Deck 6: Symmetrical Faults
1
In the circuit of Figure volts, , and . Determine (a) the rms symmetrical fault current; (b) the rms asymmetrical fault current at the instant the switch closes, assuming maximum dc offset; (c) the rms asymmetrical fault current 5 cycles after the switch closes, assuming maximum dc offset; (d) the dc offset as a function of time if the switch closes when the instantaneous source voltage is 244 volts.
(a)
(b)
(c) Using Eq. (7.1.11) and (7.1.12)
(d) Using Eq. (7.1.1)
Using Eq. (7.1.4)
(b)
(c) Using Eq. (7.1.11) and (7.1.12)
(d) Using Eq. (7.1.1)
Using Eq. (7.1.4)
2
Repeat Example 7.1 with , and .
(a)
(b)
(c)
(d)
(b)
(c)
(d)
3
A three-phase generator is connected through a Y transformer to a circuit breaker and a transmission line. The generator reactances are , and per unit, and its time constants are , and . The transformer series reactance is 0.10 per unit; transformer losses and exciting current are neglected. A three-phase short-circuit occurs on the line side of the circuit breaker when the generator is operated at rated terminal voltage and at no-load. The breaker interrupts the fault 3 cycles after fault inception. Determine (a) the subtransient current through the breaker in per-unit and in kA rms; and (b) the rms asymmetrical fault current the breaker interrupts, assuming maximum dc offset. Neglect the effect of the transformer on the time constants.
(a) Neglecting the transformer winding resistance,
The base current on the high-voltage side of the transformer is:
(b) Using Eq (7.2.1) at cycles with the transformer reactance included:
Using Eq (7.2.5),
The rms asymmetrical current that the breaker interrupts is
The base current on the high-voltage side of the transformer is:
(b) Using Eq (7.2.1) at cycles with the transformer reactance included:
Using Eq (7.2.5),
The rms asymmetrical current that the breaker interrupts is
4
For Test Bank Problem 7.3, determine (a) the instantaneous symmetrical fault current in kA in phase of the generator as a function of time, assuming maximum dc offset occurs in this generator phase; and (b) the maximum dc offset current in kA as a function of time that can occur in any one generator phase.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 5 في هذه المجموعة.
فتح الحزمة
k this deck
5
A three-phase transmission line has a continuous current rating and a maximum short-time overload rating, with a maximum operating voltage. Maximum symmetrical fault current on the line is . Select a circuit breaker for this line from Table 7.10.in the text