سؤال
Items to be procured during the project are identified

A) as work gets underway during project execution
B) during the WBS process or earlier
C) mostly during the contract negotiation process
استخدم زر المسافة أو
up arrow
down arrow
لقلب البطاقة.
سؤال
The customer advertises for project price bids usually when

A) scope of the project is complex, requirements are ill-defined, and bidder qualifications are unknown
B) scope of the project is somewhat simple, requirements are well defined, and bidders are pre-qualified.
C) scope of the project is somewhat simple, requirements are well defined, and bidders are pre-qualified
D) the customer is most interested in learning different contractors' ideas about the project
E) the customer is interested in negotiating with contractor to settle on the best process
سؤال
Sole-sourcing means:

A) multiple qualified bidders will be invited to bid
B) among several qualified sources, just one will be invited to bid
C) one (and only one) bidder is qualified and available to do the work
سؤال
Single-sourcing means

A) multiple qualified bidders will be invited to bid
B) among several qualified sources, just one will be invited to bid
C) one (and only one) bidder is qualified and available to do the work
سؤال
Multiple sourcing means

A) multiple qualified bidders will be invited to bid
B) among several qualified sources, just one will be invited to bid
C) one (and only one) bidder is qualified and available to do the work
سؤال
Ordinarily, the...

A) prime contractor freely selects its own subcontractors
B) customer chooses the subcontractors that will report to the prime contractor
C) customer selects and manages the subcontractors with the prime contractor's assistance
D) subcontractors to work under the prime contractor are specified in the RFP
سؤال
With a Time and Materials (T&M) contract

A) the customer pays a contracted fixed price that is estimated before the rpoject based on labor time and material
B) the contractor is reimbursed for direct labor hours at a specified per-person hourly rate plus material costs and a mark-up
C) the time represents the duration of the project (start to finish) and the materials are whatever was needed to produce the estimate
D) the contractor has an incentive to perform the work in the shortest time and with the fewest materials
سؤال
Which of the following contracts is most risky to the customer?

A) cost plus fixed fee
B) guaranteed maximum price
C) time & materials
D) firm fixed price
سؤال
Which of the following contracts is most risky to the contractor?

A) cost plus fixed fee
B) guaranteed maximum price
C) time & materials
D) firm fixed price
سؤال
In which of the following kinds of contracts is the actual, final cost of the project unknown until after the project is completed (circle all that apply):

A) cost plus fixed fee
B) fixed price
C) cost plus incentive fee
D) none of these
سؤال
The purpose of contract negotiation is to (circle all that apply):

A) clarify technical terms of the contract
B) reach agreement on time, cost, and performance requirements
C) convince the user that the project has been completed
D) reach a contract agreement to the best advantage of the parties involved
سؤال
Procurement management refers to management of (circle all that apply)

A) "bought" or "purchased" items for the project
B) design work or services provided by contractors
C) items that are produced internally
D) all off-the-shelf items, whether obtained internally of externally
E) "turnkey" items or systems
سؤال
Procurement management can involve which if the following (circle all that apply)

A) definition of work, materials, or services in the WBS or similar process
B) scheduling
C) budgeting
D) RFP/proposal/contracting process
E) logistical planning
سؤال
Procurement management addresses everything associated with (circle all that apply)

A) procuring
B) purchasing and contracting
C) contracted work
D) project scheduling and budgeting
E) working with "hired help"
سؤال
Procurement can include (circle all that apply)

A) acquisition of a complex system
B) purchasing parts and components
C) selecting a supplier of parts and components
D) acquiring the services of a design firm
E) monitoring the work of internal project staff
سؤال
"Procured items" include which of the following (circle all that apply)

A) products
B) materials
C) equipment
D) work
E) services
سؤال
A "solicitation package" includes (circle all that apply)

A) solicitation documents (RFP, RFQ, RFT, etc.)
B) list of qualified bidders
C) final signed contracts
D) proposal evaluation process and criteria
E) project close-out procedures
سؤال
The proposal/negotiation/solicitation method is more appropriate for

A) work that requires design, development, and/or research
B) scope of the project is somewhat simple, requirements are well defined, and bidders are pre-qualified
C) large and somewhat undefined systems
D) artistic work or other work that requires intellectual input
سؤال
During the negotiation process, the project manager

A) must be intimately familiar with the technical details of the proposed system's design and related costs
B) must try to learn about any competitor bidders
C) must be familiar with those parts of the project plan (schedule, work, or price) that are relatively "fixed" and those that can be negotiated
D) try to know as much as possible about the customer's needs and current position
سؤال
The role of contract administration is

A) authorizing work to begin
B) monitoring work
C) insuring compliance to contractors' responsibilities
D) managing waivers and changes
E) ensuring that the customer is invoiced for deliverables
سؤال
Contract administration is responsible for

A) determining which work should be done in-house and which should be outsourced
B) determining whether project end-items meet requirements as specified in the contract
C) determining whether all, some, or none of the deliverables should be accepted
D) precuring RFPs in the initial solicitation process
سؤال
With a Firm Fixed Price Contract (FFP)

A) the customer assumes the risk of cost overruns
B) the price to the customer remains the same
C) the contractor is assured of being reimbursed for all allowable expenses
D) contractor risks underestimating the cost and losing money on the project
E) cutting-corners to reduce costs is a potential risk
سؤال
In a Fixed Price Incentive Fee Contract (FPIF)

A) the customer can pay a lower price if the contractor can reduce costs
B) the incentive can be determined by the cost sharing ratio
C) the contractor can earn a larger profit by reducing costs
D) is not really a fixed-price contract
E) the price is periodically adjusted to allow for changes in materials, labor, or overhead costs
سؤال
With a Cost Plus Fixed Fee (CPFF)

A) the customer assumes the risk of cost overruns
B) the price to the customer remains the same
C) the contractor is assured of being reimbursed for all allowable expenses
D) contractor risks underestimating the cost and losing money on the project
E) cutting-corners to reduce costs is a potential risk
سؤال
With a Cost Plus Incentive Fee (CPIF)

A) the customer can pay a lower price if the contractor can reduce costs
B) the incentive is to come at or below the target cost
C) the contractor can earn a larger profit by reducing costs
D) is not really a cost-reimbursable contract
E) the price is periodically adjusted to allow for changes in materials, labor, or overhead costs
سؤال
Statement: Procurement management refers to the management of items produced or work done internally.
سؤال
Statement: Portions of or even entire work packages might fall under "procurement management."
سؤال
Statement: Procurement management involves selection of the right suppliers, vendors, and contractors.
سؤال
Statement: Major areas of work that must be procured will be identified in the WBS.
سؤال
Statement: The schedule for procured items can be created independently of the project schedule.
سؤال
Statement: Procurement management follows a process similar to the project klife cycle: plan, conduct, control, and close out
سؤال
Statement: The "make or buy" decision can pertain to virtually everything to be done in the project
سؤال
Statement: The "conduct procurement" stage is also referred to as the solicitation or conduct-procurement process
سؤال
Statement: Usually, obligations in subcontracts exist solely between the customer and subcontractors.
سؤال
Statement: With a Cost Plus Incentive Fee (CPIF) the incentive is on meeting a target due date
سؤال
Statement: A Guaranteed Maximum Price (GMP) contract is like a Cost-Plus Fixed Fee contract with a cap on the price.
فتح الحزمة
قم بالتسجيل لفتح البطاقات في هذه المجموعة!
Unlock Deck
Unlock Deck
1/36
auto play flashcards
العب
simple tutorial
ملء الشاشة (f)
exit full mode
Deck 12: Project Procurement Management and Contracting
1
Items to be procured during the project are identified

A) as work gets underway during project execution
B) during the WBS process or earlier
C) mostly during the contract negotiation process
during the WBS process or earlier
2
The customer advertises for project price bids usually when

A) scope of the project is complex, requirements are ill-defined, and bidder qualifications are unknown
B) scope of the project is somewhat simple, requirements are well defined, and bidders are pre-qualified.
C) scope of the project is somewhat simple, requirements are well defined, and bidders are pre-qualified
D) the customer is most interested in learning different contractors' ideas about the project
E) the customer is interested in negotiating with contractor to settle on the best process
scope of the project is somewhat simple, requirements are well defined, and bidders are pre-qualified
3
Sole-sourcing means:

A) multiple qualified bidders will be invited to bid
B) among several qualified sources, just one will be invited to bid
C) one (and only one) bidder is qualified and available to do the work
one (and only one) bidder is qualified and available to do the work
4
Single-sourcing means

A) multiple qualified bidders will be invited to bid
B) among several qualified sources, just one will be invited to bid
C) one (and only one) bidder is qualified and available to do the work
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 36 في هذه المجموعة.
فتح الحزمة
k this deck
5
Multiple sourcing means

A) multiple qualified bidders will be invited to bid
B) among several qualified sources, just one will be invited to bid
C) one (and only one) bidder is qualified and available to do the work
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 36 في هذه المجموعة.
فتح الحزمة
k this deck
6
Ordinarily, the...

A) prime contractor freely selects its own subcontractors
B) customer chooses the subcontractors that will report to the prime contractor
C) customer selects and manages the subcontractors with the prime contractor's assistance
D) subcontractors to work under the prime contractor are specified in the RFP
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 36 في هذه المجموعة.
فتح الحزمة
k this deck
7
With a Time and Materials (T&M) contract

A) the customer pays a contracted fixed price that is estimated before the rpoject based on labor time and material
B) the contractor is reimbursed for direct labor hours at a specified per-person hourly rate plus material costs and a mark-up
C) the time represents the duration of the project (start to finish) and the materials are whatever was needed to produce the estimate
D) the contractor has an incentive to perform the work in the shortest time and with the fewest materials
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 36 في هذه المجموعة.
فتح الحزمة
k this deck
8
Which of the following contracts is most risky to the customer?

A) cost plus fixed fee
B) guaranteed maximum price
C) time & materials
D) firm fixed price
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 36 في هذه المجموعة.
فتح الحزمة
k this deck
9
Which of the following contracts is most risky to the contractor?

A) cost plus fixed fee
B) guaranteed maximum price
C) time & materials
D) firm fixed price
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 36 في هذه المجموعة.
فتح الحزمة
k this deck
10
In which of the following kinds of contracts is the actual, final cost of the project unknown until after the project is completed (circle all that apply):

A) cost plus fixed fee
B) fixed price
C) cost plus incentive fee
D) none of these
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 36 في هذه المجموعة.
فتح الحزمة
k this deck
11
The purpose of contract negotiation is to (circle all that apply):

A) clarify technical terms of the contract
B) reach agreement on time, cost, and performance requirements
C) convince the user that the project has been completed
D) reach a contract agreement to the best advantage of the parties involved
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 36 في هذه المجموعة.
فتح الحزمة
k this deck
12
Procurement management refers to management of (circle all that apply)

A) "bought" or "purchased" items for the project
B) design work or services provided by contractors
C) items that are produced internally
D) all off-the-shelf items, whether obtained internally of externally
E) "turnkey" items or systems
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 36 في هذه المجموعة.
فتح الحزمة
k this deck
13
Procurement management can involve which if the following (circle all that apply)

A) definition of work, materials, or services in the WBS or similar process
B) scheduling
C) budgeting
D) RFP/proposal/contracting process
E) logistical planning
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 36 في هذه المجموعة.
فتح الحزمة
k this deck
14
Procurement management addresses everything associated with (circle all that apply)

A) procuring
B) purchasing and contracting
C) contracted work
D) project scheduling and budgeting
E) working with "hired help"
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 36 في هذه المجموعة.
فتح الحزمة
k this deck
15
Procurement can include (circle all that apply)

A) acquisition of a complex system
B) purchasing parts and components
C) selecting a supplier of parts and components
D) acquiring the services of a design firm
E) monitoring the work of internal project staff
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 36 في هذه المجموعة.
فتح الحزمة
k this deck
16
"Procured items" include which of the following (circle all that apply)

A) products
B) materials
C) equipment
D) work
E) services
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 36 في هذه المجموعة.
فتح الحزمة
k this deck
17
A "solicitation package" includes (circle all that apply)

A) solicitation documents (RFP, RFQ, RFT, etc.)
B) list of qualified bidders
C) final signed contracts
D) proposal evaluation process and criteria
E) project close-out procedures
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 36 في هذه المجموعة.
فتح الحزمة
k this deck
18
The proposal/negotiation/solicitation method is more appropriate for

A) work that requires design, development, and/or research
B) scope of the project is somewhat simple, requirements are well defined, and bidders are pre-qualified
C) large and somewhat undefined systems
D) artistic work or other work that requires intellectual input
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 36 في هذه المجموعة.
فتح الحزمة
k this deck
19
During the negotiation process, the project manager

A) must be intimately familiar with the technical details of the proposed system's design and related costs
B) must try to learn about any competitor bidders
C) must be familiar with those parts of the project plan (schedule, work, or price) that are relatively "fixed" and those that can be negotiated
D) try to know as much as possible about the customer's needs and current position
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 36 في هذه المجموعة.
فتح الحزمة
k this deck
20
The role of contract administration is

A) authorizing work to begin
B) monitoring work
C) insuring compliance to contractors' responsibilities
D) managing waivers and changes
E) ensuring that the customer is invoiced for deliverables
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 36 في هذه المجموعة.
فتح الحزمة
k this deck
21
Contract administration is responsible for

A) determining which work should be done in-house and which should be outsourced
B) determining whether project end-items meet requirements as specified in the contract
C) determining whether all, some, or none of the deliverables should be accepted
D) precuring RFPs in the initial solicitation process
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 36 في هذه المجموعة.
فتح الحزمة
k this deck
22
With a Firm Fixed Price Contract (FFP)

A) the customer assumes the risk of cost overruns
B) the price to the customer remains the same
C) the contractor is assured of being reimbursed for all allowable expenses
D) contractor risks underestimating the cost and losing money on the project
E) cutting-corners to reduce costs is a potential risk
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 36 في هذه المجموعة.
فتح الحزمة
k this deck
23
In a Fixed Price Incentive Fee Contract (FPIF)

A) the customer can pay a lower price if the contractor can reduce costs
B) the incentive can be determined by the cost sharing ratio
C) the contractor can earn a larger profit by reducing costs
D) is not really a fixed-price contract
E) the price is periodically adjusted to allow for changes in materials, labor, or overhead costs
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 36 في هذه المجموعة.
فتح الحزمة
k this deck
24
With a Cost Plus Fixed Fee (CPFF)

A) the customer assumes the risk of cost overruns
B) the price to the customer remains the same
C) the contractor is assured of being reimbursed for all allowable expenses
D) contractor risks underestimating the cost and losing money on the project
E) cutting-corners to reduce costs is a potential risk
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 36 في هذه المجموعة.
فتح الحزمة
k this deck
25
With a Cost Plus Incentive Fee (CPIF)

A) the customer can pay a lower price if the contractor can reduce costs
B) the incentive is to come at or below the target cost
C) the contractor can earn a larger profit by reducing costs
D) is not really a cost-reimbursable contract
E) the price is periodically adjusted to allow for changes in materials, labor, or overhead costs
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 36 في هذه المجموعة.
فتح الحزمة
k this deck
26
Statement: Procurement management refers to the management of items produced or work done internally.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 36 في هذه المجموعة.
فتح الحزمة
k this deck
27
Statement: Portions of or even entire work packages might fall under "procurement management."
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 36 في هذه المجموعة.
فتح الحزمة
k this deck
28
Statement: Procurement management involves selection of the right suppliers, vendors, and contractors.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 36 في هذه المجموعة.
فتح الحزمة
k this deck
29
Statement: Major areas of work that must be procured will be identified in the WBS.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 36 في هذه المجموعة.
فتح الحزمة
k this deck
30
Statement: The schedule for procured items can be created independently of the project schedule.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 36 في هذه المجموعة.
فتح الحزمة
k this deck
31
Statement: Procurement management follows a process similar to the project klife cycle: plan, conduct, control, and close out
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 36 في هذه المجموعة.
فتح الحزمة
k this deck
32
Statement: The "make or buy" decision can pertain to virtually everything to be done in the project
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 36 في هذه المجموعة.
فتح الحزمة
k this deck
33
Statement: The "conduct procurement" stage is also referred to as the solicitation or conduct-procurement process
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 36 في هذه المجموعة.
فتح الحزمة
k this deck
34
Statement: Usually, obligations in subcontracts exist solely between the customer and subcontractors.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 36 في هذه المجموعة.
فتح الحزمة
k this deck
35
Statement: With a Cost Plus Incentive Fee (CPIF) the incentive is on meeting a target due date
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 36 في هذه المجموعة.
فتح الحزمة
k this deck
36
Statement: A Guaranteed Maximum Price (GMP) contract is like a Cost-Plus Fixed Fee contract with a cap on the price.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 36 في هذه المجموعة.
فتح الحزمة
k this deck
locked card icon
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 36 في هذه المجموعة.