Deck 13: Schedule

ملء الشاشة (f)
exit full mode
سؤال
The extra costs related to directed acceleration will be paid for
استخدم زر المسافة أو
up arrow
down arrow
لقلب البطاقة.
سؤال
Once a contract is signed, usually the most important issue for the Owner is

A) cost
B) schedule
C) quality
D) safety
سؤال
A Contractor knows the schedule is important to

A) negotiating changes in how the work is done
B) keep the crews happy
C) prevent a drain on profits due to schedule overruns
D) keep from making safety mistakes
سؤال
Liquidated damages are

A) no longer legal
B) agreed to by the Contractor when the Contract is signed
C) inflated costs for not finishing on time
D) seldom enforced
سؤال
Liquidated damages are

A) seldom enforced
B) always enforced
C) capable of being challenged, but requiring good documentation
D) not capable of being challenged if the Contractor has missed the completion date
سؤال
Delays along any part of the schedule that contains float are considered

A) non-critical delays
B) critical delays
C) critical but inconsequential delays
D) floating delays
سؤال
In regard to use of float

A) the Owner or Designers might use it first
B) the contract generally prevents anyone but the Constructor from using it
C) the Contractor can always prevent the Owner from using it
D) no one should use it without first getting the Owner's permission
سؤال
Float is often seen as belonging to

A) the Owner to distribute as needed
B) whoever uses it first
C) the Design Professional
D) whoever needs it most
سؤال
If the Owner cannot extend the completion date after a delay

A) the Contractor will need to perform some sort of acceleration
B) the project will have to be canceled
C) the General will have to hold Subcontractors accountable for the delay
D) the Contractor has no recourse but to sue the Owner and the Design Professional
سؤال
In a non-compensable delay, the Contractor is not entitled to a time extension or more money
سؤال
An Act of God will automatically increase contract completion time
سؤال
Trade stacking usually occurs at the beginning of the project before everyone understands the full scope of work
سؤال
Acts of God are compensable delays
سؤال
A concurrent delay is when two or more delays overlap each other
سؤال
A critical delay will affect the schedule for completion
سؤال
An excusable delay will involve additional compensation by the Owner
سؤال
Float on a schedule is not found on the critical path
سؤال
Liquidated damages are usually covered by flood insurance
سؤال
A compensable delay has to affect the critical path
سؤال
""Time is of the essence"" clauses are so common they no longer are strictly enforceable
سؤال
""Construed against the drafter"" is

A) no longer a legal principle
B) the first issue a Constructor might raise regarding an error in the plans
C) negated by the Spearin Doctrine
D) the reason an Owner is not responsible for design changes
فتح الحزمة
قم بالتسجيل لفتح البطاقات في هذه المجموعة!
Unlock Deck
Unlock Deck
1/21
auto play flashcards
العب
simple tutorial
ملء الشاشة (f)
exit full mode
Deck 13: Schedule
1
The extra costs related to directed acceleration will be paid for
True
2
Once a contract is signed, usually the most important issue for the Owner is

A) cost
B) schedule
C) quality
D) safety
B
3
A Contractor knows the schedule is important to

A) negotiating changes in how the work is done
B) keep the crews happy
C) prevent a drain on profits due to schedule overruns
D) keep from making safety mistakes
C
4
Liquidated damages are

A) no longer legal
B) agreed to by the Contractor when the Contract is signed
C) inflated costs for not finishing on time
D) seldom enforced
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 21 في هذه المجموعة.
فتح الحزمة
k this deck
5
Liquidated damages are

A) seldom enforced
B) always enforced
C) capable of being challenged, but requiring good documentation
D) not capable of being challenged if the Contractor has missed the completion date
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 21 في هذه المجموعة.
فتح الحزمة
k this deck
6
Delays along any part of the schedule that contains float are considered

A) non-critical delays
B) critical delays
C) critical but inconsequential delays
D) floating delays
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 21 في هذه المجموعة.
فتح الحزمة
k this deck
7
In regard to use of float

A) the Owner or Designers might use it first
B) the contract generally prevents anyone but the Constructor from using it
C) the Contractor can always prevent the Owner from using it
D) no one should use it without first getting the Owner's permission
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 21 في هذه المجموعة.
فتح الحزمة
k this deck
8
Float is often seen as belonging to

A) the Owner to distribute as needed
B) whoever uses it first
C) the Design Professional
D) whoever needs it most
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 21 في هذه المجموعة.
فتح الحزمة
k this deck
9
If the Owner cannot extend the completion date after a delay

A) the Contractor will need to perform some sort of acceleration
B) the project will have to be canceled
C) the General will have to hold Subcontractors accountable for the delay
D) the Contractor has no recourse but to sue the Owner and the Design Professional
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 21 في هذه المجموعة.
فتح الحزمة
k this deck
10
In a non-compensable delay, the Contractor is not entitled to a time extension or more money
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 21 في هذه المجموعة.
فتح الحزمة
k this deck
11
An Act of God will automatically increase contract completion time
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 21 في هذه المجموعة.
فتح الحزمة
k this deck
12
Trade stacking usually occurs at the beginning of the project before everyone understands the full scope of work
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 21 في هذه المجموعة.
فتح الحزمة
k this deck
13
Acts of God are compensable delays
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 21 في هذه المجموعة.
فتح الحزمة
k this deck
14
A concurrent delay is when two or more delays overlap each other
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 21 في هذه المجموعة.
فتح الحزمة
k this deck
15
A critical delay will affect the schedule for completion
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 21 في هذه المجموعة.
فتح الحزمة
k this deck
16
An excusable delay will involve additional compensation by the Owner
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 21 في هذه المجموعة.
فتح الحزمة
k this deck
17
Float on a schedule is not found on the critical path
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 21 في هذه المجموعة.
فتح الحزمة
k this deck
18
Liquidated damages are usually covered by flood insurance
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 21 في هذه المجموعة.
فتح الحزمة
k this deck
19
A compensable delay has to affect the critical path
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 21 في هذه المجموعة.
فتح الحزمة
k this deck
20
""Time is of the essence"" clauses are so common they no longer are strictly enforceable
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 21 في هذه المجموعة.
فتح الحزمة
k this deck
21
""Construed against the drafter"" is

A) no longer a legal principle
B) the first issue a Constructor might raise regarding an error in the plans
C) negated by the Spearin Doctrine
D) the reason an Owner is not responsible for design changes
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 21 في هذه المجموعة.
فتح الحزمة
k this deck
locked card icon
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 21 في هذه المجموعة.