Deck 8: Managing Project Stakeholders and Communication

ملء الشاشة (f)
exit full mode
سؤال
Budget At Completion (BAC) is the total planned cost of a project.
استخدم زر المسافة أو
up arrow
down arrow
لقلب البطاقة.
سؤال
A cost variance (CV) can be positive or negative, but never zero.
سؤال
The purpose of a project review is to not only show evidence that the project work is being completed, but also that the work is being completed according to various standards or agreed upon requirements.
سؤال
Earned value provides a performance measurement that tells us how much of the budget we really should have spent for the work completed so far.
سؤال
One attribute of a good project metric is that it should be subjective so that a stakeholder can understand the project manager's personal opinion or insight as to how the project is progressing.
سؤال
Given the advances that have been made in telecommunications and IT technology in general, there is little value or necessity today for Face-to-Face (F2F) meetings.
سؤال
The Estimate At Completion (EAC) is a project metric that can be used to estimate the most likely total or final cost of the project based on the project's performance and any risks that should be considered.
سؤال
A good project metric should be understandable, quantifiable, cost effective, proven, and be effective.
سؤال
If a stakeholder has been judged to adversarial and having a vested interest in the failure of your project, it would probably be wise to keep him/her out of the communication loop.
سؤال
Which of the following is not likely a characteristic of a good project metric?:

A) Understandable
B) Quantifiable
C) Cost Effective
D) Subjective
E) High Impact
سؤال
The project communications plan may be informal depending on the needs of the project stakeholders and the size of the project.
سؤال
The project manager must have a clear picture of how the actual progress or work compares to the baseline plan in order to make well-informed decisions, take appropriate actions, or to make adjustments to the project plan.
سؤال
All of the project stakeholders should receive exactly the same information regarding the project's progress in order to eliminate any miscommunication.
سؤال
The schedule variance (SV) shows the difference between the current progress of the project and its original or planned value.
سؤال
The Schedule Performance Index (SPI) for our project is greater than one (1) and so we would anticipate that all other things being equal, our project will finish ahead of schedule.
سؤال
Generally, the more metrics one adopts, the greater the project control.
سؤال
A project metric should be obtained from observable, quantifiable data that allows the team and other stakeholders to gauge the efficiency and effectiveness of the work being done.
سؤال
Planned value (PV) is the planned or budgeted cost of work scheduled for an activity or component of the WBS.
سؤال
The Expected Time Complete (ETC) provides an estimate for completing the scheduled work that remains.
سؤال
As a project manager, you would be pleased see a Cost Performance Index CPI less than one (1) for your project.
سؤال
Schedule Variance (SV) is __________

A) how much time it took to complete the work
B) how long we expected the task to take
C) how much time we have left to complete the project
D) how much time it should have taken to complete the task
E) the difference between the current progress and the original schedule
سؤال
Barring a change in project scope and given a Schedule Performance Index (SPI) that is greater than 1, the most reasonable inference to draw is that:

A) The project will likely finish earlier than planned.
B) The project will likely finish later than planned.
C) The project will likely cost more than planned.
D) The project will likely cost less than planned.
E) The project will likely be on time and on budget.
سؤال
The cost incurred for completing a scheduled task or WBS component is the

A) Planned Value (PV)
B) Budget At Completion (BAC)
C) Actual Cost (AC)
D) Expected Time Complete (ETC)
E) Estimate at Completion (EAC)
سؤال
A _________ is a formal or informal meeting that shows evidence of project work that has been completed and work and provides a forum for surfacing issues, problems, decision-making.

A) Budget report
B) Project review
C) Progress report
D) Forecast report
E) News report
سؤال
Cost Variance (CV) = Earned Value - ___________.

A) Budget at Completion (BAC)
B) Budgeted cost of remaining work (BCRW)
C) Schedule Variance (SV)
D) Actual Cost (AC)
E) None of these
سؤال
A _________ shows how the scope, features or functionality, or work is being completed over time.

A) Budget report
B) Status report
C) Progress report
D) Forecast report
E) Burn-down Chart
سؤال
The metric that provides an estimate of the most likely total or final cost of the project based on the project's performance and any risks that should be considered is the:

A) Planned Value (PV)
B) Budget At Completion (BAC)
C) Actual Cost (AC)
D) Expected Time Complete (ETC)
E) Estimate at Completion (EAC)
سؤال
The total planned cost of the project is computed before the project work begins. This metric is called the:

A) Planned Value (PV)
B) Budget At Completion (BAC)
C) Actual Cost (AC)
D) Expected Time Complete (ETC)
E) Estimate at Completion (EAC)
سؤال
Budget At Completion (BAC) is __________

A) how much we actually spent for work completed
B) how much we budgeted to spend at the beginning of the project
C) how much of the budget we have left to spend on the project
D) how much of the budget we really should have spent on the work completed so far
E) None of these
سؤال
EV-AC =

A) Cost performance index (CPI)
B) Scheduled performance index (SPI)
C) Cost Variance (CV)
D) Minimum funds needed (MFN)
E) None of these
سؤال
If you hired a consulting firm to develop a system which is estimated to take four months to complete with the tasks evenly divided over the four months and you agree to pay for the project with equal monthly installments, those payments would be called:

A) Planned Value (PV)
B) Budget At Completion (BAC)
C) Actual Cost (AC)
D) Earned Value (EV)
E) None of these
سؤال
The budgeted cost of work scheduled for an activity or component of the WBS is the _____.

A) Planned Value (PV)
B) Budget At Completion (BAC)
C) Actual Cost (AC)
D) Expected Time Complete (ETC)
E) Estimate at Completion (EAC)
سؤال
Cost Variance (CV) is __________

A) how much we actually spent for work completed
B) how much we budgeted to spend at the beginning of the project
C) how much of the budget we have left to spend on the project
D) how much of the budget we really should have spent on the work completed so far
E) the difference between the estimated cost and how much we have actually spent
سؤال
Earned Value tells us __________

A) how much we actually spent for work completed
B) how much we budgeted to spend at the beginning of the project
C) how much of the budget we have left to spend on the project
D) how much of the budget we really should have spent on the work completed so far
E) None of these
سؤال
Expected Time to Completion (ETC) is __________

A) how much time it took to complete the work
B) how long we expected the task to take
C) how much time we have left to complete the project
D) how much time it should have taken to complete the task
E) how much longer it will take to complete the project
سؤال
Barring a change in project scope and given a Cost Performance Index (CPI) that is less than 1, the most reasonable inference to draw is that:

A) The project will likely finish earlier than planned.
B) The project will likely finish later than planned.
C) The project will likely cost more than planned.
D) The project will likely cost less than planned.
E) The project will likely be on time and on budget.
سؤال
A metric that provides an estimate for completing the scheduled work that remains once the project is started is called the

A) Planned Value (PV)
B) Budget At Completion (BAC)
C) Actual Cost (AC)
D) Expected Time Complete (ETC)
E) Estimate at Completion (EAC)
سؤال
Actual Cost (AC) is __________

A) how much we actually spent for work completed
B) how much we budgeted to spend at the beginning of the project
C) how much of the budget we have left to spend on the project
D) how much of the budget we really should have spent on the work completed so far
E) None of these
سؤال
If we know the Actual Cost of a WBS component, what other value do we need to know in order to calculate the cost performance index (CPI)?

A) Budget at Completion (BAC)
B) Budget costs of remaining work (BCRW)
C) Schedule Variance (SV)
D) Expected Time Complete (ETC)
E) Earned Value (EV)
سؤال
Estimate at Completion (EAC) is __________

A) how much we actually spent for work completed
B) how much we budgeted to spend at the beginning of the project
C) how much of the budget we have left to spend on the project
D) how much of the budget we really should have spent on the work completed so far
E) how much we spent to complete the project
سؤال
Describe how the SPI and CPI can be used to forecast the final cost of a project.
سؤال
What is a project review and what purpose does it serve?
سؤال
Describe the concept of earned value.
سؤال
Why is communications among project stakeholders so important?
سؤال
What is a forecast report?
سؤال
Why is effective and efficient communication vital to a project?
سؤال
What is Planned Value (PV)?
سؤال
What is the purpose of a project communications plan? What kinds of things should this plan address?
سؤال
What is Actual Cost (AC)?
سؤال
What is a progress report?
سؤال
Describe the qualities of a good project metric.
سؤال
What are project metrics?
سؤال
A _________ predicts the future status or progress of the project.

A) Budget report
B) Status report
C) Progress report
D) Forecast report
E) News report
سؤال
Why would a project manager be unwilling to share bad news about unexpected problems with senior management or other high profile stakeholders?
سؤال
Sketch out a table with headings that represent the essential elements of a project communications plan.Fill in a hypothetical entry under each heading.
سؤال
A _________ describes the present state of the project and provides compares the project's actual progress to the baseline plan.

A) Budget report
B) Status report
C) Progress report
D) Forecast report
E) News report
سؤال
What is a status report?
سؤال
What is Budget at Completion (BAC)?
سؤال
Why should a project manager be concerned with monitoring a project's progress?
سؤال
Information distribution includes all of the following EXCEPT:

A) Face-To-Face Meetings
B) Telephone, e-mail, and other wireless devices
C) Web-based technologies
D) None of these are examples of information distribution
E) All of these are examples of information distribution
سؤال
How is the Cost Performance Index calculated and what can one learn from computing it?
سؤال
What are the strengths and weaknesses of the major information distribution channels covered in the text?
سؤال
What are the characteristics of a good project metric?
سؤال
Briefly describe the common categories of project reporting.
سؤال
How is the Schedule Performance Index calculated and what can one learn from computing it?
سؤال
Explain the concept of Earned Value and illustrate it with hypothetical values.
فتح الحزمة
قم بالتسجيل لفتح البطاقات في هذه المجموعة!
Unlock Deck
Unlock Deck
1/66
auto play flashcards
العب
simple tutorial
ملء الشاشة (f)
exit full mode
Deck 8: Managing Project Stakeholders and Communication
1
Budget At Completion (BAC) is the total planned cost of a project.
True
2
A cost variance (CV) can be positive or negative, but never zero.
False
3
The purpose of a project review is to not only show evidence that the project work is being completed, but also that the work is being completed according to various standards or agreed upon requirements.
True
4
Earned value provides a performance measurement that tells us how much of the budget we really should have spent for the work completed so far.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
5
One attribute of a good project metric is that it should be subjective so that a stakeholder can understand the project manager's personal opinion or insight as to how the project is progressing.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
6
Given the advances that have been made in telecommunications and IT technology in general, there is little value or necessity today for Face-to-Face (F2F) meetings.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
7
The Estimate At Completion (EAC) is a project metric that can be used to estimate the most likely total or final cost of the project based on the project's performance and any risks that should be considered.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
8
A good project metric should be understandable, quantifiable, cost effective, proven, and be effective.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
9
If a stakeholder has been judged to adversarial and having a vested interest in the failure of your project, it would probably be wise to keep him/her out of the communication loop.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
10
Which of the following is not likely a characteristic of a good project metric?:

A) Understandable
B) Quantifiable
C) Cost Effective
D) Subjective
E) High Impact
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
11
The project communications plan may be informal depending on the needs of the project stakeholders and the size of the project.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
12
The project manager must have a clear picture of how the actual progress or work compares to the baseline plan in order to make well-informed decisions, take appropriate actions, or to make adjustments to the project plan.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
13
All of the project stakeholders should receive exactly the same information regarding the project's progress in order to eliminate any miscommunication.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
14
The schedule variance (SV) shows the difference between the current progress of the project and its original or planned value.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
15
The Schedule Performance Index (SPI) for our project is greater than one (1) and so we would anticipate that all other things being equal, our project will finish ahead of schedule.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
16
Generally, the more metrics one adopts, the greater the project control.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
17
A project metric should be obtained from observable, quantifiable data that allows the team and other stakeholders to gauge the efficiency and effectiveness of the work being done.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
18
Planned value (PV) is the planned or budgeted cost of work scheduled for an activity or component of the WBS.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
19
The Expected Time Complete (ETC) provides an estimate for completing the scheduled work that remains.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
20
As a project manager, you would be pleased see a Cost Performance Index CPI less than one (1) for your project.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
21
Schedule Variance (SV) is __________

A) how much time it took to complete the work
B) how long we expected the task to take
C) how much time we have left to complete the project
D) how much time it should have taken to complete the task
E) the difference between the current progress and the original schedule
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
22
Barring a change in project scope and given a Schedule Performance Index (SPI) that is greater than 1, the most reasonable inference to draw is that:

A) The project will likely finish earlier than planned.
B) The project will likely finish later than planned.
C) The project will likely cost more than planned.
D) The project will likely cost less than planned.
E) The project will likely be on time and on budget.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
23
The cost incurred for completing a scheduled task or WBS component is the

A) Planned Value (PV)
B) Budget At Completion (BAC)
C) Actual Cost (AC)
D) Expected Time Complete (ETC)
E) Estimate at Completion (EAC)
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
24
A _________ is a formal or informal meeting that shows evidence of project work that has been completed and work and provides a forum for surfacing issues, problems, decision-making.

A) Budget report
B) Project review
C) Progress report
D) Forecast report
E) News report
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
25
Cost Variance (CV) = Earned Value - ___________.

A) Budget at Completion (BAC)
B) Budgeted cost of remaining work (BCRW)
C) Schedule Variance (SV)
D) Actual Cost (AC)
E) None of these
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
26
A _________ shows how the scope, features or functionality, or work is being completed over time.

A) Budget report
B) Status report
C) Progress report
D) Forecast report
E) Burn-down Chart
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
27
The metric that provides an estimate of the most likely total or final cost of the project based on the project's performance and any risks that should be considered is the:

A) Planned Value (PV)
B) Budget At Completion (BAC)
C) Actual Cost (AC)
D) Expected Time Complete (ETC)
E) Estimate at Completion (EAC)
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
28
The total planned cost of the project is computed before the project work begins. This metric is called the:

A) Planned Value (PV)
B) Budget At Completion (BAC)
C) Actual Cost (AC)
D) Expected Time Complete (ETC)
E) Estimate at Completion (EAC)
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
29
Budget At Completion (BAC) is __________

A) how much we actually spent for work completed
B) how much we budgeted to spend at the beginning of the project
C) how much of the budget we have left to spend on the project
D) how much of the budget we really should have spent on the work completed so far
E) None of these
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
30
EV-AC =

A) Cost performance index (CPI)
B) Scheduled performance index (SPI)
C) Cost Variance (CV)
D) Minimum funds needed (MFN)
E) None of these
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
31
If you hired a consulting firm to develop a system which is estimated to take four months to complete with the tasks evenly divided over the four months and you agree to pay for the project with equal monthly installments, those payments would be called:

A) Planned Value (PV)
B) Budget At Completion (BAC)
C) Actual Cost (AC)
D) Earned Value (EV)
E) None of these
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
32
The budgeted cost of work scheduled for an activity or component of the WBS is the _____.

A) Planned Value (PV)
B) Budget At Completion (BAC)
C) Actual Cost (AC)
D) Expected Time Complete (ETC)
E) Estimate at Completion (EAC)
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
33
Cost Variance (CV) is __________

A) how much we actually spent for work completed
B) how much we budgeted to spend at the beginning of the project
C) how much of the budget we have left to spend on the project
D) how much of the budget we really should have spent on the work completed so far
E) the difference between the estimated cost and how much we have actually spent
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
34
Earned Value tells us __________

A) how much we actually spent for work completed
B) how much we budgeted to spend at the beginning of the project
C) how much of the budget we have left to spend on the project
D) how much of the budget we really should have spent on the work completed so far
E) None of these
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
35
Expected Time to Completion (ETC) is __________

A) how much time it took to complete the work
B) how long we expected the task to take
C) how much time we have left to complete the project
D) how much time it should have taken to complete the task
E) how much longer it will take to complete the project
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
36
Barring a change in project scope and given a Cost Performance Index (CPI) that is less than 1, the most reasonable inference to draw is that:

A) The project will likely finish earlier than planned.
B) The project will likely finish later than planned.
C) The project will likely cost more than planned.
D) The project will likely cost less than planned.
E) The project will likely be on time and on budget.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
37
A metric that provides an estimate for completing the scheduled work that remains once the project is started is called the

A) Planned Value (PV)
B) Budget At Completion (BAC)
C) Actual Cost (AC)
D) Expected Time Complete (ETC)
E) Estimate at Completion (EAC)
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
38
Actual Cost (AC) is __________

A) how much we actually spent for work completed
B) how much we budgeted to spend at the beginning of the project
C) how much of the budget we have left to spend on the project
D) how much of the budget we really should have spent on the work completed so far
E) None of these
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
39
If we know the Actual Cost of a WBS component, what other value do we need to know in order to calculate the cost performance index (CPI)?

A) Budget at Completion (BAC)
B) Budget costs of remaining work (BCRW)
C) Schedule Variance (SV)
D) Expected Time Complete (ETC)
E) Earned Value (EV)
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
40
Estimate at Completion (EAC) is __________

A) how much we actually spent for work completed
B) how much we budgeted to spend at the beginning of the project
C) how much of the budget we have left to spend on the project
D) how much of the budget we really should have spent on the work completed so far
E) how much we spent to complete the project
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
41
Describe how the SPI and CPI can be used to forecast the final cost of a project.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
42
What is a project review and what purpose does it serve?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
43
Describe the concept of earned value.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
44
Why is communications among project stakeholders so important?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
45
What is a forecast report?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
46
Why is effective and efficient communication vital to a project?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
47
What is Planned Value (PV)?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
48
What is the purpose of a project communications plan? What kinds of things should this plan address?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
49
What is Actual Cost (AC)?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
50
What is a progress report?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
51
Describe the qualities of a good project metric.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
52
What are project metrics?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
53
A _________ predicts the future status or progress of the project.

A) Budget report
B) Status report
C) Progress report
D) Forecast report
E) News report
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
54
Why would a project manager be unwilling to share bad news about unexpected problems with senior management or other high profile stakeholders?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
55
Sketch out a table with headings that represent the essential elements of a project communications plan.Fill in a hypothetical entry under each heading.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
56
A _________ describes the present state of the project and provides compares the project's actual progress to the baseline plan.

A) Budget report
B) Status report
C) Progress report
D) Forecast report
E) News report
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
57
What is a status report?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
58
What is Budget at Completion (BAC)?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
59
Why should a project manager be concerned with monitoring a project's progress?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
60
Information distribution includes all of the following EXCEPT:

A) Face-To-Face Meetings
B) Telephone, e-mail, and other wireless devices
C) Web-based technologies
D) None of these are examples of information distribution
E) All of these are examples of information distribution
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
61
How is the Cost Performance Index calculated and what can one learn from computing it?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
62
What are the strengths and weaknesses of the major information distribution channels covered in the text?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
63
What are the characteristics of a good project metric?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
64
Briefly describe the common categories of project reporting.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
65
How is the Schedule Performance Index calculated and what can one learn from computing it?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 66 في هذه المجموعة.
فتح الحزمة
k this deck
66
Explain the concept of Earned Value and illustrate it with hypothetical values.