Deck 6: Allocating Resources to the Project

ملء الشاشة (f)
exit full mode
سؤال
When crashing a task, the usual assumption is that a task is crashed the full amount or none at all.
استخدم زر المسافة أو
up arrow
down arrow
لقلب البطاقة.
سؤال
If resources were not scarce, the resource allocation problem would be concerned solely with profit maximization.
سؤال
If resources were not scarce, the resource allocation problem would be concerned solely with cost minimization.
سؤال
Projects often compete with each other for the same resources.
سؤال
All projects are carried out under conditions of uncertainty.
سؤال
Trade-offs must be made in order to optimize the use of limited resources.
سؤال
Often it is beneficial to crash activities not on the critical path.
سؤال
When the work is routine, fast-tracking rarely causes serious problems.
سؤال
The time to complete a task with normal or standard-practice resource usage is referred to as the crash duration.
سؤال
Good project managers are able to estimate project task times with absolute certainty.
سؤال
Resource loading refers to the amounts of specific resources that are scheduled for use on specific activities or projects at specific times.
سؤال
Fast-tracking a project is used primarily in the pharmaceutical industry.
سؤال
The CPM method cannot be used when task durations are probabilistic.
سؤال
All tasks can be crashed to some extent.
سؤال
The amount of resources a project can use depends in part on the timing of the allocation.
سؤال
Resource loading refers to the amounts of specific resources that are scheduled for use on specific activities or projects at specific times.
سؤال
The variance of the normal time can be quite different from the variance of the crash time.
سؤال
It is considered good management to crash the least costly activities before the more costly ones.
سؤال
A project that must be completed by a fixed time is referred to as resource constrained.
سؤال
For resources that are consumed when used, the problem is which project gets to use the resource first and which must wait.
سؤال
Pools of like workers are most useful when labor is subdivided into highly specialized subtasks.
سؤال
According to research minimum slack rule is the overall best priority rule.
سؤال
The task duration with standard-practice resource usage is referred to as the…

A) expected task duration
B) nominal task duration
C) crash duration
D) normal task duration
E) planned task duration
سؤال
The primary cause of concern in resource allocation is…

A) labor cost
B) resource scarcity
C) lack of solution methodologies
D) parallel activities
E) equipment downtime
سؤال
The process of line balancing is when individual production lines are made to generate the required amount of product with a little excess capacity as possible.
سؤال
Crashing non-critical activities will influence project duration.
سؤال
Microsoft Project allows the project manager to create an individual availability calendar for each resource on the project
سؤال
A limitation associated with traditional approaches to project management is that the dependency between resources and tasks is often ignored.
سؤال
One limitation of Microsoft Project is that all resources must share the same availability calendar.
سؤال
The as late as possible priority rule is considered the standard scheduling rule.
سؤال
Pools of like resources from which labor can be added temporarily to projects tend to increase costs for the firm as a whole.
سؤال
. The shortest duration task first rule minimizes the number of tasks that can be completed by s system in a given time period.
سؤال
A task has a normal duration of 9 days and a crash duration of 7 days. Its normal cost is $40 and its crash cost is $100. What is the crash cost per day?

A) $140
B) $70
C) $50
D) $40
E) $30
سؤال
A resource allocation decision may be intended to avoid a future problem rather than correct a current problem.
سؤال
Activities that have duration but do not require resources are referred to as pseudoactivities.
سؤال
A task's duration is a function of both the amount of labor required to complete the task as well as the calendar time required to complete it.
سؤال
Allocating specific, limited resources to specific activities is called…

A) resource allocation
B) resource leveling
C) resource tracking
D) expediting a project
E) crashing a project
سؤال
A project that must be completed by a specific time is considered…

A) time constrained
B) schedule constrained
C) resource constrained
D) performance constrained
E) critically constrained
سؤال
In general, steady state demand for human resources is highly desirable.
سؤال
Applying "line balancing" techniques to balance the capacity of a project typically yields significant benefits.
سؤال
All of the following are criteria available to help choose the priority rule mentioned in the textbook except;

A) Schedule slippage
B) Project cost
C) resource utilization
D) in-process inventory
سؤال
What is fast-tracking a project?
سؤال
The practice of assigning project team members to multiple projects is called…

A) concurrent engineering
B) parallel activities
C) fast-tracking
D) project crashing
E) multitasking
سؤال
Which of the following priority rules makes resources available so that activities start on their LSTs whenever possible without increasing the project's duration?

A) as soon as possible
B) as late as possible
C) shortest task duration first
D) minimum slack first
E) most critical successor
سؤال
Crashing refers to…

A) expediting the project so as to minimizing the total cost of completing the project.
B) expediting the project so as to minimizing the number of activities in the project
C) expediting the project so as to completing the project by a specified time.
D) all of the above
E) none of the above.
سؤال
A project that must be completed with in the specified performance requirements is considered…

A) time constrained
B) schedule constrained
C) resource constrained
D) performance constrained
E) critically constrained
سؤال
Which of the following is not commonly used to help select a priority rule?

A) schedule slippage
B) resource utilization
C) in-process inventory
D) cost overruns
E) all of the above are used
سؤال
The safety time added to chains other than the critical chain is called…

A) feeding buffer
B) project buffer
C) path buffer
D) critical buffer
E) team buffer
سؤال
What is the student syndrome? In what ways can it create problems for a project?
سؤال
Which of the following is a measure of the amount by which a project is delayed by application of a leveling rule?

A) schedule inflation
B) schedule progression
C) schedule efficacy
D) schedule efficiency
E) schedule slippage
سؤال
What is resource loading?
سؤال
Which of the following is not considered a resource?

A) Money
B) People
C) Equipment
D) Material
E) None of the above
سؤال
According to research, the best overall priority rule is…

A) as soon as possible
B) as late as possible
C) shortest task duration first
D) minimum slack first
E) most critical successor
سؤال
Explain how the commonly made assumption of known activity times can lead to unrealistic project deadlines.
سؤال
What is resource leveling? Why is it needed?
سؤال
List and briefly explain five priority rules used to assign preference to activities when allocating scarce resources.
سؤال
Which of the following rules maximizes the number of tasks that can be completed by a system in a given period of time?

A) as soon as possible
B) as late as possible
C) shortest task duration first
D) minimum slack first
E) most critical successor
سؤال
Starting the building phase before the design and planning phases is called…

A) operations overlapping
B) concurrent engineering
C) fast-tracking
D) concurrent construction
E) construction overlapping
سؤال
To crash a project, which of the following principles apply? 1) Focus on the critical path(s) when trying to shorten the duration of a project, 2) Select the least expensive way to do it 3) Crash non-critical activities

A) All three are correct
B) Only 1 and 3 are correct
C) Only 1 and 2 are correct
D) Only 1 is correct
سؤال
Explain how you would choose a priority rule.
سؤال
Explain the concept of a safety buffer.
سؤال
Briefly overview Goldratt's common chain of events.
سؤال
What is the effect of not reporting the early completion of project activities?
سؤال
Explain the concept of a feeding buffer.
سؤال
Why are scarce resources referred to as "Walts"?
سؤال
Explain the concept of a project buffer.
فتح الحزمة
قم بالتسجيل لفتح البطاقات في هذه المجموعة!
Unlock Deck
Unlock Deck
1/66
auto play flashcards
العب
simple tutorial
ملء الشاشة (f)
exit full mode
Deck 6: Allocating Resources to the Project
1
When crashing a task, the usual assumption is that a task is crashed the full amount or none at all.
False
2
If resources were not scarce, the resource allocation problem would be concerned solely with profit maximization.
True
3
If resources were not scarce, the resource allocation problem would be concerned solely with cost minimization.
False
4
Projects often compete with each other for the same resources.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
5
All projects are carried out under conditions of uncertainty.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
6
Trade-offs must be made in order to optimize the use of limited resources.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
7
Often it is beneficial to crash activities not on the critical path.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
8
When the work is routine, fast-tracking rarely causes serious problems.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
9
The time to complete a task with normal or standard-practice resource usage is referred to as the crash duration.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
10
Good project managers are able to estimate project task times with absolute certainty.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
11
Resource loading refers to the amounts of specific resources that are scheduled for use on specific activities or projects at specific times.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
12
Fast-tracking a project is used primarily in the pharmaceutical industry.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
13
The CPM method cannot be used when task durations are probabilistic.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
14
All tasks can be crashed to some extent.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
15
The amount of resources a project can use depends in part on the timing of the allocation.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
16
Resource loading refers to the amounts of specific resources that are scheduled for use on specific activities or projects at specific times.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
17
The variance of the normal time can be quite different from the variance of the crash time.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
18
It is considered good management to crash the least costly activities before the more costly ones.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
19
A project that must be completed by a fixed time is referred to as resource constrained.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
20
For resources that are consumed when used, the problem is which project gets to use the resource first and which must wait.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
21
Pools of like workers are most useful when labor is subdivided into highly specialized subtasks.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
22
According to research minimum slack rule is the overall best priority rule.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
23
The task duration with standard-practice resource usage is referred to as the…

A) expected task duration
B) nominal task duration
C) crash duration
D) normal task duration
E) planned task duration
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
24
The primary cause of concern in resource allocation is…

A) labor cost
B) resource scarcity
C) lack of solution methodologies
D) parallel activities
E) equipment downtime
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
25
The process of line balancing is when individual production lines are made to generate the required amount of product with a little excess capacity as possible.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
26
Crashing non-critical activities will influence project duration.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
27
Microsoft Project allows the project manager to create an individual availability calendar for each resource on the project
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
28
A limitation associated with traditional approaches to project management is that the dependency between resources and tasks is often ignored.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
29
One limitation of Microsoft Project is that all resources must share the same availability calendar.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
30
The as late as possible priority rule is considered the standard scheduling rule.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
31
Pools of like resources from which labor can be added temporarily to projects tend to increase costs for the firm as a whole.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
32
. The shortest duration task first rule minimizes the number of tasks that can be completed by s system in a given time period.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
33
A task has a normal duration of 9 days and a crash duration of 7 days. Its normal cost is $40 and its crash cost is $100. What is the crash cost per day?

A) $140
B) $70
C) $50
D) $40
E) $30
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
34
A resource allocation decision may be intended to avoid a future problem rather than correct a current problem.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
35
Activities that have duration but do not require resources are referred to as pseudoactivities.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
36
A task's duration is a function of both the amount of labor required to complete the task as well as the calendar time required to complete it.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
37
Allocating specific, limited resources to specific activities is called…

A) resource allocation
B) resource leveling
C) resource tracking
D) expediting a project
E) crashing a project
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
38
A project that must be completed by a specific time is considered…

A) time constrained
B) schedule constrained
C) resource constrained
D) performance constrained
E) critically constrained
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
39
In general, steady state demand for human resources is highly desirable.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
40
Applying "line balancing" techniques to balance the capacity of a project typically yields significant benefits.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
41
All of the following are criteria available to help choose the priority rule mentioned in the textbook except;

A) Schedule slippage
B) Project cost
C) resource utilization
D) in-process inventory
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
42
What is fast-tracking a project?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
43
The practice of assigning project team members to multiple projects is called…

A) concurrent engineering
B) parallel activities
C) fast-tracking
D) project crashing
E) multitasking
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
44
Which of the following priority rules makes resources available so that activities start on their LSTs whenever possible without increasing the project's duration?

A) as soon as possible
B) as late as possible
C) shortest task duration first
D) minimum slack first
E) most critical successor
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
45
Crashing refers to…

A) expediting the project so as to minimizing the total cost of completing the project.
B) expediting the project so as to minimizing the number of activities in the project
C) expediting the project so as to completing the project by a specified time.
D) all of the above
E) none of the above.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
46
A project that must be completed with in the specified performance requirements is considered…

A) time constrained
B) schedule constrained
C) resource constrained
D) performance constrained
E) critically constrained
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
47
Which of the following is not commonly used to help select a priority rule?

A) schedule slippage
B) resource utilization
C) in-process inventory
D) cost overruns
E) all of the above are used
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
48
The safety time added to chains other than the critical chain is called…

A) feeding buffer
B) project buffer
C) path buffer
D) critical buffer
E) team buffer
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
49
What is the student syndrome? In what ways can it create problems for a project?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
50
Which of the following is a measure of the amount by which a project is delayed by application of a leveling rule?

A) schedule inflation
B) schedule progression
C) schedule efficacy
D) schedule efficiency
E) schedule slippage
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
51
What is resource loading?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
52
Which of the following is not considered a resource?

A) Money
B) People
C) Equipment
D) Material
E) None of the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
53
According to research, the best overall priority rule is…

A) as soon as possible
B) as late as possible
C) shortest task duration first
D) minimum slack first
E) most critical successor
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
54
Explain how the commonly made assumption of known activity times can lead to unrealistic project deadlines.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
55
What is resource leveling? Why is it needed?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
56
List and briefly explain five priority rules used to assign preference to activities when allocating scarce resources.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
57
Which of the following rules maximizes the number of tasks that can be completed by a system in a given period of time?

A) as soon as possible
B) as late as possible
C) shortest task duration first
D) minimum slack first
E) most critical successor
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
58
Starting the building phase before the design and planning phases is called…

A) operations overlapping
B) concurrent engineering
C) fast-tracking
D) concurrent construction
E) construction overlapping
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
59
To crash a project, which of the following principles apply? 1) Focus on the critical path(s) when trying to shorten the duration of a project, 2) Select the least expensive way to do it 3) Crash non-critical activities

A) All three are correct
B) Only 1 and 3 are correct
C) Only 1 and 2 are correct
D) Only 1 is correct
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
60
Explain how you would choose a priority rule.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
61
Explain the concept of a safety buffer.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
62
Briefly overview Goldratt's common chain of events.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
63
What is the effect of not reporting the early completion of project activities?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
64
Explain the concept of a feeding buffer.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
65
Why are scarce resources referred to as "Walts"?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
66
Explain the concept of a project buffer.