Deck 5: Scheduling the Project

ملء الشاشة (f)
exit full mode
سؤال
Technical dependencies are often harder to see on a Gantt chart than on a PERT/CPM network.
استخدم زر المسافة أو
up arrow
down arrow
لقلب البطاقة.
سؤال
To manage a project successfully,the project manager need only pay close attention to tasks on the critical path.
سؤال
"Merger" is a term used to describe the situation in which two or more paths in a network join together.
سؤال
AON and AOA networks can both be used to depict any project network.
سؤال
A disadvantage of Gantt charts is that they are hard to draw.
سؤال
Milestones cannot be identified on a Gantt Chart.
سؤال
The difference between EST and LFT is called slack.
سؤال
The difference between LST and LFT is called slack.
سؤال
If task duration estimates are carefully made,the project manager needs to only examine the critical path when conducting a risk analysis.
سؤال
A Gantt chart can NOT depict a critical path,only a PERT/CPM chart can.
سؤال
Standard Pert/CPM networks can be use to resolve probabilistic concerns
سؤال
Critical path tasks always have zero slack.
سؤال
A start-to-finish linkage is the most common way of linking to successive task.
سؤال
The actual project duration will be known with certainty after the project is completed.
سؤال
The formula for the expected time of an activity in a network assumes that the optimistic,pessimistic,and most likely time estimates have a Beta distribution.
سؤال
A project schedule is a project action plan converted into a timetable.
سؤال
When it was originally developed,PERT used certain (deterministic)methods to estimate activity duration.
سؤال
It is easiest to see lead and lag time in a project task on a PERT/CPM networks.
سؤال
The difference between the LST and EST is called slack.
سؤال
The shortest time to complete a network is equal to the duration of the longest path through the network.
سؤال
The tasks of project planning,project budgeting,and project scheduling are largely separable from one another.
سؤال
An event is a series of connected activities.
سؤال
For which purpose is simulation NOT used with regard to project scheduling?

A) to overcome the limitations associated with statistical techniques used to develop probability of completion time estimates
B) to investigate the range of project completion times
C) to investigate the distribution of project completion times
D) to verify the accuracy of the optimistic, pessimistic and most likely time estimates
E) all of the above
سؤال
A disadvantage of using beta distribution to approximate activity times is that it is generally less flexible than the normal distribution.
سؤال
What is project slack?

A) The amount of time a non-critical task can be delayed without making the project late.
B) The amount of time the critical path of a project can be delayed without making the project late.
C) The amount of time an activity on the critical path can be delayed without making the project late.
D) The difference between how long the project would take if all tasks were completed based on their pessimistic versus optimistic time estimates.
E) None of the above.
سؤال
PERT was originally used for what type of project?

A) construction
B) R & D
C) military
D) computer software development
E) advertising
سؤال
Which of the following is typically used as the best estimate of task duration?

A) expected time
B) pessimistic time
C) optimistic time
D) most likely time
E) none of the above
سؤال
A big advantage of AON networks is that they are easier to draw.
سؤال
The start-to-finish linkage is used in situations where is it desirable for two or more activities to finish at the same time.
سؤال
What is the expected time to complete a task with an optimistic,most likely,and pessimistic times of 3,4,and 7 days respectively?

A) 3
B) 4
C) 4.3
D) 4.7
E) 7
سؤال
Another name for total slack is free slack.
سؤال
What is the standard deviation of a task with optimistic,most likely,and pessimistic times of 3,4,and 7 days respectively assuming the estimates were made at the 99% plus level?

A) )444
B) )667
C) 1.212
D) 1.469
E) 1.540
سؤال
Technical dependencies on a project plan are easiest to see on a:

A) Gantt chart
B) Cost chart
C) PERT/CPM chart
D) Work Breakdown Structure
E) RACI Matrix
سؤال
The simulation approach is generally preferred over the statistical method.
سؤال
Which of the following is NOT an element of the Gantt chart?

A) actual progress
B) variance of the critical path
C) the current date
D) scheduled milestones
E) all of the above are elements
سؤال
The difference between LFT and EFT is called slack.
سؤال
Which of the following terms is most closely associated with a task required by the project?

A) activity
B) event
C) milestone
D) network
E) path
سؤال
What is it a milestone?

A) a significant event in the project
B) a mark on a chart that depicts project progress
C) an activity on the critical path
D) an activity with an uncertain completion time
E) all of the above
سؤال
Technical dependencies are generally easier to see on a Gantt chart than on PERT/CPM networks.
سؤال
.Milestones are not depended upon the predecessor activities in the project plan.
سؤال
An identifiable state resulting from the completion of one or more activities is called?

A) an event
B) an activity
C) a milestone
D) a path
E) the critical path
سؤال
A Term NOT used in the discussion of PERT/CPM analysis is

A) Activity
B) Events
C) Critical Path
D) Sensitivity path
E) network s
سؤال
The amount of time a noncritical task can be delayed without delaying the project is called?

A) surplus
B) flop
C) slack
D) critical time
E) safety
سؤال
Slack is calculated as?

A) LFT - EST
B) LFT - LST
C) LST - LFT
D) LFT - EFT
E) EFT - EST
سؤال
What is a merger and what problems do mergers create?
سؤال
Which of the following linkages is used to start two or more activities at the same time?

A) finish-to-start
B) start-to-start
C) finish-to-finish
D) start-to-finish
E) They can all be used to start two or more activities at the same time.
فتح الحزمة
قم بالتسجيل لفتح البطاقات في هذه المجموعة!
Unlock Deck
Unlock Deck
1/46
auto play flashcards
العب
simple tutorial
ملء الشاشة (f)
exit full mode
Deck 5: Scheduling the Project
1
Technical dependencies are often harder to see on a Gantt chart than on a PERT/CPM network.
True
2
To manage a project successfully,the project manager need only pay close attention to tasks on the critical path.
False
3
"Merger" is a term used to describe the situation in which two or more paths in a network join together.
True
4
AON and AOA networks can both be used to depict any project network.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
5
A disadvantage of Gantt charts is that they are hard to draw.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
6
Milestones cannot be identified on a Gantt Chart.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
7
The difference between EST and LFT is called slack.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
8
The difference between LST and LFT is called slack.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
9
If task duration estimates are carefully made,the project manager needs to only examine the critical path when conducting a risk analysis.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
10
A Gantt chart can NOT depict a critical path,only a PERT/CPM chart can.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
11
Standard Pert/CPM networks can be use to resolve probabilistic concerns
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
12
Critical path tasks always have zero slack.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
13
A start-to-finish linkage is the most common way of linking to successive task.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
14
The actual project duration will be known with certainty after the project is completed.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
15
The formula for the expected time of an activity in a network assumes that the optimistic,pessimistic,and most likely time estimates have a Beta distribution.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
16
A project schedule is a project action plan converted into a timetable.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
17
When it was originally developed,PERT used certain (deterministic)methods to estimate activity duration.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
18
It is easiest to see lead and lag time in a project task on a PERT/CPM networks.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
19
The difference between the LST and EST is called slack.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
20
The shortest time to complete a network is equal to the duration of the longest path through the network.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
21
The tasks of project planning,project budgeting,and project scheduling are largely separable from one another.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
22
An event is a series of connected activities.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
23
For which purpose is simulation NOT used with regard to project scheduling?

A) to overcome the limitations associated with statistical techniques used to develop probability of completion time estimates
B) to investigate the range of project completion times
C) to investigate the distribution of project completion times
D) to verify the accuracy of the optimistic, pessimistic and most likely time estimates
E) all of the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
24
A disadvantage of using beta distribution to approximate activity times is that it is generally less flexible than the normal distribution.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
25
What is project slack?

A) The amount of time a non-critical task can be delayed without making the project late.
B) The amount of time the critical path of a project can be delayed without making the project late.
C) The amount of time an activity on the critical path can be delayed without making the project late.
D) The difference between how long the project would take if all tasks were completed based on their pessimistic versus optimistic time estimates.
E) None of the above.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
26
PERT was originally used for what type of project?

A) construction
B) R & D
C) military
D) computer software development
E) advertising
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
27
Which of the following is typically used as the best estimate of task duration?

A) expected time
B) pessimistic time
C) optimistic time
D) most likely time
E) none of the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
28
A big advantage of AON networks is that they are easier to draw.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
29
The start-to-finish linkage is used in situations where is it desirable for two or more activities to finish at the same time.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
30
What is the expected time to complete a task with an optimistic,most likely,and pessimistic times of 3,4,and 7 days respectively?

A) 3
B) 4
C) 4.3
D) 4.7
E) 7
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
31
Another name for total slack is free slack.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
32
What is the standard deviation of a task with optimistic,most likely,and pessimistic times of 3,4,and 7 days respectively assuming the estimates were made at the 99% plus level?

A) )444
B) )667
C) 1.212
D) 1.469
E) 1.540
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
33
Technical dependencies on a project plan are easiest to see on a:

A) Gantt chart
B) Cost chart
C) PERT/CPM chart
D) Work Breakdown Structure
E) RACI Matrix
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
34
The simulation approach is generally preferred over the statistical method.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
35
Which of the following is NOT an element of the Gantt chart?

A) actual progress
B) variance of the critical path
C) the current date
D) scheduled milestones
E) all of the above are elements
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
36
The difference between LFT and EFT is called slack.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
37
Which of the following terms is most closely associated with a task required by the project?

A) activity
B) event
C) milestone
D) network
E) path
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
38
What is it a milestone?

A) a significant event in the project
B) a mark on a chart that depicts project progress
C) an activity on the critical path
D) an activity with an uncertain completion time
E) all of the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
39
Technical dependencies are generally easier to see on a Gantt chart than on PERT/CPM networks.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
40
.Milestones are not depended upon the predecessor activities in the project plan.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
41
An identifiable state resulting from the completion of one or more activities is called?

A) an event
B) an activity
C) a milestone
D) a path
E) the critical path
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
42
A Term NOT used in the discussion of PERT/CPM analysis is

A) Activity
B) Events
C) Critical Path
D) Sensitivity path
E) network s
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
43
The amount of time a noncritical task can be delayed without delaying the project is called?

A) surplus
B) flop
C) slack
D) critical time
E) safety
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
44
Slack is calculated as?

A) LFT - EST
B) LFT - LST
C) LST - LFT
D) LFT - EFT
E) EFT - EST
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
45
What is a merger and what problems do mergers create?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
46
Which of the following linkages is used to start two or more activities at the same time?

A) finish-to-start
B) start-to-start
C) finish-to-finish
D) start-to-finish
E) They can all be used to start two or more activities at the same time.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
locked card icon
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.