Deck 2: Executing Strategy: Project Management

ملء الشاشة (f)
exit full mode
سؤال
The amount of flexibility the project manager has in terms of starting and completing an activity is referred to as its slack.
استخدم زر المسافة أو
up arrow
down arrow
لقلب البطاقة.
سؤال
Which of the following project categories typically seeks the development of a new generation of outputs?

A)Derivative projects
B)Breakthrough projects
C)Platform projects
D)R&D projects
E)Construction Projects
سؤال
Which of the following terms provides the basis for the project schedule,often formatted as a project Gantt chart?

A)Critical path
B)Slack
C)Float
D)Earned value
E)Work breakdown structure
سؤال
All of the following are important outputs of project scheduling,except:

A)Identification of slack times for all activities and paths
B)Earliest and latest time each activity can be completed
C)Networks and paths
D)Identification of critical activities
سؤال
Project charters should contain some level of information regarding which of the following elements:

A)Business case,goals,or scope
B)Overview,general approach,schedules or milestones
C)Work breakdown structure and path dependencies
D)Both A and B
E)None of the above
سؤال
According to Goldratt,to complete a project on time,the highest priority should be given to the:

A)Critical buffer
B)Feeding chain
C)Project buffer
D)Critical chain
E)Slack activities
سؤال
When workers receive approval for a task based on inflated time estimate,they may perceive that they now have plenty of time to complete the task and therefore delay starting the task.What has this concept been called?

A)Senioritis
B)Inflation syndrome
C)Time-shift
D)Goldratt delay
E)Student syndrome
سؤال
An event is a series of connected activities from the start to the finish of the project.
سؤال
Which of the following is NOT an example of a project?

A)Constructing highways,bridges,tunnels and dams
B)Managing research and development (R&D)activities such as the development of the atomic bomb
C)Building a long tunnel
D)Running political or advertising campaigns,war or fire-fighting operations
E)Building MP3 players for massive distribution
سؤال
Among the reasons for the growth in project operations we find:

A)People have more leisure time to follow and participate in projects
B)More sophisticated technology has increased public awareness of project operations
C)More customization for suppliers makes it important to meet their needs
D)Both A and B
سؤال
The amount of time a project manager estimates it will take to complete the activity under ideal conditions is known as:

A)Pessimistic time
B)Optimistic time
C)Likeliest time
D)Utopian time
E)Slack time
سؤال
Which of the following statement(s)concerning probabilities of completion is/are incorrect?

A)Using the variance of each activity,we can compute the likelihood of completing the project in a given time period.
B)The probability of completing a path is found by calculating the standard normal deviate of the desired completion time less the expected completion time.
C)The distribution of a path's completion time will be approximately normally distributed if the path has a large number of activities on it.
D)The individual activity completion times must be normally distributed
E)All of the above are incorrect
سؤال
Duration of critical path - path duration = __________?

A)Latest finish time
B)Critical time
C)Path slack
D)Latest start time
E)Project slack
سؤال
The set of all project activities graphically interrelated through precedence relationships is known as a/an:

A)Activity
B)Event
C)Network
D)Path
E)Gantt chart
سؤال
Any path that if delayed will delay the completion of the entire project is known as a:

A)Significant path
B)Critical path
C)Central path
D)Network path
E)Troublesome path
سؤال
Which of the following project categories might lead to the other project categories?

A)Derivative projects
B)Breakthrough projects
C)Platform projects
D)R&D projects
E)None of the above
سؤال
An optimal procedure for organizations to accept projects is to specify a return on investment (ROI)and fund only projects that meet this criterion.
سؤال
Projects should be evaluated against standards and by methods established at their completion,including procedures for monitoring,collecting,storing,and evaluating the history of the project.
سؤال
The amount of flexibility the project manager has in terms of starting and completing an activity is referred to as its:

A)Slack
B)Float
C)Flex
D)Give
E)Both A and B
سؤال
The project life cycle typically has a stretched-s or an exponential form.
سؤال
When a project cost,schedule,or time variance is significant,the project manager must identify (or at least try to do so)an __________ cause for the variance so that the proper remedy can be used to keep it from recurring.
سؤال
How are projects not like other typical or routine processes?
سؤال
The objective of feeding buffers is to ensure that non-critical chains are completed so that they do not delay tasks on the critical chain.
سؤال
What three outcomes must a project manager determine when scheduling a project with uncertain activity times and the significance of each?
سؤال
How does benchmarking improve operations? And give a relevant example.
سؤال
Give an example of Activity Time Variability with Path Interdependencies.
سؤال
Give an example of Resource Dependence.
سؤال
The optimistic time is the amount of time the project will take under the worst-case scenario.
سؤال
Three phenomena that tend to bias the expected completion time of projects are inflated time estimates,activity time variability with path interdependencies,and resource dependence.
سؤال
The amount of safety time needed to protect a particular path in a project is less than the sum of the safety times required to protect the individual activities making up the path.
سؤال
Using CPM,when activity times are not known with certainty,we still can determine how long it will actually take to complete the project.
سؤال
Why might it be useful to simulate project completion times?
سؤال
What is the product life cycle (PLC)?
سؤال
Both PERT and CPM are based on variations of the __________ chart?
سؤال
Briefly describe the importance of a Project charter.
سؤال
The amount of _____ _____ needed to protect a particular path in a project is less than the sum of the _____ _____ required to protect the individual activities making up the path.
سؤال
Why is being able to predict activity times crucial in order to meet the demands of your customer?
سؤال
Why is a project portfolio a better approach to a project than the ROI approach?
سؤال
Give an example of Inflated Activity Time Estimates.
سؤال
Favorable variances do not require corrective action or further investigation;only unfavorable variances in performance.
سؤال
Describe the two types of project organizational structure were discussed and the advantages of both.
سؤال
Describe the four qualities are sought after in a project manager.
سؤال
Give an example of a derivative project and explain why your reasoning.
سؤال
Give an example of a project with the exponential life cycle and describe why this is a good example.
سؤال
Provide an example of how a project manager can use slack time.
سؤال
Compare and contrast PERT and CPM.
سؤال
Explain the importance of slack time and how it can impact the critical path.
سؤال
Many projects require different emphases during their life cycle.For example,technical performance may be crucial at the beginning,cost overruns in the middle,and on-time completion at the end.Given the project of running a political campaign,what would be there top three emphases starting from the beginning to end?
فتح الحزمة
قم بالتسجيل لفتح البطاقات في هذه المجموعة!
Unlock Deck
Unlock Deck
1/48
auto play flashcards
العب
simple tutorial
ملء الشاشة (f)
exit full mode
Deck 2: Executing Strategy: Project Management
1
The amount of flexibility the project manager has in terms of starting and completing an activity is referred to as its slack.
True
2
Which of the following project categories typically seeks the development of a new generation of outputs?

A)Derivative projects
B)Breakthrough projects
C)Platform projects
D)R&D projects
E)Construction Projects
Breakthrough projects
3
Which of the following terms provides the basis for the project schedule,often formatted as a project Gantt chart?

A)Critical path
B)Slack
C)Float
D)Earned value
E)Work breakdown structure
Work breakdown structure
4
All of the following are important outputs of project scheduling,except:

A)Identification of slack times for all activities and paths
B)Earliest and latest time each activity can be completed
C)Networks and paths
D)Identification of critical activities
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
5
Project charters should contain some level of information regarding which of the following elements:

A)Business case,goals,or scope
B)Overview,general approach,schedules or milestones
C)Work breakdown structure and path dependencies
D)Both A and B
E)None of the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
6
According to Goldratt,to complete a project on time,the highest priority should be given to the:

A)Critical buffer
B)Feeding chain
C)Project buffer
D)Critical chain
E)Slack activities
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
7
When workers receive approval for a task based on inflated time estimate,they may perceive that they now have plenty of time to complete the task and therefore delay starting the task.What has this concept been called?

A)Senioritis
B)Inflation syndrome
C)Time-shift
D)Goldratt delay
E)Student syndrome
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
8
An event is a series of connected activities from the start to the finish of the project.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
9
Which of the following is NOT an example of a project?

A)Constructing highways,bridges,tunnels and dams
B)Managing research and development (R&D)activities such as the development of the atomic bomb
C)Building a long tunnel
D)Running political or advertising campaigns,war or fire-fighting operations
E)Building MP3 players for massive distribution
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
10
Among the reasons for the growth in project operations we find:

A)People have more leisure time to follow and participate in projects
B)More sophisticated technology has increased public awareness of project operations
C)More customization for suppliers makes it important to meet their needs
D)Both A and B
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
11
The amount of time a project manager estimates it will take to complete the activity under ideal conditions is known as:

A)Pessimistic time
B)Optimistic time
C)Likeliest time
D)Utopian time
E)Slack time
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
12
Which of the following statement(s)concerning probabilities of completion is/are incorrect?

A)Using the variance of each activity,we can compute the likelihood of completing the project in a given time period.
B)The probability of completing a path is found by calculating the standard normal deviate of the desired completion time less the expected completion time.
C)The distribution of a path's completion time will be approximately normally distributed if the path has a large number of activities on it.
D)The individual activity completion times must be normally distributed
E)All of the above are incorrect
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
13
Duration of critical path - path duration = __________?

A)Latest finish time
B)Critical time
C)Path slack
D)Latest start time
E)Project slack
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
14
The set of all project activities graphically interrelated through precedence relationships is known as a/an:

A)Activity
B)Event
C)Network
D)Path
E)Gantt chart
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
15
Any path that if delayed will delay the completion of the entire project is known as a:

A)Significant path
B)Critical path
C)Central path
D)Network path
E)Troublesome path
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
16
Which of the following project categories might lead to the other project categories?

A)Derivative projects
B)Breakthrough projects
C)Platform projects
D)R&D projects
E)None of the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
17
An optimal procedure for organizations to accept projects is to specify a return on investment (ROI)and fund only projects that meet this criterion.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
18
Projects should be evaluated against standards and by methods established at their completion,including procedures for monitoring,collecting,storing,and evaluating the history of the project.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
19
The amount of flexibility the project manager has in terms of starting and completing an activity is referred to as its:

A)Slack
B)Float
C)Flex
D)Give
E)Both A and B
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
20
The project life cycle typically has a stretched-s or an exponential form.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
21
When a project cost,schedule,or time variance is significant,the project manager must identify (or at least try to do so)an __________ cause for the variance so that the proper remedy can be used to keep it from recurring.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
22
How are projects not like other typical or routine processes?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
23
The objective of feeding buffers is to ensure that non-critical chains are completed so that they do not delay tasks on the critical chain.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
24
What three outcomes must a project manager determine when scheduling a project with uncertain activity times and the significance of each?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
25
How does benchmarking improve operations? And give a relevant example.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
26
Give an example of Activity Time Variability with Path Interdependencies.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
27
Give an example of Resource Dependence.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
28
The optimistic time is the amount of time the project will take under the worst-case scenario.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
29
Three phenomena that tend to bias the expected completion time of projects are inflated time estimates,activity time variability with path interdependencies,and resource dependence.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
30
The amount of safety time needed to protect a particular path in a project is less than the sum of the safety times required to protect the individual activities making up the path.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
31
Using CPM,when activity times are not known with certainty,we still can determine how long it will actually take to complete the project.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
32
Why might it be useful to simulate project completion times?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
33
What is the product life cycle (PLC)?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
34
Both PERT and CPM are based on variations of the __________ chart?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
35
Briefly describe the importance of a Project charter.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
36
The amount of _____ _____ needed to protect a particular path in a project is less than the sum of the _____ _____ required to protect the individual activities making up the path.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
37
Why is being able to predict activity times crucial in order to meet the demands of your customer?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
38
Why is a project portfolio a better approach to a project than the ROI approach?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
39
Give an example of Inflated Activity Time Estimates.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
40
Favorable variances do not require corrective action or further investigation;only unfavorable variances in performance.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
41
Describe the two types of project organizational structure were discussed and the advantages of both.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
42
Describe the four qualities are sought after in a project manager.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
43
Give an example of a derivative project and explain why your reasoning.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
44
Give an example of a project with the exponential life cycle and describe why this is a good example.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
45
Provide an example of how a project manager can use slack time.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
46
Compare and contrast PERT and CPM.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
47
Explain the importance of slack time and how it can impact the critical path.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
48
Many projects require different emphases during their life cycle.For example,technical performance may be crucial at the beginning,cost overruns in the middle,and on-time completion at the end.Given the project of running a political campaign,what would be there top three emphases starting from the beginning to end?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
locked card icon
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.