitate scheduling of the activities.
B) To determine when a project should be completed and to schedule when each activity in the project must begin in order to keep the project on schedule.
C) To estimate the probability of completing a project by a given deadline when the time required to perform the activity is essentially a random variable.
D) To structure the activities of a project in order to eliminate or reduce critical dependencies among the activities.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
14
Which of the following definitions correctly defines the acronym, PERT?

A) Program Evaluation and Review Technique.
B) Process Evaluation and Review Technique.
C) Program Evaluation and Reduction Technique.
D) Program Explanation and Reduction Technique.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
15
The critical path is the ____ path throughout the network.

A) longest
B) most expensive
C) shortest
D) least expensive
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
16
Activity-on-Arc (AOA) networks do not allow multiple arcs with common start and finish nodes. If this must be represented, how is an AOA network modified?

A) The network is redrawn into an Activity-on-Node network.
B) Connect the arcs to the node using an IFERROR() function.
C) Phantom (dummy) activity arcs are added.
D) Zero duration activity arcs are added.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
17
Critical activities are distinguished by the presence of

A) slack.
B) idle resources.
C) wasted time.
D) zero slack.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
18
What is the formula for the earliest finish time for activity i?

A) EFTi = ESTi + ti
B) EFTi = EFTj + tj
C) EFTi = EFTi1 + ti
D) EFTi = ESTi ti
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
19
Which of the following is true regarding projects?

A) Projects can have a unique start activity and a unique finish activity.
B) Projects can have multiple start activities and a unique finish activity.
C) Projects can have multiple start and finish activities.
D) All of these are true regarding projects.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
20
The term "time zero" identifies

A) the start time for each activity.
B) the start time for the project.
C) midnight on each work day.
D) days with not wasted effort.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
21
Exhibit 15.1
The following questions employ the AON network and partial spreadsheet below.
 <strong>Exhibit 15.1 The following questions employ the AON network and partial spreadsheet below.    \begin{array}{|c|c|c|c|c|c|c|c|c|c|} \hline & \text { A } & \text { B } & \text { C } & \mathrm{D} & \mathrm{E} & \mathrm{F} & \mathrm{G} & \mathrm{H} & \mathrm{I} \\ \hline 1 & \text { Activity } & \text { Description } & \text { Predecessor } & \text { Time } & \text { EST } & \text { EFT } & \text { LST } & \text { LFT } & \text { Slack } \\ \hline 2 & \text { A } & \text { Activity A } & & 4 & 0 & 4 & 0 & 4 & \\ \hline 3 & \text { B } & \text { Activity B } & \text { A } & 3 & 4 & 7 & 4 & 7 & \\ \hline 4 & \text { C } & \text { Activity C } & \text { A } & 2 & 4 & 6 & 5 & 7 & \\ \hline 5 & \text { D } & \text { Activity D } & ? & 7 & ? & ? & ? & ? & \\ \hline 6 & \text { E } & \text { Activity E } & \text { D } & 1 & 14 & 15 & 15 & 16 & \\ \hline 7 & \text { F } & \text { Activity F } & \text { D } & 2 & 14 & 16 & 14 & 16 & \\ \hline 8 & \text { G } & \text { Activity G } & \text { E,F } & 3 & 16 & 19 & 16 & 19 & \\ \hline \end{array}    -Refer to Exhibit 15.1. What values are placed in cell C5 of the spreadsheet?</strong> A) E, F B) B C) C D) B, C   A  B  C DEFGHI1 Activity  Description  Predecessor  Time  EST  EFT  LST  LFT  Slack 2 A  Activity A 404043 B  Activity B  A 347474 C  Activity C  A 246575 D  Activity D ?7????6 E  Activity E  D 1141515167 F  Activity F  D 2141614168 G  Activity G  E,F 316191619\begin{array}{|c|c|c|c|c|c|c|c|c|c|}\hline & \text { A } & \text { B } & \text { C } & \mathrm{D} & \mathrm{E} & \mathrm{F} & \mathrm{G} & \mathrm{H} & \mathrm{I} \\\hline 1 & \text { Activity } & \text { Description } & \text { Predecessor } & \text { Time } & \text { EST } & \text { EFT } & \text { LST } & \text { LFT } & \text { Slack } \\\hline 2 & \text { A } & \text { Activity A } & & 4 & 0 & 4 & 0 & 4 & \\\hline 3 & \text { B } & \text { Activity B } & \text { A } & 3 & 4 & 7 & 4 & 7 & \\\hline 4 & \text { C } & \text { Activity C } & \text { A } & 2 & 4 & 6 & 5 & 7 & \\\hline 5 & \text { D } & \text { Activity D } & ? & 7 & ? & ? & ? & ? & \\\hline 6 & \text { E } & \text { Activity E } & \text { D } & 1 & 14 & 15 & 15 & 16 & \\\hline 7 & \text { F } & \text { Activity F } & \text { D } & 2 & 14 & 16 & 14 & 16 & \\\hline 8 & \text { G } & \text { Activity G } & \text { E,F } & 3 & 16 & 19 & 16 & 19 & \\\hline\end{array}


-Refer to Exhibit 15.1. What values are placed in cell C5 of the spreadsheet?

A) E, F
B) B
C) C
D) B, C
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
22
One of PERT's bold assumptions is that

A) individual activity times are independent of each other.
B) individual activity times are dependent of each other.
C) individual activity times are constant.
D) individual activity times can be added together.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
23
Exhibit 15.1
The following questions employ the AON network and partial spreadsheet below.
 <strong>Exhibit 15.1 The following questions employ the AON network and partial spreadsheet below.    \begin{array}{|c|c|c|c|c|c|c|c|c|c|} \hline & \text { A } & \text { B } & \text { C } & \mathrm{D} & \mathrm{E} & \mathrm{F} & \mathrm{G} & \mathrm{H} & \mathrm{I} \\ \hline 1 & \text { Activity } & \text { Description } & \text { Predecessor } & \text { Time } & \text { EST } & \text { EFT } & \text { LST } & \text { LFT } & \text { Slack } \\ \hline 2 & \text { A } & \text { Activity A } & & 4 & 0 & 4 & 0 & 4 & \\ \hline 3 & \text { B } & \text { Activity B } & \text { A } & 3 & 4 & 7 & 4 & 7 & \\ \hline 4 & \text { C } & \text { Activity C } & \text { A } & 2 & 4 & 6 & 5 & 7 & \\ \hline 5 & \text { D } & \text { Activity D } & ? & 7 & ? & ? & ? & ? & \\ \hline 6 & \text { E } & \text { Activity E } & \text { D } & 1 & 14 & 15 & 15 & 16 & \\ \hline 7 & \text { F } & \text { Activity F } & \text { D } & 2 & 14 & 16 & 14 & 16 & \\ \hline 8 & \text { G } & \text { Activity G } & \text { E,F } & 3 & 16 & 19 & 16 & 19 & \\ \hline \end{array}    -Refer to Exhibit 15.1. What array formula is placed in cell E5 to calculate the Earliest Start Time?</strong> A) E2 + D2 B) MAX(IF(ISERR(FIND($A$5:$A$17,C5)),0,$F$5:$F$17)) C) H2 <font face=symbol>?</font> D2 D) MIN(IF(ISNUMBER(FIND(A5,$C$2:$C$8)),$G$2:$G$8))   A  B  C DEFGHI1 Activity  Description  Predecessor  Time  EST  EFT  LST  LFT  Slack 2 A  Activity A 404043 B  Activity B  A 347474 C  Activity C  A 246575 D  Activity D ?7????6 E  Activity E  D 1141515167 F  Activity F  D 2141614168 G  Activity G  E,F 316191619\begin{array}{|c|c|c|c|c|c|c|c|c|c|}\hline & \text { A } & \text { B } & \text { C } & \mathrm{D} & \mathrm{E} & \mathrm{F} & \mathrm{G} & \mathrm{H} & \mathrm{I} \\\hline 1 & \text { Activity } & \text { Description } & \text { Predecessor } & \text { Time } & \text { EST } & \text { EFT } & \text { LST } & \text { LFT } & \text { Slack } \\\hline 2 & \text { A } & \text { Activity A } & & 4 & 0 & 4 & 0 & 4 & \\\hline 3 & \text { B } & \text { Activity B } & \text { A } & 3 & 4 & 7 & 4 & 7 & \\\hline 4 & \text { C } & \text { Activity C } & \text { A } & 2 & 4 & 6 & 5 & 7 & \\\hline 5 & \text { D } & \text { Activity D } & ? & 7 & ? & ? & ? & ? & \\\hline 6 & \text { E } & \text { Activity E } & \text { D } & 1 & 14 & 15 & 15 & 16 & \\\hline 7 & \text { F } & \text { Activity F } & \text { D } & 2 & 14 & 16 & 14 & 16 & \\\hline 8 & \text { G } & \text { Activity G } & \text { E,F } & 3 & 16 & 19 & 16 & 19 & \\\hline\end{array}


-Refer to Exhibit 15.1. What array formula is placed in cell E5 to calculate the Earliest Start Time?

A) E2 + D2
B) MAX(IF(ISERR(FIND($A$5:$A$17,C5)),0,$F$5:$F$17))
C) H2 ? D2
D) MIN(IF(ISNUMBER(FIND(A5,$C$2:$C$8)),$G$2:$G$8))
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
24
The purpose of the backward pass in the Critical Path Method (CPM) technique is to

A) review each of the precedence relationships in the activity network.
B) calculate the slack time within each node on the activity network.
C) determine the earliest time each activity can start and finish.
D) determine the latest time each activity can start and finish.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
25
If the following project must be completed by day 18 at minimum cost how do we change the LP model? <strong>If the following project must be completed by day 18 at minimum cost how do we change the LP model?  </strong> A) Enter 18 in cell E14. B) Add a constraint that E14 <font face=symbol></font> 18. C) Make cell E14 the target cell. D) Add a constraint that E14 = 18.

A) Enter 18 in cell E14.
B) Add a constraint that E14 18.
C) Make cell E14 the target cell.
D) Add a constraint that E14 = 18.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
26
Slack represents the amount of time by which an activity can be delayed without delaying the entire project, assuming that

A) all successor activities start at their earliest start times.
B) all predecessor activities start at their earliest start times.
C) immediate predecessor activities start at their earliest start times.
D) all predecessor activities start at their latest start times.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
27
Exhibit 15.1
The following questions employ the AON network and partial spreadsheet below.
 <strong>Exhibit 15.1 The following questions employ the AON network and partial spreadsheet below.    \begin{array}{|c|c|c|c|c|c|c|c|c|c|} \hline & \text { A } & \text { B } & \text { C } & \mathrm{D} & \mathrm{E} & \mathrm{F} & \mathrm{G} & \mathrm{H} & \mathrm{I} \\ \hline 1 & \text { Activity } & \text { Description } & \text { Predecessor } & \text { Time } & \text { EST } & \text { EFT } & \text { LST } & \text { LFT } & \text { Slack } \\ \hline 2 & \text { A } & \text { Activity A } & & 4 & 0 & 4 & 0 & 4 & \\ \hline 3 & \text { B } & \text { Activity B } & \text { A } & 3 & 4 & 7 & 4 & 7 & \\ \hline 4 & \text { C } & \text { Activity C } & \text { A } & 2 & 4 & 6 & 5 & 7 & \\ \hline 5 & \text { D } & \text { Activity D } & ? & 7 & ? & ? & ? & ? & \\ \hline 6 & \text { E } & \text { Activity E } & \text { D } & 1 & 14 & 15 & 15 & 16 & \\ \hline 7 & \text { F } & \text { Activity F } & \text { D } & 2 & 14 & 16 & 14 & 16 & \\ \hline 8 & \text { G } & \text { Activity G } & \text { E,F } & 3 & 16 & 19 & 16 & 19 & \\ \hline \end{array}    -Refer to Exhibit 15.1. What array formula is placed in cell H5 to calculate the Latest Finish Time?</strong> A) E2 + D2 B) MAX(IF(ISNUMBER(FIND($A$2:$A$8,C5)),$F$2:$F$8)) C) H2 <font face=symbol>?</font> D2 D) MIN(IF(ISERR(FIND(A5,$C$5:$C$17)),MAX($F$5:$F$17),$G$5:$G$17))   A  B  C DEFGHI1 Activity  Description  Predecessor  Time  EST  EFT  LST  LFT  Slack 2 A  Activity A 404043 B  Activity B  A 347474 C  Activity C  A 246575 D  Activity D ?7????6 E  Activity E  D 1141515167 F  Activity F  D 2141614168 G  Activity G  E,F 316191619\begin{array}{|c|c|c|c|c|c|c|c|c|c|}\hline & \text { A } & \text { B } & \text { C } & \mathrm{D} & \mathrm{E} & \mathrm{F} & \mathrm{G} & \mathrm{H} & \mathrm{I} \\\hline 1 & \text { Activity } & \text { Description } & \text { Predecessor } & \text { Time } & \text { EST } & \text { EFT } & \text { LST } & \text { LFT } & \text { Slack } \\\hline 2 & \text { A } & \text { Activity A } & & 4 & 0 & 4 & 0 & 4 & \\\hline 3 & \text { B } & \text { Activity B } & \text { A } & 3 & 4 & 7 & 4 & 7 & \\\hline 4 & \text { C } & \text { Activity C } & \text { A } & 2 & 4 & 6 & 5 & 7 & \\\hline 5 & \text { D } & \text { Activity D } & ? & 7 & ? & ? & ? & ? & \\\hline 6 & \text { E } & \text { Activity E } & \text { D } & 1 & 14 & 15 & 15 & 16 & \\\hline 7 & \text { F } & \text { Activity F } & \text { D } & 2 & 14 & 16 & 14 & 16 & \\\hline 8 & \text { G } & \text { Activity G } & \text { E,F } & 3 & 16 & 19 & 16 & 19 & \\\hline\end{array}


-Refer to Exhibit 15.1. What array formula is placed in cell H5 to calculate the Latest Finish Time?

A) E2 + D2
B) MAX(IF(ISNUMBER(FIND($A$2:$A$8,C5)),$F$2:$F$8))
C) H2 ? D2
D) MIN(IF(ISERR(FIND(A5,$C$5:$C$17)),MAX($F$5:$F$17),$G$5:$G$17))
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
28
Which activities are critical in the following diagram? <strong>Which activities are critical in the following diagram?  </strong> A) A, C, D, F B) B, D, E C) A, C, D, E D) A, B, D, E, F

A) A, C, D, F
B) B, D, E
C) A, C, D, E
D) A, B, D, E, F
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
29
A strength of Gantt charts is that they

A) clearly portray precedence relationships.
B) model uncertainty in activity duration times.
C) provide a timeline-based, graphical view of when activities can begin and end.
D) clearly identifies the critical path.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
30
What formula should go in cell I5 of the following spreadsheet to compute Actual Time Between Starts? <strong>What formula should go in cell I5 of the following spreadsheet to compute Actual Time Between Starts?  </strong> A) =VLOOKUP(H5,$B$5:$D$11,3)-VLOOKUP(G5,$B$5:$D$11,3) B) =VLOOKUP(H5,$B$5:$D$11,2)-VLOOKUP(G5,$B$5:$D$11,2) C) =VLOOKUP(G5,$B$5:$D$11,3)-VLOOKUP(H5,$B$5:$D$11,3) D) =VLOOKUP(H5,$B$5:$D$11,3)-VLOOKUP(G5,$B$5:$D$11,3)

A) =VLOOKUP(H5,$B$5:$D$11,3)-VLOOKUP(G5,$B$5:$D$11,3)
B) =VLOOKUP(H5,$B$5:$D$11,2)-VLOOKUP(G5,$B$5:$D$11,2)
C) =VLOOKUP(G5,$B$5:$D$11,3)-VLOOKUP(H5,$B$5:$D$11,3)
D) =VLOOKUP(H5,$B$5:$D$11,3)-VLOOKUP(G5,$B$5:$D$11,3)
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
31
Which activities have slack in the following diagram? <strong>Which activities have slack in the following diagram?  </strong> A) A, C, D, F B) B, E C) A, C, D, E D) B, D, E

A) A, C, D, F
B) B, E
C) A, C, D, E
D) B, D, E
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
32
A company wants to use PERT to manage a project. They have developed the following spreadsheet for the problem. If The Risk Solver Platform (RSP) is used, what formula should go in cell F3 of the spreadsheet to compute the Activity Time when simulating a PERT analysis? <strong>A company wants to use PERT to manage a project. They have developed the following spreadsheet for the problem. If The Risk Solver Platform (RSP) is used, what formula should go in cell F3 of the spreadsheet to compute the Activity Time when simulating a PERT analysis?  </strong> A) =IF(E3<font face=symbol></font>(C3-E3)/(D3-B3),D3-SQRT((D3-B3)*(D3-C3)*(1-E3)),B3+SQRT((D3-E3)*(C3-B3)*E3)) B) =IF(E3<font face=symbol></font>(D3-B3)/(C3-E3),B3+SQRT((D3-E3)*(C3-B3)*E3),D3-SQRT((D3-B3)*(D3-C3)*(1-E3))) C) =IF(E3<font face=symbol></font>(C3-E3)/(D3-B3),B3-SQRT((D3-E3)*(C3-B3)*E3),D3+SQRT((D3-B3)*(D3-C3)*(1-E3))) D) =PsiTriangular(B3,C3,D3)

A) =IF(E3(C3-E3)/(D3-B3),D3-SQRT((D3-B3)*(D3-C3)*(1-E3)),B3+SQRT((D3-E3)*(C3-B3)*E3))
B) =IF(E3(D3-B3)/(C3-E3),B3+SQRT((D3-E3)*(C3-B3)*E3),D3-SQRT((D3-B3)*(D3-C3)*(1-E3)))
C) =IF(E3(C3-E3)/(D3-B3),B3-SQRT((D3-E3)*(C3-B3)*E3),D3+SQRT((D3-B3)*(D3-C3)*(1-E3)))
D) =PsiTriangular(B3,C3,D3)
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
33
Exhibit 15.2
The following questions employ the AON network and completed spreadsheet below.
 <strong>Exhibit 15.2 The following questions employ the AON network and completed spreadsheet below.    \begin{array}{|c|c|c|c|c|c|c|c|c|c|} \hline & \text { A } & \text { B } & \text { C } & \mathrm{D} & \mathrm{E} & \mathrm{F} & \mathrm{G} & \mathrm{H} & \mathrm{I} \\ \hline 1 & \text { Activity } & \text { Description } & \text { Predecessor } & \text { Time } & \text { EST } & \text { EFT } & \text { LST } & \text { LFT } & \text { Slack } \\ \hline 2 & \text { A } & \text { Activity A } & & 4 & 0 & 4 & 0 & 4 & 0 \\ \hline 3 & \text { B } & \text { Activity B } & \text { A } & 3 & 4 & 7 & 4 & 7 & 0 \\ \hline 4 & \text { C } & \text { Activity C } & \text { A } & 2 & 4 & 6 & 5 & 7 & 1 \\ \hline 5 & \text { D } & \text { Activity D } & \text { B,C } & 7 & 7 & 14 & 7 & 14 & 0 \\ \hline 6 & \text { E } & \text { Activity E } & \text { D } & 1 & 14 & 15 & 15 & 16 & 1 \\ \hline 7 & \text { F } & \text { Activity F } & \text { D } & 2 & 14 & 16 & 14 & 16 & 0 \\ \hline 8 & \text { G } & \text { Activity G } & \text { E,F } & 3 & 16 & 19 & 16 & 19 & 0 \\ \hline \end{array}    -Refer to Exhibit 15.2. Which of the following activities is not on the critical path for the network?</strong> A) Activity A B) Activity C C) Activity D D) Activity G   A  B  C DEFGHI1 Activity  Description  Predecessor  Time  EST  EFT  LST  LFT  Slack 2 A  Activity A 4040403 B  Activity B  A 3474704 C  Activity C  A 2465715 D  Activity D  B,C 771471406 E  Activity E  D 11415151617 F  Activity F  D 21416141608 G  Activity G  E,F 3161916190\begin{array}{|c|c|c|c|c|c|c|c|c|c|}\hline & \text { A } & \text { B } & \text { C } & \mathrm{D} & \mathrm{E} & \mathrm{F} & \mathrm{G} & \mathrm{H} & \mathrm{I} \\\hline 1 & \text { Activity } & \text { Description } & \text { Predecessor } & \text { Time } & \text { EST } & \text { EFT } & \text { LST } & \text { LFT } & \text { Slack } \\\hline 2 & \text { A } & \text { Activity A } & & 4 & 0 & 4 & 0 & 4 & 0 \\\hline 3 & \text { B } & \text { Activity B } & \text { A } & 3 & 4 & 7 & 4 & 7 & 0 \\\hline 4 & \text { C } & \text { Activity C } & \text { A } & 2 & 4 & 6 & 5 & 7 & 1 \\\hline 5 & \text { D } & \text { Activity D } & \text { B,C } & 7 & 7 & 14 & 7 & 14 & 0 \\\hline 6 & \text { E } & \text { Activity E } & \text { D } & 1 & 14 & 15 & 15 & 16 & 1 \\\hline 7 & \text { F } & \text { Activity F } & \text { D } & 2 & 14 & 16 & 14 & 16 & 0 \\\hline 8 & \text { G } & \text { Activity G } & \text { E,F } & 3 & 16 & 19 & 16 & 19 & 0 \\\hline\end{array}


-Refer to Exhibit 15.2. Which of the following activities is not on the critical path for the network?

A) Activity A
B) Activity C
C) Activity D
D) Activity G
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
34
Shortening the activity completion time is called

A) expediting
B) speeding
C) accelerating
D) crashing
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
35
What formula should go in cell H3 of the following spreadsheet to compute Crash Cost Per Day? <strong>What formula should go in cell H3 of the following spreadsheet to compute Crash Cost Per Day?  </strong> A) =(C3-E3)/(F3-D3) B) =(F3-D3)/(C3-E3) C) =(F3)/(C3-E3) D) =(F3-D3)/(E3)

A) =(C3-E3)/(F3-D3)
B) =(F3-D3)/(C3-E3)
C) =(F3)/(C3-E3)
D) =(F3-D3)/(E3)
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
36
Exhibit 15.2
The following questions employ the AON network and completed spreadsheet below.
 <strong>Exhibit 15.2 The following questions employ the AON network and completed spreadsheet below.    \begin{array}{|c|c|c|c|c|c|c|c|c|c|} \hline & \text { A } & \text { B } & \text { C } & \mathrm{D} & \mathrm{E} & \mathrm{F} & \mathrm{G} & \mathrm{H} & \mathrm{I} \\ \hline 1 & \text { Activity } & \text { Description } & \text { Predecessor } & \text { Time } & \text { EST } & \text { EFT } & \text { LST } & \text { LFT } & \text { Slack } \\ \hline 2 & \text { A } & \text { Activity A } & & 4 & 0 & 4 & 0 & 4 & 0 \\ \hline 3 & \text { B } & \text { Activity B } & \text { A } & 3 & 4 & 7 & 4 & 7 & 0 \\ \hline 4 & \text { C } & \text { Activity C } & \text { A } & 2 & 4 & 6 & 5 & 7 & 1 \\ \hline 5 & \text { D } & \text { Activity D } & \text { B,C } & 7 & 7 & 14 & 7 & 14 & 0 \\ \hline 6 & \text { E } & \text { Activity E } & \text { D } & 1 & 14 & 15 & 15 & 16 & 1 \\ \hline 7 & \text { F } & \text { Activity F } & \text { D } & 2 & 14 & 16 & 14 & 16 & 0 \\ \hline 8 & \text { G } & \text { Activity G } & \text { E,F } & 3 & 16 & 19 & 16 & 19 & 0 \\ \hline \end{array}    -Refer to Exhibit 15.2. What formula is placed in cell G5 to calculate the Latest Start Time?</strong> A) H5 <font face=symbol>?</font> G5 B) F5 <font face=symbol>?</font> G5 C) H5 <font face=symbol>?</font> D5 D) F5 <font face=symbol>?</font> D5   A  B  C DEFGHI1 Activity  Description  Predecessor  Time  EST  EFT  LST  LFT  Slack 2 A  Activity A 4040403 B  Activity B  A 3474704 C  Activity C  A 2465715 D  Activity D  B,C 771471406 E  Activity E  D 11415151617 F  Activity F  D 21416141608 G  Activity G  E,F 3161916190\begin{array}{|c|c|c|c|c|c|c|c|c|c|}\hline & \text { A } & \text { B } & \text { C } & \mathrm{D} & \mathrm{E} & \mathrm{F} & \mathrm{G} & \mathrm{H} & \mathrm{I} \\\hline 1 & \text { Activity } & \text { Description } & \text { Predecessor } & \text { Time } & \text { EST } & \text { EFT } & \text { LST } & \text { LFT } & \text { Slack } \\\hline 2 & \text { A } & \text { Activity A } & & 4 & 0 & 4 & 0 & 4 & 0 \\\hline 3 & \text { B } & \text { Activity B } & \text { A } & 3 & 4 & 7 & 4 & 7 & 0 \\\hline 4 & \text { C } & \text { Activity C } & \text { A } & 2 & 4 & 6 & 5 & 7 & 1 \\\hline 5 & \text { D } & \text { Activity D } & \text { B,C } & 7 & 7 & 14 & 7 & 14 & 0 \\\hline 6 & \text { E } & \text { Activity E } & \text { D } & 1 & 14 & 15 & 15 & 16 & 1 \\\hline 7 & \text { F } & \text { Activity F } & \text { D } & 2 & 14 & 16 & 14 & 16 & 0 \\\hline 8 & \text { G } & \text { Activity G } & \text { E,F } & 3 & 16 & 19 & 16 & 19 & 0 \\\hline\end{array}


-Refer to Exhibit 15.2. What formula is placed in cell G5 to calculate the Latest Start Time?

A) H5 ? G5
B) F5 ? G5
C) H5 ? D5
D) F5 ? D5
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
37
The purpose of the forward pass in the Critical Path Method (CPM) technique is to

A) review each of the precedence relationships in the activity network.
B) calculate the slack time within each node on the activity network.
C) determine the earliest time each activity can start and finish.
D) determine the latest time each activity can start and finish.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
38
A weakness of Gantt charts is that they do not explicitly

A) indicate activity times.
B) show precedence relationships.
C) show activity start times.
D) show activity finish times.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
39
In a PERT network the time required to complete a path is a(n)

A) constant
B) random variable
C) Poisson distributed variable
D) exponentially distributed variable
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
40
The critical path in PERT analysis is the path with the

A) smallest variance.
B) longest expected completion time.
C) smallest number of tasks.
D) smallest variance and longest expected completion time.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
41
Exhibit 15.3
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Exhibit 15.3 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities:   Refer to Exhibit 15.3. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. Based on the data in the spreadsheet, which activities are on the critical path?
Refer to Exhibit 15.3. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. Based on the data in the spreadsheet, which activities are on the critical path?
Exhibit 15.3 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities:   Refer to Exhibit 15.3. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. Based on the data in the spreadsheet, which activities are on the critical path?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
42
Exhibit 15.4
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Exhibit 15.4 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities:   Refer to Exhibit 15.4. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells E2:E8 to calculate Earliest Start Times?
Refer to Exhibit 15.4. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells E2:E8 to calculate Earliest Start Times?
Exhibit 15.4 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities:   Refer to Exhibit 15.4. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells E2:E8 to calculate Earliest Start Times?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
43
A company wants to use PERT to manage a project. They have developed the following spreadsheet for the problem. What formula should go in cell F3 of the spreadsheet to compute the Activity Time when simulating a PERT analysis?
A company wants to use PERT to manage a project. They have developed the following spreadsheet for the problem. What formula should go in cell F3 of the spreadsheet to compute the Activity Time when simulating a PERT analysis?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
44
Exhibit 15.4
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Exhibit 15.4 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities:   Refer to Exhibit 15.4. Manually determine the earliest and latest start and finish times for each activity and the amount of slack for each activity. What is the critical path for the project and how long should it take to complete it?
Refer to Exhibit 15.4. Manually determine the earliest and latest start and finish times for each activity and the amount of slack for each activity. What is the critical path for the project and how long should it take to complete it?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
45
Exhibit 15.4
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Exhibit 15.4 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities:   Refer to Exhibit 15.4. Draw the CPM network for this problem. Use AON notation.
Refer to Exhibit 15.4. Draw the CPM network for this problem. Use AON notation.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
46
Exhibit 15.3
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Exhibit 15.3 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities:   Refer to Exhibit 15.3. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells H2:H8 to calculate Latest Finish Times?
Refer to Exhibit 15.3. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells H2:H8 to calculate Latest Finish Times?
Exhibit 15.3 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities:   Refer to Exhibit 15.3. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells H2:H8 to calculate Latest Finish Times?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
47
Exhibit 15.5
The following questions use the information below.
A company wants to crash a project and reduce the time required to complete it. They have developed the following table of activity costs and times and a spreadsheet to compute starting time for each activity.
Exhibit 15.5 The following questions use the information below. A company wants to crash a project and reduce the time required to complete it. They have developed the following table of activity costs and times and a spreadsheet to compute starting time for each activity.     Refer to Exhibit 15.5. What formula should go in cell H3 of the Costs spreadsheet to compute Crash Cost Per Day? Exhibit 15.5 The following questions use the information below. A company wants to crash a project and reduce the time required to complete it. They have developed the following table of activity costs and times and a spreadsheet to compute starting time for each activity.     Refer to Exhibit 15.5. What formula should go in cell H3 of the Costs spreadsheet to compute Crash Cost Per Day?
Refer to Exhibit 15.5. What formula should go in cell H3 of the Costs spreadsheet to compute Crash Cost Per Day?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
48
Exhibit 15.5
The following questions use the information below.
A company wants to crash a project and reduce the time required to complete it. They have developed the following table of activity costs and times and a spreadsheet to compute starting time for each activity.
Exhibit 15.5 The following questions use the information below. A company wants to crash a project and reduce the time required to complete it. They have developed the following table of activity costs and times and a spreadsheet to compute starting time for each activity.     Refer to Exhibit 15.5. What formula should go in cell I5 of the Model spreadsheet to compute Actual Time Between Starts? Exhibit 15.5 The following questions use the information below. A company wants to crash a project and reduce the time required to complete it. They have developed the following table of activity costs and times and a spreadsheet to compute starting time for each activity.     Refer to Exhibit 15.5. What formula should go in cell I5 of the Model spreadsheet to compute Actual Time Between Starts?
Refer to Exhibit 15.5. What formula should go in cell I5 of the Model spreadsheet to compute Actual Time Between Starts?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
49
Exhibit 15.6
The following questions use the information below.
Consider the CPM network for the following set of activities:
Exhibit 15.6 The following questions use the information below. Consider the CPM network for the following set of activities:   Refer to Exhibit 15.6. Is it necessary to draw an arc from the node for activity F to the node for activity I?
Refer to Exhibit 15.6. Is it necessary to draw an arc from the node for activity F to the node for activity I?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
50
Exhibit 15.3
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Exhibit 15.3 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities:   Refer to Exhibit 15.3. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells E2:E8 to calculate Earliest Start Times?
Refer to Exhibit 15.3. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells E2:E8 to calculate Earliest Start Times?
Exhibit 15.3 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities:   Refer to Exhibit 15.3. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells E2:E8 to calculate Earliest Start Times?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
51
Exhibit 15.3
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Exhibit 15.3 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities:   Refer to Exhibit 15.3. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells F2:F8 to calculate Earliest Finish Times, G2:G8 to calculate Latest Start Times, and cells I2:I8 to calculate the Slack?
Refer to Exhibit 15.3. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells F2:F8 to calculate Earliest Finish Times, G2:G8 to calculate Latest Start Times, and cells I2:I8 to calculate the Slack?
Exhibit 15.3 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities:   Refer to Exhibit 15.3. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells F2:F8 to calculate Earliest Finish Times, G2:G8 to calculate Latest Start Times, and cells I2:I8 to calculate the Slack?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
52
Exhibit 15.4
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Exhibit 15.4 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities:   Refer to Exhibit 15.4. Identify each path through the network and its expected length.
Refer to Exhibit 15.4. Identify each path through the network and its expected length.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
53
Exhibit 15.3
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Exhibit 15.3 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities:   Refer to Exhibit 15.3. Identify each path through the network and its expected length.
Refer to Exhibit 15.3. Identify each path through the network and its expected length.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
54
Exhibit 15.3
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Exhibit 15.3 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities:   Refer to Exhibit 15.3. Draw the CPM network for this problem. Use AON notation.
Refer to Exhibit 15.3. Draw the CPM network for this problem. Use AON notation.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
55
Exhibit 15.4
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Exhibit 15.4 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities:   Refer to Exhibit 15.4. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells F2:F8 to calculate Earliest Finish Times, G2:G8 to calculate Latest Start Times, and cells I2:I8 to calculate the Slack?
Refer to Exhibit 15.4. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells F2:F8 to calculate Earliest Finish Times, G2:G8 to calculate Latest Start Times, and cells I2:I8 to calculate the Slack?
Exhibit 15.4 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities:   Refer to Exhibit 15.4. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells F2:F8 to calculate Earliest Finish Times, G2:G8 to calculate Latest Start Times, and cells I2:I8 to calculate the Slack?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
56
Exhibit 15.3
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Exhibit 15.3 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities:   Refer to Exhibit 15.3. Manually determine the earliest and latest start and finish times for each activity and the amount of slack for each activity. What is the critical path for the project and how long should it take to complete it?
Refer to Exhibit 15.3. Manually determine the earliest and latest start and finish times for each activity and the amount of slack for each activity. What is the critical path for the project and how long should it take to complete it?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
57
Exhibit 15.6
The following questions use the information below.
Consider the CPM network for the following set of activities:
Exhibit 15.6 The following questions use the information below. Consider the CPM network for the following set of activities:   Refer to Exhibit 15.6. Is it necessary to draw an arc from the node for activity A to the node for activity C?
Refer to Exhibit 15.6. Is it necessary to draw an arc from the node for activity A to the node for activity C?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
58
Exhibit 15.4
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Exhibit 15.4 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities:   Refer to Exhibit 15.4. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. Based on the data in the spreadsheet, which activities are on the critical path?
Refer to Exhibit 15.4. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. Based on the data in the spreadsheet, which activities are on the critical path?
Exhibit 15.4 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities:   Refer to Exhibit 15.4. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. Based on the data in the spreadsheet, which activities are on the critical path?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
59
Exhibit 15.4
The following questions are based on the information below.
A company needs to manage a project which consists of the following set of activities:
Exhibit 15.4 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities:   Refer to Exhibit 15.4. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells H2:H8 to calculate Latest Finish Times?
Refer to Exhibit 15.4. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells H2:H8 to calculate Latest Finish Times?
Exhibit 15.4 The following questions are based on the information below. A company needs to manage a project which consists of the following set of activities:   Refer to Exhibit 15.4. The following spreadsheet was developed to determine the earliest start times and latest start times for the project. What formulas should go into cells H2:H8 to calculate Latest Finish Times?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
60
Exhibit 15.5
The following questions use the information below.
A company wants to crash a project and reduce the time required to complete it. They have developed the following table of activity costs and times and a spreadsheet to compute starting time for each activity.
Exhibit 15.5 The following questions use the information below. A company wants to crash a project and reduce the time required to complete it. They have developed the following table of activity costs and times and a spreadsheet to compute starting time for each activity.     Refer to Exhibit 15.5. If the following project must be completed by day 18 at minimum cost how do we change the LP model? Exhibit 15.5 The following questions use the information below. A company wants to crash a project and reduce the time required to complete it. They have developed the following table of activity costs and times and a spreadsheet to compute starting time for each activity.     Refer to Exhibit 15.5. If the following project must be completed by day 18 at minimum cost how do we change the LP model?
Refer to Exhibit 15.5. If the following project must be completed by day 18 at minimum cost how do we change the LP model?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
61
Exhibit 15.6
The following questions use the information below.
Consider the CPM network for the following set of activities:
Exhibit 15.6 The following questions use the information below. Consider the CPM network for the following set of activities:   Refer to Exhibit 15.6. Modify the table above by completing the following table. For column 3, list only the immediate predecessors for each activity.
Refer to Exhibit 15.6. Modify the table above by completing the following table. For column 3, list only the immediate predecessors for each activity.
Exhibit 15.6 The following questions use the information below. Consider the CPM network for the following set of activities:   Refer to Exhibit 15.6. Modify the table above by completing the following table. For column 3, list only the immediate predecessors for each activity.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
locked card icon
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.