________ is a knowledge area that concerns contracts with outside vendors for services,materials,and outsourcing of functions.

A)Communications management
B)Quality management
C)Project integration
D)Procurement management
استخدم زر المسافة أو
up arrow
down arrow
لقلب البطاقة.
سؤال
The ________ is the sequence of activities that determine the earliest date by which the project can be completed.

A)Gantt chart
B)critical path
C)baseline
D)scope
سؤال
Systems development projects require the balancing of three critical drivers: requirements,cost,and ________.

A)scope
B)time
C)performance
D)value
سؤال
The purpose of risk management is to ensure that managers understand project risks and balance risk factors.
سؤال
Larger projects with longer development intervals will find it easier to keep to the baseline or plan.
سؤال
________ is the knowledge area that refers to the management of the overall project and the construction of the final product.

A)Project integration
B)Communications management
C)Procurement management
D)Quality management
سؤال
________ is a knowledge area that concerns the methods,media,and schedules for exchanging information with the project's sponsors,within the team itself,and with others having an interest in the progress of the project.

A)Procurement management
B)Communications management
C)Quality management
D)Project integration
سؤال
The development of large-scale systems can involve integrating products and services from different companies.
سؤال
Each task in a systems development project should culminate in one or more ________.

A)deliverables
B)zones
C)segments
D)designs
سؤال
Large-scale systems development projects require the balancing of three critical drivers: requirements,cost,and time.
سؤال
The PMBOK® Guide does not describe the details of each practice or technique but instead,identifies those practices that are known to be effective for different situations and briefly describes their use.
سؤال
With respect to WBS,________ means to define the system boundaries.

A)Gantt chart
B)critical path
C)scope
D)baseline
سؤال
Which of the following is a technique that stipulates phases and processes for constructing information systems,but does not address the management of large-scale projects?

A)SDLC
B)PMP
C)PMI
D)ANSI
سؤال
The term ________ refers to a set of management policies,practices,and tools that developers use to maintain control over the project's resources.

A)perceptual mapping
B)coordination control
C)critical path analysis
D)configuration control
سؤال
The biggest challenge in planning systems development is ________.

A)creating
B)scheduling
C)analyzing
D)testing
سؤال
In the PMBOK® Guide,________ refer to different stages in the life of a project.

A)configuration controls
B)knowledge areas
C)process groups
D)resource zones
سؤال
A ________ is a hierarchy of the tasks required to complete a project.

A)baseline
B)work-breakdown structure
C)reliable analysis
D)V-Model
سؤال
________ is the process by which users agree to one set of conditions,then add a bit more,then add a bit more,and so forth.

A)Requirements creep
B)Diseconomies of scale
C)Configuration control
D)Coordination
سؤال
The trade-off between time and cost is a simple process; the time involved in a project can always be reduced by increasing cost.
سؤال
A plan,known as the ________,of a project stipulates the tasks to be accomplished,the labor and other resources assigned to those tasks,and the schedule for completion.

A)baseline
B)data model
C)bottom line
D)database designs
سؤال
The biggest challenge in planning large-scale systems development is scheduling.Describe the three approaches organizations take to address this challenge.
سؤال
The term "configuration control" refers to a set of management policies,practices,and tools that developers use to maintain control over the project's resources.
سؤال
What are the biggest challenges for managing a large-scale systems development project?
سؤال
Requirements creep is the process by which a project manager reduces his/her responsibilities for requirements through miniscule rollbacks.
سؤال
Avoiding the major schedule risks and never developing software in-house is one of the approaches businesses take to address the challenges of scheduling for large-scale systems.
سؤال
Documents,designs,prototypes,data models,database designs,working data entry screens,and the like are examples of deliverables in a systems development project.
سؤال
What is a critical path? How is a critical path analysis done?
سؤال
The biggest challenge in planning systems development is scheduling.
سؤال
Regarding task dependencies,all tasks must begin and end at the same time.
سؤال
A loss of control over a project's configuration is easily fixed through remedial measures.
سؤال
Users must take responsibility for managing requirements changes and for avoiding requirements creep.
سؤال
A well-managed project will never face problems of diseconomies of scale.
سؤال
The critical path is a hierarchy of the tasks required to complete a project.
سؤال
What is the PMBOK ® Guide for project management? List the components of the grid in PMBOK ® Guide 2004.
سؤال
What are the characteristics of large-scale systems development projects?
سؤال
The baseline WBS can be used for monitoring the project.
سؤال
Taking responsibility for requirements is the single most important task a user can perform for a large-scale development project.
سؤال
Function points can be used to determine the number of lines of code,which can then be used to estimate project schedules.
فتح الحزمة
قم بالتسجيل لفتح البطاقات في هذه المجموعة!
Unlock Deck
Unlock Deck
1/38
auto play flashcards
العب
simple tutorial
ملء الشاشة (f)
exit full mode
Deck 27: Systems Development Project Management
1
________ is a knowledge area that concerns contracts with outside vendors for services,materials,and outsourcing of functions.

A)Communications management
B)Quality management
C)Project integration
D)Procurement management
D
2
The ________ is the sequence of activities that determine the earliest date by which the project can be completed.

A)Gantt chart
B)critical path
C)baseline
D)scope
B
3
Systems development projects require the balancing of three critical drivers: requirements,cost,and ________.

A)scope
B)time
C)performance
D)value
B
4
The purpose of risk management is to ensure that managers understand project risks and balance risk factors.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 38 في هذه المجموعة.
فتح الحزمة
k this deck
5
Larger projects with longer development intervals will find it easier to keep to the baseline or plan.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 38 في هذه المجموعة.
فتح الحزمة
k this deck
6
________ is the knowledge area that refers to the management of the overall project and the construction of the final product.

A)Project integration
B)Communications management
C)Procurement management
D)Quality management
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 38 في هذه المجموعة.
فتح الحزمة
k this deck
7
________ is a knowledge area that concerns the methods,media,and schedules for exchanging information with the project's sponsors,within the team itself,and with others having an interest in the progress of the project.

A)Procurement management
B)Communications management
C)Quality management
D)Project integration
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 38 في هذه المجموعة.
فتح الحزمة
k this deck
8
The development of large-scale systems can involve integrating products and services from different companies.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 38 في هذه المجموعة.
فتح الحزمة
k this deck
9
Each task in a systems development project should culminate in one or more ________.

A)deliverables
B)zones
C)segments
D)designs
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 38 في هذه المجموعة.
فتح الحزمة
k this deck
10
Large-scale systems development projects require the balancing of three critical drivers: requirements,cost,and time.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 38 في هذه المجموعة.
فتح الحزمة
k this deck
11
The PMBOK® Guide does not describe the details of each practice or technique but instead,identifies those practices that are known to be effective for different situations and briefly describes their use.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 38 في هذه المجموعة.
فتح الحزمة
k this deck
12
With respect to WBS,________ means to define the system boundaries.

A)Gantt chart
B)critical path
C)scope
D)baseline
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 38 في هذه المجموعة.
فتح الحزمة
k this deck
13
Which of the following is a technique that stipulates phases and processes for constructing information systems,but does not address the management of large-scale projects?

A)SDLC
B)PMP
C)PMI
D)ANSI
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 38 في هذه المجموعة.
فتح الحزمة
k this deck
14
The term ________ refers to a set of management policies,practices,and tools that developers use to maintain control over the project's resources.

A)perceptual mapping
B)coordination control
C)critical path analysis
D)configuration control
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 38 في هذه المجموعة.
فتح الحزمة
k this deck
15
The biggest challenge in planning systems development is ________.

A)creating
B)scheduling
C)analyzing
D)testing
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 38 في هذه المجموعة.
فتح الحزمة
k this deck
16
In the PMBOK® Guide,________ refer to different stages in the life of a project.

A)configuration controls
B)knowledge areas
C)process groups
D)resource zones
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 38 في هذه المجموعة.
فتح الحزمة
k this deck
17
A ________ is a hierarchy of the tasks required to complete a project.

A)baseline
B)work-breakdown structure
C)reliable analysis
D)V-Model
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 38 في هذه المجموعة.
فتح الحزمة
k this deck
18
________ is the process by which users agree to one set of conditions,then add a bit more,then add a bit more,and so forth.

A)Requirements creep
B)Diseconomies of scale
C)Configuration control
D)Coordination
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 38 في هذه المجموعة.
فتح الحزمة
k this deck
19
The trade-off between time and cost is a simple process; the time involved in a project can always be reduced by increasing cost.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 38 في هذه المجموعة.
فتح الحزمة
k this deck
20
A plan,known as the ________,of a project stipulates the tasks to be accomplished,the labor and other resources assigned to those tasks,and the schedule for completion.

A)baseline
B)data model
C)bottom line
D)database designs
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 38 في هذه المجموعة.
فتح الحزمة
k this deck
21
The biggest challenge in planning large-scale systems development is scheduling.Describe the three approaches organizations take to address this challenge.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 38 في هذه المجموعة.
فتح الحزمة
k this deck
22
The term "configuration control" refers to a set of management policies,practices,and tools that developers use to maintain control over the project's resources.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 38 في هذه المجموعة.
فتح الحزمة
k this deck
23
What are the biggest challenges for managing a large-scale systems development project?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 38 في هذه المجموعة.
فتح الحزمة
k this deck
24
Requirements creep is the process by which a project manager reduces his/her responsibilities for requirements through miniscule rollbacks.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 38 في هذه المجموعة.
فتح الحزمة
k this deck
25
Avoiding the major schedule risks and never developing software in-house is one of the approaches businesses take to address the challenges of scheduling for large-scale systems.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 38 في هذه المجموعة.
فتح الحزمة
k this deck
26
Documents,designs,prototypes,data models,database designs,working data entry screens,and the like are examples of deliverables in a systems development project.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 38 في هذه المجموعة.
فتح الحزمة
k this deck
27
What is a critical path? How is a critical path analysis done?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 38 في هذه المجموعة.
فتح الحزمة
k this deck
28
The biggest challenge in planning systems development is scheduling.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 38 في هذه المجموعة.
فتح الحزمة
k this deck
29
Regarding task dependencies,all tasks must begin and end at the same time.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 38 في هذه المجموعة.
فتح الحزمة
k this deck
30
A loss of control over a project's configuration is easily fixed through remedial measures.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 38 في هذه المجموعة.
فتح الحزمة
k this deck
31
Users must take responsibility for managing requirements changes and for avoiding requirements creep.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 38 في هذه المجموعة.
فتح الحزمة
k this deck
32
A well-managed project will never face problems of diseconomies of scale.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 38 في هذه المجموعة.
فتح الحزمة
k this deck
33
The critical path is a hierarchy of the tasks required to complete a project.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 38 في هذه المجموعة.
فتح الحزمة
k this deck
34
What is the PMBOK ® Guide for project management? List the components of the grid in PMBOK ® Guide 2004.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 38 في هذه المجموعة.
فتح الحزمة
k this deck
35
What are the characteristics of large-scale systems development projects?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 38 في هذه المجموعة.
فتح الحزمة
k this deck
36
The baseline WBS can be used for monitoring the project.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 38 في هذه المجموعة.
فتح الحزمة
k this deck
37
Taking responsibility for requirements is the single most important task a user can perform for a large-scale development project.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 38 في هذه المجموعة.
فتح الحزمة
k this deck
38
Function points can be used to determine the number of lines of code,which can then be used to estimate project schedules.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 38 في هذه المجموعة.
فتح الحزمة
k this deck
locked card icon
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 38 في هذه المجموعة.