Deck 2: Organization Strategy and Project Selection

ملء الشاشة (f)
exit full mode
سؤال
The assessment of the external and internal environments is called _______ analysis.

A)SWOT analysis
B)Competitive
C)Industry
D)Market
E)Strategic
استخدم زر المسافة أو
up arrow
down arrow
لقلب البطاقة.
سؤال
Which of the following is the correct order for the strategic management process?

A)Strategies, mission, goals, projects
B)Goals, projects, mission, strategies
C)Mission, goals, strategies, projects
D)Goals, mission, strategies, projects
E)Projects, mission, strategies, goals
سؤال
Which of the following is a main reason why project managers need to understand their organization's mission and strategy?

A)They can better focus on the immediate customer
B)They can make appropriate decisions and adjustments
C)So they can be effective project advocates
D)Both B and C are correct
E)A, B, and C are all correct
سؤال
Which of the following would not be classified as an organizational opportunity?

A)Increasing product demand
B)Excellent employees
C)Emerging markets
D)demographics
E)All of these are organizational opportunities
سؤال
Which of the follow is not one of the commonly heard comments of project managers?

A)Where did this project come from?
B)Why are we doing this project?
C)How can all these projects be first priority?
D)Why is this project so strongly linked to the strategic plan?
E)Where are we going to get the resources to do this project?
سؤال
The textbook indicated that ________ is the major dimension of strategic management.

A)Responding to changes in the external market
B)Allocating scarce resources of the organization
C)Beating competition to the market
D)Both a and b are correct
E)Both a and c are correct
سؤال
Which of the following is not one of the requirements for successful implementation of strategies through projects?

A)Allocation of resources
B)Prioritizing of projects
C)Motivation of project contributors
D)Adequate planning and control systems
E)All of these are requirements
سؤال
The intended outcome of strategy/projects integration is

A)Clear organization focus
B)Best use of scare organization resources
C)Improved communication across projects and departments
D)Both A and C are correct
E)A, B, and C are all correct
سؤال
Susie's department is implementing many projects.She finds herself starting and stopping work on one task to go and work on another task, and then return to the work on the original task.Susie is experiencing

A)Poor scheduling
B)Excess work burden
C)Flexible tasking
D)Multitasking
E)Burnout
سؤال
Which of the following is not one of the characteristics of effective objectives?

A)Realistic
B)Assignable
C)Flexible
D)Specific
E)Measurable
سؤال
Strategy formulation includes which of the following activities?

A)Determining alternatives
B)Creating profitability targets
C)Evaluating alternatives
D)Both a and c are correct
E)A, B, and C are all correct
سؤال
A critical factor to ensure the success of integrating the strategic plan with projects lies in a process that

A)Is open and published for all participants to review
B)Starts with top management's directives
C)With projects first and integrates them with the strategic plan
D)Both B and C are correct
E)A, B, and C are all correct
سؤال
Which of the following is not one of the traditional components found in mission statements?

A)Major products and services
B)Profitability
C)Target customers and markets
D)Geographic domain
E)Contribution to society
سؤال
Which of the following terms is often used to denote a project that a powerful, high-ranking official is advocating?

A)Sacred cow
B)Pet project
C)Political necessity
D)Special undertaking
E)Strategic ploy
سؤال
Strategy considered to be under purview of senior management is

A)Old school thinking
B)A new school of management thought
C)Necessary in a company structure
D)Beneficial to the Project Manager
E)Depended on company goals
سؤال
Which of the following is not true for strategic management?

A)It should be done once each year just before developing the operating plan
B)It supports consistency of action at every level of the organization
C)It develops an integrated and coordinated long-term plan of action
D)It positions the firm to meet the needs of its customers
E)All of these are true statements
سؤال
In today's business environment, project managers find it valuable to have a keen understanding of

A)Strategic management
B)Technical issues
C)Project selection process
D)Both A and C are correct
E)A, B, and C are all correct
سؤال
Which of the following questions does the organization's mission statement answer?

A)What are our long-term strategies?
B)What are our long-term goals and objectives?
C)How do we operate in the existing environment?
D)What do we want to become?
E)All of these are answered by the mission statement
سؤال
Which of the following would not be classified as an organizational threat?

A)Slowing of the economy
B)A maturing life cycle
C)Poor product quality
D)Government regulations
E)All of these are organizational threats
سؤال
Project managers who do not understand the role that their project plays in accomplishing the organization's strategy tend to make all the following mistakes except:

A)Focusing on low priority problems
B)Overemphasizing technology as an end in and of itself
C)Focusing on the immediate customer
D)Trying to solve every customer issue
E)All the above are likely mistakes
سؤال
Successful ________ requires strong links among mission statements, goals, objectives, and strategies.
سؤال
Which of the following is a common multicriteria selection model?

A)Checklist
B)Net Present Value
C)Weighted criteria model
D)Both A and C are correct
E)All of these are common multicriteria selection models
سؤال
Which of the following is the reason(s) why project managers need to understand their organization's mission and strategy?

A)To make appropriate decisions and adjustments
B)To be effective project advocates
C)To be able to get their job done
D)Both A and B are correct
E)A, B, and C are all correct
سؤال
Projects are usually classified into all but one of the following categories.Which one is not one of the typical classifications?

A)Compliance and emergency
B)Operational
C)Strategic
D)Political necessity
E)All of these are typical classifications
سؤال
________ change infrequently and may require revision only when the nature of the business changes or shifts.
سؤال
Which of the following is not one of the classifications for assessing a project portfolio?

A)Sacred cow
B)Bread-and-butter
C)Pearls
D)Oysters
E)White elephants
سؤال
In the Snapshot from Practice, Intel's CEO has concentrated Intel's strategy toward?

A)Creating chips to support the digital device market
B)Eliminating AMD as a competitor
C)Strengthening Intel's position in the PC market
D)Expanding Intel's international market
E)Expand efforts in the mainframe computer market
سؤال
Which of the following is not true of multi-weighted scoring models?

A)Will include quantitative criteria
B)Will include qualitative criteria
C)Each criterion is assigned a weight
D)Projects with higher scores are considered more desirable
E)All of the above are true
سؤال
In a SWOT analysis, strong competition, reduced product demand, and a maturing product life cycle are examples of ________.
سؤال
A major project proposal form will likely include all of the following except:

A)Project Classification
B)Schedule objective
C)Major deliverables of the project
D)How success will be measured
E)All of these are likely to be included
سؤال
________ answers the question of how strategies will be realized, given available resources.
سؤال
The __________ identifies what the organization wants to become and the scope of the firm in terms of its product or service.
سؤال
Project ________ are typically high-ranking managers who endorse and lend political support for the completion of a specific project.
سؤال
________ translate the organization's mission statement into specific, concrete, and measurable terms.
سؤال
In a SWOT analysis, good product quality, low debt, and an established dealer network are examples of positive ________.
سؤال
A weighted scoring model such as _________ typically uses several weighted selection criteria to evaluate project proposals.
سؤال
Project selection criteria are typically classified as:

A)Financial and non-financial
B)Short-term and long-term
C)Strategic and tactical
D)Required and optional
E)Cost and schedule
سؤال
A project screening matrix typically contains all of the following except:

A)The list of available projects
B)Specific criteria
C)Weights assigned to specific criteria
D)Costs to complete each project
E)All of the above are typically contained
سؤال
The assessment of the internal and external environments is known as a ________.
سؤال
Which of the following financial models are typically included in project selection?

A)Payback
B)Net present value
C)Internal rate of return
D)Both A and B are correct
E)A, B, and C are all correct
سؤال
Organizational objectives set targets for all levels of the organization not just for top management.
سؤال
In classifying the kinds of projects an organization has in its portfolio, ________ projects are typically those that directly support the organization's long run mission.
سؤال
Formulating strategy answers the questions who and when the tasks will be performed to reach objectives.
سؤال
A written mission statement provides focus for decision making when shared by organizational managers and employees.
سؤال
Capacity overload which inevitably leads to confusion and inefficient use of scarce resources is an __________.
سؤال
The ________ financial model measures the current value of all cash inflows and outflows using management's minimum desired rate of return.
سؤال
The problem in many organizations is not with formulating strategies but with implementing the strategies.
سؤال
Project Management historically has been preoccupied solely with the planning and execution of projects while strategy was under the purview of senior management.
سؤال
Xerox's ALTO computer and the Ford Mustang are examples of the significance that ________ can play in project management.
سؤال
Strategy formulation ends with cascading objectives or projects assigned to lower divisions, departments, or individuals.
سؤال
Effective objectives can be created to apply only at the department level and not relating to organizational objectives.
سؤال
Apple Computers has been successful in developing a turnaround strategy that has developed new markets and increased market share.This began with strict adherence to the ________.
سؤال
A ___________ will typically include a list of potential projects, several criteria, weights for those criteria, and criteria scores for those projects.
سؤال
In classifying the kinds of projects an organization has in its portfolio, ________ projects are typically those needed to meet regulatory conditions required to operate in a region.
سؤال
The term ________ is often used to denote a project that a powerful, high-ranking official is advocating.
سؤال
Using the Project Portfolio Matrix, software upgrades and manufacturing cost reduction projects are examples of ________ projects that involve evolutionary improvements to existing products.
سؤال
The most common approach to selecting project has been to use the __________ model.
سؤال
In classifying the kinds of projects an organization has in its portfolio, ________ projects are typically those needed to support current operations.
سؤال
In some cases organizations will use a __________ to solicit ideas for projects when the knowledge requirements for the project are not available in the organization.
سؤال
The _______ financial model measures the time it will take to recover the project investment.
سؤال
One way to offset the influence of politics on project management within an organization is to have a well-defined project selection model.
سؤال
The first step in the Strategic Management Process is to set long-range goals and objectives.
سؤال
Reviewing and revising the organization's mission is best achieve through the use of a SWOT analysis.
سؤال
Lee Iacocca's career was built on successfully leading the design and development of the highly successful Ford Mustang.
سؤال
Many organizations find they have three different kinds of projects in their portfolio, compliance, operational, and sacred cows.
سؤال
Opportunities and threats are the flip sides of each other; that is, a threat can be viewed as an opportunity, and vice versa.
سؤال
What is strategic management?
سؤال
It is necessary to have exactly the same strategic and operations criteria for different projects
سؤال
Generally, people working on several projects at the same time are more efficient than having several people working part-time on the same projects.
سؤال
The typical Strategic Management Process includes four activities.Identify and briefly describe each of those four activities.
سؤال
Identify and briefly discuss the three intended outcomes of integrating and linking projects with the strategic plan.
سؤال
"Politics and project management should not mix." Agree or Disagree and support your position.
سؤال
Identify and briefly describe the four components of strategic management and why they must be strongly linked.
سؤال
Intel's CEO, Craig R.Barrett, is envisioning Intel's future as being beyond computers and to include all digital products as Intel's potential customers.
سؤال
Multi-weighted scoring models include only quantitative criteria, not qualitative.
سؤال
The information gap refers to the lack of understanding and consensus of organization strategy among top and middle-level managers.
سؤال
The NPV financial model measures the time it will take to recover the project investment.
سؤال
If a proposed project does not meet one of the designated "must" objectives it is immediately removed from consideration.
سؤال
Using the Project Portfolio Matrix, revolutionary commercial advances using proven technical advances are classified as Oyster projects.
سؤال
The two axes of the Project Portfolio Matrix are technical feasibility and commercial potential.
فتح الحزمة
قم بالتسجيل لفتح البطاقات في هذه المجموعة!
Unlock Deck
Unlock Deck
1/88
auto play flashcards
العب
simple tutorial
ملء الشاشة (f)
exit full mode
Deck 2: Organization Strategy and Project Selection
1
The assessment of the external and internal environments is called _______ analysis.

A)SWOT analysis
B)Competitive
C)Industry
D)Market
E)Strategic
A
Explanation: The keys are to attempt to forecast fundamental industry changes and stay in a proactive mode rather than a reactive one.This assessment of the external and internal environments is known as the SWOT analysis (strengths, weaknesses, opportunities, and threats).
2
Which of the following is the correct order for the strategic management process?

A)Strategies, mission, goals, projects
B)Goals, projects, mission, strategies
C)Mission, goals, strategies, projects
D)Goals, mission, strategies, projects
E)Projects, mission, strategies, goals
C
3
Which of the following is a main reason why project managers need to understand their organization's mission and strategy?

A)They can better focus on the immediate customer
B)They can make appropriate decisions and adjustments
C)So they can be effective project advocates
D)Both B and C are correct
E)A, B, and C are all correct
D
Explanation: There are two main reasons why project managers need to understand their organization's mission and strategy.The first reason is so they can make appropriate decisions and adjustments.For example, how a project manager would respond to a suggestion to modify the design of a product to enhance performance will vary depending upon whether his company strives to be a product leader through innovation or to achieve operational excellence through low cost solutions.The second reason project managers need to understand their organization's strategy is so that they can be effective project advocates.Project managers have to be able to demonstrate to senior management how their project contributes to their firm's mission.
4
Which of the following would not be classified as an organizational opportunity?

A)Increasing product demand
B)Excellent employees
C)Emerging markets
D)demographics
E)All of these are organizational opportunities
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
5
Which of the follow is not one of the commonly heard comments of project managers?

A)Where did this project come from?
B)Why are we doing this project?
C)How can all these projects be first priority?
D)Why is this project so strongly linked to the strategic plan?
E)Where are we going to get the resources to do this project?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
6
The textbook indicated that ________ is the major dimension of strategic management.

A)Responding to changes in the external market
B)Allocating scarce resources of the organization
C)Beating competition to the market
D)Both a and b are correct
E)Both a and c are correct
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
7
Which of the following is not one of the requirements for successful implementation of strategies through projects?

A)Allocation of resources
B)Prioritizing of projects
C)Motivation of project contributors
D)Adequate planning and control systems
E)All of these are requirements
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
8
The intended outcome of strategy/projects integration is

A)Clear organization focus
B)Best use of scare organization resources
C)Improved communication across projects and departments
D)Both A and C are correct
E)A, B, and C are all correct
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
9
Susie's department is implementing many projects.She finds herself starting and stopping work on one task to go and work on another task, and then return to the work on the original task.Susie is experiencing

A)Poor scheduling
B)Excess work burden
C)Flexible tasking
D)Multitasking
E)Burnout
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
10
Which of the following is not one of the characteristics of effective objectives?

A)Realistic
B)Assignable
C)Flexible
D)Specific
E)Measurable
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
11
Strategy formulation includes which of the following activities?

A)Determining alternatives
B)Creating profitability targets
C)Evaluating alternatives
D)Both a and c are correct
E)A, B, and C are all correct
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
12
A critical factor to ensure the success of integrating the strategic plan with projects lies in a process that

A)Is open and published for all participants to review
B)Starts with top management's directives
C)With projects first and integrates them with the strategic plan
D)Both B and C are correct
E)A, B, and C are all correct
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
13
Which of the following is not one of the traditional components found in mission statements?

A)Major products and services
B)Profitability
C)Target customers and markets
D)Geographic domain
E)Contribution to society
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
14
Which of the following terms is often used to denote a project that a powerful, high-ranking official is advocating?

A)Sacred cow
B)Pet project
C)Political necessity
D)Special undertaking
E)Strategic ploy
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
15
Strategy considered to be under purview of senior management is

A)Old school thinking
B)A new school of management thought
C)Necessary in a company structure
D)Beneficial to the Project Manager
E)Depended on company goals
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
16
Which of the following is not true for strategic management?

A)It should be done once each year just before developing the operating plan
B)It supports consistency of action at every level of the organization
C)It develops an integrated and coordinated long-term plan of action
D)It positions the firm to meet the needs of its customers
E)All of these are true statements
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
17
In today's business environment, project managers find it valuable to have a keen understanding of

A)Strategic management
B)Technical issues
C)Project selection process
D)Both A and C are correct
E)A, B, and C are all correct
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
18
Which of the following questions does the organization's mission statement answer?

A)What are our long-term strategies?
B)What are our long-term goals and objectives?
C)How do we operate in the existing environment?
D)What do we want to become?
E)All of these are answered by the mission statement
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
19
Which of the following would not be classified as an organizational threat?

A)Slowing of the economy
B)A maturing life cycle
C)Poor product quality
D)Government regulations
E)All of these are organizational threats
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
20
Project managers who do not understand the role that their project plays in accomplishing the organization's strategy tend to make all the following mistakes except:

A)Focusing on low priority problems
B)Overemphasizing technology as an end in and of itself
C)Focusing on the immediate customer
D)Trying to solve every customer issue
E)All the above are likely mistakes
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
21
Successful ________ requires strong links among mission statements, goals, objectives, and strategies.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
22
Which of the following is a common multicriteria selection model?

A)Checklist
B)Net Present Value
C)Weighted criteria model
D)Both A and C are correct
E)All of these are common multicriteria selection models
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
23
Which of the following is the reason(s) why project managers need to understand their organization's mission and strategy?

A)To make appropriate decisions and adjustments
B)To be effective project advocates
C)To be able to get their job done
D)Both A and B are correct
E)A, B, and C are all correct
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
24
Projects are usually classified into all but one of the following categories.Which one is not one of the typical classifications?

A)Compliance and emergency
B)Operational
C)Strategic
D)Political necessity
E)All of these are typical classifications
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
25
________ change infrequently and may require revision only when the nature of the business changes or shifts.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
26
Which of the following is not one of the classifications for assessing a project portfolio?

A)Sacred cow
B)Bread-and-butter
C)Pearls
D)Oysters
E)White elephants
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
27
In the Snapshot from Practice, Intel's CEO has concentrated Intel's strategy toward?

A)Creating chips to support the digital device market
B)Eliminating AMD as a competitor
C)Strengthening Intel's position in the PC market
D)Expanding Intel's international market
E)Expand efforts in the mainframe computer market
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
28
Which of the following is not true of multi-weighted scoring models?

A)Will include quantitative criteria
B)Will include qualitative criteria
C)Each criterion is assigned a weight
D)Projects with higher scores are considered more desirable
E)All of the above are true
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
29
In a SWOT analysis, strong competition, reduced product demand, and a maturing product life cycle are examples of ________.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
30
A major project proposal form will likely include all of the following except:

A)Project Classification
B)Schedule objective
C)Major deliverables of the project
D)How success will be measured
E)All of these are likely to be included
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
31
________ answers the question of how strategies will be realized, given available resources.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
32
The __________ identifies what the organization wants to become and the scope of the firm in terms of its product or service.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
33
Project ________ are typically high-ranking managers who endorse and lend political support for the completion of a specific project.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
34
________ translate the organization's mission statement into specific, concrete, and measurable terms.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
35
In a SWOT analysis, good product quality, low debt, and an established dealer network are examples of positive ________.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
36
A weighted scoring model such as _________ typically uses several weighted selection criteria to evaluate project proposals.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
37
Project selection criteria are typically classified as:

A)Financial and non-financial
B)Short-term and long-term
C)Strategic and tactical
D)Required and optional
E)Cost and schedule
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
38
A project screening matrix typically contains all of the following except:

A)The list of available projects
B)Specific criteria
C)Weights assigned to specific criteria
D)Costs to complete each project
E)All of the above are typically contained
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
39
The assessment of the internal and external environments is known as a ________.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
40
Which of the following financial models are typically included in project selection?

A)Payback
B)Net present value
C)Internal rate of return
D)Both A and B are correct
E)A, B, and C are all correct
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
41
Organizational objectives set targets for all levels of the organization not just for top management.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
42
In classifying the kinds of projects an organization has in its portfolio, ________ projects are typically those that directly support the organization's long run mission.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
43
Formulating strategy answers the questions who and when the tasks will be performed to reach objectives.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
44
A written mission statement provides focus for decision making when shared by organizational managers and employees.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
45
Capacity overload which inevitably leads to confusion and inefficient use of scarce resources is an __________.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
46
The ________ financial model measures the current value of all cash inflows and outflows using management's minimum desired rate of return.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
47
The problem in many organizations is not with formulating strategies but with implementing the strategies.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
48
Project Management historically has been preoccupied solely with the planning and execution of projects while strategy was under the purview of senior management.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
49
Xerox's ALTO computer and the Ford Mustang are examples of the significance that ________ can play in project management.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
50
Strategy formulation ends with cascading objectives or projects assigned to lower divisions, departments, or individuals.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
51
Effective objectives can be created to apply only at the department level and not relating to organizational objectives.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
52
Apple Computers has been successful in developing a turnaround strategy that has developed new markets and increased market share.This began with strict adherence to the ________.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
53
A ___________ will typically include a list of potential projects, several criteria, weights for those criteria, and criteria scores for those projects.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
54
In classifying the kinds of projects an organization has in its portfolio, ________ projects are typically those needed to meet regulatory conditions required to operate in a region.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
55
The term ________ is often used to denote a project that a powerful, high-ranking official is advocating.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
56
Using the Project Portfolio Matrix, software upgrades and manufacturing cost reduction projects are examples of ________ projects that involve evolutionary improvements to existing products.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
57
The most common approach to selecting project has been to use the __________ model.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
58
In classifying the kinds of projects an organization has in its portfolio, ________ projects are typically those needed to support current operations.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
59
In some cases organizations will use a __________ to solicit ideas for projects when the knowledge requirements for the project are not available in the organization.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
60
The _______ financial model measures the time it will take to recover the project investment.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
61
One way to offset the influence of politics on project management within an organization is to have a well-defined project selection model.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
62
The first step in the Strategic Management Process is to set long-range goals and objectives.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
63
Reviewing and revising the organization's mission is best achieve through the use of a SWOT analysis.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
64
Lee Iacocca's career was built on successfully leading the design and development of the highly successful Ford Mustang.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
65
Many organizations find they have three different kinds of projects in their portfolio, compliance, operational, and sacred cows.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
66
Opportunities and threats are the flip sides of each other; that is, a threat can be viewed as an opportunity, and vice versa.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
67
What is strategic management?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
68
It is necessary to have exactly the same strategic and operations criteria for different projects
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
69
Generally, people working on several projects at the same time are more efficient than having several people working part-time on the same projects.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
70
The typical Strategic Management Process includes four activities.Identify and briefly describe each of those four activities.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
71
Identify and briefly discuss the three intended outcomes of integrating and linking projects with the strategic plan.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
72
"Politics and project management should not mix." Agree or Disagree and support your position.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
73
Identify and briefly describe the four components of strategic management and why they must be strongly linked.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
74
Intel's CEO, Craig R.Barrett, is envisioning Intel's future as being beyond computers and to include all digital products as Intel's potential customers.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
75
Multi-weighted scoring models include only quantitative criteria, not qualitative.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
76
The information gap refers to the lack of understanding and consensus of organization strategy among top and middle-level managers.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
77
The NPV financial model measures the time it will take to recover the project investment.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
78
If a proposed project does not meet one of the designated "must" objectives it is immediately removed from consideration.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
79
Using the Project Portfolio Matrix, revolutionary commercial advances using proven technical advances are classified as Oyster projects.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
80
The two axes of the Project Portfolio Matrix are technical feasibility and commercial potential.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.
فتح الحزمة
k this deck
locked card icon
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 88 في هذه المجموعة.