Deck 2: Project, program, and Portfolio Selection

ملء الشاشة (f)
exit full mode
سؤال
According to Dr.Robert Kaplan and Dr.David Norton,a balanced scorecard rejects most traditional financial measures.
استخدم زر المسافة أو
up arrow
down arrow
لقلب البطاقة.
سؤال
When using the hierarchical four-stage planning process for selecting projects,you must start at the bottom of the pyramid.
سؤال
Low- or medium-priority projects that can be finished in less time than high-priority projects should always be completed first.
سؤال
Organizations need to narrow down the list of potential projects to those projects that will be most beneficial.
سؤال
Projects with higher NPVs are preferred to projects with lower NPVs if all other factors are equal.
سؤال
Payback occurs in the year when the cumulative benefits minus costs reach zero.
سؤال
Money earned today is worth more than money earned in the future,primarily due to inflation.
سؤال
Some core projects can be high risk,have high value,and require good timing.
سؤال
In practice,organizations usually use a single approach to select projects.
سؤال
If you assign weights to criteria based on percentage,the sum of all the criteria's weights must total 100 percent.
سؤال
Organizations should only pursue projects that have the best financial value.
سؤال
The main goal of programs is to obtain benefits and control not available from managing projects separately.
سؤال
Organizations-both large and small-cannot undertake most of the potential projects identified because of resource limitations and other constraints.
سؤال
A weighted scoring model is a tool that provides a systematic process for selecting projects based on many criteria.
سؤال
Most crucial projects,such as drug development or major transportation projects,will achieve payback in less than a year.
سؤال
An organization should consider only projects with a negative NPV if financial value is a key criterion for project selection.
سؤال
From the viewpoint of NPV only,if Project 2 has a higher NPV than Project 1,Project 1 should be chosen.
سؤال
The required rate of return is the minimum acceptable rate of return on an investment.
سؤال
With respect to NPV,all organizations start discounting in Year 0 (immediately).
سؤال
Just as projects are unique,so are project portfolios.
سؤال
Given discounted benefits of $516,000 and discounted costs of $243,200,your ROI is ____ %.

A) 10
B) 89
C) 112
D) 212
سؤال
After assigning weights for the criteria and scores for each project,you calculate a weighted score for each project by multiplying the weight for each criterion by its score and ____ the resulting values.

A) multiplying
B) adding
C) dividing
D) subtracting
سؤال
The SWOT analysis looks at ____.

A) Services, Weaknesses, Opportunities and Threats
B) Strengths, Weaknesses, Objectives and Threats
C) Strengths, Weaknesses, Opportunities and Threads
D) Strengths, Weaknesses, Opportunities and Threats
سؤال
According to the ____ value of money,a dollar today is worth more than a dollar tomorrow.

A) financial
B) time
C) economic
D) discretionary
سؤال
Three primary methods for determining the projected financial value of projects include net present value analysis,return on investment,and ____ analysis.

A) growth
B) payback
C) environmental impact
D) efficiency
سؤال
Project managers must be sure to check with their organization to find out its guidelines for when discounting starts,what discount rate to use,and what ____ the organization prefers.

A) charts
B) technique
C) format
D) results
سؤال
Which of the following formulas is used by Excel to calculate NPV?

A) =npv()
B) =npv(range of cash flows)
C) =npv(discount rate, range of cash flows)
D) =npv(discount rate)
سؤال
In the four-stage planning process for selecting projects,____ is the last step.

A) project planning
B) resource allocation
C) business area analysis
D) strategic planning
سؤال
One method for selecting projects based on broad organizational needs is to first determine whether they meet three important criteria: need,____,and will.

A) ambition
B) practicality
C) funding
D) vision
سؤال
If you create the weighted scoring model in a spreadsheet,you can enter the data,create and copy formulas,and perform a "____" analysis.

A) scenario
B) query
C) what-if
D) hypothetical
سؤال
A ____ rate is the rate used in discounting future cash flows.

A) prime
B) markup
C) cash flow
D) discount
سؤال
Projects that address competitive ____ are much more likely to be successful because they will be important to the organization's competitive position.

A) value
B) products
C) tactics
D) strategy
سؤال
Projects should first and foremost address business ____.

A) portfolios
B) ventures
C) needs
D) practices
سؤال
An organization should consider only projects with a ____ NPV if financial value is a key criterion for project selection.

A) positive
B) negative
C) zero
D) well-defined
سؤال
Payback occurs in the year when the cumulative benefits minus costs reach ____.

A) ($1400)
B) ($100)
C) $0
D) $100
سؤال
A(n)____ scoring model is a tool that provides a systematic process for selecting projects based on many criteria.

A) weighted
B) biased
C) variable
D) opportunity
سؤال
____ period is the amount of time it will take to recoup-in the form of net cash inflows-the total dollars invested in a project.

A) Return
B) Payback
C) Accrual
D) Residual
سؤال
You calculate cash ____ by subtracting costs from benefits,or expenses from income.

A) flow
B) statements
C) budgets
D) structure
سؤال
A positive NPV means the return from a project exceeds the ____ cost of capital-the return available by investing the capital elsewhere.

A) fixed
B) variable
C) alternative
D) opportunity
سؤال
____ is the result of subtracting the project costs from the benefits and then dividing by the costs.

A) Return on investment
B) Internal Return Rate
C) NPV
D) The payback period
سؤال
An IT project in the ____ category could help transform the business.

A) growth
B) assessment
C) venture
D) discretionary
سؤال
You can determine a project's ____________________ by finding what discount rate results in an NPV of zero for the project.
سؤال
____ should be formed and continuously updated to help the organization as a whole make better strategic decisions.

A) Monitors
B) Portfolios
C) Projects
D) Programs
سؤال
A(n)____________________ rate is the rate used in discounting future cash flows.
سؤال
____________________ is the result of subtracting the project costs from the benefits and then dividing by the costs.
سؤال
____________________ planning involves determining long-term objectives by analyzing the strengths and weaknesses of an organization,studying opportunities and threats in the business environment,predicting future trends,and projecting the need for new products and services.
سؤال
The annual discount ____________________ is a multiplier for each year that is based on the discount rate and year.
سؤال
____ are new requirements imposed by government,management,or some external influence.

A) Directives
B) Problems
C) Opportunities
D) Thresholds
سؤال
NPV analysis is a method for making equal ____________________ between cash flow for multiyear projects.
سؤال
After deciding which projects to pursue,organizations need to decide if it is advantageous to manage several projects together as part of a(n)____.

A) aggregate
B) program
C) cluster
D) group
سؤال
Studies show that one of the main reasons people quit their jobs is because ____.

A) there is too much risk
B) they feel they do not make enough money
C) they feel they do not make a difference
D) they feel overworked
سؤال
An organization can view project portfolio management as having ____ levels,from simplest to most complex.

A) two
B) five
C) six
D) ten
سؤال
____________________ analysis is a method of calculating the expected net monetary gain or loss from a project by discounting all expected future cash inflows and outflows to the present point in time.
سؤال
You can establish weights by assigning ____.

A) results
B) values
C) scores
D) points
سؤال
In portfolio management the "____" task should occur first.

A) prioritize projects on a list
B) apply modern portfolio theory
C) divide projects into investment categories
D) put all projects in one list
سؤال
____________________ analysis determines how much time will lapse before accrued benefits overtake accrued and continuing costs.
سؤال
____________________ considerations are often an important aspect of the project selection process,especially during tough economic times.
سؤال
A SWOT analysis involves the examination of Strengths,Weaknesses,Opportunities,and ____________________.
سؤال
An IT project in the ____ category must be accomplished to run the business.

A) ancillary
B) redundant
C) growth
D) core
سؤال
The goal of ____ portfolio management is clear: to help maximize business value to ensure enterprise success.

A) investment
B) interest
C) project
D) program
سؤال
Describe how problems,opportunities,and directives can drive the project selection process.
سؤال
It is important for organizations to develop a fair,consistent,and logical process for selecting projects,programs,and ____________________.
سؤال
Describe the role of the project portfolio manager in relation to the roles of project manager and program manager.
سؤال
A balanced ____________________ is a methodology that converts an organization's value drivers-such as customer service,innovation,operational efficiency,and financial performance-to a series of defined metrics.
سؤال
A(n)____________________ is a group of projects managed in a coordinated way to obtain benefits and control not available from managing them individually.
سؤال
Provide two examples demonstrating the value of identifying projects through the observation of day-to-day operations.
سؤال
The core category of IT projects labeled as ____________________ costs must be funded for a company to stay in business.
سؤال
Project portfolio management focuses on ____________________ issues while individual projects often focus on tactical issues.
سؤال
Grouping related ____________________ into programs helps improve coordination through better communications,planning,management,and control.
سؤال
Describe how coordinating housing projects within one program can lead to saving time and increasing authority.
سؤال
When creating a weighted scoring model,how do you identify criteria important to the project selection process?
سؤال
A program for IT ____________________ projects might include purchasing new hardware,software,and networking equipment,or determining standards for IT.
سؤال
____________________ projects helps you see the big picture,such as how many projects are supporting a growth strategy,how many are helping to increase profit margins,how many relate to marketing,and how many relate to materials.
سؤال
You can determine minimum scores or ____________________ for specific criteria in a weighted scoring model.
سؤال
A construction firm using ____________________ of scale can purchase materials,obtain services,and hire workers for less money if it is managing the construction of 100 houses instead of just one house.
فتح الحزمة
قم بالتسجيل لفتح البطاقات في هذه المجموعة!
Unlock Deck
Unlock Deck
1/75
auto play flashcards
العب
simple tutorial
ملء الشاشة (f)
exit full mode
Deck 2: Project, program, and Portfolio Selection
1
According to Dr.Robert Kaplan and Dr.David Norton,a balanced scorecard rejects most traditional financial measures.
False
2
When using the hierarchical four-stage planning process for selecting projects,you must start at the bottom of the pyramid.
False
3
Low- or medium-priority projects that can be finished in less time than high-priority projects should always be completed first.
False
4
Organizations need to narrow down the list of potential projects to those projects that will be most beneficial.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
5
Projects with higher NPVs are preferred to projects with lower NPVs if all other factors are equal.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
6
Payback occurs in the year when the cumulative benefits minus costs reach zero.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
7
Money earned today is worth more than money earned in the future,primarily due to inflation.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
8
Some core projects can be high risk,have high value,and require good timing.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
9
In practice,organizations usually use a single approach to select projects.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
10
If you assign weights to criteria based on percentage,the sum of all the criteria's weights must total 100 percent.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
11
Organizations should only pursue projects that have the best financial value.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
12
The main goal of programs is to obtain benefits and control not available from managing projects separately.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
13
Organizations-both large and small-cannot undertake most of the potential projects identified because of resource limitations and other constraints.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
14
A weighted scoring model is a tool that provides a systematic process for selecting projects based on many criteria.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
15
Most crucial projects,such as drug development or major transportation projects,will achieve payback in less than a year.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
16
An organization should consider only projects with a negative NPV if financial value is a key criterion for project selection.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
17
From the viewpoint of NPV only,if Project 2 has a higher NPV than Project 1,Project 1 should be chosen.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
18
The required rate of return is the minimum acceptable rate of return on an investment.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
19
With respect to NPV,all organizations start discounting in Year 0 (immediately).
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
20
Just as projects are unique,so are project portfolios.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
21
Given discounted benefits of $516,000 and discounted costs of $243,200,your ROI is ____ %.

A) 10
B) 89
C) 112
D) 212
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
22
After assigning weights for the criteria and scores for each project,you calculate a weighted score for each project by multiplying the weight for each criterion by its score and ____ the resulting values.

A) multiplying
B) adding
C) dividing
D) subtracting
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
23
The SWOT analysis looks at ____.

A) Services, Weaknesses, Opportunities and Threats
B) Strengths, Weaknesses, Objectives and Threats
C) Strengths, Weaknesses, Opportunities and Threads
D) Strengths, Weaknesses, Opportunities and Threats
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
24
According to the ____ value of money,a dollar today is worth more than a dollar tomorrow.

A) financial
B) time
C) economic
D) discretionary
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
25
Three primary methods for determining the projected financial value of projects include net present value analysis,return on investment,and ____ analysis.

A) growth
B) payback
C) environmental impact
D) efficiency
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
26
Project managers must be sure to check with their organization to find out its guidelines for when discounting starts,what discount rate to use,and what ____ the organization prefers.

A) charts
B) technique
C) format
D) results
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
27
Which of the following formulas is used by Excel to calculate NPV?

A) =npv()
B) =npv(range of cash flows)
C) =npv(discount rate, range of cash flows)
D) =npv(discount rate)
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
28
In the four-stage planning process for selecting projects,____ is the last step.

A) project planning
B) resource allocation
C) business area analysis
D) strategic planning
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
29
One method for selecting projects based on broad organizational needs is to first determine whether they meet three important criteria: need,____,and will.

A) ambition
B) practicality
C) funding
D) vision
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
30
If you create the weighted scoring model in a spreadsheet,you can enter the data,create and copy formulas,and perform a "____" analysis.

A) scenario
B) query
C) what-if
D) hypothetical
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
31
A ____ rate is the rate used in discounting future cash flows.

A) prime
B) markup
C) cash flow
D) discount
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
32
Projects that address competitive ____ are much more likely to be successful because they will be important to the organization's competitive position.

A) value
B) products
C) tactics
D) strategy
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
33
Projects should first and foremost address business ____.

A) portfolios
B) ventures
C) needs
D) practices
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
34
An organization should consider only projects with a ____ NPV if financial value is a key criterion for project selection.

A) positive
B) negative
C) zero
D) well-defined
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
35
Payback occurs in the year when the cumulative benefits minus costs reach ____.

A) ($1400)
B) ($100)
C) $0
D) $100
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
36
A(n)____ scoring model is a tool that provides a systematic process for selecting projects based on many criteria.

A) weighted
B) biased
C) variable
D) opportunity
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
37
____ period is the amount of time it will take to recoup-in the form of net cash inflows-the total dollars invested in a project.

A) Return
B) Payback
C) Accrual
D) Residual
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
38
You calculate cash ____ by subtracting costs from benefits,or expenses from income.

A) flow
B) statements
C) budgets
D) structure
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
39
A positive NPV means the return from a project exceeds the ____ cost of capital-the return available by investing the capital elsewhere.

A) fixed
B) variable
C) alternative
D) opportunity
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
40
____ is the result of subtracting the project costs from the benefits and then dividing by the costs.

A) Return on investment
B) Internal Return Rate
C) NPV
D) The payback period
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
41
An IT project in the ____ category could help transform the business.

A) growth
B) assessment
C) venture
D) discretionary
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
42
You can determine a project's ____________________ by finding what discount rate results in an NPV of zero for the project.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
43
____ should be formed and continuously updated to help the organization as a whole make better strategic decisions.

A) Monitors
B) Portfolios
C) Projects
D) Programs
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
44
A(n)____________________ rate is the rate used in discounting future cash flows.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
45
____________________ is the result of subtracting the project costs from the benefits and then dividing by the costs.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
46
____________________ planning involves determining long-term objectives by analyzing the strengths and weaknesses of an organization,studying opportunities and threats in the business environment,predicting future trends,and projecting the need for new products and services.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
47
The annual discount ____________________ is a multiplier for each year that is based on the discount rate and year.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
48
____ are new requirements imposed by government,management,or some external influence.

A) Directives
B) Problems
C) Opportunities
D) Thresholds
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
49
NPV analysis is a method for making equal ____________________ between cash flow for multiyear projects.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
50
After deciding which projects to pursue,organizations need to decide if it is advantageous to manage several projects together as part of a(n)____.

A) aggregate
B) program
C) cluster
D) group
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
51
Studies show that one of the main reasons people quit their jobs is because ____.

A) there is too much risk
B) they feel they do not make enough money
C) they feel they do not make a difference
D) they feel overworked
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
52
An organization can view project portfolio management as having ____ levels,from simplest to most complex.

A) two
B) five
C) six
D) ten
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
53
____________________ analysis is a method of calculating the expected net monetary gain or loss from a project by discounting all expected future cash inflows and outflows to the present point in time.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
54
You can establish weights by assigning ____.

A) results
B) values
C) scores
D) points
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
55
In portfolio management the "____" task should occur first.

A) prioritize projects on a list
B) apply modern portfolio theory
C) divide projects into investment categories
D) put all projects in one list
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
56
____________________ analysis determines how much time will lapse before accrued benefits overtake accrued and continuing costs.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
57
____________________ considerations are often an important aspect of the project selection process,especially during tough economic times.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
58
A SWOT analysis involves the examination of Strengths,Weaknesses,Opportunities,and ____________________.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
59
An IT project in the ____ category must be accomplished to run the business.

A) ancillary
B) redundant
C) growth
D) core
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
60
The goal of ____ portfolio management is clear: to help maximize business value to ensure enterprise success.

A) investment
B) interest
C) project
D) program
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
61
Describe how problems,opportunities,and directives can drive the project selection process.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
62
It is important for organizations to develop a fair,consistent,and logical process for selecting projects,programs,and ____________________.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
63
Describe the role of the project portfolio manager in relation to the roles of project manager and program manager.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
64
A balanced ____________________ is a methodology that converts an organization's value drivers-such as customer service,innovation,operational efficiency,and financial performance-to a series of defined metrics.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
65
A(n)____________________ is a group of projects managed in a coordinated way to obtain benefits and control not available from managing them individually.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
66
Provide two examples demonstrating the value of identifying projects through the observation of day-to-day operations.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
67
The core category of IT projects labeled as ____________________ costs must be funded for a company to stay in business.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
68
Project portfolio management focuses on ____________________ issues while individual projects often focus on tactical issues.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
69
Grouping related ____________________ into programs helps improve coordination through better communications,planning,management,and control.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
70
Describe how coordinating housing projects within one program can lead to saving time and increasing authority.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
71
When creating a weighted scoring model,how do you identify criteria important to the project selection process?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
72
A program for IT ____________________ projects might include purchasing new hardware,software,and networking equipment,or determining standards for IT.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
73
____________________ projects helps you see the big picture,such as how many projects are supporting a growth strategy,how many are helping to increase profit margins,how many relate to marketing,and how many relate to materials.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
74
You can determine minimum scores or ____________________ for specific criteria in a weighted scoring model.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
75
A construction firm using ____________________ of scale can purchase materials,obtain services,and hire workers for less money if it is managing the construction of 100 houses instead of just one house.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.
فتح الحزمة
k this deck
locked card icon
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 75 في هذه المجموعة.