A Master Production Schedule is an engineering document that shows an inclusive listing of all component parts and subassemblies making up the end item.
استخدم زر المسافة أو
up arrow
down arrow
لقلب البطاقة.
سؤال
An ERP system is generally a multi-module application software for managing an enterprise's internal functional activities, as well as its suppliers and customers.
سؤال
A level production strategy works well for make-to-stock manufacturing firms, which typically emphasize immediate delivery of off-the-shelf, standard goods at relatively low prices.
سؤال
ERP Implosion is the process of converting a parent item's planned order releases into component gross requirements.
سؤال
An MRP system has a subassembly with a lot size of 500 units.In terms of filling future requirements, this would mean that planned order releases for the subassembly would always have to be exactly 500 units.
سؤال
Distribution requirements plan (DRP) operates in a dependent demand situation.
سؤال
Legacy systems were designed to perform a very specific operational function.
سؤال
In general, single integrator ERP solutions are better suited to more intricate workplaces.
سؤال
Two reasons ERP implementations have been known to fail include: lack of top management commitment and lack of communication between the firm and its ERP software provider.
سؤال
ERP systems were designed to coordinate the information requirements for purchasing, planning, scheduling and distribution of an organization operating in a complex multi-unit global environment.
سؤال
The chase production strategy works well when highly skilled workers are needed, especially in a tight labor market.
سؤال
MRP is the production planning system intended to develop long-range plans (more than a year away) concerning product families manufactured by the organization.
سؤال
The three basic production strategies for addressing the aggregate planning problem are the chase production strategy, the level production strategy, and the aggregate production strategy.
سؤال
When a single company that is implementing an ERP system chooses to use one company to provide an operations module, another to provide the sales and marketing application, and yet another company to provide the finance and accounting module, that single company has chosen to utilize the single integrator approach.
سؤال
System nervousness is when even small changes to upper-level production plans cause major changes in lower-level production plans.
سؤال
Legacy MRP systems typically utilized multiple software packages and databases which caused the same information to be stored in multiple locations.
سؤال
ERP provides the mechanism for supply chain members to share information so that scarce resources can be fully utilized to meet demand, while minimizing the bullwhip effect and supply chain inventories.
سؤال
The legacy MRP system was programmed to coordinate with other functional areas in the firm.
سؤال
The mixed strategy uses overtime and subcontracting to cope with the high demand periods.
سؤال
Lead Capacity Strategy is a reactive approach that adjusts its capacity in response to demand.
سؤال
The best-of-breed solution picks all the desired applications from a single vendor for the ERP system.
سؤال
Which of the following MRP terms represents a committed order awaiting delivery for a specific period?

A) Projected on-hand inventory
B) Time bucket
C) Net requirement
D) Scheduled receipt
سؤال
If an available-to-promise (ATP) for any period is negative, the deficit must be subtracted from the:

A) Master Production Schedule
B) Most recent positive ATP
C) Beginning inventory
D) Bill of materials
سؤال
Which of the following basic production strategies works best with make-to-order manufacturing firms?

A) Capacity Production Strategy
B) Mixed production Strategy
C) Level Production Strategy
D) Chase Production Strategy
سؤال
Calculate the final discrete available-to-promise quantity for Week 1 using the following table. <strong>Calculate the final discrete available-to-promise quantity for Week 1 using the following table.  </strong> A) ATP1 = 0 B) ATP1 = 10 C) ATP1 = 15 D) ATP1 = 20 <div style=padding-top: 35px>

A) ATP1 = 0
B) ATP1 = 10
C) ATP1 = 15
D) ATP1 = 20
سؤال
In a bill of materials, items at which level are independent demand items?

A) Level 0
B) Level 1
C) Level 2
D) Level 3
سؤال
What is the most important output of the MRP?

A) Bill of materials
B) Distribution requirements plan
C) Planned order releases
D) Aggregate production plan
سؤال
The __________ specifies which end product is to be made, how many are required, and when they need to be completed.

A) Aggregate production plan
B) Master production schedule
C) Bill of material
D) Super bill of materials
سؤال
Which of the following is NOT one of the three basic methods used to calculate the available-to-promise quantities?

A) Discrete available-to-promise
B) Cumulative available-to-promise without looking ahead
C) Indiscrete available-to-promise
D) Cumulative available-to-promise with looking ahead
سؤال
Which strategy allows finished goods inventories to accrue and relies on backlogs to handle the demand?

A) The Level Production Strategy
B) Mixed Production Strategy
C) The Chase Production Strategy
D) The Aggregate Production Strategy
سؤال
The _______________ is used to check the feasibility of the Master Production Schedule.

A) Distribution Requirement Plan
B) Material Requirement Plan
C) Capacity Requirement Plan
D) Rough-Cut Capacity Plan
سؤال
Which of the following keeps the production plan's capacity fixed during the planning horizon?

A) Materials Requirements Plan
B) Master Capacity Plan
C) Aggregate Production Plan
D) Capacity Requirements Plan
سؤال
Implementing a best-of-breed solution may cause firms to link databases from multiple software applications of different vendors.
سؤال
Complete the following MRP record and provide the planned order releases for Week 1.Lead time is 2 weeks.Safety stock is 3.Use LFL lot sizes. <strong>Complete the following MRP record and provide the planned order releases for Week 1.Lead time is 2 weeks.Safety stock is 3.Use LFL lot sizes.  </strong> A) 34 B) 26 C) 29 D) 14 <div style=padding-top: 35px>

A) 34
B) 26
C) 29
D) 14
سؤال
Which of the following MRP terms represents the parts demanded by a parent?

A) Gross requirement
B) Component
C) Net requirement
D) Scheduled receipt
سؤال
Which of the following results from using the chase production strategy?

A) The workforce fluctuates in response to the demand pattern
B) Finished goods inventories remain constant
C) Both A & B
D) None of these
سؤال
Which strategy uses overtime and subcontracting to cope with the high demand periods ?

A) The Level Production Strategy
B) Mixed Production Strategy
C) The Chase Production Strategy
D) The Aggregate Production Strategy
سؤال
Which of the following seeks to develop short range plans seeking to effectively and efficiently manage components and/or subassemblies over time period of few days to a few weeks?

A) Resource requirements plan
B) Material requirements plan
C) Rough-cut capacity plan
D) Master production schedule
سؤال
The ___________ planning horizon is shorter than the aggregate production plan's, but must be longer than a firm's production lead time to ensure the end item can be completed within the planning horizon?

A) Material requirements plan
B) Master production schedule
C) Demand time fence
D) Capacity Requirements Plan
سؤال
Lack of communication between the implementing firm and its ERP software provider can become a major hindrance for a successful implementation.
سؤال
According to the textbook, which of the following is considered a reason that ERP implementations fail?

A) Top management becomes overcommitted to the point where they constantly encourage the employees during implementation
B) Lack of communication within an organization
C) Organizations tend to spend too much time and money training their employees on the new system
D) All of the above
سؤال
Legacy MRP systems had which of the following limitations?

A) The systems needed continuous modifications
B) The systems were not user-friendly
C) The systems were designed to perform a very specific operational function
D) All of these
سؤال
While ERP is a relatively new technology, it has grown rapidly since the early 1990s.Which of the following is the reason that has contributed to its rapid growth?

A) The increased use of email during the 1990's
B) The trend for companies to eliminate their supply chain partners
C) The year 2000 millennium bug
D) All of the above
سؤال
Which of the following is NOT a common module of ERP systems?

A) Human Resources Management
B) Customer Relationship Management
C) Marketing Resources Management
D) Supply Chain Management
سؤال
This chapter discussed both materials planning and capacity planning.Consider those concepts in answering the following questions:
a.Which is more appropriate for a conventional service organization? Why?
b.Which is more appropriate for a conventional manufacturing organization? Why?
c.What are the three hierarchical components of materials planning? Provide a brief description of each.
d.What are the three hierarchical components of capacity planning? Provide a brief description of each.
سؤال
The acronym ERP is short for:

A) Enterprise Resource Planning
B) Electronic Resource Provider
C) Executive Resource Plan
D) Electronic Requirements Provider
سؤال
Legacy MRP systems typically utilized multiple software packages and databases which caused:

A) The system to crash often
B) The same information to be stored in multiple locations
C) Data integrity
D) Planned order releases
سؤال
Which of the following is considered a disadvantage of utilizing an ERP system?

A) ERP systems reduce the bullwhip effect
B) ERP systems are very complex and have proven difficult to implement
C) ERP systems use a single database and common infrastructure
D) Once ERP information is entered it is made available to all users
سؤال
Calculate the final discrete available-to-promise quantity row using the following table below and explain how the numbers are generated.
Calculate the final discrete available-to-promise quantity row using the following table below and explain how the numbers are generated.  <div style=padding-top: 35px>
سؤال
The ___________ solution picks all the desired applications from a single vendor for the ERP system.

A) Best-of-breed
B) Elite integrator
C) Single integrator
D) Premier application
سؤال
What is ERP? Why was it developed?
سؤال
What does it mean if your organization has chosen to adopt a best-of-breed solution?
سؤال
Why are firms migrating to ERP systems?

A) ERP systems are easy to implement, particularly in large organizations
B) ERP systems tie together a variety of specialized systems
C) ERP systems are successful with two-dimensional processes
D) ERP systems are inexpensive to implement
سؤال
Which of the following is considered an advantage/benefit of utilizing an ERP system?

A) Fairly inexpensive to purchase and implement
B) Enables the company to utilize a single centralized database system, thus eliminating duplicate data entries
C) Flexible enough that it allows different companies with different business models to mold the new ERP system to fit the company's business model
D) All of the above
سؤال
An advantage/benefit of utilizing an ERP system includes which of the following?

A) ERP systems are designed to take advantage of Internet technology
B) ERP systems enable the firm to automate some of the steps of a manufacturing process
C) Both A & B
D) None of the above
سؤال
Explain the three basic production strategies used to complete the aggregate plan.
سؤال
Not all ERP software is designed to provide the exact same tools, nonetheless, some of the common modules usually included in ERP software packages include:

A) Customer relationship management and Human resource management
B) Computer assisted drawing and Photo enhancing
C) Operating systems and Internet browsing
D) All of the above
سؤال
Complete the Projected on Hand Inventory and Planned Order Release rows.
Complete the Projected on Hand Inventory and Planned Order Release rows.  <div style=padding-top: 35px>
سؤال
Describe the limitations of a legacy MRP system.?
سؤال
Using the ________________ multiple software infrastructures and databases may have to be used to link the multiple applications obtained from different vendors.

A) Best-of-breed solution
B) Elite integrator solution
C) Multi-modular solution
D) Premier application solution
سؤال
Your firm is considering modernizing its organizational information systems.
Your boss asks you, "Do you think our company needs an ERP system?" Obviously, without knowing the details of this company or the industry in which it operates, it would be difficult to provide a detailed answer to this question.
Your new project may take days, weeks, or even months to answer accurately, but before you begin your research you should develop a short but detailed outline for a paper that will inform the boss about the basics of ERP, the advantages of ERP, as well as the disadvantages of ERP.
Answer some of these questions within your outline/answer:
•What is ERP?
•Why should the organization get an ERP system?
•Why might the organization not want to get ERP?
•If we did get an ERP system what would be required for successful implementation?
سؤال
Given the following information, complete the MRP records below and explain how the numbers are generated.Note the bill of materials.Also note the lot sizes and lead times.There are no scheduled receipts and no safety stock is required.
Given the following information, complete the MRP records below and explain how the numbers are generated.Note the bill of materials.Also note the lot sizes and lead times.There are no scheduled receipts and no safety stock is required.  <div style=padding-top: 35px>
فتح الحزمة
قم بالتسجيل لفتح البطاقات في هذه المجموعة!
Unlock Deck
Unlock Deck
1/62
auto play flashcards
العب
simple tutorial
ملء الشاشة (f)
exit full mode
Deck 6: Resource Planning Systems
1
A Master Production Schedule is an engineering document that shows an inclusive listing of all component parts and subassemblies making up the end item.
False
2
An ERP system is generally a multi-module application software for managing an enterprise's internal functional activities, as well as its suppliers and customers.
True
3
A level production strategy works well for make-to-stock manufacturing firms, which typically emphasize immediate delivery of off-the-shelf, standard goods at relatively low prices.
True
4
ERP Implosion is the process of converting a parent item's planned order releases into component gross requirements.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
5
An MRP system has a subassembly with a lot size of 500 units.In terms of filling future requirements, this would mean that planned order releases for the subassembly would always have to be exactly 500 units.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
6
Distribution requirements plan (DRP) operates in a dependent demand situation.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
7
Legacy systems were designed to perform a very specific operational function.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
8
In general, single integrator ERP solutions are better suited to more intricate workplaces.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
9
Two reasons ERP implementations have been known to fail include: lack of top management commitment and lack of communication between the firm and its ERP software provider.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
10
ERP systems were designed to coordinate the information requirements for purchasing, planning, scheduling and distribution of an organization operating in a complex multi-unit global environment.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
11
The chase production strategy works well when highly skilled workers are needed, especially in a tight labor market.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
12
MRP is the production planning system intended to develop long-range plans (more than a year away) concerning product families manufactured by the organization.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
13
The three basic production strategies for addressing the aggregate planning problem are the chase production strategy, the level production strategy, and the aggregate production strategy.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
14
When a single company that is implementing an ERP system chooses to use one company to provide an operations module, another to provide the sales and marketing application, and yet another company to provide the finance and accounting module, that single company has chosen to utilize the single integrator approach.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
15
System nervousness is when even small changes to upper-level production plans cause major changes in lower-level production plans.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
16
Legacy MRP systems typically utilized multiple software packages and databases which caused the same information to be stored in multiple locations.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
17
ERP provides the mechanism for supply chain members to share information so that scarce resources can be fully utilized to meet demand, while minimizing the bullwhip effect and supply chain inventories.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
18
The legacy MRP system was programmed to coordinate with other functional areas in the firm.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
19
The mixed strategy uses overtime and subcontracting to cope with the high demand periods.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
20
Lead Capacity Strategy is a reactive approach that adjusts its capacity in response to demand.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
21
The best-of-breed solution picks all the desired applications from a single vendor for the ERP system.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
22
Which of the following MRP terms represents a committed order awaiting delivery for a specific period?

A) Projected on-hand inventory
B) Time bucket
C) Net requirement
D) Scheduled receipt
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
23
If an available-to-promise (ATP) for any period is negative, the deficit must be subtracted from the:

A) Master Production Schedule
B) Most recent positive ATP
C) Beginning inventory
D) Bill of materials
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
24
Which of the following basic production strategies works best with make-to-order manufacturing firms?

A) Capacity Production Strategy
B) Mixed production Strategy
C) Level Production Strategy
D) Chase Production Strategy
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
25
Calculate the final discrete available-to-promise quantity for Week 1 using the following table. <strong>Calculate the final discrete available-to-promise quantity for Week 1 using the following table.  </strong> A) ATP1 = 0 B) ATP1 = 10 C) ATP1 = 15 D) ATP1 = 20

A) ATP1 = 0
B) ATP1 = 10
C) ATP1 = 15
D) ATP1 = 20
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
26
In a bill of materials, items at which level are independent demand items?

A) Level 0
B) Level 1
C) Level 2
D) Level 3
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
27
What is the most important output of the MRP?

A) Bill of materials
B) Distribution requirements plan
C) Planned order releases
D) Aggregate production plan
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
28
The __________ specifies which end product is to be made, how many are required, and when they need to be completed.

A) Aggregate production plan
B) Master production schedule
C) Bill of material
D) Super bill of materials
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
29
Which of the following is NOT one of the three basic methods used to calculate the available-to-promise quantities?

A) Discrete available-to-promise
B) Cumulative available-to-promise without looking ahead
C) Indiscrete available-to-promise
D) Cumulative available-to-promise with looking ahead
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
30
Which strategy allows finished goods inventories to accrue and relies on backlogs to handle the demand?

A) The Level Production Strategy
B) Mixed Production Strategy
C) The Chase Production Strategy
D) The Aggregate Production Strategy
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
31
The _______________ is used to check the feasibility of the Master Production Schedule.

A) Distribution Requirement Plan
B) Material Requirement Plan
C) Capacity Requirement Plan
D) Rough-Cut Capacity Plan
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
32
Which of the following keeps the production plan's capacity fixed during the planning horizon?

A) Materials Requirements Plan
B) Master Capacity Plan
C) Aggregate Production Plan
D) Capacity Requirements Plan
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
33
Implementing a best-of-breed solution may cause firms to link databases from multiple software applications of different vendors.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
34
Complete the following MRP record and provide the planned order releases for Week 1.Lead time is 2 weeks.Safety stock is 3.Use LFL lot sizes. <strong>Complete the following MRP record and provide the planned order releases for Week 1.Lead time is 2 weeks.Safety stock is 3.Use LFL lot sizes.  </strong> A) 34 B) 26 C) 29 D) 14

A) 34
B) 26
C) 29
D) 14
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
35
Which of the following MRP terms represents the parts demanded by a parent?

A) Gross requirement
B) Component
C) Net requirement
D) Scheduled receipt
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
36
Which of the following results from using the chase production strategy?

A) The workforce fluctuates in response to the demand pattern
B) Finished goods inventories remain constant
C) Both A & B
D) None of these
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
37
Which strategy uses overtime and subcontracting to cope with the high demand periods ?

A) The Level Production Strategy
B) Mixed Production Strategy
C) The Chase Production Strategy
D) The Aggregate Production Strategy
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
38
Which of the following seeks to develop short range plans seeking to effectively and efficiently manage components and/or subassemblies over time period of few days to a few weeks?

A) Resource requirements plan
B) Material requirements plan
C) Rough-cut capacity plan
D) Master production schedule
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
39
The ___________ planning horizon is shorter than the aggregate production plan's, but must be longer than a firm's production lead time to ensure the end item can be completed within the planning horizon?

A) Material requirements plan
B) Master production schedule
C) Demand time fence
D) Capacity Requirements Plan
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
40
Lack of communication between the implementing firm and its ERP software provider can become a major hindrance for a successful implementation.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
41
According to the textbook, which of the following is considered a reason that ERP implementations fail?

A) Top management becomes overcommitted to the point where they constantly encourage the employees during implementation
B) Lack of communication within an organization
C) Organizations tend to spend too much time and money training their employees on the new system
D) All of the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
42
Legacy MRP systems had which of the following limitations?

A) The systems needed continuous modifications
B) The systems were not user-friendly
C) The systems were designed to perform a very specific operational function
D) All of these
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
43
While ERP is a relatively new technology, it has grown rapidly since the early 1990s.Which of the following is the reason that has contributed to its rapid growth?

A) The increased use of email during the 1990's
B) The trend for companies to eliminate their supply chain partners
C) The year 2000 millennium bug
D) All of the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
44
Which of the following is NOT a common module of ERP systems?

A) Human Resources Management
B) Customer Relationship Management
C) Marketing Resources Management
D) Supply Chain Management
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
45
This chapter discussed both materials planning and capacity planning.Consider those concepts in answering the following questions:
a.Which is more appropriate for a conventional service organization? Why?
b.Which is more appropriate for a conventional manufacturing organization? Why?
c.What are the three hierarchical components of materials planning? Provide a brief description of each.
d.What are the three hierarchical components of capacity planning? Provide a brief description of each.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
46
The acronym ERP is short for:

A) Enterprise Resource Planning
B) Electronic Resource Provider
C) Executive Resource Plan
D) Electronic Requirements Provider
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
47
Legacy MRP systems typically utilized multiple software packages and databases which caused:

A) The system to crash often
B) The same information to be stored in multiple locations
C) Data integrity
D) Planned order releases
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
48
Which of the following is considered a disadvantage of utilizing an ERP system?

A) ERP systems reduce the bullwhip effect
B) ERP systems are very complex and have proven difficult to implement
C) ERP systems use a single database and common infrastructure
D) Once ERP information is entered it is made available to all users
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
49
Calculate the final discrete available-to-promise quantity row using the following table below and explain how the numbers are generated.
Calculate the final discrete available-to-promise quantity row using the following table below and explain how the numbers are generated.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
50
The ___________ solution picks all the desired applications from a single vendor for the ERP system.

A) Best-of-breed
B) Elite integrator
C) Single integrator
D) Premier application
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
51
What is ERP? Why was it developed?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
52
What does it mean if your organization has chosen to adopt a best-of-breed solution?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
53
Why are firms migrating to ERP systems?

A) ERP systems are easy to implement, particularly in large organizations
B) ERP systems tie together a variety of specialized systems
C) ERP systems are successful with two-dimensional processes
D) ERP systems are inexpensive to implement
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
54
Which of the following is considered an advantage/benefit of utilizing an ERP system?

A) Fairly inexpensive to purchase and implement
B) Enables the company to utilize a single centralized database system, thus eliminating duplicate data entries
C) Flexible enough that it allows different companies with different business models to mold the new ERP system to fit the company's business model
D) All of the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
55
An advantage/benefit of utilizing an ERP system includes which of the following?

A) ERP systems are designed to take advantage of Internet technology
B) ERP systems enable the firm to automate some of the steps of a manufacturing process
C) Both A & B
D) None of the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
56
Explain the three basic production strategies used to complete the aggregate plan.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
57
Not all ERP software is designed to provide the exact same tools, nonetheless, some of the common modules usually included in ERP software packages include:

A) Customer relationship management and Human resource management
B) Computer assisted drawing and Photo enhancing
C) Operating systems and Internet browsing
D) All of the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
58
Complete the Projected on Hand Inventory and Planned Order Release rows.
Complete the Projected on Hand Inventory and Planned Order Release rows.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
59
Describe the limitations of a legacy MRP system.?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
60
Using the ________________ multiple software infrastructures and databases may have to be used to link the multiple applications obtained from different vendors.

A) Best-of-breed solution
B) Elite integrator solution
C) Multi-modular solution
D) Premier application solution
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
61
Your firm is considering modernizing its organizational information systems.
Your boss asks you, "Do you think our company needs an ERP system?" Obviously, without knowing the details of this company or the industry in which it operates, it would be difficult to provide a detailed answer to this question.
Your new project may take days, weeks, or even months to answer accurately, but before you begin your research you should develop a short but detailed outline for a paper that will inform the boss about the basics of ERP, the advantages of ERP, as well as the disadvantages of ERP.
Answer some of these questions within your outline/answer:
•What is ERP?
•Why should the organization get an ERP system?
•Why might the organization not want to get ERP?
•If we did get an ERP system what would be required for successful implementation?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
62
Given the following information, complete the MRP records below and explain how the numbers are generated.Note the bill of materials.Also note the lot sizes and lead times.There are no scheduled receipts and no safety stock is required.
Given the following information, complete the MRP records below and explain how the numbers are generated.Note the bill of materials.Also note the lot sizes and lead times.There are no scheduled receipts and no safety stock is required.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.
فتح الحزمة
k this deck
locked card icon
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 62 في هذه المجموعة.