Deck 5: Construction Tendering and Contract Management

ملء الشاشة (f)
exit full mode
سؤال
The notice inviting tender should published in minimum........ daily news paper

A)3
B)2
C)4
D)5
استخدم زر المسافة أو
up arrow
down arrow
لقلب البطاقة.
سؤال
Who will sign the contract deed on behalf of government

A)Chief engineer
B)Superintendent engineer
C)Executive engineer
D)Head clerk
سؤال
Who will draft contract agreement?

A)Chief engineer
B)Divisional head clerk
C)Executive engineer
D)None of the above
سؤال
Which are the criteria to be checked for pre- qualification of contractor

A)Financial strength
B)Past five year experience
C)Technical personnel engaged
D)All of the above
سؤال
How many envelops are required to submitted Tender form

A)3
B)1
C)4
D)2
سؤال
Total no of grades for registration of contractor with governments are

A)3
B)5
C)7
D)4
سؤال
Contract is terminated in case of

A)Slow progress and time limit exceeds
B)Work is not being executed as per specifications and instruction of EIC
C)Contractor tries to admit sub-contractor
D)All of the above
سؤال
Form no .........is used for material at site account

A)35
B)28
C)16
D)9
سؤال
Mobilization advance

A)Shall be 2 to 5 % of project cost.
B)Shall be 3 to 7 % of project cost.
C)Shall be 10 to 15 % of project cost.
D)Shall be 12 to 18 % of project cost.
سؤال
PERT analysis is based upon

A)Optimistic time
B)Pessimistic time
C)Most likely time
D)All of the above
سؤال
The time activity consumes in most adverse conditions is

A)Optimistic time
B)Pessimistic time
C)Most likely time
D)All of the above
سؤال
The time activity consumes in normal conditions is

A)Optimistic time
B)Pessimistic time
C)Most likely time
D)All of the above
سؤال
The difference between the total float and free float is called

A)Duration
B)Interfering float
C)Critical activity
D)None of the above
سؤال
The critical path is

A)The longest path of the network
B)The shortest path of the network
C)The average duration path of the network
D)None of the above
سؤال
The float of critical activity is always

A)Maximum
B)Minimum
C)Zero
D)None of the above
سؤال
A dummy activity in a network

A)Is represented by dotted line
B)Is an artificial activity
C)Does not consume time and resources
D)All of the above
سؤال
Activity starts from

A)Head event
B)Tail event
C)Dual role event
D)None of the above
سؤال
Which of the following is an activity

A)Excavation
B)Curing
C)Laying concrete
D)All of the above
سؤال
Earliest start time of activity equals to

A)TE of tail event of an activity
B)TE of head event of an activity
C)Average time of TE of tail event and head event
D)None of the above
سؤال
................is provided to safeguard scaffolding against overturning.

A)Standards
B)Inclined rackers
C)Put-logs
D)Rails
سؤال
Ladder leading to landing should be extended at least ....... meter above the landing

A)1.2
B)1.5
C)1
D)1.8
سؤال
While using ladder one should not lean sideways more than......... cms.

A)40
B)60
C)30
D)45
سؤال
Wooden ladders should be inspected at least........... a month.

A)Once
B)Twice
C)Three times
D)Four times
سؤال
In sheds for ceiling works, ......................... scaffolding is economical.

A)Suspended
B)Needle
C)Ordinary
D)None of the above
فتح الحزمة
قم بالتسجيل لفتح البطاقات في هذه المجموعة!
Unlock Deck
Unlock Deck
1/24
auto play flashcards
العب
simple tutorial
ملء الشاشة (f)
exit full mode
Deck 5: Construction Tendering and Contract Management
1
The notice inviting tender should published in minimum........ daily news paper

A)3
B)2
C)4
D)5
2
2
Who will sign the contract deed on behalf of government

A)Chief engineer
B)Superintendent engineer
C)Executive engineer
D)Head clerk
Executive engineer
3
Who will draft contract agreement?

A)Chief engineer
B)Divisional head clerk
C)Executive engineer
D)None of the above
Divisional head clerk
4
Which are the criteria to be checked for pre- qualification of contractor

A)Financial strength
B)Past five year experience
C)Technical personnel engaged
D)All of the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 24 في هذه المجموعة.
فتح الحزمة
k this deck
5
How many envelops are required to submitted Tender form

A)3
B)1
C)4
D)2
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 24 في هذه المجموعة.
فتح الحزمة
k this deck
6
Total no of grades for registration of contractor with governments are

A)3
B)5
C)7
D)4
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 24 في هذه المجموعة.
فتح الحزمة
k this deck
7
Contract is terminated in case of

A)Slow progress and time limit exceeds
B)Work is not being executed as per specifications and instruction of EIC
C)Contractor tries to admit sub-contractor
D)All of the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 24 في هذه المجموعة.
فتح الحزمة
k this deck
8
Form no .........is used for material at site account

A)35
B)28
C)16
D)9
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 24 في هذه المجموعة.
فتح الحزمة
k this deck
9
Mobilization advance

A)Shall be 2 to 5 % of project cost.
B)Shall be 3 to 7 % of project cost.
C)Shall be 10 to 15 % of project cost.
D)Shall be 12 to 18 % of project cost.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 24 في هذه المجموعة.
فتح الحزمة
k this deck
10
PERT analysis is based upon

A)Optimistic time
B)Pessimistic time
C)Most likely time
D)All of the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 24 في هذه المجموعة.
فتح الحزمة
k this deck
11
The time activity consumes in most adverse conditions is

A)Optimistic time
B)Pessimistic time
C)Most likely time
D)All of the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 24 في هذه المجموعة.
فتح الحزمة
k this deck
12
The time activity consumes in normal conditions is

A)Optimistic time
B)Pessimistic time
C)Most likely time
D)All of the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 24 في هذه المجموعة.
فتح الحزمة
k this deck
13
The difference between the total float and free float is called

A)Duration
B)Interfering float
C)Critical activity
D)None of the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 24 في هذه المجموعة.
فتح الحزمة
k this deck
14
The critical path is

A)The longest path of the network
B)The shortest path of the network
C)The average duration path of the network
D)None of the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 24 في هذه المجموعة.
فتح الحزمة
k this deck
15
The float of critical activity is always

A)Maximum
B)Minimum
C)Zero
D)None of the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 24 في هذه المجموعة.
فتح الحزمة
k this deck
16
A dummy activity in a network

A)Is represented by dotted line
B)Is an artificial activity
C)Does not consume time and resources
D)All of the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 24 في هذه المجموعة.
فتح الحزمة
k this deck
17
Activity starts from

A)Head event
B)Tail event
C)Dual role event
D)None of the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 24 في هذه المجموعة.
فتح الحزمة
k this deck
18
Which of the following is an activity

A)Excavation
B)Curing
C)Laying concrete
D)All of the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 24 في هذه المجموعة.
فتح الحزمة
k this deck
19
Earliest start time of activity equals to

A)TE of tail event of an activity
B)TE of head event of an activity
C)Average time of TE of tail event and head event
D)None of the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 24 في هذه المجموعة.
فتح الحزمة
k this deck
20
................is provided to safeguard scaffolding against overturning.

A)Standards
B)Inclined rackers
C)Put-logs
D)Rails
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 24 في هذه المجموعة.
فتح الحزمة
k this deck
21
Ladder leading to landing should be extended at least ....... meter above the landing

A)1.2
B)1.5
C)1
D)1.8
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 24 في هذه المجموعة.
فتح الحزمة
k this deck
22
While using ladder one should not lean sideways more than......... cms.

A)40
B)60
C)30
D)45
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 24 في هذه المجموعة.
فتح الحزمة
k this deck
23
Wooden ladders should be inspected at least........... a month.

A)Once
B)Twice
C)Three times
D)Four times
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 24 في هذه المجموعة.
فتح الحزمة
k this deck
24
In sheds for ceiling works, ......................... scaffolding is economical.

A)Suspended
B)Needle
C)Ordinary
D)None of the above