Deck 12: Managing Projects

ملء الشاشة (f)
exit full mode
سؤال
Ivy Inc. has planned a simple project having four tasks. The task information for the project is shown:
<strong>Ivy Inc. has planned a simple project having four tasks. The task information for the project is shown:    -Based on the information, what are the days to completion?</strong> A)29 days B)25 days C)22 days D)19 days E)Need more information to answer the question <div style=padding-top: 35px>

-Based on the information, what are the days to completion?

A)29 days
B)25 days
C)22 days
D)19 days
E)Need more information to answer the question
استخدم زر المسافة أو
up arrow
down arrow
لقلب البطاقة.
سؤال
Ivy Inc. has planned a simple project having four tasks. The task information for the project is shown:
<strong>Ivy Inc. has planned a simple project having four tasks. The task information for the project is shown:    -Based on the information, which of the following statements is true?</strong> A)None of the paths in the project is a critical path. B)Path BOD is the critical path for the project. C)Path BLD is the critical path for the project. D)Path BOLD is a valid path for the project. E)Tasks B, O, L, and D lie in the critical path for the project. <div style=padding-top: 35px>

-Based on the information, which of the following statements is true?

A)None of the paths in the project is a critical path.
B)Path BOD is the critical path for the project.
C)Path BLD is the critical path for the project.
D)Path BOLD is a valid path for the project.
E)Tasks B, O, L, and D lie in the critical path for the project.
سؤال
Ivy Inc. has planned a simple project having four tasks. The task information for the project is shown:
<strong>Ivy Inc. has planned a simple project having four tasks. The task information for the project is shown:    -Based on the information, which of the following statements is true?</strong> A)None of the tasks have slack. B)Task O has 3 days of slack. C)Task L has 4 days of slack. D)Task D has 2 days of slack. E)Task L has 3 days of slack. <div style=padding-top: 35px>

-Based on the information, which of the following statements is true?

A)None of the tasks have slack.
B)Task O has 3 days of slack.
C)Task L has 4 days of slack.
D)Task D has 2 days of slack.
E)Task L has 3 days of slack.
سؤال
Poisson Corporation has the following six tasks and the associated times for those tasks to complete a project.
<strong>Poisson Corporation has the following six tasks and the associated times for those tasks to complete a project.    -Based on the information, what are the days to completion?</strong> A)37 days B)21 weeks C)24 weeks D)19 weeks E)28 weeks <div style=padding-top: 35px>

-Based on the information, what are the days to completion?

A)37 days
B)21 weeks
C)24 weeks
D)19 weeks
E)28 weeks
سؤال
Poisson Corporation has the following six tasks and the associated times for those tasks to complete a project.
<strong>Poisson Corporation has the following six tasks and the associated times for those tasks to complete a project.    -Calculate the late start (LS) time for Task F.</strong> A)2 weeks B)5 weeks C)6 weeks D)9 weeks E)12 weeks <div style=padding-top: 35px>

-Calculate the late start (LS) time for Task F.

A)2 weeks
B)5 weeks
C)6 weeks
D)9 weeks
E)12 weeks
سؤال
Poisson Corporation has the following six tasks and the associated times for those tasks to complete a project.
<strong>Poisson Corporation has the following six tasks and the associated times for those tasks to complete a project.    -Calculate the early finish (EF) time for Task T.</strong> A)6 weeks B)17 weeks C)12 weeks D)23 weeks E)18 weeks <div style=padding-top: 35px>

-Calculate the early finish (EF) time for Task T.

A)6 weeks
B)17 weeks
C)12 weeks
D)23 weeks
E)18 weeks
سؤال
Poisson Corporation has the following six tasks and the associated times for those tasks to complete a project.
<strong>Poisson Corporation has the following six tasks and the associated times for those tasks to complete a project.    -Which task has non-zero slack?</strong> A)S B)O C)E D)F E)N <div style=padding-top: 35px>

-Which task has non-zero slack?

A)S
B)O
C)E
D)F
E)N
سؤال
Poisson Corporation has the following six tasks and the associated times for those tasks to complete a project.
<strong>Poisson Corporation has the following six tasks and the associated times for those tasks to complete a project.    -Which task has the greatest amount of slack?</strong> A)O B)F C)T D)E E)N <div style=padding-top: 35px>

-Which task has the greatest amount of slack?

A)O
B)F
C)T
D)E
E)N
سؤال
Poisson Corporation has the following six tasks and the associated times for those tasks to complete a project.
<strong>Poisson Corporation has the following six tasks and the associated times for those tasks to complete a project.    -Which of the following identifies the critical path tasks?</strong> A)S, O, E, N B)S, O, T, N C)S, O, F, T, E, N D)S, F, E, N E)All the tasks are critical path tasks <div style=padding-top: 35px>

-Which of the following identifies the critical path tasks?

A)S, O, E, N
B)S, O, T, N
C)S, O, F, T, E, N
D)S, F, E, N
E)All the tasks are critical path tasks
سؤال
Poisson Corporation has the following six tasks and the associated times for those tasks to complete a project.
<strong>Poisson Corporation has the following six tasks and the associated times for those tasks to complete a project.    -Calculate the late finish (LF) time for Task N.</strong> A)18 weeks B)17 weeks C)12 weeks D)23 weeks E)24 weeks <div style=padding-top: 35px>

-Calculate the late finish (LF) time for Task N.

A)18 weeks
B)17 weeks
C)12 weeks
D)23 weeks
E)24 weeks
سؤال
The table below shows the tasks required to complete a project and the expected duration and predecessor for each task. Which of the following tasks has a non-zero slack? <strong>The table below shows the tasks required to complete a project and the expected duration and predecessor for each task. Which of the following tasks has a non-zero slack?  </strong> A)A B)B C)D D)F E)C <div style=padding-top: 35px>

A)A
B)B
C)D
D)F
E)C
سؤال
The table below shows the tasks required to complete a project and the expected duration and predecessor for each task. Calculate the late finish (LF) time for Task E. <strong>The table below shows the tasks required to complete a project and the expected duration and predecessor for each task. Calculate the late finish (LF) time for Task E.  </strong> A)20 weeks B)21 weeks C)19 weeks D)10 weeks E)9 weeks <div style=padding-top: 35px>

A)20 weeks
B)21 weeks
C)19 weeks
D)10 weeks
E)9 weeks
سؤال
What is the latest that Task B can start if A takes 35 days, B takes 5 days, C takes 6 days, and D takes 7 days? <strong>What is the latest that Task B can start if A takes 35 days, B takes 5 days, C takes 6 days, and D takes 7 days?  </strong> A)35 B)36 C)40 D)41 E)Cannot determine from the information given <div style=padding-top: 35px>

A)35
B)36
C)40
D)41
E)Cannot determine from the information given
سؤال
This Gantt chart can be used to show the following: <strong>This Gantt chart can be used to show the following:  </strong> A)Task C must come before Task D. B)Task F can be done at the same time as D. C)Task E can begin as soon as Task A is complete. D)Tasks D and B can be done simultaneously. E)Cannot determine from the information given <div style=padding-top: 35px>

A)Task C must come before Task D.
B)Task F can be done at the same time as D.
C)Task E can begin as soon as Task A is complete.
D)Tasks D and B can be done simultaneously.
E)Cannot determine from the information given
سؤال
The table provides a project with the task lengths (in days) and precedence requirements.
<strong>The table provides a project with the task lengths (in days) and precedence requirements.    -Based on the information, what are the days to completion?</strong> A)33 days B)30 days C)25 days D)18 days E)Need more information to answer the question <div style=padding-top: 35px>

-Based on the information, what are the days to completion?

A)33 days
B)30 days
C)25 days
D)18 days
E)Need more information to answer the question
سؤال
The table provides a project with the task lengths (in days) and precedence requirements.
<strong>The table provides a project with the task lengths (in days) and precedence requirements.    -Based on the information, which of the following statements is true?</strong> A)None of the paths in the project is a critical path. B)Path ACD is the critical path for the project. C)Path ABD is the critical path for the project. D)Path ABCD is a valid path for the project. E)Tasks A, B, C, and D lie in the critical path for the project. <div style=padding-top: 35px>

-Based on the information, which of the following statements is true?

A)None of the paths in the project is a critical path.
B)Path ACD is the critical path for the project.
C)Path ABD is the critical path for the project.
D)Path ABCD is a valid path for the project.
E)Tasks A, B, C, and D lie in the critical path for the project.
سؤال
The table provides a project with the task lengths (in days) and precedence requirements.
<strong>The table provides a project with the task lengths (in days) and precedence requirements.    -Calculate the late start (LS) time for Task C.</strong> A)23 days B)15 days C)30 days D)18 days E)20 days <div style=padding-top: 35px>

-Calculate the late start (LS) time for Task C.

A)23 days
B)15 days
C)30 days
D)18 days
E)20 days
سؤال
A project is composed of 6 tasks that have durations and precedence requirements shown in the table. How long should we expect it to take to complete this project? <strong>A project is composed of 6 tasks that have durations and precedence requirements shown in the table. How long should we expect it to take to complete this project?  </strong> A)25 B)21 C)29 D)19 E)36 <div style=padding-top: 35px>

A)25
B)21
C)29
D)19
E)36
سؤال
A project is composed of 6 tasks that have durations and precedence requirements shown in the table. Which of these tasks is not on the critical path? <strong>A project is composed of 6 tasks that have durations and precedence requirements shown in the table. Which of these tasks is not on the critical path?  </strong> A)A B)B C)C D)D E)F <div style=padding-top: 35px>

A)A
B)B
C)C
D)D
E)F
سؤال
A project is composed of 6 tasks that have durations and precedence requirements shown in the table. The late finish (LF) time for Task C is _______. <strong>A project is composed of 6 tasks that have durations and precedence requirements shown in the table. The late finish (LF) time for Task C is _______.  </strong> A)5 B)8 C)9 D)12 E)19 <div style=padding-top: 35px>

A)5
B)8
C)9
D)12
E)19
سؤال
Following are the three estimates for a project:
<strong>Following are the three estimates for a project:    -Calculate the expected completion time for Task B.</strong> A)9.96 B)7.03 C)4.00 D)8.07 E)25.06 <div style=padding-top: 35px>

-Calculate the expected completion time for Task B.

A)9.96
B)7.03
C)4.00
D)8.07
E)25.06
سؤال
Following are the three estimates for a project:
<strong>Following are the three estimates for a project:    -Calculate the expected completion time for Task O.</strong> A)9.96 B)7.03 C)4.00 D)8.07 E)25.06 <div style=padding-top: 35px>

-Calculate the expected completion time for Task O.

A)9.96
B)7.03
C)4.00
D)8.07
E)25.06
سؤال
Following are the three estimates for a project:
<strong>Following are the three estimates for a project:    -Calculate the expected completion time for Task D.</strong> A)9.96 B)7.03 C)4.00 D)8.07 E)25.06 <div style=padding-top: 35px>

-Calculate the expected completion time for Task D.

A)9.96
B)7.03
C)4.00
D)8.07
E)25.06
سؤال
Following are the three estimates for a project:
<strong>Following are the three estimates for a project:    -Calculate the completion time variance for Task A.</strong> A)0.274 B)0.004 C)0.134 D)0.085 E)0.054 <div style=padding-top: 35px>

-Calculate the completion time variance for Task A.

A)0.274
B)0.004
C)0.134
D)0.085
E)0.054
سؤال
Following are the three estimates for a project:
<strong>Following are the three estimates for a project:    -Calculate the completion time variance for Task C.</strong> A)0.274 B)0.004 C)0.134 D)0.085 E)0.054 <div style=padding-top: 35px>

-Calculate the completion time variance for Task C.

A)0.274
B)0.004
C)0.134
D)0.085
E)0.054
سؤال
Following are the three estimates for a project:
<strong>Following are the three estimates for a project:    -Calculate the completion time variance for Task D.</strong> A)0.274 B)0.004 C)0.134 D)0.085 E)0.054 <div style=padding-top: 35px>

-Calculate the completion time variance for Task D.

A)0.274
B)0.004
C)0.134
D)0.085
E)0.054
سؤال
Following are the three estimates for a project:
<strong>Following are the three estimates for a project:    -Considering tasks B, O, and D are the critical path tasks, what is the expected completion time for the project?</strong> A)9.96 B)7.03 C)4.00 D)8.07 E)25.06 <div style=padding-top: 35px>

-Considering tasks B, O, and D are the critical path tasks, what is the expected completion time for the project?

A)9.96
B)7.03
C)4.00
D)8.07
E)25.06
سؤال
The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates.
<strong>The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates.    -Based on the information, what are the days to completion?</strong> A)21 days B)22 days C)26 days D)32 days E)Need more information to answer the question <div style=padding-top: 35px>

-Based on the information, what are the days to completion?

A)21 days
B)22 days
C)26 days
D)32 days
E)Need more information to answer the question
سؤال
The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates.
<strong>The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates.    -Based on the information, which of the following statements is true?</strong> A)None of the paths in the project is a critical path. B)Path ABEF is the critical path for the project. C)Path ABDF is the critical path for the project. D)Path ACDF is the critical path for the project. E)Tasks A, B, C, D, and F lie in the critical path for the project. <div style=padding-top: 35px>

-Based on the information, which of the following statements is true?

A)None of the paths in the project is a critical path.
B)Path ABEF is the critical path for the project.
C)Path ABDF is the critical path for the project.
D)Path ACDF is the critical path for the project.
E)Tasks A, B, C, D, and F lie in the critical path for the project.
سؤال
The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates.
<strong>The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates.    -Calculate expected completion time for Task D.</strong> A)3.08 B)7.03 C)3.00 D)1.97 E)6.93 <div style=padding-top: 35px>

-Calculate expected completion time for Task D.

A)3.08
B)7.03
C)3.00
D)1.97
E)6.93
سؤال
The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates.
<strong>The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates.    -Calculate completion time variance for Task B.</strong> A)0.054 B)0.174 C)0.399 D)0.117 E)0.340 <div style=padding-top: 35px>

-Calculate completion time variance for Task B.

A)0.054
B)0.174
C)0.399
D)0.117
E)0.340
سؤال
The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates.
<strong>The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates.    -What are the expected days to completion?</strong> A)20.98 B)25.93 C)22.09 D)31.98 E)26.00 <div style=padding-top: 35px>

-What are the expected days to completion?

A)20.98
B)25.93
C)22.09
D)31.98
E)26.00
سؤال
The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates.
<strong>The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates.    -Calculate the variance of the project's expected completion time.</strong> A)0.054 B)0.174 C)0.399 D)0.117 E)0.340 <div style=padding-top: 35px>

-Calculate the variance of the project's expected completion time.

A)0.054
B)0.174
C)0.399
D)0.117
E)0.340
سؤال
The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates.
<strong>The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates.    -Calculate the standard deviation of the project's expected completion time.</strong> A)0.583 B)0.417 C)0.342 D)0.632 E)0.232 <div style=padding-top: 35px>

-Calculate the standard deviation of the project's expected completion time.

A)0.583
B)0.417
C)0.342
D)0.632
E)0.232
سؤال
The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates.
<strong>The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates.    -What should be the desired completion days, if one needed a 99% confidence level?</strong> A)27.39 B)27.24 C)27.16 D)25.93 E)26.96 <div style=padding-top: 35px>

-What should be the desired completion days, if one needed a 99% confidence level?

A)27.39
B)27.24
C)27.16
D)25.93
E)26.96
سؤال
The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates.
<strong>The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates.    -Which non-critical task should be monitored closely because of high completion time variance?</strong> A)C B)F C)A D)D E)B <div style=padding-top: 35px>

-Which non-critical task should be monitored closely because of high completion time variance?

A)C
B)F
C)A
D)D
E)B
سؤال
The table provides a project with the task lengths (in days) and precedence requirements, as well as the associated task costs, crashed time, and crash costs.
<strong>The table provides a project with the task lengths (in days) and precedence requirements, as well as the associated task costs, crashed time, and crash costs.    -What is the crash costs for Task A?</strong> A)$1,500 B)$1,350 C)$750 D)$800 E)$600 <div style=padding-top: 35px>

-What is the crash costs for Task A?

A)$1,500
B)$1,350
C)$750
D)$800
E)$600
سؤال
The table provides a project with the task lengths (in days) and precedence requirements, as well as the associated task costs, crashed time, and crash costs.
<strong>The table provides a project with the task lengths (in days) and precedence requirements, as well as the associated task costs, crashed time, and crash costs.    -Which statement out of the following is NOT correct?</strong> A)The crash cost per day for Task A is greater than the crash cost per day for Task C. B)The crash cost per day for Task E is 200 dollars less than the crash cost per day for Task D. C)The crash cost per day for Task B is $750. D)The crash cost per day for Task C is more than the crash cost per day for Task F. E)The total normal cost of the project is $3,650. <div style=padding-top: 35px>

-Which statement out of the following is NOT correct?

A)The crash cost per day for Task A is greater than the crash cost per day for Task C.
B)The crash cost per day for Task E is 200 dollars less than the crash cost per day for Task D.
C)The crash cost per day for Task B is $750.
D)The crash cost per day for Task C is more than the crash cost per day for Task F.
E)The total normal cost of the project is $3,650.
سؤال
The table provides a project with the task lengths (in days) and precedence requirements, as well as the associated task costs, crashed time, and crash costs.
<strong>The table provides a project with the task lengths (in days) and precedence requirements, as well as the associated task costs, crashed time, and crash costs.    -It is desired to reduce the project completion time by 1 day. Based on the crash costs per day values, which task should be crashed first?</strong> A)A B)C C)F D)D E)E <div style=padding-top: 35px>

-It is desired to reduce the project completion time by 1 day. Based on the crash costs per day values, which task should be crashed first?

A)A
B)C
C)F
D)D
E)E
سؤال
The table provides a project with the task lengths (in days) and precedence requirements, as well as the associated task costs, crashed time, and crash costs.
<strong>The table provides a project with the task lengths (in days) and precedence requirements, as well as the associated task costs, crashed time, and crash costs.    -Task F is crashed for 1 day at a cost of $50 per day. Calculate the new project cost.</strong> A)$600 B)$3,600 C)$2,750 D)$400 E)$3,450 <div style=padding-top: 35px>

-Task F is crashed for 1 day at a cost of $50 per day. Calculate the new project cost.

A)$600
B)$3,600
C)$2,750
D)$400
E)$3,450
سؤال
A procurement specialist wished to assess the risks associated with finalizing a new tier-one supplier in another country. She estimated the risks as (where 1 = low concern, 10 = extreme concern), and the owner decided to weigh the risks equally. Which type of risk has the highest level of risk? <strong>A procurement specialist wished to assess the risks associated with finalizing a new tier-one supplier in another country. She estimated the risks as (where 1 = low concern, 10 = extreme concern), and the owner decided to weigh the risks equally. Which type of risk has the highest level of risk?  </strong> A)Political issues B)Environmental issues C)Labor issues D)Regulations E)Social responsibility <div style=padding-top: 35px>

A)Political issues
B)Environmental issues
C)Labor issues
D)Regulations
E)Social responsibility
سؤال
A procurement specialist wished to assess the risks associated with finalizing a new tier-one supplier in another country. She estimated the risks as (where 1 = low concern, 10 = extreme concern), and the owner decided to weigh the risks equally. Which type of risk has the lowest level of risk? <strong>A procurement specialist wished to assess the risks associated with finalizing a new tier-one supplier in another country. She estimated the risks as (where 1 = low concern, 10 = extreme concern), and the owner decided to weigh the risks equally. Which type of risk has the lowest level of risk?  </strong> A)Political issues B)Environmental issues C)Labor issues D)Regulations E)Social responsibility <div style=padding-top: 35px>

A)Political issues
B)Environmental issues
C)Labor issues
D)Regulations
E)Social responsibility
فتح الحزمة
قم بالتسجيل لفتح البطاقات في هذه المجموعة!
Unlock Deck
Unlock Deck
1/42
auto play flashcards
العب
simple tutorial
ملء الشاشة (f)
exit full mode
Deck 12: Managing Projects
1
Ivy Inc. has planned a simple project having four tasks. The task information for the project is shown:
<strong>Ivy Inc. has planned a simple project having four tasks. The task information for the project is shown:    -Based on the information, what are the days to completion?</strong> A)29 days B)25 days C)22 days D)19 days E)Need more information to answer the question

-Based on the information, what are the days to completion?

A)29 days
B)25 days
C)22 days
D)19 days
E)Need more information to answer the question
25 days
2
Ivy Inc. has planned a simple project having four tasks. The task information for the project is shown:
<strong>Ivy Inc. has planned a simple project having four tasks. The task information for the project is shown:    -Based on the information, which of the following statements is true?</strong> A)None of the paths in the project is a critical path. B)Path BOD is the critical path for the project. C)Path BLD is the critical path for the project. D)Path BOLD is a valid path for the project. E)Tasks B, O, L, and D lie in the critical path for the project.

-Based on the information, which of the following statements is true?

A)None of the paths in the project is a critical path.
B)Path BOD is the critical path for the project.
C)Path BLD is the critical path for the project.
D)Path BOLD is a valid path for the project.
E)Tasks B, O, L, and D lie in the critical path for the project.
Path BOD is the critical path for the project.
3
Ivy Inc. has planned a simple project having four tasks. The task information for the project is shown:
<strong>Ivy Inc. has planned a simple project having four tasks. The task information for the project is shown:    -Based on the information, which of the following statements is true?</strong> A)None of the tasks have slack. B)Task O has 3 days of slack. C)Task L has 4 days of slack. D)Task D has 2 days of slack. E)Task L has 3 days of slack.

-Based on the information, which of the following statements is true?

A)None of the tasks have slack.
B)Task O has 3 days of slack.
C)Task L has 4 days of slack.
D)Task D has 2 days of slack.
E)Task L has 3 days of slack.
Task L has 3 days of slack.
4
Poisson Corporation has the following six tasks and the associated times for those tasks to complete a project.
<strong>Poisson Corporation has the following six tasks and the associated times for those tasks to complete a project.    -Based on the information, what are the days to completion?</strong> A)37 days B)21 weeks C)24 weeks D)19 weeks E)28 weeks

-Based on the information, what are the days to completion?

A)37 days
B)21 weeks
C)24 weeks
D)19 weeks
E)28 weeks
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 42 في هذه المجموعة.
فتح الحزمة
k this deck
5
Poisson Corporation has the following six tasks and the associated times for those tasks to complete a project.
<strong>Poisson Corporation has the following six tasks and the associated times for those tasks to complete a project.    -Calculate the late start (LS) time for Task F.</strong> A)2 weeks B)5 weeks C)6 weeks D)9 weeks E)12 weeks

-Calculate the late start (LS) time for Task F.

A)2 weeks
B)5 weeks
C)6 weeks
D)9 weeks
E)12 weeks
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 42 في هذه المجموعة.
فتح الحزمة
k this deck
6
Poisson Corporation has the following six tasks and the associated times for those tasks to complete a project.
<strong>Poisson Corporation has the following six tasks and the associated times for those tasks to complete a project.    -Calculate the early finish (EF) time for Task T.</strong> A)6 weeks B)17 weeks C)12 weeks D)23 weeks E)18 weeks

-Calculate the early finish (EF) time for Task T.

A)6 weeks
B)17 weeks
C)12 weeks
D)23 weeks
E)18 weeks
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 42 في هذه المجموعة.
فتح الحزمة
k this deck
7
Poisson Corporation has the following six tasks and the associated times for those tasks to complete a project.
<strong>Poisson Corporation has the following six tasks and the associated times for those tasks to complete a project.    -Which task has non-zero slack?</strong> A)S B)O C)E D)F E)N

-Which task has non-zero slack?

A)S
B)O
C)E
D)F
E)N
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 42 في هذه المجموعة.
فتح الحزمة
k this deck
8
Poisson Corporation has the following six tasks and the associated times for those tasks to complete a project.
<strong>Poisson Corporation has the following six tasks and the associated times for those tasks to complete a project.    -Which task has the greatest amount of slack?</strong> A)O B)F C)T D)E E)N

-Which task has the greatest amount of slack?

A)O
B)F
C)T
D)E
E)N
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 42 في هذه المجموعة.
فتح الحزمة
k this deck
9
Poisson Corporation has the following six tasks and the associated times for those tasks to complete a project.
<strong>Poisson Corporation has the following six tasks and the associated times for those tasks to complete a project.    -Which of the following identifies the critical path tasks?</strong> A)S, O, E, N B)S, O, T, N C)S, O, F, T, E, N D)S, F, E, N E)All the tasks are critical path tasks

-Which of the following identifies the critical path tasks?

A)S, O, E, N
B)S, O, T, N
C)S, O, F, T, E, N
D)S, F, E, N
E)All the tasks are critical path tasks
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 42 في هذه المجموعة.
فتح الحزمة
k this deck
10
Poisson Corporation has the following six tasks and the associated times for those tasks to complete a project.
<strong>Poisson Corporation has the following six tasks and the associated times for those tasks to complete a project.    -Calculate the late finish (LF) time for Task N.</strong> A)18 weeks B)17 weeks C)12 weeks D)23 weeks E)24 weeks

-Calculate the late finish (LF) time for Task N.

A)18 weeks
B)17 weeks
C)12 weeks
D)23 weeks
E)24 weeks
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 42 في هذه المجموعة.
فتح الحزمة
k this deck
11
The table below shows the tasks required to complete a project and the expected duration and predecessor for each task. Which of the following tasks has a non-zero slack? <strong>The table below shows the tasks required to complete a project and the expected duration and predecessor for each task. Which of the following tasks has a non-zero slack?  </strong> A)A B)B C)D D)F E)C

A)A
B)B
C)D
D)F
E)C
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 42 في هذه المجموعة.
فتح الحزمة
k this deck
12
The table below shows the tasks required to complete a project and the expected duration and predecessor for each task. Calculate the late finish (LF) time for Task E. <strong>The table below shows the tasks required to complete a project and the expected duration and predecessor for each task. Calculate the late finish (LF) time for Task E.  </strong> A)20 weeks B)21 weeks C)19 weeks D)10 weeks E)9 weeks

A)20 weeks
B)21 weeks
C)19 weeks
D)10 weeks
E)9 weeks
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 42 في هذه المجموعة.
فتح الحزمة
k this deck
13
What is the latest that Task B can start if A takes 35 days, B takes 5 days, C takes 6 days, and D takes 7 days? <strong>What is the latest that Task B can start if A takes 35 days, B takes 5 days, C takes 6 days, and D takes 7 days?  </strong> A)35 B)36 C)40 D)41 E)Cannot determine from the information given

A)35
B)36
C)40
D)41
E)Cannot determine from the information given
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 42 في هذه المجموعة.
فتح الحزمة
k this deck
14
This Gantt chart can be used to show the following: <strong>This Gantt chart can be used to show the following:  </strong> A)Task C must come before Task D. B)Task F can be done at the same time as D. C)Task E can begin as soon as Task A is complete. D)Tasks D and B can be done simultaneously. E)Cannot determine from the information given

A)Task C must come before Task D.
B)Task F can be done at the same time as D.
C)Task E can begin as soon as Task A is complete.
D)Tasks D and B can be done simultaneously.
E)Cannot determine from the information given
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 42 في هذه المجموعة.
فتح الحزمة
k this deck
15
The table provides a project with the task lengths (in days) and precedence requirements.
<strong>The table provides a project with the task lengths (in days) and precedence requirements.    -Based on the information, what are the days to completion?</strong> A)33 days B)30 days C)25 days D)18 days E)Need more information to answer the question

-Based on the information, what are the days to completion?

A)33 days
B)30 days
C)25 days
D)18 days
E)Need more information to answer the question
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 42 في هذه المجموعة.
فتح الحزمة
k this deck
16
The table provides a project with the task lengths (in days) and precedence requirements.
<strong>The table provides a project with the task lengths (in days) and precedence requirements.    -Based on the information, which of the following statements is true?</strong> A)None of the paths in the project is a critical path. B)Path ACD is the critical path for the project. C)Path ABD is the critical path for the project. D)Path ABCD is a valid path for the project. E)Tasks A, B, C, and D lie in the critical path for the project.

-Based on the information, which of the following statements is true?

A)None of the paths in the project is a critical path.
B)Path ACD is the critical path for the project.
C)Path ABD is the critical path for the project.
D)Path ABCD is a valid path for the project.
E)Tasks A, B, C, and D lie in the critical path for the project.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 42 في هذه المجموعة.
فتح الحزمة
k this deck
17
The table provides a project with the task lengths (in days) and precedence requirements.
<strong>The table provides a project with the task lengths (in days) and precedence requirements.    -Calculate the late start (LS) time for Task C.</strong> A)23 days B)15 days C)30 days D)18 days E)20 days

-Calculate the late start (LS) time for Task C.

A)23 days
B)15 days
C)30 days
D)18 days
E)20 days
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 42 في هذه المجموعة.
فتح الحزمة
k this deck
18
A project is composed of 6 tasks that have durations and precedence requirements shown in the table. How long should we expect it to take to complete this project? <strong>A project is composed of 6 tasks that have durations and precedence requirements shown in the table. How long should we expect it to take to complete this project?  </strong> A)25 B)21 C)29 D)19 E)36

A)25
B)21
C)29
D)19
E)36
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 42 في هذه المجموعة.
فتح الحزمة
k this deck
19
A project is composed of 6 tasks that have durations and precedence requirements shown in the table. Which of these tasks is not on the critical path? <strong>A project is composed of 6 tasks that have durations and precedence requirements shown in the table. Which of these tasks is not on the critical path?  </strong> A)A B)B C)C D)D E)F

A)A
B)B
C)C
D)D
E)F
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 42 في هذه المجموعة.
فتح الحزمة
k this deck
20
A project is composed of 6 tasks that have durations and precedence requirements shown in the table. The late finish (LF) time for Task C is _______. <strong>A project is composed of 6 tasks that have durations and precedence requirements shown in the table. The late finish (LF) time for Task C is _______.  </strong> A)5 B)8 C)9 D)12 E)19

A)5
B)8
C)9
D)12
E)19
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 42 في هذه المجموعة.
فتح الحزمة
k this deck
21
Following are the three estimates for a project:
<strong>Following are the three estimates for a project:    -Calculate the expected completion time for Task B.</strong> A)9.96 B)7.03 C)4.00 D)8.07 E)25.06

-Calculate the expected completion time for Task B.

A)9.96
B)7.03
C)4.00
D)8.07
E)25.06
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 42 في هذه المجموعة.
فتح الحزمة
k this deck
22
Following are the three estimates for a project:
<strong>Following are the three estimates for a project:    -Calculate the expected completion time for Task O.</strong> A)9.96 B)7.03 C)4.00 D)8.07 E)25.06

-Calculate the expected completion time for Task O.

A)9.96
B)7.03
C)4.00
D)8.07
E)25.06
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 42 في هذه المجموعة.
فتح الحزمة
k this deck
23
Following are the three estimates for a project:
<strong>Following are the three estimates for a project:    -Calculate the expected completion time for Task D.</strong> A)9.96 B)7.03 C)4.00 D)8.07 E)25.06

-Calculate the expected completion time for Task D.

A)9.96
B)7.03
C)4.00
D)8.07
E)25.06
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 42 في هذه المجموعة.
فتح الحزمة
k this deck
24
Following are the three estimates for a project:
<strong>Following are the three estimates for a project:    -Calculate the completion time variance for Task A.</strong> A)0.274 B)0.004 C)0.134 D)0.085 E)0.054

-Calculate the completion time variance for Task A.

A)0.274
B)0.004
C)0.134
D)0.085
E)0.054
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 42 في هذه المجموعة.
فتح الحزمة
k this deck
25
Following are the three estimates for a project:
<strong>Following are the three estimates for a project:    -Calculate the completion time variance for Task C.</strong> A)0.274 B)0.004 C)0.134 D)0.085 E)0.054

-Calculate the completion time variance for Task C.

A)0.274
B)0.004
C)0.134
D)0.085
E)0.054
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 42 في هذه المجموعة.
فتح الحزمة
k this deck
26
Following are the three estimates for a project:
<strong>Following are the three estimates for a project:    -Calculate the completion time variance for Task D.</strong> A)0.274 B)0.004 C)0.134 D)0.085 E)0.054

-Calculate the completion time variance for Task D.

A)0.274
B)0.004
C)0.134
D)0.085
E)0.054
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 42 في هذه المجموعة.
فتح الحزمة
k this deck
27
Following are the three estimates for a project:
<strong>Following are the three estimates for a project:    -Considering tasks B, O, and D are the critical path tasks, what is the expected completion time for the project?</strong> A)9.96 B)7.03 C)4.00 D)8.07 E)25.06

-Considering tasks B, O, and D are the critical path tasks, what is the expected completion time for the project?

A)9.96
B)7.03
C)4.00
D)8.07
E)25.06
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 42 في هذه المجموعة.
فتح الحزمة
k this deck
28
The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates.
<strong>The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates.    -Based on the information, what are the days to completion?</strong> A)21 days B)22 days C)26 days D)32 days E)Need more information to answer the question

-Based on the information, what are the days to completion?

A)21 days
B)22 days
C)26 days
D)32 days
E)Need more information to answer the question
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 42 في هذه المجموعة.
فتح الحزمة
k this deck
29
The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates.
<strong>The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates.    -Based on the information, which of the following statements is true?</strong> A)None of the paths in the project is a critical path. B)Path ABEF is the critical path for the project. C)Path ABDF is the critical path for the project. D)Path ACDF is the critical path for the project. E)Tasks A, B, C, D, and F lie in the critical path for the project.

-Based on the information, which of the following statements is true?

A)None of the paths in the project is a critical path.
B)Path ABEF is the critical path for the project.
C)Path ABDF is the critical path for the project.
D)Path ACDF is the critical path for the project.
E)Tasks A, B, C, D, and F lie in the critical path for the project.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 42 في هذه المجموعة.
فتح الحزمة
k this deck
30
The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates.
<strong>The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates.    -Calculate expected completion time for Task D.</strong> A)3.08 B)7.03 C)3.00 D)1.97 E)6.93

-Calculate expected completion time for Task D.

A)3.08
B)7.03
C)3.00
D)1.97
E)6.93
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 42 في هذه المجموعة.
فتح الحزمة
k this deck
31
The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates.
<strong>The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates.    -Calculate completion time variance for Task B.</strong> A)0.054 B)0.174 C)0.399 D)0.117 E)0.340

-Calculate completion time variance for Task B.

A)0.054
B)0.174
C)0.399
D)0.117
E)0.340
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 42 في هذه المجموعة.
فتح الحزمة
k this deck
32
The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates.
<strong>The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates.    -What are the expected days to completion?</strong> A)20.98 B)25.93 C)22.09 D)31.98 E)26.00

-What are the expected days to completion?

A)20.98
B)25.93
C)22.09
D)31.98
E)26.00
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 42 في هذه المجموعة.
فتح الحزمة
k this deck
33
The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates.
<strong>The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates.    -Calculate the variance of the project's expected completion time.</strong> A)0.054 B)0.174 C)0.399 D)0.117 E)0.340

-Calculate the variance of the project's expected completion time.

A)0.054
B)0.174
C)0.399
D)0.117
E)0.340
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 42 في هذه المجموعة.
فتح الحزمة
k this deck
34
The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates.
<strong>The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates.    -Calculate the standard deviation of the project's expected completion time.</strong> A)0.583 B)0.417 C)0.342 D)0.632 E)0.232

-Calculate the standard deviation of the project's expected completion time.

A)0.583
B)0.417
C)0.342
D)0.632
E)0.232
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 42 في هذه المجموعة.
فتح الحزمة
k this deck
35
The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates.
<strong>The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates.    -What should be the desired completion days, if one needed a 99% confidence level?</strong> A)27.39 B)27.24 C)27.16 D)25.93 E)26.96

-What should be the desired completion days, if one needed a 99% confidence level?

A)27.39
B)27.24
C)27.16
D)25.93
E)26.96
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 42 في هذه المجموعة.
فتح الحزمة
k this deck
36
The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates.
<strong>The table provides a project with the task lengths (in days) and precedence requirements, as well as the three time estimates.    -Which non-critical task should be monitored closely because of high completion time variance?</strong> A)C B)F C)A D)D E)B

-Which non-critical task should be monitored closely because of high completion time variance?

A)C
B)F
C)A
D)D
E)B
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 42 في هذه المجموعة.
فتح الحزمة
k this deck
37
The table provides a project with the task lengths (in days) and precedence requirements, as well as the associated task costs, crashed time, and crash costs.
<strong>The table provides a project with the task lengths (in days) and precedence requirements, as well as the associated task costs, crashed time, and crash costs.    -What is the crash costs for Task A?</strong> A)$1,500 B)$1,350 C)$750 D)$800 E)$600

-What is the crash costs for Task A?

A)$1,500
B)$1,350
C)$750
D)$800
E)$600
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 42 في هذه المجموعة.
فتح الحزمة
k this deck
38
The table provides a project with the task lengths (in days) and precedence requirements, as well as the associated task costs, crashed time, and crash costs.
<strong>The table provides a project with the task lengths (in days) and precedence requirements, as well as the associated task costs, crashed time, and crash costs.    -Which statement out of the following is NOT correct?</strong> A)The crash cost per day for Task A is greater than the crash cost per day for Task C. B)The crash cost per day for Task E is 200 dollars less than the crash cost per day for Task D. C)The crash cost per day for Task B is $750. D)The crash cost per day for Task C is more than the crash cost per day for Task F. E)The total normal cost of the project is $3,650.

-Which statement out of the following is NOT correct?

A)The crash cost per day for Task A is greater than the crash cost per day for Task C.
B)The crash cost per day for Task E is 200 dollars less than the crash cost per day for Task D.
C)The crash cost per day for Task B is $750.
D)The crash cost per day for Task C is more than the crash cost per day for Task F.
E)The total normal cost of the project is $3,650.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 42 في هذه المجموعة.
فتح الحزمة
k this deck
39
The table provides a project with the task lengths (in days) and precedence requirements, as well as the associated task costs, crashed time, and crash costs.
<strong>The table provides a project with the task lengths (in days) and precedence requirements, as well as the associated task costs, crashed time, and crash costs.    -It is desired to reduce the project completion time by 1 day. Based on the crash costs per day values, which task should be crashed first?</strong> A)A B)C C)F D)D E)E

-It is desired to reduce the project completion time by 1 day. Based on the crash costs per day values, which task should be crashed first?

A)A
B)C
C)F
D)D
E)E
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 42 في هذه المجموعة.
فتح الحزمة
k this deck
40
The table provides a project with the task lengths (in days) and precedence requirements, as well as the associated task costs, crashed time, and crash costs.
<strong>The table provides a project with the task lengths (in days) and precedence requirements, as well as the associated task costs, crashed time, and crash costs.    -Task F is crashed for 1 day at a cost of $50 per day. Calculate the new project cost.</strong> A)$600 B)$3,600 C)$2,750 D)$400 E)$3,450

-Task F is crashed for 1 day at a cost of $50 per day. Calculate the new project cost.

A)$600
B)$3,600
C)$2,750
D)$400
E)$3,450
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 42 في هذه المجموعة.
فتح الحزمة
k this deck
41
A procurement specialist wished to assess the risks associated with finalizing a new tier-one supplier in another country. She estimated the risks as (where 1 = low concern, 10 = extreme concern), and the owner decided to weigh the risks equally. Which type of risk has the highest level of risk? <strong>A procurement specialist wished to assess the risks associated with finalizing a new tier-one supplier in another country. She estimated the risks as (where 1 = low concern, 10 = extreme concern), and the owner decided to weigh the risks equally. Which type of risk has the highest level of risk?  </strong> A)Political issues B)Environmental issues C)Labor issues D)Regulations E)Social responsibility

A)Political issues
B)Environmental issues
C)Labor issues
D)Regulations
E)Social responsibility
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 42 في هذه المجموعة.
فتح الحزمة
k this deck
42
A procurement specialist wished to assess the risks associated with finalizing a new tier-one supplier in another country. She estimated the risks as (where 1 = low concern, 10 = extreme concern), and the owner decided to weigh the risks equally. Which type of risk has the lowest level of risk? <strong>A procurement specialist wished to assess the risks associated with finalizing a new tier-one supplier in another country. She estimated the risks as (where 1 = low concern, 10 = extreme concern), and the owner decided to weigh the risks equally. Which type of risk has the lowest level of risk?  </strong> A)Political issues B)Environmental issues C)Labor issues D)Regulations E)Social responsibility

A)Political issues
B)Environmental issues
C)Labor issues
D)Regulations
E)Social responsibility
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 42 في هذه المجموعة.
فتح الحزمة
k this deck
locked card icon
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 42 في هذه المجموعة.