سؤال
Time variance is calculated by subtracting actual time used for work performed from scheduled time for work performed.
استخدم زر المسافة أو
up arrow
down arrow
لقلب البطاقة.
سؤال
The term Late Finish refers to the latest time an activity can begin without delaying the completion of the project.
سؤال
A project can be defined as a set of complex interrelated tasks with different requirements regarding activity time and resources, but with a high degree of repetitiveness.
سؤال
Developing a project network is the only major concern for implementing critical path analysis.
سؤال
It is possible to delay the start of a non-critical activity and, in the process, make a following activity critical.
سؤال
The term calendar is used in project management to keep track of the days and hours required for completion of projects.
سؤال
When delays occur owing to technical difficulties, performance becomes the source of unexpected project management problems.
سؤال
The single important attribute of a project manager is leadership ability.
سؤال
A major flaw in critical path analysis with uncertain activity times is the conservative nature of the expected project completion time.
سؤال
The critical path refers to the sequence of activities that represent the longest time path through a project network.
سؤال
Merge node bias occurs where the project network contains non-critical paths with small total slack times.
سؤال
Schedule variance is the difference between budgeted cost for work performed and actual cost of work performed.
سؤال
The term total slack refers to the amount of time an activity can be delayed without delaying the start of a subsequent activity.
سؤال
Total slack for an activity can be shared with following activities.
سؤال
Gantt charts fail to indicate the interdependence among project activities.
سؤال
A major assumption in project network analysis is that sufficient resources are available to perform many activities concurrently.
Multiple Choice
سؤال
When crashing activities for construction projects, the contractor's minimum cost duration might not coincide with the client's target completion date.
سؤال
The critical path for a project with uncertain activity times is not known for certain until after the project is completed.
سؤال
Estimates of project expected completion time and variance usually are not biased when based on the single critical path.
سؤال
Before calculating a Late Start time for an activity, the Late Finish time must be known.
سؤال
A major weakness with project completion time analysis with uncertain activity times is the:

A) possibility that more than one critical path might exist.
B) need to solicit three time estimates for each activity.
C) assumption that the project completion time is normally distributed.
D) bias associated with the expected project completion time.
سؤال
For a project with uncertain activity times, the probability of project completion exceeding the expected time calculated for the critical path is:

A) 25 percent.
B) 50 percent.
C) 75 percent.
D) none of the above.
سؤال
The four sequential stages of team development include all but one of the following:

A) forming.
B) storming.
C) coalescing.
D) performing.
سؤال
Which one of the following is not a critical time estimate for a Beta distribution?

A) optimistic time.
B) pessimistic time.
C) most likely time.
D) expected time.
سؤال
Which of the following is not true about a critical path in a project network with certain activity times?

A) Activities on the critical path have the least slack.
B) The longest activity in the project must lie on the critical path.
C) There can be several critical paths in a project network.
D) The first activity in the network is always on the critical path.
سؤال
Implementing critical path analysis is faced with all but one of the following problems:

A) availability of project management software.
B) agreement on the project network.
C) eliciting time estimates for activities.
D) introduction of bias in activity time estimates.
سؤال
Which oneof the following is not considered a source of unexpected project management problems?

A) cost.
B) time.
C) economy.
D) performance.
سؤال
A project history report should include all but one of the following items:

A) project performance.
B) organization structure.
C) project success and failures.
D) project and administrative team.
سؤال
The Beta distribution is useful in network analysis because it:

A) provides formulas for calculating the activity mean and variance.
B) can be approximated by a normal distribution.
C) provides probability estimates for project completion time.
D) requires only three time estimates to describe uncertain activity duration.
سؤال
Which one of the following attributes is not considered in the selection of a project manager?

A) credibility.
B) originality.
C) sensitivity.
D) ability to handle stress.
سؤال
The amount of time an activity can be delayed without delaying the completion of the project is referred to as:

A) total slack.
B) late finish.
C) late start.
D) free slack.
سؤال
Gantt project charts are useful for all but one of the following reasons:

A) visual presentation is appealing.
B) they show interdependence of activities.
C) they are easy to understand.
D) they assist in planning construction forces.
سؤال
Which one of the following is not considered a source of variance on the earned value chart?

A) time.
B) cost.
C) schedule.
D) none of the above.
سؤال
Which one of the following allows the manager to make probability statements with regard to meeting project objectives?

A) Gantt chart.
B) CPM.
C) PERT.
D) earned-value chart.
سؤال
Monte Carlo simulation of project networks is not recommended when:

A) activity times are deterministic.
B) more than one critical path exists.
C) bias in project completion time is important.
D) activity time distributions are Beta.
سؤال
Projects are terminated for all but one of the following reasons:

A) subtraction.
B) addition.
C) integration.
D) starvation.
سؤال
Which one of the following makes performance a source of unexpected project management problem?

A) delays owing to technical difficulties.
B) unexpected technical problems.
C) unforeseen government regulations.
D) increase in the scope of work.
سؤال
A resource-leveled schedule would have all but one of the following characteristics:

A) the project duration could be longer than normal.
B) slack time is used to begin some activities later than their early start time.
C) the critical path may be changed.
D) a more balanced use of labor resources would be exhibited.
سؤال
Which one of the following is not an objective of activity crashing?

A) reduce the total cost of completing a project.
B) complete a project in less time than normally expected.
C) create multiple critical paths.
D) prepare a contract bid.
سؤال
A key assumption underlying project networks is:

A) dummy activities take up no time.
B) the critical path is known with certainty.
C) an activity begins only after all predecessors are completed.
D) a project network is cyclic.
فتح الحزمة
قم بالتسجيل لفتح البطاقات في هذه المجموعة!
Unlock Deck
Unlock Deck
1/40
auto play flashcards
العب
simple tutorial
ملء الشاشة (f)
exit full mode
Deck 16: Managing Service Projects
1
Time variance is calculated by subtracting actual time used for work performed from scheduled time for work performed.
True
2
The term Late Finish refers to the latest time an activity can begin without delaying the completion of the project.
False
3
A project can be defined as a set of complex interrelated tasks with different requirements regarding activity time and resources, but with a high degree of repetitiveness.
False
4
Developing a project network is the only major concern for implementing critical path analysis.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 40 في هذه المجموعة.
فتح الحزمة
k this deck
5
It is possible to delay the start of a non-critical activity and, in the process, make a following activity critical.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 40 في هذه المجموعة.
فتح الحزمة
k this deck
6
The term calendar is used in project management to keep track of the days and hours required for completion of projects.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 40 في هذه المجموعة.
فتح الحزمة
k this deck
7
When delays occur owing to technical difficulties, performance becomes the source of unexpected project management problems.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 40 في هذه المجموعة.
فتح الحزمة
k this deck
8
The single important attribute of a project manager is leadership ability.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 40 في هذه المجموعة.
فتح الحزمة
k this deck
9
A major flaw in critical path analysis with uncertain activity times is the conservative nature of the expected project completion time.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 40 في هذه المجموعة.
فتح الحزمة
k this deck
10
The critical path refers to the sequence of activities that represent the longest time path through a project network.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 40 في هذه المجموعة.
فتح الحزمة
k this deck
11
Merge node bias occurs where the project network contains non-critical paths with small total slack times.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 40 في هذه المجموعة.
فتح الحزمة
k this deck
12
Schedule variance is the difference between budgeted cost for work performed and actual cost of work performed.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 40 في هذه المجموعة.
فتح الحزمة
k this deck
13
The term total slack refers to the amount of time an activity can be delayed without delaying the start of a subsequent activity.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 40 في هذه المجموعة.
فتح الحزمة
k this deck
14
Total slack for an activity can be shared with following activities.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 40 في هذه المجموعة.
فتح الحزمة
k this deck
15
Gantt charts fail to indicate the interdependence among project activities.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 40 في هذه المجموعة.
فتح الحزمة
k this deck
16
A major assumption in project network analysis is that sufficient resources are available to perform many activities concurrently.
Multiple Choice
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 40 في هذه المجموعة.
فتح الحزمة
k this deck
17
When crashing activities for construction projects, the contractor's minimum cost duration might not coincide with the client's target completion date.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 40 في هذه المجموعة.
فتح الحزمة
k this deck
18
The critical path for a project with uncertain activity times is not known for certain until after the project is completed.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 40 في هذه المجموعة.
فتح الحزمة
k this deck
19
Estimates of project expected completion time and variance usually are not biased when based on the single critical path.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 40 في هذه المجموعة.
فتح الحزمة
k this deck
20
Before calculating a Late Start time for an activity, the Late Finish time must be known.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 40 في هذه المجموعة.
فتح الحزمة
k this deck
21
A major weakness with project completion time analysis with uncertain activity times is the:

A) possibility that more than one critical path might exist.
B) need to solicit three time estimates for each activity.
C) assumption that the project completion time is normally distributed.
D) bias associated with the expected project completion time.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 40 في هذه المجموعة.
فتح الحزمة
k this deck
22
For a project with uncertain activity times, the probability of project completion exceeding the expected time calculated for the critical path is:

A) 25 percent.
B) 50 percent.
C) 75 percent.
D) none of the above.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 40 في هذه المجموعة.
فتح الحزمة
k this deck
23
The four sequential stages of team development include all but one of the following:

A) forming.
B) storming.
C) coalescing.
D) performing.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 40 في هذه المجموعة.
فتح الحزمة
k this deck
24
Which one of the following is not a critical time estimate for a Beta distribution?

A) optimistic time.
B) pessimistic time.
C) most likely time.
D) expected time.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 40 في هذه المجموعة.
فتح الحزمة
k this deck
25
Which of the following is not true about a critical path in a project network with certain activity times?

A) Activities on the critical path have the least slack.
B) The longest activity in the project must lie on the critical path.
C) There can be several critical paths in a project network.
D) The first activity in the network is always on the critical path.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 40 في هذه المجموعة.
فتح الحزمة
k this deck
26
Implementing critical path analysis is faced with all but one of the following problems:

A) availability of project management software.
B) agreement on the project network.
C) eliciting time estimates for activities.
D) introduction of bias in activity time estimates.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 40 في هذه المجموعة.
فتح الحزمة
k this deck
27
Which oneof the following is not considered a source of unexpected project management problems?

A) cost.
B) time.
C) economy.
D) performance.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 40 في هذه المجموعة.
فتح الحزمة
k this deck
28
A project history report should include all but one of the following items:

A) project performance.
B) organization structure.
C) project success and failures.
D) project and administrative team.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 40 في هذه المجموعة.
فتح الحزمة
k this deck
29
The Beta distribution is useful in network analysis because it:

A) provides formulas for calculating the activity mean and variance.
B) can be approximated by a normal distribution.
C) provides probability estimates for project completion time.
D) requires only three time estimates to describe uncertain activity duration.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 40 في هذه المجموعة.
فتح الحزمة
k this deck
30
Which one of the following attributes is not considered in the selection of a project manager?

A) credibility.
B) originality.
C) sensitivity.
D) ability to handle stress.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 40 في هذه المجموعة.
فتح الحزمة
k this deck
31
The amount of time an activity can be delayed without delaying the completion of the project is referred to as:

A) total slack.
B) late finish.
C) late start.
D) free slack.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 40 في هذه المجموعة.
فتح الحزمة
k this deck
32
Gantt project charts are useful for all but one of the following reasons:

A) visual presentation is appealing.
B) they show interdependence of activities.
C) they are easy to understand.
D) they assist in planning construction forces.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 40 في هذه المجموعة.
فتح الحزمة
k this deck
33
Which one of the following is not considered a source of variance on the earned value chart?

A) time.
B) cost.
C) schedule.
D) none of the above.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 40 في هذه المجموعة.
فتح الحزمة
k this deck
34
Which one of the following allows the manager to make probability statements with regard to meeting project objectives?

A) Gantt chart.
B) CPM.
C) PERT.
D) earned-value chart.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 40 في هذه المجموعة.
فتح الحزمة
k this deck
35
Monte Carlo simulation of project networks is not recommended when:

A) activity times are deterministic.
B) more than one critical path exists.
C) bias in project completion time is important.
D) activity time distributions are Beta.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 40 في هذه المجموعة.
فتح الحزمة
k this deck
36
Projects are terminated for all but one of the following reasons:

A) subtraction.
B) addition.
C) integration.
D) starvation.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 40 في هذه المجموعة.
فتح الحزمة
k this deck
37
Which one of the following makes performance a source of unexpected project management problem?

A) delays owing to technical difficulties.
B) unexpected technical problems.
C) unforeseen government regulations.
D) increase in the scope of work.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 40 في هذه المجموعة.
فتح الحزمة
k this deck
38
A resource-leveled schedule would have all but one of the following characteristics:

A) the project duration could be longer than normal.
B) slack time is used to begin some activities later than their early start time.
C) the critical path may be changed.
D) a more balanced use of labor resources would be exhibited.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 40 في هذه المجموعة.
فتح الحزمة
k this deck
39
Which one of the following is not an objective of activity crashing?

A) reduce the total cost of completing a project.
B) complete a project in less time than normally expected.
C) create multiple critical paths.
D) prepare a contract bid.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 40 في هذه المجموعة.
فتح الحزمة
k this deck
40
A key assumption underlying project networks is:

A) dummy activities take up no time.
B) the critical path is known with certainty.
C) an activity begins only after all predecessors are completed.
D) a project network is cyclic.