Deck 7: Managing Systems Development

ملء الشاشة (f)
exit full mode
سؤال
The project management activity "corrective action" involves:

A) analysis of the work breakdown
B) allocating resources to tasks
C) assessing progress on tasks and actioning changes
D) placing tasks in order
E) the project closedown review
استخدم زر المسافة أو
up arrow
down arrow
لقلب البطاقة.
سؤال
Which of the following is NOT a primary objective of a project?

A) Quality
B) Time
C) Cost
D) Structure
E) None of the above
سؤال
Which of the following is most appropriate for monitoring progress against plan?

A) Network diagram
B) Capacity loading graphs
C) Gantt chart
D) Flow diagram
E) None of the above
سؤال
Which is a typical sequence of activities at the start of a systems implementation project?

A) Initiation, Design, Analysis
B) Analysis, Initiation, Design
C) Design, Initiation, Analysis
D) Analysis, Design, Initiation
E) None of the above
سؤال
Which is a typical sequence of activities at the end of a systems implementation project?

A) Implementation, Development, Maintenance
B) Development, Maintenance, Implementation
C) Implementation, Maintenance, Development
D) Development, Implementation, Maintenance
E) None of the above
سؤال
What are the typical stages in risk management?

A) Identify risks, Identify probabilities and impacts, identify and implement solutions
B) Identify probabilities and impacts, identify and implement solutions, identify risks
C) Identify probabilities and impacts, identify risks, identify and implement solutions
D) Identify risks, identify and implement solutions, Identify probabilities and impacts
E) None of the above
سؤال
Which of the following systems development activities would you not expect to undertake in a standard off the shelf package is being purchased?

A) Data conversion
B) Program writing
C) Detailed analysis of user requirements
D) Constructing a list of desirable features
E) Conducting a feasibility study
سؤال
In the Waterfall model, what normally happens when one of the steps cannot be completed because of errors or oversights?

A) The personnel involved are replaced by better or more experienced staff
B) The previous step is revisited and corrections made
C) The project continues as planned and errors are fixed at the end
D) The development is abandoned completely
E) None of the above
سؤال
Rapid Applications development has been adopted as a solution to some of the difficulties associated with the traditional approach to systems development because:

A) the traditional approach is often perceived as a 'quick and dirty' method of system development
B) typical long development times associated with traditional development
C) RAD increases the probability of users getting the system they want
D) it is a proven methodology
E) none of the above
سؤال
When in-house IS/IT expertise is high and the degree of uniqueness of the business process to be supported is high, the most appropriate method of acquiring applications software is:

A) purchase of a standard off the shelf package
B) having a system integrator tailor a standard package to the needs of the business
C) development of software by a software house
D) development of bespoke software by the in-house team
E) none of the above
فتح الحزمة
قم بالتسجيل لفتح البطاقات في هذه المجموعة!
Unlock Deck
Unlock Deck
1/10
auto play flashcards
العب
simple tutorial
ملء الشاشة (f)
exit full mode
Deck 7: Managing Systems Development
1
The project management activity "corrective action" involves:

A) analysis of the work breakdown
B) allocating resources to tasks
C) assessing progress on tasks and actioning changes
D) placing tasks in order
E) the project closedown review
assessing progress on tasks and actioning changes
2
Which of the following is NOT a primary objective of a project?

A) Quality
B) Time
C) Cost
D) Structure
E) None of the above
Structure
3
Which of the following is most appropriate for monitoring progress against plan?

A) Network diagram
B) Capacity loading graphs
C) Gantt chart
D) Flow diagram
E) None of the above
Gantt chart
4
Which is a typical sequence of activities at the start of a systems implementation project?

A) Initiation, Design, Analysis
B) Analysis, Initiation, Design
C) Design, Initiation, Analysis
D) Analysis, Design, Initiation
E) None of the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 10 في هذه المجموعة.
فتح الحزمة
k this deck
5
Which is a typical sequence of activities at the end of a systems implementation project?

A) Implementation, Development, Maintenance
B) Development, Maintenance, Implementation
C) Implementation, Maintenance, Development
D) Development, Implementation, Maintenance
E) None of the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 10 في هذه المجموعة.
فتح الحزمة
k this deck
6
What are the typical stages in risk management?

A) Identify risks, Identify probabilities and impacts, identify and implement solutions
B) Identify probabilities and impacts, identify and implement solutions, identify risks
C) Identify probabilities and impacts, identify risks, identify and implement solutions
D) Identify risks, identify and implement solutions, Identify probabilities and impacts
E) None of the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 10 في هذه المجموعة.
فتح الحزمة
k this deck
7
Which of the following systems development activities would you not expect to undertake in a standard off the shelf package is being purchased?

A) Data conversion
B) Program writing
C) Detailed analysis of user requirements
D) Constructing a list of desirable features
E) Conducting a feasibility study
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 10 في هذه المجموعة.
فتح الحزمة
k this deck
8
In the Waterfall model, what normally happens when one of the steps cannot be completed because of errors or oversights?

A) The personnel involved are replaced by better or more experienced staff
B) The previous step is revisited and corrections made
C) The project continues as planned and errors are fixed at the end
D) The development is abandoned completely
E) None of the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 10 في هذه المجموعة.
فتح الحزمة
k this deck
9
Rapid Applications development has been adopted as a solution to some of the difficulties associated with the traditional approach to systems development because:

A) the traditional approach is often perceived as a 'quick and dirty' method of system development
B) typical long development times associated with traditional development
C) RAD increases the probability of users getting the system they want
D) it is a proven methodology
E) none of the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 10 في هذه المجموعة.
فتح الحزمة
k this deck
10
When in-house IS/IT expertise is high and the degree of uniqueness of the business process to be supported is high, the most appropriate method of acquiring applications software is:

A) purchase of a standard off the shelf package
B) having a system integrator tailor a standard package to the needs of the business
C) development of software by a software house
D) development of bespoke software by the in-house team
E) none of the above