Deck 7: Killer Clauses

ملء الشاشة (f)
exit full mode
سؤال
Acceleration clauses cannot require a Constructor to perform work in a manner that is more costly than originally planned
استخدم زر المسافة أو
up arrow
down arrow
لقلب البطاقة.
سؤال
Generally not included in a Time and Material cost is

A) home office personnel
B) required equipment rental
C) consumed material
D) all of these
سؤال
For progress billing, the Contract Administrator should coordinate with

A) the Design Professional
B) Subcontractors
C) field supervision
D) all of these
سؤال
If a Supplier might go bankrupt, the Contract Administrator should

A) get a copy of keys to any storage of materials the Contractor might need
B) have material delivered to the project site or other facility
C) wait for notification of the bankruptcy so no one is pushed into the situation
D) cancel the order and get a new supplier
سؤال
If there is a ""no damage for delay clause"" the Contract Administrator

A) can relax
B) can thank the Owner
C) should still make sure all delays are documented
D) pursue arbitration related to any delays
سؤال
If a hazardous substance is exposed

A) the crew should immediately cover it back
B) the crew should notify management and refrain from disturbing it more
C) should stop all work and leave the project site until it is safe and secure
D) should carefully remove it and dispose of it immediately or as soon as possible
سؤال
When terminating for cause

A) be sure all reasonable efforts to accommodate the performance of the party to be terminated have been documented
B) stop the party to be terminated from performing work immediately upon notice
C) pay any monies due and then terminate the Contractor
D) all of these
سؤال
Exculpatory clauses

A) usually contain risks that are insurable
B) usually contain risks that are not insurable
C) are illegal
D) are not able to be passed on to a lower-tier party
سؤال
Indemnity clauses

A) usually contain issues that are insurable
B) usually contain issues that are not insurable
C) are illegal
D) are not able to be passed on to a lower-tier party
سؤال
Contractors should be alert to hazardous substances in buildings

A) constructed before 1990
B) constructed before 1980
C) constructed before 2000
D) all residences and townhouses regardless of when they were built
سؤال
It is often said that the most dangerous clause in any Contract is

A) the signature block
B) the one you don't know about
C) the ""Notice Clause""
D) the General Conditions
سؤال
Constructive Acceleration

A) helps everyone
B) is when the Owner requires the Constructor to increase production without agreeing to pay additional money
C) is determined by the Constructor in counsel with the Subcontractors
D) is usually required based on design errors
سؤال
Notice clauses can be critical for

A) differing site conditions
B) change orders affecting time and/or money
C) RFI related to an ambiguity
D) all of these
سؤال
When an Owner exercises a ""Termination for Convenience"" the Constructor is not entitled to any further compensation
سؤال
An exculpatory clause shifts responsibility for actions done or caused by one party to another party
سؤال
Contracts can contain indemnity clauses requiring another party to assume the costs for damages done by another party
سؤال
A Constructor cannot be held responsible for hidden conditions
سؤال
An Owner cannot delay the whole or a portion of the work without compensating the Constructor
سؤال
A PRP does not have to be the party or entity that installed the hazardous material
سؤال
A Contract can be terminated for cause or convenience
سؤال
UCC stands for Uniform Cost Code
سؤال
The contract will usually clearly define what will be included in Time and Material costs
سؤال
In the event of bankruptcy of a Supplier, materials stored at the Supplier's facility become the property of the Contractor
سؤال
Whether there is a ""notice clause"" or not in the contract, the Contract Administrator should notify the owner of any delays
سؤال
An Acceleration clause is illegal
سؤال
A Mechanics Lien is

A) a bad idea
B) a good way to get quick payment
C) also known as a Construction Lien
D) good for an Owner with poor cash flow
فتح الحزمة
قم بالتسجيل لفتح البطاقات في هذه المجموعة!
Unlock Deck
Unlock Deck
1/26
auto play flashcards
العب
simple tutorial
ملء الشاشة (f)
exit full mode
Deck 7: Killer Clauses
1
Acceleration clauses cannot require a Constructor to perform work in a manner that is more costly than originally planned
False
2
Generally not included in a Time and Material cost is

A) home office personnel
B) required equipment rental
C) consumed material
D) all of these
A
3
For progress billing, the Contract Administrator should coordinate with

A) the Design Professional
B) Subcontractors
C) field supervision
D) all of these
D
4
If a Supplier might go bankrupt, the Contract Administrator should

A) get a copy of keys to any storage of materials the Contractor might need
B) have material delivered to the project site or other facility
C) wait for notification of the bankruptcy so no one is pushed into the situation
D) cancel the order and get a new supplier
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 26 في هذه المجموعة.
فتح الحزمة
k this deck
5
If there is a ""no damage for delay clause"" the Contract Administrator

A) can relax
B) can thank the Owner
C) should still make sure all delays are documented
D) pursue arbitration related to any delays
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 26 في هذه المجموعة.
فتح الحزمة
k this deck
6
If a hazardous substance is exposed

A) the crew should immediately cover it back
B) the crew should notify management and refrain from disturbing it more
C) should stop all work and leave the project site until it is safe and secure
D) should carefully remove it and dispose of it immediately or as soon as possible
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 26 في هذه المجموعة.
فتح الحزمة
k this deck
7
When terminating for cause

A) be sure all reasonable efforts to accommodate the performance of the party to be terminated have been documented
B) stop the party to be terminated from performing work immediately upon notice
C) pay any monies due and then terminate the Contractor
D) all of these
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 26 في هذه المجموعة.
فتح الحزمة
k this deck
8
Exculpatory clauses

A) usually contain risks that are insurable
B) usually contain risks that are not insurable
C) are illegal
D) are not able to be passed on to a lower-tier party
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 26 في هذه المجموعة.
فتح الحزمة
k this deck
9
Indemnity clauses

A) usually contain issues that are insurable
B) usually contain issues that are not insurable
C) are illegal
D) are not able to be passed on to a lower-tier party
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 26 في هذه المجموعة.
فتح الحزمة
k this deck
10
Contractors should be alert to hazardous substances in buildings

A) constructed before 1990
B) constructed before 1980
C) constructed before 2000
D) all residences and townhouses regardless of when they were built
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 26 في هذه المجموعة.
فتح الحزمة
k this deck
11
It is often said that the most dangerous clause in any Contract is

A) the signature block
B) the one you don't know about
C) the ""Notice Clause""
D) the General Conditions
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 26 في هذه المجموعة.
فتح الحزمة
k this deck
12
Constructive Acceleration

A) helps everyone
B) is when the Owner requires the Constructor to increase production without agreeing to pay additional money
C) is determined by the Constructor in counsel with the Subcontractors
D) is usually required based on design errors
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 26 في هذه المجموعة.
فتح الحزمة
k this deck
13
Notice clauses can be critical for

A) differing site conditions
B) change orders affecting time and/or money
C) RFI related to an ambiguity
D) all of these
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 26 في هذه المجموعة.
فتح الحزمة
k this deck
14
When an Owner exercises a ""Termination for Convenience"" the Constructor is not entitled to any further compensation
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 26 في هذه المجموعة.
فتح الحزمة
k this deck
15
An exculpatory clause shifts responsibility for actions done or caused by one party to another party
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 26 في هذه المجموعة.
فتح الحزمة
k this deck
16
Contracts can contain indemnity clauses requiring another party to assume the costs for damages done by another party
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 26 في هذه المجموعة.
فتح الحزمة
k this deck
17
A Constructor cannot be held responsible for hidden conditions
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 26 في هذه المجموعة.
فتح الحزمة
k this deck
18
An Owner cannot delay the whole or a portion of the work without compensating the Constructor
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 26 في هذه المجموعة.
فتح الحزمة
k this deck
19
A PRP does not have to be the party or entity that installed the hazardous material
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 26 في هذه المجموعة.
فتح الحزمة
k this deck
20
A Contract can be terminated for cause or convenience
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 26 في هذه المجموعة.
فتح الحزمة
k this deck
21
UCC stands for Uniform Cost Code
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 26 في هذه المجموعة.
فتح الحزمة
k this deck
22
The contract will usually clearly define what will be included in Time and Material costs
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 26 في هذه المجموعة.
فتح الحزمة
k this deck
23
In the event of bankruptcy of a Supplier, materials stored at the Supplier's facility become the property of the Contractor
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 26 في هذه المجموعة.
فتح الحزمة
k this deck
24
Whether there is a ""notice clause"" or not in the contract, the Contract Administrator should notify the owner of any delays
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 26 في هذه المجموعة.
فتح الحزمة
k this deck
25
An Acceleration clause is illegal
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 26 في هذه المجموعة.
فتح الحزمة
k this deck
26
A Mechanics Lien is

A) a bad idea
B) a good way to get quick payment
C) also known as a Construction Lien
D) good for an Owner with poor cash flow