Deck 13: Project Management and SDLC

ملء الشاشة (f)
exit full mode
سؤال
Project managers must manage the __________,which consists of all tasks that must start and finish on schedule or the project will be delayed unless corrective action is taken.

A)Over allocation
B)Critical path
C)Triple constraints
D)Scope creep
استخدم زر المسافة أو
up arrow
down arrow
لقلب البطاقة.
سؤال
Lessons learned to keep projects on track include all of the following except ________.

A)Set realistic and detailed project plans with adequate time and resources.
B)Encourage timely feedback and be willing to listen.
C)Manage risk with regular project status reviews.
D)Perform a postmortem with all members of the project team.
سؤال
A project plan is specified in a __________.

A)Resource pool
B)Gantt chart
C)Work breakdown structure
D)Critical path
سؤال
A project is a series of tasks to produce one or more ________,which are items that you hand off to the client or management for their review and approval.

A)Critical paths
B)Deliverables
C)Resources
D)Gantt charts
سؤال
Which of the following is not a red flag that indicates IT project problems?

A)Project has launched without senior buy-in
B)Users have too much early involvement
C)No detailed testing plan exists
D)No detailed project plan exists
سؤال
The triple constraint refers to the three attributes that must be managed effectively for successful completion and closure of any project.Which is not one of those attributes?

A)Cost or budget
B)Deliverables
C)Scope
D)Time
سؤال
Too often the final stage of a project,the ________,is skipped to save time and effort.

A)budgeting
B)executing
C)postmortem
D)controlling
سؤال
During project analysis,IT projects should be examined holistically-that is,in combination to identify investment synergies.This approach is known as ________.

A)ROI analysis
B)Business impact analysis
C)Project portfolio management
D)Capital budgeting
سؤال
Project managers need to recognize the risk of __________,which is the piling up of small changes that by themselves are manageable,but collectively can cause significant project growth.

A)Over allocation
B)Critical path
C)Triple constraints
D)Scope creep
سؤال
________ is a structured methodology to plan,manage,and control the completion of a project throughout its life cycle.

A)Project planning
B)Project management
C)Systems development
D)System design
سؤال
Enterprises face the challenge of deciding which investments to make and how to allocate scarce resources to competing projects.Typically a senior manager composes a(n)________ that outlines the justification for the start-up and funding of a project.

A)Project portfolio
B)Business case
C)ROI analysis
D)Business impact statement
سؤال
The ________ identifies all work or activities that need to be performed,the schedule of work,and who will perform the work.

A)Business case
B)Project plan review
C)Statement of work
D)Work breakdown structure
سؤال
________ are used to manage the project work effort,monitor results,and report meaningful status to project stakeholders.

A)Milestones
B)Project plan review
C)Statement of work
D)Work breakdown structure
سؤال
Project management is gaining in importance for all types of projects because of _________.

A)Regulations and compliance requirements
B)The increased use of consultants and vendors
C)Technology complexity,tighter budgets,tougher competition,and shorter time-to-delivery requirements
D)Migration from data centers to cloud computing,tough competition,and cost control.
سؤال
The ________ defines the project plan and is a legal contract used to document the agreement between parties.

A)Business case
B)Project plan review
C)Statement of work
D)Work breakdown structure
سؤال
_________ lets everyone know who is responsible for the completion of each of the tasks.

A)Milestones
B)Project plan review
C)Responsibility matrix
D)Gantt chart
سؤال
Michelle Symonds suggested a set of seven deadly sins of project management,that is,the common mistakes that companies commit that contribute to project failure.Which is not one of these deadly mistakes?

A)No organizing schedule
B)No project plan
C)No budget tracking
D)No change management process
سؤال
A project has each of the following characteristics except ________.

A)Clearly defined scope,deliverables,and results
B)An estimated budget that is subject to a high degree of uncertainty
C)Low risk with a high profit potential or benefits
D)An estimated time frame or schedule that is subject to a high degree of uncertainty
سؤال
Except in extreme cases,the evaluation of success or failure is ________ because time and cost to complete the project are _________.

A)Subjective;estimates
B)Done by the project manager;fixed
C)Objective;inflexible
D)Done by the project team;set by them
سؤال
The financial services sector has been compelled by strict international anti-money-laundering (AML)guidelines that require firms to _________.

A)know your customer
B)implement master data management
C)adhere to project portfolio management
D)demonstrate data consistency and accuracy
سؤال
Monitoring and control processes should occur _________ while the project work is being executed.

A)weekly or bi-weekly
B)continuously and continually
C)monthly
D)at each milestone
سؤال
The system development life cycle (SDLC)is the traditional system development method for ________.

A)Updating legacy systems
B)Low risk IT projects,such as sales support
C)Systems integration projects
D)Large IT projects,such as IT infrastructure or an enterprise system.
سؤال
Controls help to prevent ________,which refer to system development projects that are so far over budget and past deadline that they must be abandoned,typically with large monetary loss.

A)Deficient critical paths
B)runaway projects
C)scope creep
D)missed deadlines
سؤال
Each task or activity has a start date and ________,which determines its finish date.

A)duration
B)resource requirements
C)milestone
D)critical path
سؤال
Covert resistance to a new IS from employees may take the form of __________.

A)Sabotaging the new system by entering data incorrectly
B)Continuing to do their jobs using their old methods
C)Complaining about the new system for extended time
D)Resisting change and training
سؤال
Once the new system's operations are stabilized,________ are performed during operation to assess the system's capabilities and determine if it is being used correctly.

A)Audits
B)Compliance analyses
C)Feasibility studies
D)Implementation tests
سؤال
The __________ is the traditional systems development method used by organizations for large IT projects such as IT infrastructure.

A)Prototyping method
B)System development life cycle
C)Critical path method
D)Sourcing method
سؤال
________ should not be considered in the decision to kill a project.

A)Completed deliverables
B)Project scope
C)Sunk costs
D)SOW
سؤال
Which of the following issues about the SDLC methodology is false?

A)Requirements analysis is critical to the success of the project.
B)System development practitioners agree that the more time invested in analyzing the current system and understanding problems that are likely to occur during system development,the greater the probability that the IS will be a success
C)The requirements study determines the probability of success of the proposed project.
D)Testing verifies that apps,interfaces,data transfers,and so on,work correctly under all possible conditions.
سؤال
Project ________ depends on prompt and candid feedback from the project team,while ________ depends on systems and decision rules for managing variances between the project's scope,cost,and schedule.

A)Monitoring;control
B)Management;monitoring
C)Critical path;scope creep
D)Timeline;baseline
سؤال
__________ conversion is the least expensive and highest risk IS conversion strategy because the old system is cut off and the new system is turned on at a certain point in time.

A)Parallel
B)Direct
C)Pilot
D)Phased
سؤال
Closing out a project benefits the _________.

A)enterprise and people who worked on the project
B)completed project
C)client
D)completed project and enterprise
سؤال
The first stage of the SDLC is __________ to understand the business problem or opportunity.

A)Systems analysis
B)Systems investigation
C)Prototyping
D)Systems design
سؤال
During the system investigation stage,__________ studies are done to determine if the hardware,software,and communications components can be developed and/or acquired to solve the business problem.

A)Economic feasibility
B)Technical feasibility
C)ROI
D)NPV
سؤال
________ are multipurpose visualization tools that show the timeline of the project schedule;and are used for planning,scheduling,and at-a-glance status reports.

A)Baselines
B)Gantt charts
C)Statements of work
D)Critical paths
سؤال
Project management is a structured methodology to plan,manage,and control the completion of a project throughout its life cycle.
سؤال
System development life cycle involves processes that __________,which means that they are revised when new information or conditions make change the smart thing to do.

A)Are iterative
B)Are subject to infinite revisions
C)Have constraints
D)Are prototyped
سؤال
During the systems investigation stage,__________ studies are done to assess the skills and the training needed to use the new system.

A)Economic feasibility
B)Technical feasibility
C)Organizational feasibility
D)Behavioral feasibility
سؤال
Which is not a characteristic of system testing?

A)Testing verifies that apps,interfaces,data transfers,and so on,work correctly under all possible conditions.
B)The risk of costly lawsuits needs to be considered.
C)Improper testing is very risky.
D)Proper testing can be done quickly and with little effort and expense.
سؤال
Critical path is the ________ path of tasks through a project,as shown on a Gantt chart.

A)most complex
B)first
C)longest
D)shortest
سؤال
Baseline is a specification of the project plan that has been formally reviewed and agreed upon.It can be updated or changed through casual or informal change control processes.
سؤال
Not using a best practices project management approach is the biggest IT project mistake a business can make.
سؤال
The DIA baggage-handling project represents practically every possible project management mistake.
سؤال
Projects are subject to unanticipated and uncontrollable events so they need to have slack built into the schedule and budget.
سؤال
After the project plan in the SOW is reviewed,a go or no-go decision is made;and if a go decision is made,the project is initiated.
سؤال
During project analysis,IT projects should be examined holistically-that is,in combination in order to identify investment synergies-using a project portfolio management approach.
سؤال
The major take-away from the triple constraint being represented as a triangle is that you cannot change one side without changing the other sides.
سؤال
Projects start with an idea that is explained in a business case.If the business case is accepted,a work breakdown structure (WBS)is prepared.
سؤال
A project is a well-planned sequential series of tasks to achieve a result;and have a defined beginning and end,a scope,resources,and a budget.
سؤال
The SOW is a legal contract used to document the agreement between parties after the business terms have been accepted and a go decision is made.
سؤال
The financial services sector has been compelled by strict international anti-money-laundering (AML)guidelines that require firms to know your customer (KYC).
سؤال
During a project,the more involvement you have from users,the greater your chance of delay,conflict,and failure.
سؤال
Scope creep is the piling up of numerous small delays that by themselves may be manageable,but in aggregate are significant.
سؤال
The triple constraint refers to project scope,deliverables,and budget,which must be managed effectively for successful completion and closure of any project
سؤال
On a Gantt chart,the start and finish dates of all tasks and milestones appear as bars whose length represent its cost.
سؤال
The baseline is used for monitoring and controlling.Any change to the baseline is a deviation,or variance,to the plan-and it needs to be documented.
سؤال
A responsibility matrix shows who has primary responsibility and who has support responsibility for the activities listed in the WBS.
سؤال
The SOW breaks a project down into the tasks or activities that must be performed,and in what order,to produce the deliverables at each milestone.
سؤال
Lack of milestones has been a contributing factor in many project failures.
سؤال
Project management software computes the cost of the project based on labor time (duration)of each task in the WBS and the cost of labor or other resource.
سؤال
Starting with an initial idea,the SDLC processes are requirements analysis,systems analysis and design,development and testing,implementation,and maintenance.
سؤال
Requirements analysis is critical to the success of the project.
سؤال
Technical feasibility addresses two primary questions: Do the benefits outweigh the costs of the project? Can the project be completed as scheduled?
سؤال
Integrated change control processes are always documented and saved in the event of project failure or lawsuits related to the failure.
سؤال
All projects have a critical path,which is the shortest path.
سؤال
Project control is also used to identify when to declare the ongoing project a failure and kill it
سؤال
Monitoring and control processes are intended to occur weekly while the project work is being executed.
سؤال
Changes to a project tend to have a trickle-down effect because of task dependencies and shared resources.
سؤال
During project analysis,IT projects should be examined holistically-that is,in combination to identify investment synergies.This approach is known as ________ management.
سؤال
Critical tasks must finish on schedule because delays will delay the project unless something is done to compensate.
سؤال
________ is a presentation or document that outlines the justification for the start-up and funding of a project.
سؤال
Because scope creep is expensive,project managers impose controls on changes requested by users,which help to prevent runaway projects.
سؤال
Information system design projects are not susceptible to scope creep because of the rigorous SDLC methodology.
سؤال
The system development life cycle (SDLC)is the traditional system development method for large IT projects,such as IT infrastructure or an enterprise system.
سؤال
System testing verifies that apps,interfaces,data transfers,and so on,work correctly under standard or expected conditions.
سؤال
Management can assess economic feasibility by using cost-benefit analysis,ROI,NPV,and breakeven analysis.
سؤال
The money already spent on the project,or sunk costs,should be considered in the decision to kill a project that is out of control.
سؤال
Calculating economic feasibility in IT projects is straightforward because it is done using standard financial techniques--ROI,NPV,and breakeven analysis.
سؤال
The feasibility study is critically important to the system development process because,when done properly,the study can prevent companies from making expensive mistakes,such as creating systems that will not work,that will not work efficiently,or that people cannot or will not use.
سؤال
Postproject reviews,or postmortems,identify the reasons the project was successful or not,strengths and weaknesses of the project plan,how problems were detected and resolved,and how the project was successful in spite of them.
فتح الحزمة
قم بالتسجيل لفتح البطاقات في هذه المجموعة!
Unlock Deck
Unlock Deck
1/103
auto play flashcards
العب
simple tutorial
ملء الشاشة (f)
exit full mode
Deck 13: Project Management and SDLC
1
Project managers must manage the __________,which consists of all tasks that must start and finish on schedule or the project will be delayed unless corrective action is taken.

A)Over allocation
B)Critical path
C)Triple constraints
D)Scope creep
B
2
Lessons learned to keep projects on track include all of the following except ________.

A)Set realistic and detailed project plans with adequate time and resources.
B)Encourage timely feedback and be willing to listen.
C)Manage risk with regular project status reviews.
D)Perform a postmortem with all members of the project team.
D
3
A project plan is specified in a __________.

A)Resource pool
B)Gantt chart
C)Work breakdown structure
D)Critical path
C
4
A project is a series of tasks to produce one or more ________,which are items that you hand off to the client or management for their review and approval.

A)Critical paths
B)Deliverables
C)Resources
D)Gantt charts
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
5
Which of the following is not a red flag that indicates IT project problems?

A)Project has launched without senior buy-in
B)Users have too much early involvement
C)No detailed testing plan exists
D)No detailed project plan exists
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
6
The triple constraint refers to the three attributes that must be managed effectively for successful completion and closure of any project.Which is not one of those attributes?

A)Cost or budget
B)Deliverables
C)Scope
D)Time
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
7
Too often the final stage of a project,the ________,is skipped to save time and effort.

A)budgeting
B)executing
C)postmortem
D)controlling
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
8
During project analysis,IT projects should be examined holistically-that is,in combination to identify investment synergies.This approach is known as ________.

A)ROI analysis
B)Business impact analysis
C)Project portfolio management
D)Capital budgeting
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
9
Project managers need to recognize the risk of __________,which is the piling up of small changes that by themselves are manageable,but collectively can cause significant project growth.

A)Over allocation
B)Critical path
C)Triple constraints
D)Scope creep
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
10
________ is a structured methodology to plan,manage,and control the completion of a project throughout its life cycle.

A)Project planning
B)Project management
C)Systems development
D)System design
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
11
Enterprises face the challenge of deciding which investments to make and how to allocate scarce resources to competing projects.Typically a senior manager composes a(n)________ that outlines the justification for the start-up and funding of a project.

A)Project portfolio
B)Business case
C)ROI analysis
D)Business impact statement
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
12
The ________ identifies all work or activities that need to be performed,the schedule of work,and who will perform the work.

A)Business case
B)Project plan review
C)Statement of work
D)Work breakdown structure
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
13
________ are used to manage the project work effort,monitor results,and report meaningful status to project stakeholders.

A)Milestones
B)Project plan review
C)Statement of work
D)Work breakdown structure
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
14
Project management is gaining in importance for all types of projects because of _________.

A)Regulations and compliance requirements
B)The increased use of consultants and vendors
C)Technology complexity,tighter budgets,tougher competition,and shorter time-to-delivery requirements
D)Migration from data centers to cloud computing,tough competition,and cost control.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
15
The ________ defines the project plan and is a legal contract used to document the agreement between parties.

A)Business case
B)Project plan review
C)Statement of work
D)Work breakdown structure
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
16
_________ lets everyone know who is responsible for the completion of each of the tasks.

A)Milestones
B)Project plan review
C)Responsibility matrix
D)Gantt chart
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
17
Michelle Symonds suggested a set of seven deadly sins of project management,that is,the common mistakes that companies commit that contribute to project failure.Which is not one of these deadly mistakes?

A)No organizing schedule
B)No project plan
C)No budget tracking
D)No change management process
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
18
A project has each of the following characteristics except ________.

A)Clearly defined scope,deliverables,and results
B)An estimated budget that is subject to a high degree of uncertainty
C)Low risk with a high profit potential or benefits
D)An estimated time frame or schedule that is subject to a high degree of uncertainty
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
19
Except in extreme cases,the evaluation of success or failure is ________ because time and cost to complete the project are _________.

A)Subjective;estimates
B)Done by the project manager;fixed
C)Objective;inflexible
D)Done by the project team;set by them
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
20
The financial services sector has been compelled by strict international anti-money-laundering (AML)guidelines that require firms to _________.

A)know your customer
B)implement master data management
C)adhere to project portfolio management
D)demonstrate data consistency and accuracy
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
21
Monitoring and control processes should occur _________ while the project work is being executed.

A)weekly or bi-weekly
B)continuously and continually
C)monthly
D)at each milestone
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
22
The system development life cycle (SDLC)is the traditional system development method for ________.

A)Updating legacy systems
B)Low risk IT projects,such as sales support
C)Systems integration projects
D)Large IT projects,such as IT infrastructure or an enterprise system.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
23
Controls help to prevent ________,which refer to system development projects that are so far over budget and past deadline that they must be abandoned,typically with large monetary loss.

A)Deficient critical paths
B)runaway projects
C)scope creep
D)missed deadlines
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
24
Each task or activity has a start date and ________,which determines its finish date.

A)duration
B)resource requirements
C)milestone
D)critical path
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
25
Covert resistance to a new IS from employees may take the form of __________.

A)Sabotaging the new system by entering data incorrectly
B)Continuing to do their jobs using their old methods
C)Complaining about the new system for extended time
D)Resisting change and training
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
26
Once the new system's operations are stabilized,________ are performed during operation to assess the system's capabilities and determine if it is being used correctly.

A)Audits
B)Compliance analyses
C)Feasibility studies
D)Implementation tests
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
27
The __________ is the traditional systems development method used by organizations for large IT projects such as IT infrastructure.

A)Prototyping method
B)System development life cycle
C)Critical path method
D)Sourcing method
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
28
________ should not be considered in the decision to kill a project.

A)Completed deliverables
B)Project scope
C)Sunk costs
D)SOW
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
29
Which of the following issues about the SDLC methodology is false?

A)Requirements analysis is critical to the success of the project.
B)System development practitioners agree that the more time invested in analyzing the current system and understanding problems that are likely to occur during system development,the greater the probability that the IS will be a success
C)The requirements study determines the probability of success of the proposed project.
D)Testing verifies that apps,interfaces,data transfers,and so on,work correctly under all possible conditions.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
30
Project ________ depends on prompt and candid feedback from the project team,while ________ depends on systems and decision rules for managing variances between the project's scope,cost,and schedule.

A)Monitoring;control
B)Management;monitoring
C)Critical path;scope creep
D)Timeline;baseline
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
31
__________ conversion is the least expensive and highest risk IS conversion strategy because the old system is cut off and the new system is turned on at a certain point in time.

A)Parallel
B)Direct
C)Pilot
D)Phased
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
32
Closing out a project benefits the _________.

A)enterprise and people who worked on the project
B)completed project
C)client
D)completed project and enterprise
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
33
The first stage of the SDLC is __________ to understand the business problem or opportunity.

A)Systems analysis
B)Systems investigation
C)Prototyping
D)Systems design
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
34
During the system investigation stage,__________ studies are done to determine if the hardware,software,and communications components can be developed and/or acquired to solve the business problem.

A)Economic feasibility
B)Technical feasibility
C)ROI
D)NPV
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
35
________ are multipurpose visualization tools that show the timeline of the project schedule;and are used for planning,scheduling,and at-a-glance status reports.

A)Baselines
B)Gantt charts
C)Statements of work
D)Critical paths
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
36
Project management is a structured methodology to plan,manage,and control the completion of a project throughout its life cycle.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
37
System development life cycle involves processes that __________,which means that they are revised when new information or conditions make change the smart thing to do.

A)Are iterative
B)Are subject to infinite revisions
C)Have constraints
D)Are prototyped
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
38
During the systems investigation stage,__________ studies are done to assess the skills and the training needed to use the new system.

A)Economic feasibility
B)Technical feasibility
C)Organizational feasibility
D)Behavioral feasibility
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
39
Which is not a characteristic of system testing?

A)Testing verifies that apps,interfaces,data transfers,and so on,work correctly under all possible conditions.
B)The risk of costly lawsuits needs to be considered.
C)Improper testing is very risky.
D)Proper testing can be done quickly and with little effort and expense.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
40
Critical path is the ________ path of tasks through a project,as shown on a Gantt chart.

A)most complex
B)first
C)longest
D)shortest
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
41
Baseline is a specification of the project plan that has been formally reviewed and agreed upon.It can be updated or changed through casual or informal change control processes.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
42
Not using a best practices project management approach is the biggest IT project mistake a business can make.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
43
The DIA baggage-handling project represents practically every possible project management mistake.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
44
Projects are subject to unanticipated and uncontrollable events so they need to have slack built into the schedule and budget.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
45
After the project plan in the SOW is reviewed,a go or no-go decision is made;and if a go decision is made,the project is initiated.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
46
During project analysis,IT projects should be examined holistically-that is,in combination in order to identify investment synergies-using a project portfolio management approach.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
47
The major take-away from the triple constraint being represented as a triangle is that you cannot change one side without changing the other sides.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
48
Projects start with an idea that is explained in a business case.If the business case is accepted,a work breakdown structure (WBS)is prepared.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
49
A project is a well-planned sequential series of tasks to achieve a result;and have a defined beginning and end,a scope,resources,and a budget.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
50
The SOW is a legal contract used to document the agreement between parties after the business terms have been accepted and a go decision is made.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
51
The financial services sector has been compelled by strict international anti-money-laundering (AML)guidelines that require firms to know your customer (KYC).
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
52
During a project,the more involvement you have from users,the greater your chance of delay,conflict,and failure.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
53
Scope creep is the piling up of numerous small delays that by themselves may be manageable,but in aggregate are significant.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
54
The triple constraint refers to project scope,deliverables,and budget,which must be managed effectively for successful completion and closure of any project
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
55
On a Gantt chart,the start and finish dates of all tasks and milestones appear as bars whose length represent its cost.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
56
The baseline is used for monitoring and controlling.Any change to the baseline is a deviation,or variance,to the plan-and it needs to be documented.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
57
A responsibility matrix shows who has primary responsibility and who has support responsibility for the activities listed in the WBS.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
58
The SOW breaks a project down into the tasks or activities that must be performed,and in what order,to produce the deliverables at each milestone.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
59
Lack of milestones has been a contributing factor in many project failures.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
60
Project management software computes the cost of the project based on labor time (duration)of each task in the WBS and the cost of labor or other resource.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
61
Starting with an initial idea,the SDLC processes are requirements analysis,systems analysis and design,development and testing,implementation,and maintenance.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
62
Requirements analysis is critical to the success of the project.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
63
Technical feasibility addresses two primary questions: Do the benefits outweigh the costs of the project? Can the project be completed as scheduled?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
64
Integrated change control processes are always documented and saved in the event of project failure or lawsuits related to the failure.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
65
All projects have a critical path,which is the shortest path.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
66
Project control is also used to identify when to declare the ongoing project a failure and kill it
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
67
Monitoring and control processes are intended to occur weekly while the project work is being executed.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
68
Changes to a project tend to have a trickle-down effect because of task dependencies and shared resources.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
69
During project analysis,IT projects should be examined holistically-that is,in combination to identify investment synergies.This approach is known as ________ management.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
70
Critical tasks must finish on schedule because delays will delay the project unless something is done to compensate.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
71
________ is a presentation or document that outlines the justification for the start-up and funding of a project.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
72
Because scope creep is expensive,project managers impose controls on changes requested by users,which help to prevent runaway projects.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
73
Information system design projects are not susceptible to scope creep because of the rigorous SDLC methodology.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
74
The system development life cycle (SDLC)is the traditional system development method for large IT projects,such as IT infrastructure or an enterprise system.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
75
System testing verifies that apps,interfaces,data transfers,and so on,work correctly under standard or expected conditions.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
76
Management can assess economic feasibility by using cost-benefit analysis,ROI,NPV,and breakeven analysis.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
77
The money already spent on the project,or sunk costs,should be considered in the decision to kill a project that is out of control.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
78
Calculating economic feasibility in IT projects is straightforward because it is done using standard financial techniques--ROI,NPV,and breakeven analysis.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
79
The feasibility study is critically important to the system development process because,when done properly,the study can prevent companies from making expensive mistakes,such as creating systems that will not work,that will not work efficiently,or that people cannot or will not use.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 103 في هذه المجموعة.
فتح الحزمة
k this deck
80
Postproject reviews,or postmortems,identify the reasons the project was successful or not,strengths and weaknesses of the project plan,how problems were detected and resolved,and how the project was successful in spite of them.