Deck 3: Measurement and Estimation in Construction

ملء الشاشة (f)
exit full mode
سؤال
The measurement is made for stone work in square metre in case of

A)wall facing
B)columns, lintels, copings
C)building work
D)(a) and (d) of the above
استخدم زر المسافة أو
up arrow
down arrow
لقلب البطاقة.
سؤال
Carpet area does not include the area of

A)the walls along with doors and other openings
B)bath room and lavatory
C)kitchen and pantry
D)all the above
سؤال
The correct Prismoidal formula for volume is

A)d [first area + last area + even area + 2 odd areas]
B)d/3 [first area + last area + 4 even area + 2 odd areas]
C)d/3 [first area + last area + 2 even area + 4 odd areas]
D)d/6 [first area + odd areas]
سؤال
In case of laying gullies, siphons, intercepting traps, the cost includes

A)setting and laying
B)bed concreting
C)connection to drains
D)all of these
سؤال
The inspection pit or chamber is a manhole provided in a base drainage system

A)at every change of direction
B)at every change of gradient
C)at every 30 m intervals
D)all the above
سؤال
Pick up the incorrect statement from the following:

A)dimensions are measured to the nearest 0.01 m
B)areas are measured to the nearest 0.01 sq.m
C)cubic contents are measured to the nearest 0.1 cum
D)weights are measured to the nearest 0.001 tonnes
سؤال
The 'centre line method' is specially adopted for estimating

A)circular buildings
B)hexagonal buildings
C)octagonal buildings
D)all the above
سؤال
Pick up the incorrect statement from the following:

A)the built up covered area at the floor level of any storey of a building is called plinth area
B)the usable covered area of the rooms of any storey of a building is called carpet area
C)the carpet area of a building along with area of its kitchen, pantry, store, lavatory, bath room and glazed veranda, is called floor area
D)none of these
سؤال
The unit of measurement is per quintal for the following:

A)collapsible gates with rails
B)rolling shutters
C)expanded metal wire netting
D)m.s. reinforcement of r.c.c. works
سؤال
The diameter of a domestic sewer pipe laid at gradient 1 in 100 is recommended

A)100 mm
B)150 mm
C)200 mm
D)175 mm
سؤال
The order of booking dimensions is

A)length, breadth, height
B)breadth, length, height
C)height, breadth, length
D)none of these
سؤال
Pick up the incorrect statement regarding a master trap from the following:

A)it is provided in between the lower end of the house drain and the street sewer
B)it is provided a cleaning eye at the top of the trap
C)the mica flap valve which opens inwards only, is fitted at the top of the inlet pipe
D)the water seal is less than that of ordinary traps
سؤال
The detention period in a septic tank is assumed

A)20 minutes
B)25 minutes
C)30 minutes
D)40 minutes
سؤال
Pick up the item of work not included in the plinth area estimate

A)wall thickness
B)room area
C)w.c. area
D)courtyard area
سؤال
The minimum width of a septic tank is taken

A)70 cm
B)75 cm
C)80 cm
D)90 cm
سؤال
Pick up the item whose weight is added to the weight of respective item, is

A)cleats
B)brackets
C)bolts
D)all the above
سؤال
The expected out turn for earth work in excavation in ordinary soil per workman per day is

A)1.00 cum
B)2.00 cum
C)3.00 cum
D)4.00 cum
سؤال
The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is

A)1.00 m3
B)1.25 m3
C)1.50 m3
D)1.75 m3
سؤال
The brick work is measured in sq metre, in case of

A)honey comb brick work
B)brick flat soling
C)half brick walls or the partition
D)all the above
سؤال
The height of the sink of wash basin above floor level is kept

A)60 cm
B)70 cm
C)75 cm to 80 cm
D)80 cm
سؤال
For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is

A)0.200 m3
B)0.247 m3
C)0.274 m3
D)0.295 m3
سؤال
The item of steel work which is measured in sq.m, is

A)collapsible gates
B)rolling shutters
C)ventilators and glazing
D)all the above
سؤال
The damp proof course (D.P.C.) is measured in

A)cub. m
B)sq. m
C)metres
D)none of these
فتح الحزمة
قم بالتسجيل لفتح البطاقات في هذه المجموعة!
Unlock Deck
Unlock Deck
1/23
auto play flashcards
العب
simple tutorial
ملء الشاشة (f)
exit full mode
Deck 3: Measurement and Estimation in Construction
1
The measurement is made for stone work in square metre in case of

A)wall facing
B)columns, lintels, copings
C)building work
D)(a) and (d) of the above
(a) and (d) of the above
2
Carpet area does not include the area of

A)the walls along with doors and other openings
B)bath room and lavatory
C)kitchen and pantry
D)all the above
all the above
3
The correct Prismoidal formula for volume is

A)d [first area + last area + even area + 2 odd areas]
B)d/3 [first area + last area + 4 even area + 2 odd areas]
C)d/3 [first area + last area + 2 even area + 4 odd areas]
D)d/6 [first area + odd areas]
d/3 [first area + last area + 4 even area + 2 odd areas]
4
In case of laying gullies, siphons, intercepting traps, the cost includes

A)setting and laying
B)bed concreting
C)connection to drains
D)all of these
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 23 في هذه المجموعة.
فتح الحزمة
k this deck
5
The inspection pit or chamber is a manhole provided in a base drainage system

A)at every change of direction
B)at every change of gradient
C)at every 30 m intervals
D)all the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 23 في هذه المجموعة.
فتح الحزمة
k this deck
6
Pick up the incorrect statement from the following:

A)dimensions are measured to the nearest 0.01 m
B)areas are measured to the nearest 0.01 sq.m
C)cubic contents are measured to the nearest 0.1 cum
D)weights are measured to the nearest 0.001 tonnes
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 23 في هذه المجموعة.
فتح الحزمة
k this deck
7
The 'centre line method' is specially adopted for estimating

A)circular buildings
B)hexagonal buildings
C)octagonal buildings
D)all the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 23 في هذه المجموعة.
فتح الحزمة
k this deck
8
Pick up the incorrect statement from the following:

A)the built up covered area at the floor level of any storey of a building is called plinth area
B)the usable covered area of the rooms of any storey of a building is called carpet area
C)the carpet area of a building along with area of its kitchen, pantry, store, lavatory, bath room and glazed veranda, is called floor area
D)none of these
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 23 في هذه المجموعة.
فتح الحزمة
k this deck
9
The unit of measurement is per quintal for the following:

A)collapsible gates with rails
B)rolling shutters
C)expanded metal wire netting
D)m.s. reinforcement of r.c.c. works
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 23 في هذه المجموعة.
فتح الحزمة
k this deck
10
The diameter of a domestic sewer pipe laid at gradient 1 in 100 is recommended

A)100 mm
B)150 mm
C)200 mm
D)175 mm
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 23 في هذه المجموعة.
فتح الحزمة
k this deck
11
The order of booking dimensions is

A)length, breadth, height
B)breadth, length, height
C)height, breadth, length
D)none of these
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 23 في هذه المجموعة.
فتح الحزمة
k this deck
12
Pick up the incorrect statement regarding a master trap from the following:

A)it is provided in between the lower end of the house drain and the street sewer
B)it is provided a cleaning eye at the top of the trap
C)the mica flap valve which opens inwards only, is fitted at the top of the inlet pipe
D)the water seal is less than that of ordinary traps
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 23 في هذه المجموعة.
فتح الحزمة
k this deck
13
The detention period in a septic tank is assumed

A)20 minutes
B)25 minutes
C)30 minutes
D)40 minutes
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 23 في هذه المجموعة.
فتح الحزمة
k this deck
14
Pick up the item of work not included in the plinth area estimate

A)wall thickness
B)room area
C)w.c. area
D)courtyard area
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 23 في هذه المجموعة.
فتح الحزمة
k this deck
15
The minimum width of a septic tank is taken

A)70 cm
B)75 cm
C)80 cm
D)90 cm
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 23 في هذه المجموعة.
فتح الحزمة
k this deck
16
Pick up the item whose weight is added to the weight of respective item, is

A)cleats
B)brackets
C)bolts
D)all the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 23 في هذه المجموعة.
فتح الحزمة
k this deck
17
The expected out turn for earth work in excavation in ordinary soil per workman per day is

A)1.00 cum
B)2.00 cum
C)3.00 cum
D)4.00 cum
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 23 في هذه المجموعة.
فتح الحزمة
k this deck
18
The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is

A)1.00 m3
B)1.25 m3
C)1.50 m3
D)1.75 m3
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 23 في هذه المجموعة.
فتح الحزمة
k this deck
19
The brick work is measured in sq metre, in case of

A)honey comb brick work
B)brick flat soling
C)half brick walls or the partition
D)all the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 23 في هذه المجموعة.
فتح الحزمة
k this deck
20
The height of the sink of wash basin above floor level is kept

A)60 cm
B)70 cm
C)75 cm to 80 cm
D)80 cm
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 23 في هذه المجموعة.
فتح الحزمة
k this deck
21
For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is

A)0.200 m3
B)0.247 m3
C)0.274 m3
D)0.295 m3
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 23 في هذه المجموعة.
فتح الحزمة
k this deck
22
The item of steel work which is measured in sq.m, is

A)collapsible gates
B)rolling shutters
C)ventilators and glazing
D)all the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 23 في هذه المجموعة.
فتح الحزمة
k this deck
23
The damp proof course (D.P.C.) is measured in

A)cub. m
B)sq. m
C)metres
D)none of these
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 23 في هذه المجموعة.
فتح الحزمة
k this deck
locked card icon
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 23 في هذه المجموعة.