__________ was developed by the U.S. Navy while the __________ was developed by __________.

A)PERT, CPM, DuPont
B)PERT, Gantt, DuPont
C)Gantt, PERT, U.S. Army
D)DuPont, CPM, U.S. Army
استخدم زر المسافة أو
up arrow
down arrow
لقلب البطاقة.
سؤال
The variance of a population is a measure of the population's __________.

A)dispersion
B)proportion
C)uniqueness
D)skewness
سؤال
In application, PERT(ADM)has primarily been used for __________.

A)construction projects
B)manufacturing projects
C)industrial projects
D)research and development projects
سؤال
The calculation of the standard deviation for the beta distribution is based on the assumption that __________.

A)the range is divided by a count of the values used to compute the mean
B)the range is approximately equal to six times the standard deviation
C)the standard deviation is 50 percent of the mean
D)the standard deviation is the square of the statistical variance
سؤال
The use of PERT (ADM)has declined sharply in recent years because a large majority of project management software __________.

A)have become obsolete
B)use probabilistic techniques
C)generate CPM networks
D)are characterized by high prices
سؤال
Task F has duration of 10 days and an earliest start date of 20 days. Based on the given data, determine the early finish duration for task F.

A)10 days
B)20 days
C)30 days
D)5 days
سؤال
A precedence relationship where the completion of a successor activity depends on the completion of a predecessor activity is called a __________.

A)start to finish dependency
B)finish to start dependency
C)finish to finish dependency
D)start to start dependency
سؤال
It is important to good project management to be meticulously __________ in estimating the time required to complete each of the various tasks included in the project.

A)accurate
B)honest
C)well-timed
D)clear
سؤال
The shortest time in which the entire network can be completed is referred to as the __________.

A)critical time of the network
B)real duration of the network
C)elapsed time of the network
D)slack time of the network
سؤال
A precedent relationship where the completion of a predecessor activity depends on the initiation of a successor activity is called a __________.

A)start to finish dependency
B)finish to start dependency
C)finish to finish dependency
D)start to start dependency
سؤال
The __________ for an activity is equal to the largest early finish for its preceding activities.

A)early start
B)late start
C)late finish
D)critical path
سؤال
Which of the following is NOT an advantage of a Gantt chart?

A)It can be easily understood.
B)Gantt charts are more effective for very large projects than ordinary projects.
C)It provides a good picture of the state of the project.
D)It is relatively easy to maintain.
سؤال
__________ have a weakness of being difficult to follow when multiple paths exist, but __________ are more helpful in the hands-on task of managing the project.

A)Networks, Gantt charts
B)Activity sets, networks
C)Gantt charts, networks
D)Gantt charts, activity sets
سؤال
In the AOA network, circles depict ________.

A)networks
B)events
C)logical dependencies
D)dummy activities
سؤال
When using the beta distribution, the denominator of the formula for standard deviation should ________.

A)be approximately one-sixth of its range.
B)be adjusted by converting the range into the correct statistical variance
C)be adjusted by converting the range into the correct z-score value
D)be adjusted by converting the range into 50 percent of the mean
سؤال
The critical activities in real-world projects typically constitute less than __________% of the total activities in the project.

A)5
B)10
C)30
D)50
سؤال
The authors recommend preparing a schedule for each __________.

A)work package in the WBS
B)task in the WBS
C)major task level in the WBS
D)project that has a WBS
سؤال
Slack is also known as __________.

A)critical path
B)scope
C)float
D)precedence
سؤال
Which of the following is NOT a software tool, commonly used to manage projects, especially in relation to time and cost budgets?

A)Microsoft Project
B)Microsoft Excel
C)Crystal Ball
D)Microsoft Word
سؤال
Most commercially available project management software applications use the __________.

A)GERT chart
B)Bar chart
C)AOA network
D)AON network
سؤال
The authors define __________ as the time an activity can be delayed without affecting the start time of any successor activity
سؤال
__________ law suggests that work expands to fill the allotted time.
سؤال
A(n)__________ is a specific task or set of tasks that are required by the project, use up resources, and take time to complete.
سؤال
In a network, if the delay of an activity will delay completion of the project, the activity is called a(n)__________.
سؤال
A __________ is the conversion of the project work breakdown structure into an operating timetable.
سؤال
In AOA networks, an activity of zero duration is called a(n)________.
سؤال
The series of connected activities (or intermediate events)between any two events in a network is called __________.
سؤال
Using precedence diagramming methods, activity B must not start until after activity A has been completed. Moreover, the outcome of activity A cannot be used until 3 days after its completion. This relationship between activities A and B is an example of a(n)__________.
سؤال
The difference between the late start and early start for an activity is called its __________.

A)critical path
B)task
C)progress
D)float
سؤال
An activity or event that, if delayed, will delay project completion is called a(n)__________.
سؤال
The arrangement of all activities (and, in some cases, events)in a project arrayed in their logical sequence and represented by arcs and nodes is called a __________.
سؤال
Any time two or more paths of a network come together, the probability of both paths being on time is the product of the probabilities for the individual paths. This scenario is referred to as __________.
سؤال
The authors, when discussing networks, describe a(n)__________ as the result of completing one or more activities. It is an identifiable end state, which does not use any resources, occurring at a particular time.
سؤال
Project task E has the following estimates: (1)optimistic time - 10 days, (2)Pessimistic time - 20 days, and (3)Most likely time - 12 Days. The expected time using the beta statistical distribution is __________ days.
سؤال
Task H has duration of 5 days, an early start of 25 days, an early finish of 30 days, a late start of 25 days, and a late finish of 30 days. There are __________ days of slack for task H.
سؤال
Project task E has the following estimates: (1)optimistic time - 10 days, (2)Pessimistic time - 20 days, and (3)Most likely time - 12 Days. The standard deviation for time using the beta statistical distribution is ________ days.
سؤال
__________ is an obvious way to check the nature and impacts of interactions between probabilistic paths in a network.
سؤال
The __________ chart shows planned and actual progress for a number of tasks displayed against a horizontal timescale.
سؤال
In CPM(PDM), an activity can be conducted at a normal pace or an expedited pace, known as ________, at a greater cost.
سؤال
Assume that task J has a most likely duration of 20 days, an optimistic duration of 13 days, and a pessimistic duration of 30 days. If the optimistic and pessimistic durations are 95 percent estimates, the standard deviation for task J is ________ days.
سؤال
Describe the process for determining the critical path in a network.
سؤال
A __________ is a combination of interrelated activities and events depicted with arcs and nodes.
سؤال
Explain why it is important to evaluate non-critical paths that possess large variances and/or path times that are close to critical in duration.
سؤال
__________ is the amount of one factor that must be sacrificed in order to achieve more or less of another factor.
سؤال
A(n)__________ is a point where one or more lines (arrows)begin or terminate, commonly used for depicting an event or activity.
سؤال
Describe the benefits of forming a network of activity and event relationships that graphically portrays sequential relations between tasks in a project.
سؤال
A clearly identifiable point in a project or set of activities that commonly denotes a reporting requirement or completion of a large or important set of activities is called a(n)__________.
سؤال
The _________ was developed by Henry Gantt in 1917.
سؤال
Explain the meaning of slack in a network.
سؤال
Explain the difference between Total Slack and Free Slack in a network.
فتح الحزمة
قم بالتسجيل لفتح البطاقات في هذه المجموعة!
Unlock Deck
Unlock Deck
1/50
auto play flashcards
العب
simple tutorial
ملء الشاشة (f)
exit full mode
Deck 8: Scheduling
1
__________ was developed by the U.S. Navy while the __________ was developed by __________.

A)PERT, CPM, DuPont
B)PERT, Gantt, DuPont
C)Gantt, PERT, U.S. Army
D)DuPont, CPM, U.S. Army
A
2
The variance of a population is a measure of the population's __________.

A)dispersion
B)proportion
C)uniqueness
D)skewness
A
3
In application, PERT(ADM)has primarily been used for __________.

A)construction projects
B)manufacturing projects
C)industrial projects
D)research and development projects
D
4
The calculation of the standard deviation for the beta distribution is based on the assumption that __________.

A)the range is divided by a count of the values used to compute the mean
B)the range is approximately equal to six times the standard deviation
C)the standard deviation is 50 percent of the mean
D)the standard deviation is the square of the statistical variance
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 50 في هذه المجموعة.
فتح الحزمة
k this deck
5
The use of PERT (ADM)has declined sharply in recent years because a large majority of project management software __________.

A)have become obsolete
B)use probabilistic techniques
C)generate CPM networks
D)are characterized by high prices
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 50 في هذه المجموعة.
فتح الحزمة
k this deck
6
Task F has duration of 10 days and an earliest start date of 20 days. Based on the given data, determine the early finish duration for task F.

A)10 days
B)20 days
C)30 days
D)5 days
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 50 في هذه المجموعة.
فتح الحزمة
k this deck
7
A precedence relationship where the completion of a successor activity depends on the completion of a predecessor activity is called a __________.

A)start to finish dependency
B)finish to start dependency
C)finish to finish dependency
D)start to start dependency
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 50 في هذه المجموعة.
فتح الحزمة
k this deck
8
It is important to good project management to be meticulously __________ in estimating the time required to complete each of the various tasks included in the project.

A)accurate
B)honest
C)well-timed
D)clear
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 50 في هذه المجموعة.
فتح الحزمة
k this deck
9
The shortest time in which the entire network can be completed is referred to as the __________.

A)critical time of the network
B)real duration of the network
C)elapsed time of the network
D)slack time of the network
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 50 في هذه المجموعة.
فتح الحزمة
k this deck
10
A precedent relationship where the completion of a predecessor activity depends on the initiation of a successor activity is called a __________.

A)start to finish dependency
B)finish to start dependency
C)finish to finish dependency
D)start to start dependency
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 50 في هذه المجموعة.
فتح الحزمة
k this deck
11
The __________ for an activity is equal to the largest early finish for its preceding activities.

A)early start
B)late start
C)late finish
D)critical path
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 50 في هذه المجموعة.
فتح الحزمة
k this deck
12
Which of the following is NOT an advantage of a Gantt chart?

A)It can be easily understood.
B)Gantt charts are more effective for very large projects than ordinary projects.
C)It provides a good picture of the state of the project.
D)It is relatively easy to maintain.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 50 في هذه المجموعة.
فتح الحزمة
k this deck
13
__________ have a weakness of being difficult to follow when multiple paths exist, but __________ are more helpful in the hands-on task of managing the project.

A)Networks, Gantt charts
B)Activity sets, networks
C)Gantt charts, networks
D)Gantt charts, activity sets
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 50 في هذه المجموعة.
فتح الحزمة
k this deck
14
In the AOA network, circles depict ________.

A)networks
B)events
C)logical dependencies
D)dummy activities
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 50 في هذه المجموعة.
فتح الحزمة
k this deck
15
When using the beta distribution, the denominator of the formula for standard deviation should ________.

A)be approximately one-sixth of its range.
B)be adjusted by converting the range into the correct statistical variance
C)be adjusted by converting the range into the correct z-score value
D)be adjusted by converting the range into 50 percent of the mean
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 50 في هذه المجموعة.
فتح الحزمة
k this deck
16
The critical activities in real-world projects typically constitute less than __________% of the total activities in the project.

A)5
B)10
C)30
D)50
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 50 في هذه المجموعة.
فتح الحزمة
k this deck
17
The authors recommend preparing a schedule for each __________.

A)work package in the WBS
B)task in the WBS
C)major task level in the WBS
D)project that has a WBS
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 50 في هذه المجموعة.
فتح الحزمة
k this deck
18
Slack is also known as __________.

A)critical path
B)scope
C)float
D)precedence
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 50 في هذه المجموعة.
فتح الحزمة
k this deck
19
Which of the following is NOT a software tool, commonly used to manage projects, especially in relation to time and cost budgets?

A)Microsoft Project
B)Microsoft Excel
C)Crystal Ball
D)Microsoft Word
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 50 في هذه المجموعة.
فتح الحزمة
k this deck
20
Most commercially available project management software applications use the __________.

A)GERT chart
B)Bar chart
C)AOA network
D)AON network
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 50 في هذه المجموعة.
فتح الحزمة
k this deck
21
The authors define __________ as the time an activity can be delayed without affecting the start time of any successor activity
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 50 في هذه المجموعة.
فتح الحزمة
k this deck
22
__________ law suggests that work expands to fill the allotted time.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 50 في هذه المجموعة.
فتح الحزمة
k this deck
23
A(n)__________ is a specific task or set of tasks that are required by the project, use up resources, and take time to complete.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 50 في هذه المجموعة.
فتح الحزمة
k this deck
24
In a network, if the delay of an activity will delay completion of the project, the activity is called a(n)__________.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 50 في هذه المجموعة.
فتح الحزمة
k this deck
25
A __________ is the conversion of the project work breakdown structure into an operating timetable.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 50 في هذه المجموعة.
فتح الحزمة
k this deck
26
In AOA networks, an activity of zero duration is called a(n)________.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 50 في هذه المجموعة.
فتح الحزمة
k this deck
27
The series of connected activities (or intermediate events)between any two events in a network is called __________.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 50 في هذه المجموعة.
فتح الحزمة
k this deck
28
Using precedence diagramming methods, activity B must not start until after activity A has been completed. Moreover, the outcome of activity A cannot be used until 3 days after its completion. This relationship between activities A and B is an example of a(n)__________.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 50 في هذه المجموعة.
فتح الحزمة
k this deck
29
The difference between the late start and early start for an activity is called its __________.

A)critical path
B)task
C)progress
D)float
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 50 في هذه المجموعة.
فتح الحزمة
k this deck
30
An activity or event that, if delayed, will delay project completion is called a(n)__________.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 50 في هذه المجموعة.
فتح الحزمة
k this deck
31
The arrangement of all activities (and, in some cases, events)in a project arrayed in their logical sequence and represented by arcs and nodes is called a __________.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 50 في هذه المجموعة.
فتح الحزمة
k this deck
32
Any time two or more paths of a network come together, the probability of both paths being on time is the product of the probabilities for the individual paths. This scenario is referred to as __________.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 50 في هذه المجموعة.
فتح الحزمة
k this deck
33
The authors, when discussing networks, describe a(n)__________ as the result of completing one or more activities. It is an identifiable end state, which does not use any resources, occurring at a particular time.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 50 في هذه المجموعة.
فتح الحزمة
k this deck
34
Project task E has the following estimates: (1)optimistic time - 10 days, (2)Pessimistic time - 20 days, and (3)Most likely time - 12 Days. The expected time using the beta statistical distribution is __________ days.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 50 في هذه المجموعة.
فتح الحزمة
k this deck
35
Task H has duration of 5 days, an early start of 25 days, an early finish of 30 days, a late start of 25 days, and a late finish of 30 days. There are __________ days of slack for task H.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 50 في هذه المجموعة.
فتح الحزمة
k this deck
36
Project task E has the following estimates: (1)optimistic time - 10 days, (2)Pessimistic time - 20 days, and (3)Most likely time - 12 Days. The standard deviation for time using the beta statistical distribution is ________ days.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 50 في هذه المجموعة.
فتح الحزمة
k this deck
37
__________ is an obvious way to check the nature and impacts of interactions between probabilistic paths in a network.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 50 في هذه المجموعة.
فتح الحزمة
k this deck
38
The __________ chart shows planned and actual progress for a number of tasks displayed against a horizontal timescale.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 50 في هذه المجموعة.
فتح الحزمة
k this deck
39
In CPM(PDM), an activity can be conducted at a normal pace or an expedited pace, known as ________, at a greater cost.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 50 في هذه المجموعة.
فتح الحزمة
k this deck
40
Assume that task J has a most likely duration of 20 days, an optimistic duration of 13 days, and a pessimistic duration of 30 days. If the optimistic and pessimistic durations are 95 percent estimates, the standard deviation for task J is ________ days.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 50 في هذه المجموعة.
فتح الحزمة
k this deck
41
Describe the process for determining the critical path in a network.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 50 في هذه المجموعة.
فتح الحزمة
k this deck
42
A __________ is a combination of interrelated activities and events depicted with arcs and nodes.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 50 في هذه المجموعة.
فتح الحزمة
k this deck
43
Explain why it is important to evaluate non-critical paths that possess large variances and/or path times that are close to critical in duration.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 50 في هذه المجموعة.
فتح الحزمة
k this deck
44
__________ is the amount of one factor that must be sacrificed in order to achieve more or less of another factor.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 50 في هذه المجموعة.
فتح الحزمة
k this deck
45
A(n)__________ is a point where one or more lines (arrows)begin or terminate, commonly used for depicting an event or activity.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 50 في هذه المجموعة.
فتح الحزمة
k this deck
46
Describe the benefits of forming a network of activity and event relationships that graphically portrays sequential relations between tasks in a project.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 50 في هذه المجموعة.
فتح الحزمة
k this deck
47
A clearly identifiable point in a project or set of activities that commonly denotes a reporting requirement or completion of a large or important set of activities is called a(n)__________.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 50 في هذه المجموعة.
فتح الحزمة
k this deck
48
The _________ was developed by Henry Gantt in 1917.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 50 في هذه المجموعة.
فتح الحزمة
k this deck
49
Explain the meaning of slack in a network.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 50 في هذه المجموعة.
فتح الحزمة
k this deck
50
Explain the difference between Total Slack and Free Slack in a network.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 50 في هذه المجموعة.
فتح الحزمة
k this deck
locked card icon
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 50 في هذه المجموعة.