Deck 1: Measurement Methods for Construction Work
سؤال
سؤال
سؤال
سؤال
سؤال
سؤال
سؤال
سؤال
سؤال
سؤال
سؤال
سؤال
سؤال
سؤال
سؤال
سؤال
سؤال
فتح الحزمة
قم بالتسجيل لفتح البطاقات في هذه المجموعة!
Unlock Deck
Unlock Deck
1/17
العب
ملء الشاشة (f)
Deck 1: Measurement Methods for Construction Work
1
Brick walls are measured in sq. m if the thickness of the wall is
A)10 cm
B)15 cm
C)20 cm
D)30 cm
A)10 cm
B)15 cm
C)20 cm
D)30 cm
10 cm
2
The brick work is not measured in cu m in case of
A)one or more than one brick wall
B)brick work in arches
C)reinforced brick work
D)half brick wall
A)one or more than one brick wall
B)brick work in arches
C)reinforced brick work
D)half brick wall
half brick wall
3
The following item of earth work is not measured separately.
A)brick work
B)site clearance
C)plastering work
D)concrete work
A)brick work
B)site clearance
C)plastering work
D)concrete work
site clearance
4
The measurement is not made in square meters in case of
A)d.p.c. (damp proof course)
B)form works
C)concrete jeffries
D)r.c. chhajja
A)d.p.c. (damp proof course)
B)form works
C)concrete jeffries
D)r.c. chhajja
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 17 في هذه المجموعة.
فتح الحزمة
k this deck
5
Pick up the incorrect statement from the following:
A)dimensions are measured to the nearest 0.01 m
B)areas are measured to the nearest 0.01 sq.m
C)cubic contents are measured to the nearest 0.1 cum
D)weights are measured to the nearest 0.001 tonnes
A)dimensions are measured to the nearest 0.01 m
B)areas are measured to the nearest 0.01 sq.m
C)cubic contents are measured to the nearest 0.1 cum
D)weights are measured to the nearest 0.001 tonnes
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 17 في هذه المجموعة.
فتح الحزمة
k this deck
6
The item of steel work which is measured in sq.m, is
A)collapsible gates
B)cement work
C)brick work
D)steel work
A)collapsible gates
B)cement work
C)brick work
D)steel work
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 17 في هذه المجموعة.
فتح الحزمة
k this deck
7
The damp proof course (D.P.C.) is measured in
A)cub. m
B)sq. m
C)meters
D)rmt
A)cub. m
B)sq. m
C)meters
D)rmt
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 17 في هذه المجموعة.
فتح الحزمة
k this deck
8
For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is
A)0.90 m3
B)0.94 m3
C)0.98 m3
D)1.00 m3
A)0.90 m3
B)0.94 m3
C)0.98 m3
D)1.00 m3
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 17 في هذه المجموعة.
فتح الحزمة
k this deck
9
According to ISI method of measurement, the order of the sequence is
A)length, breadth, height
B)breadth, length, height
C)height, length, breadth
D)breath, length, height
A)length, breadth, height
B)breadth, length, height
C)height, length, breadth
D)breath, length, height
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 17 في هذه المجموعة.
فتح الحزمة
k this deck
10
Carpet area does not include the area of
A)hall area
B)bath room and lavatory
C)bed room area
D)plot area
A)hall area
B)bath room and lavatory
C)bed room area
D)plot area
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 17 في هذه المجموعة.
فتح الحزمة
k this deck
11
The item of the brick structure measured in sq.m, is
A)reinforced brick work
B)broken glass coping
C)brick edging
D)brick work in arches
A)reinforced brick work
B)broken glass coping
C)brick edging
D)brick work in arches
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 17 في هذه المجموعة.
فتح الحزمة
k this deck
12
The 'centre line method' is specially adopted for estimating
A)bridge buildings
B)rectangular buildings
C)steel buildings
D)earthen building
A)bridge buildings
B)rectangular buildings
C)steel buildings
D)earthen building
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 17 في هذه المجموعة.
فتح الحزمة
k this deck
13
The order of Taking dimensions is
A)length, breadth, height
B)breadth, length, height.
C)height, breadth, length
D)breadth, length, height
A)length, breadth, height
B)breadth, length, height.
C)height, breadth, length
D)breadth, length, height
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 17 في هذه المجموعة.
فتح الحزمة
k this deck
14
Pick up the item of work not included in the plinth area estimate
A)wall thickness
B)room area
C)w.c. area
D)courtyard area
A)wall thickness
B)room area
C)w.c. area
D)courtyard area
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 17 في هذه المجموعة.
فتح الحزمة
k this deck
15
If the formation level of a highway has a uniform gradient for a particular length, and the ground is also having a longitudinal slope, the earthwork may be calculated by
A)mid-section formula
B)center line methods
C)long wall short wall methods
D)rate analysis methods
A)mid-section formula
B)center line methods
C)long wall short wall methods
D)rate analysis methods
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 17 في هذه المجموعة.
فتح الحزمة
k this deck
16
In the mid-section formula
A)the mean depth is the average of depths of two consecutive sections
B)the area mean
C)same as prizmoidal formula
D)same as trapezoidal formula
A)the mean depth is the average of depths of two consecutive sections
B)the area mean
C)same as prizmoidal formula
D)same as trapezoidal formula
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 17 في هذه المجموعة.
فتح الحزمة
k this deck
17
The correct Prismoidal formula for volume is
A)d [first area + last area + ? even area + 2 ? odd areas]
B)d/3 [first area + last area + 4 ? even area + 2 ? odd areas]
C)d/3 [first area + last area + 2 ? even area + 4 ? odd areas]
D)d/6 [first area + last area + 2 ? even area + 4 ? odd areas]
A)d [first area + last area + ? even area + 2 ? odd areas]
B)d/3 [first area + last area + 4 ? even area + 2 ? odd areas]
C)d/3 [first area + last area + 2 ? even area + 4 ? odd areas]
D)d/6 [first area + last area + 2 ? even area + 4 ? odd areas]
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 17 في هذه المجموعة.
فتح الحزمة
k this deck