سؤال
Many project managers find ____ charts more helpful for scheduling, monitoring, and controlling projects.

A) Gantt
B) PERT/CPM
C) index
D) task
استخدم زر المسافة أو
up arrow
down arrow
لقلب البطاقة.
سؤال
A ____ path includes all tasks that are vital to the project schedule.

A) vital
B) baseline
C) critical
D) foundational
سؤال
In a PERT/CPM chart, each task has all of the following EXCEPT a(n) ____.

A) reference to successor tasks
B) ID
C) name
D) duration
سؤال
A ____ might involve maximums for one or more resources.

A) successor task
B) task group
C) constraint
D) bottom-up technique
سؤال
The first step in the creation of a PERT/CPM chart is to ____.

A) determine the logical order of project tasks
B) identify the graphical planning aids to use
C) identify all the project tasks
D) determine the status of all tasks
سؤال
<strong>  The accompanying figure shows task ____, which simplify a complex task by combining several activities.</strong> A) groups B) clusters C) aggregates D) links <div style=padding-top: 35px>
The accompanying figure shows task ____, which simplify a complex task by combining several activities.

A) groups
B) clusters
C) aggregates
D) links
سؤال
Project scheduling involves all of the following EXCEPT ____.

A) defining project constraints
B) staffing the project team
C) using Gantt charts
D) assigning specific tasks to team members
سؤال
In addition to tasks, every project has ____, which are reference points used to monitor progress and manage the project.

A) targets
B) milestones
C) members
D) workloads
سؤال
PERT/CPM is called a(n) ____ technique, because it analyzes a large, complex project as a series of individual tasks.

A) top-down
B) bottom-up
C) indexed
D) cataloging
سؤال
The first step in creating a WBS is to ____.

A) mark all recognizable events
B) determine time requirements
C) identify all tasks
D) estimate task completion time and cost
سؤال
A task is any work that requires the use of company resources including all of the following EXCEPT ____.

A) controlling capital
B) people
C) time
D) money
سؤال
All of the following are metrics of a successful project EXCEPT ____.

A) on-time completion
B) completion with the same personnel as were on the team at the outset
C) completion within budget
D) delivery of a quality product that satisfies users
سؤال
A(n) ____ chart displays complex task patterns and relationships.

A) Gantt
B) index
C) PERT/CPM
D) task
سؤال
A project manager's scheduling function _____.

A) involves guiding, supervising, and coordinating the project team's workload
B) includes monitoring the progress of the project, evaluating results, and taking corrective action when necessary to stay on target
C) involves staffing, which includes selecting the project team and assigning specific tasks to team members
D) includes identifying and arranging project tasks and estimating completion times and costs
سؤال
For a project manager, monitoring _____.

A) requires guiding, supervising, and coordinating the project team's workload
B) involves controlling capital
C) consists of staffing, which includes selecting the project team and assigning specific tasks to team members
D) includes identifying and arranging project tasks and estimating completion times and costs
سؤال
When two or more concurrent tasks depend on a single prior task, the concurrent tasks are called ____ tasks.

A) descendent
B) successor
C) children
D) antecedent
سؤال
Two or more concurrent tasks often depend on a single prior task, which is called a(n) ____ task.

A) predecessor
B) a priori
C) antecedent
D) ancestor
سؤال
When several tasks can start at the same time, each is called a(n) ____ task.

A) synchronous
B) asynchronous
C) baseline
D) concurrent
سؤال
For a project manager, monitoring _____.

A) involves controlling capital
B) includes monitoring the progress of the project, evaluating results, and taking corrective action when necessary to stay on target
C) consists of staffing, which includes selecting the project team and assigning specific tasks to team members
D) includes identifying and arranging project tasks and estimating completion times and costs
سؤال
A project manager's planning _____.

A) involves guiding, supervising, and coordinating the project team's workload
B) includes monitoring the progress of the project, evaluating results, and taking corrective action when necessary to stay on target
C) consists of staffing, which includes selecting the project team and assigning specific tasks to team members
D) includes identifying project tasks and estimating completion times and costs
سؤال
A risk ____ plan is a proactive effort to anticipate a risk and describe an action plan to deal with it.

A) identification
B) management
C) response
D) balancing
سؤال
Most risk identifications include a brief description of all of the following EXCEPT ____.

A) what might cause a risk to occur
B) who would be responsible for responding to a given risk
C) the potential impact of a given risk
D) the team member most vulnerable to a given risk
سؤال
A risk management plan includes a review of all of the following EXCEPT ____.

A) employees
B) project scope
C) stakeholders
D) budget
سؤال
Problems with timetables and project milestones can indicate ____.

A) personality conflicts among team members
B) turnover of project personnel
C) poor control methods
D) all of the above
سؤال
All of the following are claims that Microsoft makes about the risk management capabilities of Microsoft Project EXCEPT ____.

A) the linking of risks with specific vendors
B) the assignment of ownership of risks
C) the specification of probability and risk impact
D) the ability to track progress to manage projects more efficiently
سؤال
____ is open-source software that is supported by a large group of users and developers.

A) Open Workbench
B) Microsoft Project Standard
C) Microsoft Project Professional
D) Both b and c
سؤال
Microsoft's risk management model includes all of the following EXCEPT ____.

A) category, which specifies the risk type
B) probability, which indicates the degree of adverse effect should the risk occur, on a scale of 1 to 10
C) mitigation plan, which identifies plans to control or limit the risk
D) trigger, which identifies a condition that would initiate the contingency plan
سؤال
When maintaining schedules, if enough ____ and frequent checkpoints exist, problems will be detected rapidly.

A) success indices
B) critical paths
C) milestones
D) all of the above
سؤال
In developing time and cost estimates, project managers must consider _____.

A) project size and scope
B) IT resources
C) prior experience with similar projects or systems
D) all of the above
سؤال
A ____ is an event that could affect a project negatively.

A) menace
B) threat
C) doubt
D) risk
سؤال
A continuous risk-tracking process can do all of the following EXCEPT ____.

A) identify new risks
B) prevent human resource turnover issues
C) notice changes in existing risks
D) update any other areas of the risk management plan
سؤال
When a project manager first recognizes that a project is in trouble, the options available to her include ____.

A) trimming the project requirements
B) delaying the project deadline
C) adding to the project resources
D) all of the above
سؤال
A(n) ____ chart can be used to display the qualitative risk analysis matrix.

A) pie
B) XY
C) bar
D) line
سؤال
Which of the following is NOT a version in which Microsoft Project 2010 is released?

A) Standard
B) Professional
C) Open
D) Server
سؤال
Open Workbench can exchange files with Microsoft Project by importing and exporting the data in ____ file format.

A) HTML
B) TXT
C) Microsoft Word
D) XML
سؤال
All of the following are possible causes of cost overruns related to human resource factors EXCEPT ____.

A) motivation issues
B) inadequate training
C) inaccurate TCO forecast
D) turnover
سؤال
Microsoft offers a free ____ trial version that allows you to install, use, and evaluate Microsoft Project.

A) 7-day
B) 15-day
C) 30-day
D) 60-day
سؤال
A _____ cannot be started until one or more other tasks are completed.

A) dependent task
B) concurrent task
C) predecessor task
D) all of the above
سؤال
When an information system does not meet business requirements, causes might include ____.

A) unidentified requirements
B) inadequately defined scope
C) imprecise targets
D) all of the above
سؤال
Project managers always must be aware of the ____ path, so they can monitor the vital tasks and keep the project on track.

A) vital
B) baseline
C) foundational
D) critical
سؤال
Although a Gantt chart provides more detailed information about a project, a PERT/CPM chart offers a rapid overview that graphically displays the timing, duration, and progress of each task.
سؤال
If you do not have previous experience to measure a project in a given environment, you could design a prototype or pilot system to gain technical and cost estimating experience.
سؤال
Using a WBS allows you to manage a project as one large task.
سؤال
Quantitative risk analysis evaluates each risk by estimating the probability that it will occur and the degree of impact. _________________________
سؤال
Which of the following is an example of an event?

A) the start of user training
B) conversion of system data
C) project creep
D) completion of interviews
سؤال
The purpose of quantitative risk analysis is to understand the actual impact in terms of dollars, time, project scope, or quality. _________________________
سؤال
Gantt charts are an ideal tool for controlling a complex project because they provide plenty of detailed information.
سؤال
Structured walk-throughs take place throughout the SDLC and are called ____ reviews, depending on the phase in which they occur.

A) technical
B) code
C) design
D) testing
سؤال
____ is a time estimate the project manager makes for a task.

A) The weight
B) The worst-case estimate
C) The best-case estimate
D) The probable-case estimate
سؤال
Project managers typically perform the tasks of ____.

A) project planning
B) project reconciliation
C) project scheduling
D) project monitoring
سؤال
Using prior experience to make time and cost estimates works best for large projects.
سؤال
If it will take one person 20 days to perform a particular task, it is true that two people could complete the same task in 10 days or that 10 people could perform the task in two days.
سؤال
In a PERT/CPM chart, the name of a given task has to be unique in the project. _________________________
سؤال
PERT/CPM and Gantt charts are mutually exclusive techniques.
سؤال
Critical time is the amount of time that a task would be late without pushing back the completion date of the entire project. _________________________
سؤال
In most systems analysis tasks, time and people are interchangeable.
سؤال
A report published by the Standish Group concluded that only one third of software development projects were successful, in the sense that they met ____ targets.

A) budget
B) scope
C) schedule
D) quality
سؤال
System developers can initiate a formal project as early as the preliminary investigation stage, or later on, as analysis, design, and implementation activities occur.
سؤال
A project manager, or project leader, usually is a senior systems analyst or an IT department manager if the project is large.
سؤال
Gantt charts often are included in progress reports to show project status graphically. _________________________
سؤال
The ____________________ handles administrative responsibilities for a project development team and negotiates with users who might have conflicting requirements or want changes that would require additional time or expense.
سؤال
  To schedule a project, a project manager can use a(n) ____________________ like the one in the accompanying figure, which is a horizontal bar chart that represents a series of tasks.<div style=padding-top: 35px>
To schedule a project, a project manager can use a(n) ____________________ like the one in the accompanying figure, which is a horizontal bar chart that represents a series of tasks.
سؤال
  To simplify a Gantt chart for a large project, a project manager can combine related activities into ____________________ that represent several activities.<div style=padding-top: 35px>
To simplify a Gantt chart for a large project, a project manager can combine related activities into ____________________ that represent several activities.
سؤال
Project status meetings give project managers an opportunity to seek input and conduct brainstorming sessions.
سؤال
Tasks that are not on the critical path cannot be ignored.
سؤال
When several tasks can take place at the same time, each is called a sequential task.
سؤال
Often, two or more concurrent tasks depend on a single prior task, which is called a successor task.
سؤال
In a PERT/CPM chart, each rectangular box, called a task box, has five sections that contain important information about a task.
سؤال
Generally, systems analysts review the work of other systems analysts, and programmers review the work of other programmers, as a form of peer review, in structured walk-throughs.
سؤال
Project management software can highlight the series of tasks that form the critical path.
سؤال
  The chart in the accompanying figure represents a bottom-up technique, because it analyzes a large, complex project as a series of individual ____________________.<div style=padding-top: 35px>
The chart in the accompanying figure represents a bottom-up technique, because it analyzes a large, complex project as a series of individual ____________________.
سؤال
Most managers recognize that problems do occur on most projects; it is better to alert management sooner rather than later.
سؤال
When two or more concurrent tasks depend on a single prior task, each of the concurrent tasks is called a predecessor task.
سؤال
If team members lack experience with certain aspects of the required technology, temporary help might be obtained from IT consultants or part-time staff.
سؤال
In any project, large or small, tasks depend on each other and must be performed in a sequence.
سؤال
  Over time, the distinctions between the Program Evaluation Review Technique (PERT) and the Critical Path Method (CPM) have disappeared, and today the scheduling technique is called ____________________, as represented in the accompanying figure.<div style=padding-top: 35px>
Over time, the distinctions between the Program Evaluation Review Technique (PERT) and the Critical Path Method (CPM) have disappeared, and today the scheduling technique is called ____________________, as represented in the accompanying figure.
سؤال
In Open Workbench, unlike in Microsoft Project, you create tasks and durations, indicate dependencies, and assign resources.
سؤال
When tasks must be completed one after another, they are called concurrent tasks.
سؤال
If any task along the critical path falls behind schedule, the entire project is delayed.
سؤال
Project planning is a dynamic task and involves constant change.
فتح الحزمة
قم بالتسجيل لفتح البطاقات في هذه المجموعة!
Unlock Deck
Unlock Deck
1/112
auto play flashcards
العب
simple tutorial
ملء الشاشة (f)
exit full mode
Deck 3: Managing Systems Projects
1
Many project managers find ____ charts more helpful for scheduling, monitoring, and controlling projects.

A) Gantt
B) PERT/CPM
C) index
D) task
B
2
A ____ path includes all tasks that are vital to the project schedule.

A) vital
B) baseline
C) critical
D) foundational
C
3
In a PERT/CPM chart, each task has all of the following EXCEPT a(n) ____.

A) reference to successor tasks
B) ID
C) name
D) duration
A
4
A ____ might involve maximums for one or more resources.

A) successor task
B) task group
C) constraint
D) bottom-up technique
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
5
The first step in the creation of a PERT/CPM chart is to ____.

A) determine the logical order of project tasks
B) identify the graphical planning aids to use
C) identify all the project tasks
D) determine the status of all tasks
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
6
<strong>  The accompanying figure shows task ____, which simplify a complex task by combining several activities.</strong> A) groups B) clusters C) aggregates D) links
The accompanying figure shows task ____, which simplify a complex task by combining several activities.

A) groups
B) clusters
C) aggregates
D) links
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
7
Project scheduling involves all of the following EXCEPT ____.

A) defining project constraints
B) staffing the project team
C) using Gantt charts
D) assigning specific tasks to team members
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
8
In addition to tasks, every project has ____, which are reference points used to monitor progress and manage the project.

A) targets
B) milestones
C) members
D) workloads
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
9
PERT/CPM is called a(n) ____ technique, because it analyzes a large, complex project as a series of individual tasks.

A) top-down
B) bottom-up
C) indexed
D) cataloging
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
10
The first step in creating a WBS is to ____.

A) mark all recognizable events
B) determine time requirements
C) identify all tasks
D) estimate task completion time and cost
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
11
A task is any work that requires the use of company resources including all of the following EXCEPT ____.

A) controlling capital
B) people
C) time
D) money
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
12
All of the following are metrics of a successful project EXCEPT ____.

A) on-time completion
B) completion with the same personnel as were on the team at the outset
C) completion within budget
D) delivery of a quality product that satisfies users
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
13
A(n) ____ chart displays complex task patterns and relationships.

A) Gantt
B) index
C) PERT/CPM
D) task
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
14
A project manager's scheduling function _____.

A) involves guiding, supervising, and coordinating the project team's workload
B) includes monitoring the progress of the project, evaluating results, and taking corrective action when necessary to stay on target
C) involves staffing, which includes selecting the project team and assigning specific tasks to team members
D) includes identifying and arranging project tasks and estimating completion times and costs
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
15
For a project manager, monitoring _____.

A) requires guiding, supervising, and coordinating the project team's workload
B) involves controlling capital
C) consists of staffing, which includes selecting the project team and assigning specific tasks to team members
D) includes identifying and arranging project tasks and estimating completion times and costs
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
16
When two or more concurrent tasks depend on a single prior task, the concurrent tasks are called ____ tasks.

A) descendent
B) successor
C) children
D) antecedent
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
17
Two or more concurrent tasks often depend on a single prior task, which is called a(n) ____ task.

A) predecessor
B) a priori
C) antecedent
D) ancestor
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
18
When several tasks can start at the same time, each is called a(n) ____ task.

A) synchronous
B) asynchronous
C) baseline
D) concurrent
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
19
For a project manager, monitoring _____.

A) involves controlling capital
B) includes monitoring the progress of the project, evaluating results, and taking corrective action when necessary to stay on target
C) consists of staffing, which includes selecting the project team and assigning specific tasks to team members
D) includes identifying and arranging project tasks and estimating completion times and costs
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
20
A project manager's planning _____.

A) involves guiding, supervising, and coordinating the project team's workload
B) includes monitoring the progress of the project, evaluating results, and taking corrective action when necessary to stay on target
C) consists of staffing, which includes selecting the project team and assigning specific tasks to team members
D) includes identifying project tasks and estimating completion times and costs
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
21
A risk ____ plan is a proactive effort to anticipate a risk and describe an action plan to deal with it.

A) identification
B) management
C) response
D) balancing
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
22
Most risk identifications include a brief description of all of the following EXCEPT ____.

A) what might cause a risk to occur
B) who would be responsible for responding to a given risk
C) the potential impact of a given risk
D) the team member most vulnerable to a given risk
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
23
A risk management plan includes a review of all of the following EXCEPT ____.

A) employees
B) project scope
C) stakeholders
D) budget
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
24
Problems with timetables and project milestones can indicate ____.

A) personality conflicts among team members
B) turnover of project personnel
C) poor control methods
D) all of the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
25
All of the following are claims that Microsoft makes about the risk management capabilities of Microsoft Project EXCEPT ____.

A) the linking of risks with specific vendors
B) the assignment of ownership of risks
C) the specification of probability and risk impact
D) the ability to track progress to manage projects more efficiently
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
26
____ is open-source software that is supported by a large group of users and developers.

A) Open Workbench
B) Microsoft Project Standard
C) Microsoft Project Professional
D) Both b and c
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
27
Microsoft's risk management model includes all of the following EXCEPT ____.

A) category, which specifies the risk type
B) probability, which indicates the degree of adverse effect should the risk occur, on a scale of 1 to 10
C) mitigation plan, which identifies plans to control or limit the risk
D) trigger, which identifies a condition that would initiate the contingency plan
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
28
When maintaining schedules, if enough ____ and frequent checkpoints exist, problems will be detected rapidly.

A) success indices
B) critical paths
C) milestones
D) all of the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
29
In developing time and cost estimates, project managers must consider _____.

A) project size and scope
B) IT resources
C) prior experience with similar projects or systems
D) all of the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
30
A ____ is an event that could affect a project negatively.

A) menace
B) threat
C) doubt
D) risk
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
31
A continuous risk-tracking process can do all of the following EXCEPT ____.

A) identify new risks
B) prevent human resource turnover issues
C) notice changes in existing risks
D) update any other areas of the risk management plan
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
32
When a project manager first recognizes that a project is in trouble, the options available to her include ____.

A) trimming the project requirements
B) delaying the project deadline
C) adding to the project resources
D) all of the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
33
A(n) ____ chart can be used to display the qualitative risk analysis matrix.

A) pie
B) XY
C) bar
D) line
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
34
Which of the following is NOT a version in which Microsoft Project 2010 is released?

A) Standard
B) Professional
C) Open
D) Server
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
35
Open Workbench can exchange files with Microsoft Project by importing and exporting the data in ____ file format.

A) HTML
B) TXT
C) Microsoft Word
D) XML
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
36
All of the following are possible causes of cost overruns related to human resource factors EXCEPT ____.

A) motivation issues
B) inadequate training
C) inaccurate TCO forecast
D) turnover
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
37
Microsoft offers a free ____ trial version that allows you to install, use, and evaluate Microsoft Project.

A) 7-day
B) 15-day
C) 30-day
D) 60-day
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
38
A _____ cannot be started until one or more other tasks are completed.

A) dependent task
B) concurrent task
C) predecessor task
D) all of the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
39
When an information system does not meet business requirements, causes might include ____.

A) unidentified requirements
B) inadequately defined scope
C) imprecise targets
D) all of the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
40
Project managers always must be aware of the ____ path, so they can monitor the vital tasks and keep the project on track.

A) vital
B) baseline
C) foundational
D) critical
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
41
Although a Gantt chart provides more detailed information about a project, a PERT/CPM chart offers a rapid overview that graphically displays the timing, duration, and progress of each task.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
42
If you do not have previous experience to measure a project in a given environment, you could design a prototype or pilot system to gain technical and cost estimating experience.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
43
Using a WBS allows you to manage a project as one large task.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
44
Quantitative risk analysis evaluates each risk by estimating the probability that it will occur and the degree of impact. _________________________
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
45
Which of the following is an example of an event?

A) the start of user training
B) conversion of system data
C) project creep
D) completion of interviews
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
46
The purpose of quantitative risk analysis is to understand the actual impact in terms of dollars, time, project scope, or quality. _________________________
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
47
Gantt charts are an ideal tool for controlling a complex project because they provide plenty of detailed information.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
48
Structured walk-throughs take place throughout the SDLC and are called ____ reviews, depending on the phase in which they occur.

A) technical
B) code
C) design
D) testing
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
49
____ is a time estimate the project manager makes for a task.

A) The weight
B) The worst-case estimate
C) The best-case estimate
D) The probable-case estimate
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
50
Project managers typically perform the tasks of ____.

A) project planning
B) project reconciliation
C) project scheduling
D) project monitoring
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
51
Using prior experience to make time and cost estimates works best for large projects.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
52
If it will take one person 20 days to perform a particular task, it is true that two people could complete the same task in 10 days or that 10 people could perform the task in two days.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
53
In a PERT/CPM chart, the name of a given task has to be unique in the project. _________________________
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
54
PERT/CPM and Gantt charts are mutually exclusive techniques.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
55
Critical time is the amount of time that a task would be late without pushing back the completion date of the entire project. _________________________
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
56
In most systems analysis tasks, time and people are interchangeable.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
57
A report published by the Standish Group concluded that only one third of software development projects were successful, in the sense that they met ____ targets.

A) budget
B) scope
C) schedule
D) quality
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
58
System developers can initiate a formal project as early as the preliminary investigation stage, or later on, as analysis, design, and implementation activities occur.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
59
A project manager, or project leader, usually is a senior systems analyst or an IT department manager if the project is large.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
60
Gantt charts often are included in progress reports to show project status graphically. _________________________
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
61
The ____________________ handles administrative responsibilities for a project development team and negotiates with users who might have conflicting requirements or want changes that would require additional time or expense.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
62
  To schedule a project, a project manager can use a(n) ____________________ like the one in the accompanying figure, which is a horizontal bar chart that represents a series of tasks.
To schedule a project, a project manager can use a(n) ____________________ like the one in the accompanying figure, which is a horizontal bar chart that represents a series of tasks.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
63
  To simplify a Gantt chart for a large project, a project manager can combine related activities into ____________________ that represent several activities.
To simplify a Gantt chart for a large project, a project manager can combine related activities into ____________________ that represent several activities.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
64
Project status meetings give project managers an opportunity to seek input and conduct brainstorming sessions.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
65
Tasks that are not on the critical path cannot be ignored.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
66
When several tasks can take place at the same time, each is called a sequential task.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
67
Often, two or more concurrent tasks depend on a single prior task, which is called a successor task.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
68
In a PERT/CPM chart, each rectangular box, called a task box, has five sections that contain important information about a task.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
69
Generally, systems analysts review the work of other systems analysts, and programmers review the work of other programmers, as a form of peer review, in structured walk-throughs.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
70
Project management software can highlight the series of tasks that form the critical path.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
71
  The chart in the accompanying figure represents a bottom-up technique, because it analyzes a large, complex project as a series of individual ____________________.
The chart in the accompanying figure represents a bottom-up technique, because it analyzes a large, complex project as a series of individual ____________________.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
72
Most managers recognize that problems do occur on most projects; it is better to alert management sooner rather than later.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
73
When two or more concurrent tasks depend on a single prior task, each of the concurrent tasks is called a predecessor task.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
74
If team members lack experience with certain aspects of the required technology, temporary help might be obtained from IT consultants or part-time staff.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
75
In any project, large or small, tasks depend on each other and must be performed in a sequence.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
76
  Over time, the distinctions between the Program Evaluation Review Technique (PERT) and the Critical Path Method (CPM) have disappeared, and today the scheduling technique is called ____________________, as represented in the accompanying figure.
Over time, the distinctions between the Program Evaluation Review Technique (PERT) and the Critical Path Method (CPM) have disappeared, and today the scheduling technique is called ____________________, as represented in the accompanying figure.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
77
In Open Workbench, unlike in Microsoft Project, you create tasks and durations, indicate dependencies, and assign resources.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
78
When tasks must be completed one after another, they are called concurrent tasks.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
79
If any task along the critical path falls behind schedule, the entire project is delayed.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
80
Project planning is a dynamic task and involves constant change.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.
فتح الحزمة
k this deck
locked card icon
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 112 في هذه المجموعة.