Deck 8: Modifying Project Schedules to Accommodate Time and Resource Constraints

ملء الشاشة (f)
exit full mode
سؤال
In critical chain terminology, removing some of the time buffer from individual activity estimates and moving them collectively to the end of the project is an example of:

A) Inserting a project buffer
B) Inserting a feeding buffer
C) Inserting a resource buffer
D) Inserting float
E) Inserting a critical path
استخدم زر المسافة أو
up arrow
down arrow
لقلب البطاقة.
سؤال
Using the following figures, what is the incremental crash cost for this project activity?
Normal time = 6 months, Crash time = 4 months
Normal cost = $27,000, Crash cost = $35,000

A) $16,000 per month
B) $8,000 per month
C) $4,000 per month
D) $6,000 per month
E) None of the above
سؤال
The next three questions relate to the following scenario: Erica is planning a large surprise party for her best friend. She has developed the plan below which includes estimates of the time in hours) and cost necessary to perform each of the activities required.
 Activity  Predeces sor  Normal  Time  (hrs)  Crash  Time  (hrs)  Norm al  Cost  Crash  Cost  A. Create Guest List 84$200$310 B. Send Invitations  A 21$125$150 C. Plan Decorations  A 86$300$370 D. Plan Menu  A 32$150$210 E. Shop  D 42$475$550 F. Prepare Food  E 53$225$475\begin{array} { | l | c | c | c | c | c | } \hline \text { Activity } & \text { Predeces sor } & \begin{array} { c } \text { Normal } \\\text { Time } \\\text { (hrs) }\end{array} & \begin{array} { c } \text { Crash } \\\text { Time } \\\text { (hrs) }\end{array} & \begin{array} { c } \text { Norm al } \\\text { Cost }\end{array} & \begin{array} { c } \text { Crash } \\\text { Cost }\end{array} \\\hline \text { A. Create Guest List } & - - & 8 & 4 & \$ 200 & \$ 310 \\\hline \text { B. Send Invitations } & \text { A } & 2 & 1 & \$ 125 & \$ 150 \\\hline \text { C. Plan Decorations } & \text { A } & 8 & 6 & \$ 300 & \$ 370 \\\hline \text { D. Plan Menu } & \text { A } & 3 & 2 & \$ 150 & \$ 210 \\\hline \text { E. Shop } & \text { D } & 4 & 2 & \$ 475 & \$ 550 \\\hline \text { F. Prepare Food } & \text { E } & 5 & 3 & \$ 225 & \$ 475 \\\hline\end{array}


-To reduce the time for Activity F, Prepare Food, Erica can purchase some of the food from a caterer rather than cook it herself. As shown in the table above, this can reduce the time for Activity F by one or two hours, depending on how much catered food she purchases. What is the crash cost per hour for this activity?

A) $225
B) $475
C) $250
D) $125
E) $83.33
F) None of these, the answer is: ____________________
سؤال
Which of the following would NOT be considered a direct activity cost?

A) Rework expenses
B) overhead costs
C) overtime salaries
D) costs to rent or purchase additional equipment
E) costs associated with increased coordination
سؤال
Ganesh has been asked to create a project team for a major web development effort. He and the project sponsor have discussed team size and they are debating two options:
-Perform the project in 12 months with a team of 15 people
-Crash the project and complete it in 6 months with a team of 34 people
Which of the following will be true about the contrast between these two options?

A) Option II is likely to require more coordination than Option I.
B) Option I is likely to be more expensive than Option II.
C) Option II will require more than five times as many communication channels as Option I.
D) a and c only.
E) b and c only.
سؤال
Which of the following characteristics would make an activity an unattractive candidate for crashing?

A) it is in a bottleneck position
B) it has a long duration
C) employees required to do the job have highly specialized skills
D) it is on the critical path
E) it is labor intensive and employees can be added easily
سؤال
The next three questions are related to the project schedule shown below, which has been adjusted to accommodate resource constraints.
<strong>The next three questions are related to the project schedule shown below, which has been adjusted to accommodate resource constraints.     -Given the way the schedule shown above is currently planned, what sequence of activities comprises the critical chain? Dashed lines = float.) </strong> A) A-B-C-F-H-J B) A-B-D-J C) A-B-D-G-I-J D) A-B-C-G-I-J E) ABEGIJ F) A-E-J <div style=padding-top: 35px>


-Given the way the schedule shown above is currently planned, what sequence of activities comprises the critical chain? Dashed lines = float.)

A) A-B-C-F-H-J
B) A-B-D-J
C) A-B-D-G-I-J
D) A-B-C-G-I-J
E) ABEGIJ
F) A-E-J
سؤال
In evaluating time-cost tradeoffs, we start by crashing the activity on the critical path that:

A) has the lowest crash cost per unit time.
B) has the lowest total crash cost.
C) can be reduced the most.
D) is the longest.
E) none of the above.
سؤال
What is the critical chain in the schedule below?
<strong>What is the critical chain in the schedule below?   </strong> A) A-B-D-F-G B) A-C-E-G C) A-B-D-E-G D) A-B-D-E-F-G E) ABDFG F) None of the above <div style=padding-top: 35px>

A) A-B-D-F-G
B) A-C-E-G
C) A-B-D-E-G
D) A-B-D-E-F-G
E) ABDFG
F) None of the above
سؤال
The next three questions relate to the following scenario: Erica is planning a large surprise party for her best friend. She has developed the plan below which includes estimates of the time in hours) and cost necessary to perform each of the activities required.
 Activity  Predeces sor  Normal  Time  (hrs)  Crash  Time  (hrs)  Norm al  Cost  Crash  Cost  A. Create Guest List 84$200$310 B. Send Invitations  A 21$125$150 C. Plan Decorations  A 86$300$370 D. Plan Menu  A 32$150$210 E. Shop  D 42$475$550 F. Prepare Food  E 53$225$475\begin{array} { | l | c | c | c | c | c | } \hline \text { Activity } & \text { Predeces sor } & \begin{array} { c } \text { Normal } \\\text { Time } \\\text { (hrs) }\end{array} & \begin{array} { c } \text { Crash } \\\text { Time } \\\text { (hrs) }\end{array} & \begin{array} { c } \text { Norm al } \\\text { Cost }\end{array} & \begin{array} { c } \text { Crash } \\\text { Cost }\end{array} \\\hline \text { A. Create Guest List } & - - & 8 & 4 & \$ 200 & \$ 310 \\\hline \text { B. Send Invitations } & \text { A } & 2 & 1 & \$ 125 & \$ 150 \\\hline \text { C. Plan Decorations } & \text { A } & 8 & 6 & \$ 300 & \$ 370 \\\hline \text { D. Plan Menu } & \text { A } & 3 & 2 & \$ 150 & \$ 210 \\\hline \text { E. Shop } & \text { D } & 4 & 2 & \$ 475 & \$ 550 \\\hline \text { F. Prepare Food } & \text { E } & 5 & 3 & \$ 225 & \$ 475 \\\hline\end{array}


-Based on critical chain concepts, which of the following is true of a resource buffer?

A) A resource buffer involves information sharing between sequentially-linked tasks on the critical chain.
B) A resource buffer collects time at the end of the project.
C) A resource buffer specifies a minimum amount of free float to protect the critical chain from the effects of potential delays in non-critical chain activities.
D) A resource buffer adds extra human or financial resources to the critical chain to account for potential uncertainties in task times.
E) A and B only.
سؤال
Which of the following is most associated with fast tracking?

A) A waterfall-type schedule
B) Project activities are delayed to accommodate resource conflicts
C) Finish-to-start precedence logic
D) Start-to-start precedence logic
E) Paying incentives for faster work
سؤال
When is crashing beneficial to a project?

A) When the cost of crashing by one day is less than the project's daily overhead cost
B) When the cost of crashing by one day is more than the project's daily overhead cost.
C) When there are no delay penalties
D) When the task to be crashed is not on the critical path
E) A and C
سؤال
Fast tracking is defined as:

A) adding resources to reduce the time required for selected project activities.
B) eliminating tasks or deliverables from the WBS.
C) compressing a project schedule to meet market demands.
D) increasing the efficiency of the employees performing the task.
E) rescheduling sequential tasks to take place simultaneously.
سؤال
The next three questions are related to the project schedule shown below, which has been adjusted to accommodate resource constraints.
<strong>The next three questions are related to the project schedule shown below, which has been adjusted to accommodate resource constraints.     -In the network shown above, given the current placement of float, where would a feeding buffer be most appropriate from among the options below? </strong> A) Between A and B B) Between D and J C) Between E and G D) Between F and H E) Between E and I <div style=padding-top: 35px>


-In the network shown above, given the current placement of float, where would a feeding buffer be most appropriate from among the options below?

A) Between A and B
B) Between D and J
C) Between E and G
D) Between F and H
E) Between E and I
سؤال
The next three questions relate to the following scenario: Erica is planning a large surprise party for her best friend. She has developed the plan below which includes estimates of the time in hours) and cost necessary to perform each of the activities required.
 Activity  Predeces sor  Normal  Time  (hrs)  Crash  Time  (hrs)  Norm al  Cost  Crash  Cost  A. Create Guest List 84$200$310 B. Send Invitations  A 21$125$150 C. Plan Decorations  A 86$300$370 D. Plan Menu  A 32$150$210 E. Shop  D 42$475$550 F. Prepare Food  E 53$225$475\begin{array} { | l | c | c | c | c | c | } \hline \text { Activity } & \text { Predeces sor } & \begin{array} { c } \text { Normal } \\\text { Time } \\\text { (hrs) }\end{array} & \begin{array} { c } \text { Crash } \\\text { Time } \\\text { (hrs) }\end{array} & \begin{array} { c } \text { Norm al } \\\text { Cost }\end{array} & \begin{array} { c } \text { Crash } \\\text { Cost }\end{array} \\\hline \text { A. Create Guest List } & - - & 8 & 4 & \$ 200 & \$ 310 \\\hline \text { B. Send Invitations } & \text { A } & 2 & 1 & \$ 125 & \$ 150 \\\hline \text { C. Plan Decorations } & \text { A } & 8 & 6 & \$ 300 & \$ 370 \\\hline \text { D. Plan Menu } & \text { A } & 3 & 2 & \$ 150 & \$ 210 \\\hline \text { E. Shop } & \text { D } & 4 & 2 & \$ 475 & \$ 550 \\\hline \text { F. Prepare Food } & \text { E } & 5 & 3 & \$ 225 & \$ 475 \\\hline\end{array}


-Erica's internet-based business pays her about $40 per hour. Therefore, for every hour she works on this party project, she will experience a lost opportunity cost of $40. She would initially like to test the idea of reducing project duration by one hour. Which activity should she crash first?

A) A
B) D
C) C
D) E
E) B
سؤال
Research has shown that multitasking has been linked with:

A) Enhanced efficiency.
B) Expanded brain function.
C) Increased short-term memory capacity.
D) Reduced stress.
E) All of the above.
F) None of the above.
سؤال
What is the difference between the critical path and the critical chain?

A) The critical path considers resource availability and the critical chain does not
B) The critical chain considers resource availability and the critical path does not
C) There is no difference - they are exactly the same
D) It is possible to crash activities on the critical path, but activities on the critical chain have already been reduced to their shortest feasible durations.
E) None of the above
سؤال
The next three questions are related to the project schedule shown below, which has been adjusted to accommodate resource constraints.
<strong>The next three questions are related to the project schedule shown below, which has been adjusted to accommodate resource constraints.     -In the network shown above, where would a resource buffer be most appropriate from among the options below? </strong> A) Between H and J B) Between A and C C) Between B and C D) Between C and F E) Between D and J <div style=padding-top: 35px>


-In the network shown above, where would a resource buffer be most appropriate from among the options below?

A) Between H and J
B) Between A and C
C) Between B and C
D) Between C and F
E) Between D and J
فتح الحزمة
قم بالتسجيل لفتح البطاقات في هذه المجموعة!
Unlock Deck
Unlock Deck
1/18
auto play flashcards
العب
simple tutorial
ملء الشاشة (f)
exit full mode
Deck 8: Modifying Project Schedules to Accommodate Time and Resource Constraints
1
In critical chain terminology, removing some of the time buffer from individual activity estimates and moving them collectively to the end of the project is an example of:

A) Inserting a project buffer
B) Inserting a feeding buffer
C) Inserting a resource buffer
D) Inserting float
E) Inserting a critical path
Inserting a project buffer
2
Using the following figures, what is the incremental crash cost for this project activity?
Normal time = 6 months, Crash time = 4 months
Normal cost = $27,000, Crash cost = $35,000

A) $16,000 per month
B) $8,000 per month
C) $4,000 per month
D) $6,000 per month
E) None of the above
$4,000 per month
3
The next three questions relate to the following scenario: Erica is planning a large surprise party for her best friend. She has developed the plan below which includes estimates of the time in hours) and cost necessary to perform each of the activities required.
 Activity  Predeces sor  Normal  Time  (hrs)  Crash  Time  (hrs)  Norm al  Cost  Crash  Cost  A. Create Guest List 84$200$310 B. Send Invitations  A 21$125$150 C. Plan Decorations  A 86$300$370 D. Plan Menu  A 32$150$210 E. Shop  D 42$475$550 F. Prepare Food  E 53$225$475\begin{array} { | l | c | c | c | c | c | } \hline \text { Activity } & \text { Predeces sor } & \begin{array} { c } \text { Normal } \\\text { Time } \\\text { (hrs) }\end{array} & \begin{array} { c } \text { Crash } \\\text { Time } \\\text { (hrs) }\end{array} & \begin{array} { c } \text { Norm al } \\\text { Cost }\end{array} & \begin{array} { c } \text { Crash } \\\text { Cost }\end{array} \\\hline \text { A. Create Guest List } & - - & 8 & 4 & \$ 200 & \$ 310 \\\hline \text { B. Send Invitations } & \text { A } & 2 & 1 & \$ 125 & \$ 150 \\\hline \text { C. Plan Decorations } & \text { A } & 8 & 6 & \$ 300 & \$ 370 \\\hline \text { D. Plan Menu } & \text { A } & 3 & 2 & \$ 150 & \$ 210 \\\hline \text { E. Shop } & \text { D } & 4 & 2 & \$ 475 & \$ 550 \\\hline \text { F. Prepare Food } & \text { E } & 5 & 3 & \$ 225 & \$ 475 \\\hline\end{array}


-To reduce the time for Activity F, Prepare Food, Erica can purchase some of the food from a caterer rather than cook it herself. As shown in the table above, this can reduce the time for Activity F by one or two hours, depending on how much catered food she purchases. What is the crash cost per hour for this activity?

A) $225
B) $475
C) $250
D) $125
E) $83.33
F) None of these, the answer is: ____________________
$125
4
Which of the following would NOT be considered a direct activity cost?

A) Rework expenses
B) overhead costs
C) overtime salaries
D) costs to rent or purchase additional equipment
E) costs associated with increased coordination
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 18 في هذه المجموعة.
فتح الحزمة
k this deck
5
Ganesh has been asked to create a project team for a major web development effort. He and the project sponsor have discussed team size and they are debating two options:
-Perform the project in 12 months with a team of 15 people
-Crash the project and complete it in 6 months with a team of 34 people
Which of the following will be true about the contrast between these two options?

A) Option II is likely to require more coordination than Option I.
B) Option I is likely to be more expensive than Option II.
C) Option II will require more than five times as many communication channels as Option I.
D) a and c only.
E) b and c only.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 18 في هذه المجموعة.
فتح الحزمة
k this deck
6
Which of the following characteristics would make an activity an unattractive candidate for crashing?

A) it is in a bottleneck position
B) it has a long duration
C) employees required to do the job have highly specialized skills
D) it is on the critical path
E) it is labor intensive and employees can be added easily
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 18 في هذه المجموعة.
فتح الحزمة
k this deck
7
The next three questions are related to the project schedule shown below, which has been adjusted to accommodate resource constraints.
<strong>The next three questions are related to the project schedule shown below, which has been adjusted to accommodate resource constraints.     -Given the way the schedule shown above is currently planned, what sequence of activities comprises the critical chain? Dashed lines = float.) </strong> A) A-B-C-F-H-J B) A-B-D-J C) A-B-D-G-I-J D) A-B-C-G-I-J E) ABEGIJ F) A-E-J


-Given the way the schedule shown above is currently planned, what sequence of activities comprises the critical chain? Dashed lines = float.)

A) A-B-C-F-H-J
B) A-B-D-J
C) A-B-D-G-I-J
D) A-B-C-G-I-J
E) ABEGIJ
F) A-E-J
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 18 في هذه المجموعة.
فتح الحزمة
k this deck
8
In evaluating time-cost tradeoffs, we start by crashing the activity on the critical path that:

A) has the lowest crash cost per unit time.
B) has the lowest total crash cost.
C) can be reduced the most.
D) is the longest.
E) none of the above.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 18 في هذه المجموعة.
فتح الحزمة
k this deck
9
What is the critical chain in the schedule below?
<strong>What is the critical chain in the schedule below?   </strong> A) A-B-D-F-G B) A-C-E-G C) A-B-D-E-G D) A-B-D-E-F-G E) ABDFG F) None of the above

A) A-B-D-F-G
B) A-C-E-G
C) A-B-D-E-G
D) A-B-D-E-F-G
E) ABDFG
F) None of the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 18 في هذه المجموعة.
فتح الحزمة
k this deck
10
The next three questions relate to the following scenario: Erica is planning a large surprise party for her best friend. She has developed the plan below which includes estimates of the time in hours) and cost necessary to perform each of the activities required.
 Activity  Predeces sor  Normal  Time  (hrs)  Crash  Time  (hrs)  Norm al  Cost  Crash  Cost  A. Create Guest List 84$200$310 B. Send Invitations  A 21$125$150 C. Plan Decorations  A 86$300$370 D. Plan Menu  A 32$150$210 E. Shop  D 42$475$550 F. Prepare Food  E 53$225$475\begin{array} { | l | c | c | c | c | c | } \hline \text { Activity } & \text { Predeces sor } & \begin{array} { c } \text { Normal } \\\text { Time } \\\text { (hrs) }\end{array} & \begin{array} { c } \text { Crash } \\\text { Time } \\\text { (hrs) }\end{array} & \begin{array} { c } \text { Norm al } \\\text { Cost }\end{array} & \begin{array} { c } \text { Crash } \\\text { Cost }\end{array} \\\hline \text { A. Create Guest List } & - - & 8 & 4 & \$ 200 & \$ 310 \\\hline \text { B. Send Invitations } & \text { A } & 2 & 1 & \$ 125 & \$ 150 \\\hline \text { C. Plan Decorations } & \text { A } & 8 & 6 & \$ 300 & \$ 370 \\\hline \text { D. Plan Menu } & \text { A } & 3 & 2 & \$ 150 & \$ 210 \\\hline \text { E. Shop } & \text { D } & 4 & 2 & \$ 475 & \$ 550 \\\hline \text { F. Prepare Food } & \text { E } & 5 & 3 & \$ 225 & \$ 475 \\\hline\end{array}


-Based on critical chain concepts, which of the following is true of a resource buffer?

A) A resource buffer involves information sharing between sequentially-linked tasks on the critical chain.
B) A resource buffer collects time at the end of the project.
C) A resource buffer specifies a minimum amount of free float to protect the critical chain from the effects of potential delays in non-critical chain activities.
D) A resource buffer adds extra human or financial resources to the critical chain to account for potential uncertainties in task times.
E) A and B only.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 18 في هذه المجموعة.
فتح الحزمة
k this deck
11
Which of the following is most associated with fast tracking?

A) A waterfall-type schedule
B) Project activities are delayed to accommodate resource conflicts
C) Finish-to-start precedence logic
D) Start-to-start precedence logic
E) Paying incentives for faster work
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 18 في هذه المجموعة.
فتح الحزمة
k this deck
12
When is crashing beneficial to a project?

A) When the cost of crashing by one day is less than the project's daily overhead cost
B) When the cost of crashing by one day is more than the project's daily overhead cost.
C) When there are no delay penalties
D) When the task to be crashed is not on the critical path
E) A and C
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 18 في هذه المجموعة.
فتح الحزمة
k this deck
13
Fast tracking is defined as:

A) adding resources to reduce the time required for selected project activities.
B) eliminating tasks or deliverables from the WBS.
C) compressing a project schedule to meet market demands.
D) increasing the efficiency of the employees performing the task.
E) rescheduling sequential tasks to take place simultaneously.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 18 في هذه المجموعة.
فتح الحزمة
k this deck
14
The next three questions are related to the project schedule shown below, which has been adjusted to accommodate resource constraints.
<strong>The next three questions are related to the project schedule shown below, which has been adjusted to accommodate resource constraints.     -In the network shown above, given the current placement of float, where would a feeding buffer be most appropriate from among the options below? </strong> A) Between A and B B) Between D and J C) Between E and G D) Between F and H E) Between E and I


-In the network shown above, given the current placement of float, where would a feeding buffer be most appropriate from among the options below?

A) Between A and B
B) Between D and J
C) Between E and G
D) Between F and H
E) Between E and I
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 18 في هذه المجموعة.
فتح الحزمة
k this deck
15
The next three questions relate to the following scenario: Erica is planning a large surprise party for her best friend. She has developed the plan below which includes estimates of the time in hours) and cost necessary to perform each of the activities required.
 Activity  Predeces sor  Normal  Time  (hrs)  Crash  Time  (hrs)  Norm al  Cost  Crash  Cost  A. Create Guest List 84$200$310 B. Send Invitations  A 21$125$150 C. Plan Decorations  A 86$300$370 D. Plan Menu  A 32$150$210 E. Shop  D 42$475$550 F. Prepare Food  E 53$225$475\begin{array} { | l | c | c | c | c | c | } \hline \text { Activity } & \text { Predeces sor } & \begin{array} { c } \text { Normal } \\\text { Time } \\\text { (hrs) }\end{array} & \begin{array} { c } \text { Crash } \\\text { Time } \\\text { (hrs) }\end{array} & \begin{array} { c } \text { Norm al } \\\text { Cost }\end{array} & \begin{array} { c } \text { Crash } \\\text { Cost }\end{array} \\\hline \text { A. Create Guest List } & - - & 8 & 4 & \$ 200 & \$ 310 \\\hline \text { B. Send Invitations } & \text { A } & 2 & 1 & \$ 125 & \$ 150 \\\hline \text { C. Plan Decorations } & \text { A } & 8 & 6 & \$ 300 & \$ 370 \\\hline \text { D. Plan Menu } & \text { A } & 3 & 2 & \$ 150 & \$ 210 \\\hline \text { E. Shop } & \text { D } & 4 & 2 & \$ 475 & \$ 550 \\\hline \text { F. Prepare Food } & \text { E } & 5 & 3 & \$ 225 & \$ 475 \\\hline\end{array}


-Erica's internet-based business pays her about $40 per hour. Therefore, for every hour she works on this party project, she will experience a lost opportunity cost of $40. She would initially like to test the idea of reducing project duration by one hour. Which activity should she crash first?

A) A
B) D
C) C
D) E
E) B
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 18 في هذه المجموعة.
فتح الحزمة
k this deck
16
Research has shown that multitasking has been linked with:

A) Enhanced efficiency.
B) Expanded brain function.
C) Increased short-term memory capacity.
D) Reduced stress.
E) All of the above.
F) None of the above.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 18 في هذه المجموعة.
فتح الحزمة
k this deck
17
What is the difference between the critical path and the critical chain?

A) The critical path considers resource availability and the critical chain does not
B) The critical chain considers resource availability and the critical path does not
C) There is no difference - they are exactly the same
D) It is possible to crash activities on the critical path, but activities on the critical chain have already been reduced to their shortest feasible durations.
E) None of the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 18 في هذه المجموعة.
فتح الحزمة
k this deck
18
The next three questions are related to the project schedule shown below, which has been adjusted to accommodate resource constraints.
<strong>The next three questions are related to the project schedule shown below, which has been adjusted to accommodate resource constraints.     -In the network shown above, where would a resource buffer be most appropriate from among the options below? </strong> A) Between H and J B) Between A and C C) Between B and C D) Between C and F E) Between D and J


-In the network shown above, where would a resource buffer be most appropriate from among the options below?

A) Between H and J
B) Between A and C
C) Between B and C
D) Between C and F
E) Between D and J
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 18 في هذه المجموعة.
فتح الحزمة
k this deck
locked card icon
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 18 في هذه المجموعة.