Deck 8: Scheduling Resources and Costs

ملء الشاشة (f)
exit full mode
سؤال
Resource leveling or smoothing is only used on projects which are resource constrained.
استخدم زر المسافة أو
up arrow
down arrow
لقلب البطاقة.
سؤال
Splitting is a scheduling technique used to get a better schedule or better resource utilization and should be used without hesitation.
سؤال
If a project needs one earth mover six months from now in order to complete one activity, and the organization has four such machines, there is no equipment resource constraint.
سؤال
A project budget report is showing our project as spending $82,000 against a budgeted amount of $85,000. We can assume that everything is going as planned and that we are under budget.
سؤال
Since resource leveling or smoothing delays noncritical activities, a common result is a decrease in network sensitivity.
سؤال
When scheduling activities in a resource-constrained project typically the activity scheduled first has the most amount of slack.
سؤال
Scheduling projects classified as resource-constrained focuses on completing the project as soon as possible under the given resource constraints.
سؤال
The fact that you must pour foundation before you frame the house and that you have to frame the house before you can put on the roof demonstrates scheduling constraints.
سؤال
In a resource-constrained project, the completion date is most likely to change.
سؤال
Resource dependency takes priority over technological dependency but it does not violate it.
سؤال
Having too few programmers and too many engineers is an example of a people resource constraint.
سؤال
The inability to fit more than two earth movers on a construction site at the same time when more are needed to complete the activity on time is an example of a physical constraint.
سؤال
A lack of readily available engineers is a technical constraint.
سؤال
Resource bottlenecks are one of the three more common problems encountered in managing multiproject resource schedules.
سؤال
Sequential activities hold just as much potential for resource conflicts as parallel activities.
سؤال
When resource constraints are added to technical constraints the original project network may change as well as the completion date.
سؤال
All leveling techniques delay noncritical activities by using positive slack to smooth out the resource requirements.
سؤال
To determine if a project is time-constrained or resource-constrained you would consult the project priority matrix.
سؤال
Too many parallel activities for one individual is an example of a resource constraint.
سؤال
The level of resources each activity will need to be completed in the given amount of time has been estimated; therefore, there are no resource constraints.
سؤال
When considering the sequence and timing of activities, which of the following is NOT one of the types of project network constraints?

A) Physical
B) Technical
C) Resource
D) Time
E) All of these are types of constraints that could impact structure of the project network.
سؤال
Comparing Planned Costs versus Actual Costs will give the project manager a quick understanding of the status of the project.
سؤال
Resource constraints can be overcome by creative and efficient scheduling.
سؤال
All resource leveling techniques involve

A) delaying noncritical activities.
B) delaying critical activities.
C) using negative slack.
D) delaying the project.
E) adding resources.
سؤال
If resources are not adequate to meet peak demands, the resulting reschedule is termed

A) resource-constrained scheduling.
B) time-constrained scheduling.
C) mandatory leveling.
D) project resource adjustment.
E) allocation.
سؤال
A project engineer has been scheduled to run the product system test at the same time as building a marketing prototype. This is an example of what type of resource constraint?

A) Physical
B) Technical
C) People
D) Equipment
E) Time
سؤال
Without a time-phased budget a good project schedule and cost control are impossible.
سؤال
All of the following are types of resource constraints EXCEPT

A) materials.
B) people.
C) equipment.
D) information.
E) human.
سؤال
A project leader's boss has indicated that their project is very important. If the critical path is delayed, the lead will be given whatever is needed to get it back on schedule. The project is classified as ________ constrained.

A) time
B) quality
C) cost
D) performance
E) resource
سؤال
In reviewing the status of a project with top management, a team leader was told that there are only two programmers that can be used for the project. The project is classified as __________ constrained.

A) time
B) quality
C) cost
D) performance
E) resource
سؤال
A project purchasing agent is trying to order the concrete needed to continue the project. However, the supplier will not be able to deliver it until next week. This is an example of what kind of resource constraint?

A) Working capital
B) People
C) Equipment
D) Information
E) Materials
سؤال
A special truck that is needed on the project has been assigned to another project. This is an example of what type of resource constraint?

A) Working capital
B) People
C) Equipment
D) Information
E) Materials
سؤال
A test engineer is to conduct environmental testing but the chamber cannot hold all the equipment that needs to be tested. This is an example of a constraint that could impact the sequence and timing of activities in a project network. What type of constraint is it?

A) Physical
B) Technical
C) Resource
D) Scheduling
E) Time
سؤال
Having individual staff members assigned to multiple simultaneous tasks is an efficient way to split tasks and get tasks accomplished more efficiently.

A) shifting.
B) effectiveness.
C) manipulating.
D) smoothing.
E) allocation.
سؤال
When developing a new software package, logically, the software must be designed before the code is written, and the code must be written before it is tested. These activities are dependent on each other by _________ constraints.

A) physical
B) technical
C) resource
D) schedule
E) time
سؤال
Most of the scheduling methods available today require the project manager to classify the project as either _______ constrained or ______ constrained.

A) time, quality
B) quality, resource
C) cost, time
D) quality, cost
E) time, resource
سؤال
Project managers should always assign the best people to the most difficult tasks.
سؤال
Project management software is important because it will manage the project for the project manager.
سؤال
Which of the following is NOT a potential consequence of failing to identify limited resources before project implementation?

A) Activity delays
B) Project delays
C) Difficulty in taking quick corrective action
D) Increase costs
E) Scope creep
سؤال
If resources are truly limited and activity time estimates are accurate, the resource-constrained schedule will materialize as the project is implemented, not the time-constrained schedule.
سؤال
Technical constraints have been carefully considered when developing a project network. Which of the following is true at this point?

A) Resources have been assigned to each activity so they are adequate to complete the project on time.
B) Technical dependencies between activities are known.
C) The project completion date can be established.
D) The project is ready to be implemented.
E) All of these are true statements once technical constraints have been established.
سؤال
A project budget report is showing our project as spending $50,000 against a budgeted amount of $65,000. Which of the following is true?

A) We are spending less than we should for the project.
B) We are doing a good job managing the project.
C) We should check to see if all the bills have been paid.
D) We have more money to put into budget reserves.
E) We can't be sure how the project is going.
سؤال
Splitting an activity can result in all of the following EXCEPT

A) more people working on the same activity.
B) possible startup and shutdown costs.
C) a resource being moved from one activity to another and then back.
D) activity work being placed on hold for a period until more resources are available.
E) a better project schedule.
سؤال
Why is it necessary to have a time-phased budget baseline?

A) It allows proper resource allocation.
B) It shows how much work was accomplished for the money spent.
C) It reduces schedule slippage when scheduling multiproject resources.
D) It is not necessary to have a time-phased budget baseline.
E) It reduces fluctuations in cash flow during the project.
سؤال
This is used to compare the cost accounts between organizational units and deliverables.

A) Chart of Accounts
B) Earned Value
C) Project Schedule
D) Direct Labor Budget Rollup
E) Comparison Audit
سؤال
When there are not enough people, money, and / or equipment available for a project it is known as being

A) managerially resourceful.
B) operationally successful.
C) resource constrained.
D) delayed without prejudice.
E) project constrained.
سؤال
In a resource-constrained project the second priority in assigning resources is usually given to activities with the

A) smallest duration.
B) least slack.
C) most slack.
D) lowest identification number.
E) highest cost.
سؤال
Resource leveling or smoothing can have all the following results on a project EXCEPT

A) lower peak resource demand.
B) reduced resource need over the life of the project.
C) reduced fluctuations in resource demand.
D) a longer project duration.
E) a more sensitive network.
سؤال
When a company will reduce the number of projects they have to manage internally to only core projects and send noncritical projects to contractors and consulting firms this is called

A) outsourcing.
B) redistribution of projects.
C) project allocation.
D) task sharing.
E) referring.
سؤال
When leveling schedules to overcome resource constraints, ___________ is increased.

A) impact of risks
B) scheduling complexity
C) cost
D) amount of total slack
E) amount of free slack
سؤال
These are all guidelines a project manager should consider when assigning project work EXCEPT

A) select people with compatible work habits and personalities.
B) always assign the best people to the most difficult tasks.
C) when possible, team veterans up with new hires.
D) select individuals with skillsets that complement each other.
E) have people work together early so that they can become familiar with each other.
سؤال
Which of the following is NOT one of the more common problems associated with scheduling multi-project resources?

A) Overall schedule slippage
B) Inefficient resource utilization
C) Decline in project quality
D) Resource bottlenecks
E) Delays in one project causing delays in other projects
سؤال
In a resource-constrained project, which of the following is most likely to be changed?

A) The completion date
B) The budget
C) Project quality
D) Resource levels
E) Scope creep
سؤال
In a resource-constrained project the third priority in assigning resources is usually given to activities with the

A) smallest duration.
B) least slack.
C) most slack.
D) lowest identification number.
E) highest cost.
سؤال
A project scheduler is working on a project that technically allows three activities to be done at the same time. If they were to be implemented at the same time, the scheduler would need 5 contractors in order for the activities to be completed on time. There are only 3 available for the project. This is an example of what type of constraint?

A) Technical
B) People
C) Equipment
D) Physical
E) Materials
سؤال
A project leader has realized that two activities in the project cannot be done at the same time because not enough resources are available. Activity 3 is critical and has a duration of 5 days. Activity 4 has 2 days of slack and a duration of 2 days. How will the project leader decide which activity should be scheduled first?

A) The activity with the smallest duration
B) The activity with the least slack
C) The activity with the most slack
D) The activity with the lowest identification number
E) The activity with the highest cost
سؤال
A project scheduler is trying to reallocate resources in a time-constrained project to create smoother resource utilization. The scheduler should first identify activities with the

A) smallest duration.
B) least slack.
C) most slack.
D) lowest identification number.
E) highest cost.
سؤال
All of the following are benefits of scheduling resources before project implementation EXCEPT

A) it allows time for considering reasonable options if resource constraints do exist.
B) the project completion date can be established.
C) work packages can be time-phased.
D) it allows managers to share resources with other project managers if it is requested without negatively impacting their project.
E) it ensures low network sensitivity.
سؤال
In a resource-constrained project, the first, or primary, priority in assigning resources is usually given to activities with the

A) smallest duration.
B) least slack.
C) most slack.
D) lowest identification number.
E) highest cost.
سؤال
Project budgets are developed by time-phasing which of the following?

A) Resource schedules
B) Work packages
C) The network diagram
D) Critical activities
E) None of these are time-phased to develop a project budget.
سؤال
When developing project networks, which of the following is not a reason for delineating technical dependencies first before doing resource dependencies?

A) The interrelationships and interactions among time and resource constraints are complex for even small project networks.
B) Resource availability may not be known until the initial schedule is completed.
C) Even if resources are known, one cannot assess the impact of limited resources until a resource-neutral schedule is created.
D) An effort to examine the interactions between technical / logical constraints and resource limitations frequently uncovers surprising problems.
E) All of these alternatives are reasons for delineating technical dependencies first before doing resource dependencies.
سؤال
Renovation of a small compartment in a houseboat or camping trailer that is too small for more than one person is an example of a(n) ________ resource constraint.

A) physical
B) people
C) material
D) equipment
E) budget
سؤال
If resource demand varies widely over the life of the project, the project manager can try to use slack (delaying noncritical activities) to accommodate insufficient resources. This process is called____.

A) resource scheduling
B) resource smoothing
C) resource-constrained scheduling
D) splitting
E) resource accommodation
سؤال
When only one person is responsible for performing several activities, all due at the same time, this is an example of a(n) ________ constraint.

A) equipment
B) materials
C) technical
D) resource
E) logical
سؤال
Delaying noncritical activities to lower peak demand and, thus, increase resource utilization is called resource __________.

A) smoothing
B) slack utilization
C) switching
D) re-scheduling
E) overtime
سؤال
All leveling techniques delay noncritical activities by using ________ to reduce peak demand.

A) additional resources
B) additional time
C) positive risk
D) additional people
E) additional slack
سؤال
Which constraint category should be considered before all others?

A) Logical and technical constraints
B) Human resource constraints
C) Material resource constraints
D) Equipment resource constraints
E) Time constraints
سؤال
A(n) ________ constraint addresses the sequence in which project activities must occur even after considering resource constraints.

A) predecessor
B) technical or logic
C) successor
D) serial
E) hard
سؤال
The shortage of memory chips to produce a printed circuit motherboard is an example of a(n) ________ type of resource constraint.

A) physical
B) people
C) material
D) equipment
E) budget
سؤال
Resource dependency takes priority over the technological dependency but does not violate ___________ dependencies.

A) equipment
B) time
C) technical
D) resource
E) logical
سؤال
A shortage of software developers to create software is an example of a(n) ________ type of resource constraint.

A) physical
B) people
C) material
D) equipment
E) budget
سؤال
When scheduling activities in a resource-constrained project, typically the activity scheduled first has the __________ amount of slack.

A) least
B) most
C) greatest
D) maximum
E) modest
سؤال
In order that the new product is on the shelf for the Christmas buying season, the development of the new product would be classified as a(n) ________ -constrained project.

A) equipment
B) time
C) technical
D) resource
E) logical
سؤال
If three copiers are needed to produce a final report on time and only two are available, the project is facing a(n) ________ type of resource constraint.

A) physical
B) people
C) material
D) equipment
E) budget
سؤال
When deciding which staff to team-up to work on work packages, factors to consider are:

A) Work habits.
B) Practical experience.
C) Years of working in the company.
D) Both work habits and practical experience.
E) Both practical experience and years of working in the company.
سؤال
A project manager has two engineers assigned to the project and does not have access to more even if the result means extending the completion date on the project. The project manager is managing a(n) ________.

A) time-constrained project
B) people-constrained project
C) engineer-constrained project
D) resource-constrained project
E) human-constrained project
سؤال
Which of the following questions does a project manager NOT have to address when considering resources allocated to a project?

A) Will the assigned labor be adequate and available to deal with my project?
B) Will outside contractors have to be used?
C) Will scope have to be redefined / stabilized?
D) Do unforeseen resource dependencies exist?
E) How much flexibility do we have in using resources?
سؤال
When looking at the critical path for a delayed project and the project manager sees that adding resources will reduce or remove the delay, the project manager knows that the project is:

A) Over Allocated.
B) Time-Constrained.
C) Institutionally Challenged.
D) Ahead of schedule.
E) Unstable.
سؤال
If it becomes necessary to delay one or several late starts to accommodate resource limitations, this is called:

A) Resource scheduling
B) Resource smoothing
C) Resource-constrained scheduling
D) Splitting
E) Resource accommodation
سؤال
While balancing assignments, a project manager must also balance:

A) Overall project cost.
B) Talent development.
C) Earned value.
D) Work package slack.
E) Project cost.
فتح الحزمة
قم بالتسجيل لفتح البطاقات في هذه المجموعة!
Unlock Deck
Unlock Deck
1/114
auto play flashcards
العب
simple tutorial
ملء الشاشة (f)
exit full mode
Deck 8: Scheduling Resources and Costs
1
Resource leveling or smoothing is only used on projects which are resource constrained.
False
2
Splitting is a scheduling technique used to get a better schedule or better resource utilization and should be used without hesitation.
False
3
If a project needs one earth mover six months from now in order to complete one activity, and the organization has four such machines, there is no equipment resource constraint.
False
4
A project budget report is showing our project as spending $82,000 against a budgeted amount of $85,000. We can assume that everything is going as planned and that we are under budget.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
5
Since resource leveling or smoothing delays noncritical activities, a common result is a decrease in network sensitivity.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
6
When scheduling activities in a resource-constrained project typically the activity scheduled first has the most amount of slack.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
7
Scheduling projects classified as resource-constrained focuses on completing the project as soon as possible under the given resource constraints.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
8
The fact that you must pour foundation before you frame the house and that you have to frame the house before you can put on the roof demonstrates scheduling constraints.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
9
In a resource-constrained project, the completion date is most likely to change.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
10
Resource dependency takes priority over technological dependency but it does not violate it.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
11
Having too few programmers and too many engineers is an example of a people resource constraint.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
12
The inability to fit more than two earth movers on a construction site at the same time when more are needed to complete the activity on time is an example of a physical constraint.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
13
A lack of readily available engineers is a technical constraint.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
14
Resource bottlenecks are one of the three more common problems encountered in managing multiproject resource schedules.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
15
Sequential activities hold just as much potential for resource conflicts as parallel activities.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
16
When resource constraints are added to technical constraints the original project network may change as well as the completion date.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
17
All leveling techniques delay noncritical activities by using positive slack to smooth out the resource requirements.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
18
To determine if a project is time-constrained or resource-constrained you would consult the project priority matrix.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
19
Too many parallel activities for one individual is an example of a resource constraint.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
20
The level of resources each activity will need to be completed in the given amount of time has been estimated; therefore, there are no resource constraints.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
21
When considering the sequence and timing of activities, which of the following is NOT one of the types of project network constraints?

A) Physical
B) Technical
C) Resource
D) Time
E) All of these are types of constraints that could impact structure of the project network.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
22
Comparing Planned Costs versus Actual Costs will give the project manager a quick understanding of the status of the project.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
23
Resource constraints can be overcome by creative and efficient scheduling.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
24
All resource leveling techniques involve

A) delaying noncritical activities.
B) delaying critical activities.
C) using negative slack.
D) delaying the project.
E) adding resources.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
25
If resources are not adequate to meet peak demands, the resulting reschedule is termed

A) resource-constrained scheduling.
B) time-constrained scheduling.
C) mandatory leveling.
D) project resource adjustment.
E) allocation.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
26
A project engineer has been scheduled to run the product system test at the same time as building a marketing prototype. This is an example of what type of resource constraint?

A) Physical
B) Technical
C) People
D) Equipment
E) Time
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
27
Without a time-phased budget a good project schedule and cost control are impossible.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
28
All of the following are types of resource constraints EXCEPT

A) materials.
B) people.
C) equipment.
D) information.
E) human.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
29
A project leader's boss has indicated that their project is very important. If the critical path is delayed, the lead will be given whatever is needed to get it back on schedule. The project is classified as ________ constrained.

A) time
B) quality
C) cost
D) performance
E) resource
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
30
In reviewing the status of a project with top management, a team leader was told that there are only two programmers that can be used for the project. The project is classified as __________ constrained.

A) time
B) quality
C) cost
D) performance
E) resource
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
31
A project purchasing agent is trying to order the concrete needed to continue the project. However, the supplier will not be able to deliver it until next week. This is an example of what kind of resource constraint?

A) Working capital
B) People
C) Equipment
D) Information
E) Materials
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
32
A special truck that is needed on the project has been assigned to another project. This is an example of what type of resource constraint?

A) Working capital
B) People
C) Equipment
D) Information
E) Materials
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
33
A test engineer is to conduct environmental testing but the chamber cannot hold all the equipment that needs to be tested. This is an example of a constraint that could impact the sequence and timing of activities in a project network. What type of constraint is it?

A) Physical
B) Technical
C) Resource
D) Scheduling
E) Time
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
34
Having individual staff members assigned to multiple simultaneous tasks is an efficient way to split tasks and get tasks accomplished more efficiently.

A) shifting.
B) effectiveness.
C) manipulating.
D) smoothing.
E) allocation.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
35
When developing a new software package, logically, the software must be designed before the code is written, and the code must be written before it is tested. These activities are dependent on each other by _________ constraints.

A) physical
B) technical
C) resource
D) schedule
E) time
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
36
Most of the scheduling methods available today require the project manager to classify the project as either _______ constrained or ______ constrained.

A) time, quality
B) quality, resource
C) cost, time
D) quality, cost
E) time, resource
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
37
Project managers should always assign the best people to the most difficult tasks.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
38
Project management software is important because it will manage the project for the project manager.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
39
Which of the following is NOT a potential consequence of failing to identify limited resources before project implementation?

A) Activity delays
B) Project delays
C) Difficulty in taking quick corrective action
D) Increase costs
E) Scope creep
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
40
If resources are truly limited and activity time estimates are accurate, the resource-constrained schedule will materialize as the project is implemented, not the time-constrained schedule.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
41
Technical constraints have been carefully considered when developing a project network. Which of the following is true at this point?

A) Resources have been assigned to each activity so they are adequate to complete the project on time.
B) Technical dependencies between activities are known.
C) The project completion date can be established.
D) The project is ready to be implemented.
E) All of these are true statements once technical constraints have been established.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
42
A project budget report is showing our project as spending $50,000 against a budgeted amount of $65,000. Which of the following is true?

A) We are spending less than we should for the project.
B) We are doing a good job managing the project.
C) We should check to see if all the bills have been paid.
D) We have more money to put into budget reserves.
E) We can't be sure how the project is going.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
43
Splitting an activity can result in all of the following EXCEPT

A) more people working on the same activity.
B) possible startup and shutdown costs.
C) a resource being moved from one activity to another and then back.
D) activity work being placed on hold for a period until more resources are available.
E) a better project schedule.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
44
Why is it necessary to have a time-phased budget baseline?

A) It allows proper resource allocation.
B) It shows how much work was accomplished for the money spent.
C) It reduces schedule slippage when scheduling multiproject resources.
D) It is not necessary to have a time-phased budget baseline.
E) It reduces fluctuations in cash flow during the project.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
45
This is used to compare the cost accounts between organizational units and deliverables.

A) Chart of Accounts
B) Earned Value
C) Project Schedule
D) Direct Labor Budget Rollup
E) Comparison Audit
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
46
When there are not enough people, money, and / or equipment available for a project it is known as being

A) managerially resourceful.
B) operationally successful.
C) resource constrained.
D) delayed without prejudice.
E) project constrained.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
47
In a resource-constrained project the second priority in assigning resources is usually given to activities with the

A) smallest duration.
B) least slack.
C) most slack.
D) lowest identification number.
E) highest cost.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
48
Resource leveling or smoothing can have all the following results on a project EXCEPT

A) lower peak resource demand.
B) reduced resource need over the life of the project.
C) reduced fluctuations in resource demand.
D) a longer project duration.
E) a more sensitive network.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
49
When a company will reduce the number of projects they have to manage internally to only core projects and send noncritical projects to contractors and consulting firms this is called

A) outsourcing.
B) redistribution of projects.
C) project allocation.
D) task sharing.
E) referring.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
50
When leveling schedules to overcome resource constraints, ___________ is increased.

A) impact of risks
B) scheduling complexity
C) cost
D) amount of total slack
E) amount of free slack
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
51
These are all guidelines a project manager should consider when assigning project work EXCEPT

A) select people with compatible work habits and personalities.
B) always assign the best people to the most difficult tasks.
C) when possible, team veterans up with new hires.
D) select individuals with skillsets that complement each other.
E) have people work together early so that they can become familiar with each other.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
52
Which of the following is NOT one of the more common problems associated with scheduling multi-project resources?

A) Overall schedule slippage
B) Inefficient resource utilization
C) Decline in project quality
D) Resource bottlenecks
E) Delays in one project causing delays in other projects
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
53
In a resource-constrained project, which of the following is most likely to be changed?

A) The completion date
B) The budget
C) Project quality
D) Resource levels
E) Scope creep
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
54
In a resource-constrained project the third priority in assigning resources is usually given to activities with the

A) smallest duration.
B) least slack.
C) most slack.
D) lowest identification number.
E) highest cost.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
55
A project scheduler is working on a project that technically allows three activities to be done at the same time. If they were to be implemented at the same time, the scheduler would need 5 contractors in order for the activities to be completed on time. There are only 3 available for the project. This is an example of what type of constraint?

A) Technical
B) People
C) Equipment
D) Physical
E) Materials
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
56
A project leader has realized that two activities in the project cannot be done at the same time because not enough resources are available. Activity 3 is critical and has a duration of 5 days. Activity 4 has 2 days of slack and a duration of 2 days. How will the project leader decide which activity should be scheduled first?

A) The activity with the smallest duration
B) The activity with the least slack
C) The activity with the most slack
D) The activity with the lowest identification number
E) The activity with the highest cost
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
57
A project scheduler is trying to reallocate resources in a time-constrained project to create smoother resource utilization. The scheduler should first identify activities with the

A) smallest duration.
B) least slack.
C) most slack.
D) lowest identification number.
E) highest cost.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
58
All of the following are benefits of scheduling resources before project implementation EXCEPT

A) it allows time for considering reasonable options if resource constraints do exist.
B) the project completion date can be established.
C) work packages can be time-phased.
D) it allows managers to share resources with other project managers if it is requested without negatively impacting their project.
E) it ensures low network sensitivity.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
59
In a resource-constrained project, the first, or primary, priority in assigning resources is usually given to activities with the

A) smallest duration.
B) least slack.
C) most slack.
D) lowest identification number.
E) highest cost.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
60
Project budgets are developed by time-phasing which of the following?

A) Resource schedules
B) Work packages
C) The network diagram
D) Critical activities
E) None of these are time-phased to develop a project budget.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
61
When developing project networks, which of the following is not a reason for delineating technical dependencies first before doing resource dependencies?

A) The interrelationships and interactions among time and resource constraints are complex for even small project networks.
B) Resource availability may not be known until the initial schedule is completed.
C) Even if resources are known, one cannot assess the impact of limited resources until a resource-neutral schedule is created.
D) An effort to examine the interactions between technical / logical constraints and resource limitations frequently uncovers surprising problems.
E) All of these alternatives are reasons for delineating technical dependencies first before doing resource dependencies.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
62
Renovation of a small compartment in a houseboat or camping trailer that is too small for more than one person is an example of a(n) ________ resource constraint.

A) physical
B) people
C) material
D) equipment
E) budget
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
63
If resource demand varies widely over the life of the project, the project manager can try to use slack (delaying noncritical activities) to accommodate insufficient resources. This process is called____.

A) resource scheduling
B) resource smoothing
C) resource-constrained scheduling
D) splitting
E) resource accommodation
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
64
When only one person is responsible for performing several activities, all due at the same time, this is an example of a(n) ________ constraint.

A) equipment
B) materials
C) technical
D) resource
E) logical
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
65
Delaying noncritical activities to lower peak demand and, thus, increase resource utilization is called resource __________.

A) smoothing
B) slack utilization
C) switching
D) re-scheduling
E) overtime
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
66
All leveling techniques delay noncritical activities by using ________ to reduce peak demand.

A) additional resources
B) additional time
C) positive risk
D) additional people
E) additional slack
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
67
Which constraint category should be considered before all others?

A) Logical and technical constraints
B) Human resource constraints
C) Material resource constraints
D) Equipment resource constraints
E) Time constraints
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
68
A(n) ________ constraint addresses the sequence in which project activities must occur even after considering resource constraints.

A) predecessor
B) technical or logic
C) successor
D) serial
E) hard
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
69
The shortage of memory chips to produce a printed circuit motherboard is an example of a(n) ________ type of resource constraint.

A) physical
B) people
C) material
D) equipment
E) budget
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
70
Resource dependency takes priority over the technological dependency but does not violate ___________ dependencies.

A) equipment
B) time
C) technical
D) resource
E) logical
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
71
A shortage of software developers to create software is an example of a(n) ________ type of resource constraint.

A) physical
B) people
C) material
D) equipment
E) budget
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
72
When scheduling activities in a resource-constrained project, typically the activity scheduled first has the __________ amount of slack.

A) least
B) most
C) greatest
D) maximum
E) modest
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
73
In order that the new product is on the shelf for the Christmas buying season, the development of the new product would be classified as a(n) ________ -constrained project.

A) equipment
B) time
C) technical
D) resource
E) logical
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
74
If three copiers are needed to produce a final report on time and only two are available, the project is facing a(n) ________ type of resource constraint.

A) physical
B) people
C) material
D) equipment
E) budget
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
75
When deciding which staff to team-up to work on work packages, factors to consider are:

A) Work habits.
B) Practical experience.
C) Years of working in the company.
D) Both work habits and practical experience.
E) Both practical experience and years of working in the company.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
76
A project manager has two engineers assigned to the project and does not have access to more even if the result means extending the completion date on the project. The project manager is managing a(n) ________.

A) time-constrained project
B) people-constrained project
C) engineer-constrained project
D) resource-constrained project
E) human-constrained project
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
77
Which of the following questions does a project manager NOT have to address when considering resources allocated to a project?

A) Will the assigned labor be adequate and available to deal with my project?
B) Will outside contractors have to be used?
C) Will scope have to be redefined / stabilized?
D) Do unforeseen resource dependencies exist?
E) How much flexibility do we have in using resources?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
78
When looking at the critical path for a delayed project and the project manager sees that adding resources will reduce or remove the delay, the project manager knows that the project is:

A) Over Allocated.
B) Time-Constrained.
C) Institutionally Challenged.
D) Ahead of schedule.
E) Unstable.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
79
If it becomes necessary to delay one or several late starts to accommodate resource limitations, this is called:

A) Resource scheduling
B) Resource smoothing
C) Resource-constrained scheduling
D) Splitting
E) Resource accommodation
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
80
While balancing assignments, a project manager must also balance:

A) Overall project cost.
B) Talent development.
C) Earned value.
D) Work package slack.
E) Project cost.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.
فتح الحزمة
k this deck
locked card icon
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 114 في هذه المجموعة.