Deck 9: Resource Allocation

ملء الشاشة (f)
exit full mode
سؤال
The tasks that logically precede a particular task in time are referred to as __________.

A)successors
B)followers
C)predecessors
D)priorities
استخدم زر المسافة أو
up arrow
down arrow
لقلب البطاقة.
سؤال
The standard practice with AOA and AON is to estimate activity times under the assumption of resource loadings that are __________.

A)probabilistic
B)crashed
C)normal
D)dynamic
سؤال
The points between the extreme points of the relationship between time use and resource use represent __________.

A)time constrained projects
B)resource constrained projects
C)alternative trade-offs between time and resources
D)a non-feasible solution space of trade-off alternatives related to time and resource use
سؤال
The formula for computing the cost/time slope for each activity that can be crashed is __________.

A)(crash cost + normal cost)/ (crash time + normal time)
B)(crash cost - normal cost)/ (crash time - normal time)
C)(normal cost + crash cost)/ (normal time + crash time)
D)(normal cost - crash cost)/ (normal time - crash time)
سؤال
Economically speaking, crashing a project creates a technology change in the __________ for an activity.

A)deliverable demand function
B)production function
C)audit function
D)deliverable supply function
سؤال
The two fundamental approaches to constrained allocation problems are __________.

A)heuristic approaches and rules of thumb
B)linear programming approaches and optimization models
C)heuristic approaches and optimization models
D)goal programming and trial and error
سؤال
The usual purpose of the __________ scheduling heuristic is to delay cash outflows as long as possible.

A)minimum slack first
B)shortest task first
C)most successors
D)as late as possible
سؤال
Using the __________ heuristic method, the project team can complete the maximum number of tasks during a given period of time.

A)as soon as possible
B)as late as possible
C)shortest task first
D)minimum slack first
سؤال
The principal reason why a project manager is surprised by resource constraints on a project is the failure to include __________ in risk identification activities.

A)resource availability
B)resource cost
C)resource mobility
D)resource skill
سؤال
In CPM, __________ are specified.

A)exact levels of uncertainty associated with activities
B)an expected time, a crash time, and the standard deviation time
C)three costs
D)Two activity times and two costs
سؤال
The __________ heuristic provides a general solution for critical path and time and is usually the default rule for a schedule.

A)as soon as possible
B)as late as possible
C)minimum slack first
D)shortest task first
سؤال
The __________ technique overlaps the design and build phases of a project to expedite its completion.

A)crashing
B)fast-tracking
C)leading
D)blitzing
سؤال
When using heuristic solutions to build a schedule, __________ will always take precedence.

A)technological necessities
B)time constraints
C)resource constraints
D)managerial preferences
سؤال
Most heuristic solution methods start with the __________ and analyze resource usage period by period, resource by resource.

A)GERT schedule
B)Gantt chart
C)PERT/CPM schedule
D)Master schedule
سؤال
When crashing a project, our first task is to develop __________.

A)a table or graph of the cost of a project as a function of the project's possible completion dates
B)a schedule that shows the risks associated with each activity in the project
C)a list that shows the activities and the events of a project without referring to the costs
D)a table showing the noncritical activities and the cost associated with each of those activities
سؤال
If deterministic time estimates are used, and if project deadlines are firm, there is a high likelihood that it will __________.

A)not be necessary to crash any activities in projects
B)be necessary to crash the last few activities of most projects
C)be completed on time and within budget
D)be completed as per schedule
سؤال
One of the problems that Goldratt observed was that if an activity has slack time, often times the start of the task is delayed until the slack is removed. This is referred to as __________.

A)Goldratt's Law
B)Murphy's Law
C)the delay game
D)the student syndrome
سؤال
The methods to find an optimal solution to the constrained resource scheduling problem fall into two categories. They are __________.

A)mathematical programming and linear programming
B)mathematical programming and enumeration
C)statistical analysis and simulation
D)quantified heuristics and gaming
سؤال
Which of the following effects will be observed in a network if a date-constrained project is scheduled from the ending date constraint using the "as late as possible" heuristic?

A)Each activity will make use of all the slack available to it.
B)The network will not have any critical activities.
C)It would never be possible to override the "as late as possible" heuristic with a "must start no later than" date constraint.
D)Many of the activities will be scheduled prior to the start date of the project.
سؤال
The __________ approach to constrained resource scheduling problems is the only feasible method of attacking large, nonlinear, complex problems that tend to occur in the real world of project management.

A)goal programming
B)heuristic
C)optimization modeling
D)linear programming
سؤال
If the appropriate scheduling equation for task A of a project were W = D * U, and it was initialized so that W = 40d, D = 10d, and U = 4 resources, and task A is an effort-driven activity, correctly balance this equation if the value for U is changed from 4 to 5. To balance the equation, the altered variable and its new value are __________.
سؤال
The use of __________ activity time estimates may reduce the chance that crashing the project will be needed.
سؤال
Three important parameters used to assess the effectiveness of a scheduling system include schedule slippage, in-process inventory, and __________.
سؤال
When we change technology, we may also be changing the level of __________ in carrying out the activity.
سؤال
Given W = D * U for an effort-driven task. Assume an 8-hour workday. Initially, task R was assigned to Bob. Bob was expected to accomplish 32 hours of work in five days. If Bob were 100 percent available to work on task R during the entire five days, his efficiency rate is __________%.
سؤال
__________ times result from an attempt to expedite the activity by the application of additional resources.
سؤال
__________ aims to minimize the period-by-period variations in resource loading by shifting tasks within their slack allowances. The purpose is to create a smoother distribution of resource usage.
سؤال
Given a scheduling equation W = D * U, if the equation for task J is initialized so that W = 20d, D= 5d, and U = 4 resources, and task J is a non-effort-driven activity (where D is held constant when resources are changed), correctly balance this equation if the value for U is changed from 4 to 5. To balance the equation, the altered variable and its new value are __________.
سؤال
__________ describes the amounts of individual resources an existing schedule requires during specific time periods.
سؤال
With respect to project scheduling, __________ is the amount of work waiting to be processed because there is a shortage of some resource.
سؤال
Given that task A will use three carpenters and have duration of six days, task A requires __________ labor days of work.
سؤال
Studies have shown that the __________ scheduling heuristic method usually results in the minimum amount of project schedule slippage, best utilization of facilities, and minimum total system occupancy time.

A)as soon as possible
B)as late as possible
C)shortest task first
D)minimum slack first
سؤال
Thoughtless optimism, the "student syndrome," and multitasking to reduce idle time can each contribute to __________.

A)slack
B)pessimistic bias
C)optimistic bias
D)feeder buffer
سؤال
One cannot save __________, rather one can only spend more or less of it.
سؤال
Given W = D * U for an effort-driven task. Assume an 8-hour workday. Initially, task R was assigned to Bob. Bob was expected to accomplish 32 hours of work in five days. Bob was expected to be 100% available to work on task R during the entire five days. However, Bob left the company and will be replaced by Sam. Sam's efficiency rate is 90%. If Sam is only 70% available, Sam will require __________ hours to complete task R.
سؤال
In some situations, two activities are scheduled to be carried out in parallel and using the same scarce resource. If the supply of the scarce resource is not sufficient to allow both activities to be carried out simultaneously, then whichever of the two is given priority immediately lengthens the other activity's path but not its actual __________.

A)duration
B)slack
C)float
D)buffer
سؤال
A project task is said to be __________ if it requires a fixed amount of time and known quantities of resources.
سؤال
The two principles to follow when crashing a project are __________.
سؤال
__________ are tasks that logically follow a particular task in time.
سؤال
__________ refers to the amount of time past a project's due or delivery date.
سؤال
Describe the extreme points of the relationship between time use and resource use.
سؤال
Suggest some options for leveling the load placed on resources.
سؤال
Describe the basic procedure for resource leveling.
سؤال
Discuss the advantages obtained from resource leveling.
سؤال
List some of the common priority rules utilized when following heuristic solution methods.
سؤال
Discuss some other causes of the strong optimistic bias in a project schedule.
فتح الحزمة
قم بالتسجيل لفتح البطاقات في هذه المجموعة!
Unlock Deck
Unlock Deck
1/46
auto play flashcards
العب
simple tutorial
ملء الشاشة (f)
exit full mode
Deck 9: Resource Allocation
1
The tasks that logically precede a particular task in time are referred to as __________.

A)successors
B)followers
C)predecessors
D)priorities
C
2
The standard practice with AOA and AON is to estimate activity times under the assumption of resource loadings that are __________.

A)probabilistic
B)crashed
C)normal
D)dynamic
C
3
The points between the extreme points of the relationship between time use and resource use represent __________.

A)time constrained projects
B)resource constrained projects
C)alternative trade-offs between time and resources
D)a non-feasible solution space of trade-off alternatives related to time and resource use
C
4
The formula for computing the cost/time slope for each activity that can be crashed is __________.

A)(crash cost + normal cost)/ (crash time + normal time)
B)(crash cost - normal cost)/ (crash time - normal time)
C)(normal cost + crash cost)/ (normal time + crash time)
D)(normal cost - crash cost)/ (normal time - crash time)
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
5
Economically speaking, crashing a project creates a technology change in the __________ for an activity.

A)deliverable demand function
B)production function
C)audit function
D)deliverable supply function
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
6
The two fundamental approaches to constrained allocation problems are __________.

A)heuristic approaches and rules of thumb
B)linear programming approaches and optimization models
C)heuristic approaches and optimization models
D)goal programming and trial and error
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
7
The usual purpose of the __________ scheduling heuristic is to delay cash outflows as long as possible.

A)minimum slack first
B)shortest task first
C)most successors
D)as late as possible
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
8
Using the __________ heuristic method, the project team can complete the maximum number of tasks during a given period of time.

A)as soon as possible
B)as late as possible
C)shortest task first
D)minimum slack first
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
9
The principal reason why a project manager is surprised by resource constraints on a project is the failure to include __________ in risk identification activities.

A)resource availability
B)resource cost
C)resource mobility
D)resource skill
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
10
In CPM, __________ are specified.

A)exact levels of uncertainty associated with activities
B)an expected time, a crash time, and the standard deviation time
C)three costs
D)Two activity times and two costs
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
11
The __________ heuristic provides a general solution for critical path and time and is usually the default rule for a schedule.

A)as soon as possible
B)as late as possible
C)minimum slack first
D)shortest task first
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
12
The __________ technique overlaps the design and build phases of a project to expedite its completion.

A)crashing
B)fast-tracking
C)leading
D)blitzing
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
13
When using heuristic solutions to build a schedule, __________ will always take precedence.

A)technological necessities
B)time constraints
C)resource constraints
D)managerial preferences
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
14
Most heuristic solution methods start with the __________ and analyze resource usage period by period, resource by resource.

A)GERT schedule
B)Gantt chart
C)PERT/CPM schedule
D)Master schedule
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
15
When crashing a project, our first task is to develop __________.

A)a table or graph of the cost of a project as a function of the project's possible completion dates
B)a schedule that shows the risks associated with each activity in the project
C)a list that shows the activities and the events of a project without referring to the costs
D)a table showing the noncritical activities and the cost associated with each of those activities
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
16
If deterministic time estimates are used, and if project deadlines are firm, there is a high likelihood that it will __________.

A)not be necessary to crash any activities in projects
B)be necessary to crash the last few activities of most projects
C)be completed on time and within budget
D)be completed as per schedule
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
17
One of the problems that Goldratt observed was that if an activity has slack time, often times the start of the task is delayed until the slack is removed. This is referred to as __________.

A)Goldratt's Law
B)Murphy's Law
C)the delay game
D)the student syndrome
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
18
The methods to find an optimal solution to the constrained resource scheduling problem fall into two categories. They are __________.

A)mathematical programming and linear programming
B)mathematical programming and enumeration
C)statistical analysis and simulation
D)quantified heuristics and gaming
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
19
Which of the following effects will be observed in a network if a date-constrained project is scheduled from the ending date constraint using the "as late as possible" heuristic?

A)Each activity will make use of all the slack available to it.
B)The network will not have any critical activities.
C)It would never be possible to override the "as late as possible" heuristic with a "must start no later than" date constraint.
D)Many of the activities will be scheduled prior to the start date of the project.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
20
The __________ approach to constrained resource scheduling problems is the only feasible method of attacking large, nonlinear, complex problems that tend to occur in the real world of project management.

A)goal programming
B)heuristic
C)optimization modeling
D)linear programming
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
21
If the appropriate scheduling equation for task A of a project were W = D * U, and it was initialized so that W = 40d, D = 10d, and U = 4 resources, and task A is an effort-driven activity, correctly balance this equation if the value for U is changed from 4 to 5. To balance the equation, the altered variable and its new value are __________.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
22
The use of __________ activity time estimates may reduce the chance that crashing the project will be needed.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
23
Three important parameters used to assess the effectiveness of a scheduling system include schedule slippage, in-process inventory, and __________.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
24
When we change technology, we may also be changing the level of __________ in carrying out the activity.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
25
Given W = D * U for an effort-driven task. Assume an 8-hour workday. Initially, task R was assigned to Bob. Bob was expected to accomplish 32 hours of work in five days. If Bob were 100 percent available to work on task R during the entire five days, his efficiency rate is __________%.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
26
__________ times result from an attempt to expedite the activity by the application of additional resources.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
27
__________ aims to minimize the period-by-period variations in resource loading by shifting tasks within their slack allowances. The purpose is to create a smoother distribution of resource usage.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
28
Given a scheduling equation W = D * U, if the equation for task J is initialized so that W = 20d, D= 5d, and U = 4 resources, and task J is a non-effort-driven activity (where D is held constant when resources are changed), correctly balance this equation if the value for U is changed from 4 to 5. To balance the equation, the altered variable and its new value are __________.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
29
__________ describes the amounts of individual resources an existing schedule requires during specific time periods.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
30
With respect to project scheduling, __________ is the amount of work waiting to be processed because there is a shortage of some resource.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
31
Given that task A will use three carpenters and have duration of six days, task A requires __________ labor days of work.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
32
Studies have shown that the __________ scheduling heuristic method usually results in the minimum amount of project schedule slippage, best utilization of facilities, and minimum total system occupancy time.

A)as soon as possible
B)as late as possible
C)shortest task first
D)minimum slack first
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
33
Thoughtless optimism, the "student syndrome," and multitasking to reduce idle time can each contribute to __________.

A)slack
B)pessimistic bias
C)optimistic bias
D)feeder buffer
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
34
One cannot save __________, rather one can only spend more or less of it.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
35
Given W = D * U for an effort-driven task. Assume an 8-hour workday. Initially, task R was assigned to Bob. Bob was expected to accomplish 32 hours of work in five days. Bob was expected to be 100% available to work on task R during the entire five days. However, Bob left the company and will be replaced by Sam. Sam's efficiency rate is 90%. If Sam is only 70% available, Sam will require __________ hours to complete task R.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
36
In some situations, two activities are scheduled to be carried out in parallel and using the same scarce resource. If the supply of the scarce resource is not sufficient to allow both activities to be carried out simultaneously, then whichever of the two is given priority immediately lengthens the other activity's path but not its actual __________.

A)duration
B)slack
C)float
D)buffer
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
37
A project task is said to be __________ if it requires a fixed amount of time and known quantities of resources.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
38
The two principles to follow when crashing a project are __________.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
39
__________ are tasks that logically follow a particular task in time.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
40
__________ refers to the amount of time past a project's due or delivery date.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
41
Describe the extreme points of the relationship between time use and resource use.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
42
Suggest some options for leveling the load placed on resources.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
43
Describe the basic procedure for resource leveling.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
44
Discuss the advantages obtained from resource leveling.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
45
List some of the common priority rules utilized when following heuristic solution methods.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 46 في هذه المجموعة.
فتح الحزمة
k this deck
46
Discuss some other causes of the strong optimistic bias in a project schedule.