A master production schedule shows the following information: <strong>A master production schedule shows the following information:   Using a lot-for-lot rule, what is the MSP quantity for week 4?</strong> A)500 B)400 C)450 D)50 <div style=padding-top: 35px> Using a lot-for-lot rule, what is the MSP quantity for week 4?

A)500
B)400
C)450
D)50
استخدم زر المسافة أو
up arrow
down arrow
لقلب البطاقة.
سؤال
End item A is made by assembling 2 of part B and 3 of part C.Part C is made from 2 of component D and 2 of component E.Component D is considered to be a:

A)Level 0.
B)Level 1 input.
C)Level 2 input.
D)Level 3 input.
سؤال
If the cumulative lead time is 8 weeks, to be feasible the MPS planning horizon must be:

A)Exactly 8 weeks.
B)At least 8 weeks.
C)Less than 8 weeks.
D)At least 16 weeks.
سؤال
Materials requirement planning (MRP) systems are used primarily to:

A)Plan orders.
B)Plan lead time.
C)Plan amounts of end items to produce.
D)Plan distribution.
سؤال
The positioning and replenishment of finished goods inventories at the retail level can be determined using:

A)MRP.
B)CRP.
C)DRP.
D)RFID.
سؤال
Jones Company uses widgets as component parts.In a particular week it has gross requirements for 250 units of widgets, beginning inventory of 50 widgets, and scheduled receipts of 350 widgets.Available inventory for the next period is:

A)650.
B)50.
C)250.
D)150.
سؤال
Significant changes in an MPS quantity several weeks into the planning horizon can:

A)Make the MRP more accurate.
B)Cause inconsistencies in the MRP.
C)Reduce stockouts.
D)Increase safety stock.
سؤال
Constant changing of the master schedule and the resulting changes in the requirements for components is referred to as:

A)Master schedule dynamics.
B)System nervousness.
C)Bad planning.
D)MRP failure.
سؤال
Planning for which of the following products would see the LEAST benefit from the use of an MRP system?

A)Microwave ovens
B)Mobile phones
C)Shampoo
D)Power lawnmowers
سؤال
MRP is a process that would be most applicable in which situation?

A)Planning requirements for repair parts for production equipment in a manufacturing plant.
B)Planning requirements for safety stocks of finished goods in a distribution center.
C)Planning requirements for bicycle seats in a bicycle production plant.
D)None of these.
سؤال
A master production schedule shows the following information: <strong>A master production schedule shows the following information:   What is the available to promise for period 2?</strong> A)0. B)-20. C)20. D)None of these. <div style=padding-top: 35px> What is the available to promise for period 2?

A)0.
B)-20.
C)20.
D)None of these.
سؤال
A bill-of-materials file contains:

A)Invoices for materials that must be paid in this period.
B)Lists of materials required to produce end item products.
C)Accounts payable for materials.
D)None of these.
سؤال
A master production schedule shows the following information: <strong>A master production schedule shows the following information:   Using a lot-for-lot rule, what is the MPS quantity for period 1?</strong> A)90 B)80 C)100 D)40 <div style=padding-top: 35px> Using a lot-for-lot rule, what is the MPS quantity for period 1?

A)90
B)80
C)100
D)40
سؤال
Using the BOM, if 2 units of A are needed, how many used of K will be required? Assume that there is no on-hand inventory of any items. <strong>Using the BOM, if 2 units of A are needed, how many used of K will be required? Assume that there is no on-hand inventory of any items.  </strong> A)16 B)34 C)52 D)104 <div style=padding-top: 35px>

A)16
B)34
C)52
D)104
سؤال
The quantities of end items to be completed in each time period into the future is shown in a(n):

A)MRP.
B)MPS.
C)BOM.
D)ERP.
سؤال
An MRP record for a motor is shown in the following table. <strong>An MRP record for a motor is shown in the following table.   What is the planned order release for week 4?</strong> A)0 B)10,000 C)8,000 D)6,000 <div style=padding-top: 35px> What is the planned order release for week 4?

A)0
B)10,000
C)8,000
D)6,000
سؤال
Which of the following is NOT an input into the MRP?

A)Bill of materials
B)Inventory records file
C)Master production schedule
D)Planned order release
سؤال
Which of the following is NOT included in the information about the inventory records file for an item?

A)Safety stock
B)Preferred order quantity
C)Net requirements
D)Lead time
سؤال
A master production schedule shows the following information: <strong>A master production schedule shows the following information:   Based on the information in the MPS, what is the amount that is available to promise in week 4?</strong> A)1,200 B)700 C)500 D)1,500 <div style=padding-top: 35px> Based on the information in the MPS, what is the amount that is available to promise in week 4?

A)1,200
B)700
C)500
D)1,500
سؤال
The longest lead time path in the BOM is the:

A)Time bucket.
B)Planning horizon.
C)Time window.
D)Cumulative lead time.
سؤال
All of the following are outputs from an MRP system EXCEPT:

A)Order releases.
B)Change orders.
C)Forecasts.
D)Exception reports.
سؤال
Which of the following would benefit the most from MRP:

A)Gasoline production.
B)Building of a new bridge.
C)Production of vacuum cleaners.
D)Production of aluminum soft drink cans
سؤال
Capacity requirements planning does all of the following EXCEPT:

A)Determines if a work center has the capacity to implement the MRP plan.
B)Uses planned order releases and scheduled receipts to estimate work center loads.
C)Develops a load profile.
D)Recalculates the MRP plan.
سؤال
Zanda Company is looking for a requirements planning system to help plan replenishment of its finished goods throughout its network of distribution centers.The type of system Zanda should consider is known as:

A)CRP.
B)DRP.
C)MRP.
D)ERP.
سؤال
Which of the following is NOT an input to an MRP system?

A)Order releases.
B)Actual orders.
C)Inventory receipts.
D)Bill of materials.
سؤال
Benefits of ERP systems include all of the following EXCEPT:

A)Easy implementation.
B)Fewer data entry errors.
C)More informed business decisions.
D)Improved customer service.
سؤال
The following table shows capacity requirements data for making Blodgetts. <strong>The following table shows capacity requirements data for making Blodgetts.   A load profile would show:</strong> A)Load above capacity in periods 3 and 5. B)Load below capacity in periods 1 and 3. C)Load is exactly equal to capacity in period 5. D)None of these. <div style=padding-top: 35px> A load profile would show:

A)Load above capacity in periods 3 and 5.
B)Load below capacity in periods 1 and 3.
C)Load is exactly equal to capacity in period 5.
D)None of these.
سؤال
An MPS shows:

A)The number of each type of part that is needed to make the final product.
B)The change orders that are required.
C)The quantities of end items to be completed in each time period.
D)The scheduled releases for all parts and components.
سؤال
If the planning horizon is 12 weeks, the cumulative lead time must be:

A)Greater than 12 weeks.
B)Exactly equal to 12 weeks.
C)Greater than 6 weeks.
D)Less than or equal to 12 weeks.
سؤال
Software that consolidates all of the business planning systems and data throughout an organization is:

A)MPS.
B)MRP.
C)DRP.
D)ERP.
سؤال
A detailed description of an "end item" along with a list of all of its raw materials, parts, and subassemblies is shown in a:

A)MPS
B)Planning horizon.
C)BOM.
D)DRP.
سؤال
A master production schedule shows the beginning inventory is 200 units, the forecast is 600 units and the actual customer orders is 500 units.Using a lot-for-lot rule, what is the MPS quantity for period 1?

A)400
B)300
C)600
D)500
سؤال
A master production schedule shows the beginning inventory is 100 units, the forecast is 250 units and actual customer orders are 400 units.Using a lot-for-lot rule, what is the MPS quantity for period 1?

A)150
B)250
C)300
D)400
سؤال
A master production schedule shows the beginning inventory is 50 units, the forecast is 200 units and actual customer orders are 220 units.What is the quantity that is available to promise in period 1?

A)50
B)150
C)170
D)0
سؤال
The entire time period covered by the MPS is the:

A)Time bucket.
B)Cumulative lead time.
C)Planning horizon.
D)Production schedule.
سؤال
The primary purpose of an MRP system is to:

A)Develop forecasts.
B)Plan transportation and deliveries.
C)Schedule personnel.
D)Match supply and demand
سؤال
A master production schedule shows the beginning inventory is 50 units, the forecast is 80 unitsand actual customer orders are 70 units.Using a lot-for-lot rule, what is the MPS quantity for period 1?

A)30
B)80
C)70
D)20
سؤال
The following table shows capacity requirements data for making table tops. <strong>The following table shows capacity requirements data for making table tops.   Which of the following is TRUE?</strong> A)Overtime is needed in day 1. B)Capacity exactly meets demand in day 5. C)All of the excess demand in days 4 and 5 can be shifted to day 3. D)New machines are needed. <div style=padding-top: 35px> Which of the following is TRUE?

A)Overtime is needed in day 1.
B)Capacity exactly meets demand in day 5.
C)All of the excess demand in days 4 and 5 can be shifted to day 3.
D)New machines are needed.
سؤال
A master production schedule shows the beginning inventory is 40 units, the forecast is 100 units and actual customer orders are 80 units.What is the quantity that is available to promise in period 1?

A)40
B)80
C)100
D)60
سؤال
Advanced planning and scheduling systems:

A)Use a simpler logic than the logic used in MRP.
B)Consolidate all business planning systems and data throughout an organization.
C)Integrate materials and capacity planning into one system.
D)All of these.
سؤال
An end item A is made by assembling 4 of component B and 1 of component C.Component B is made from 2 of part D and 4 of part E.Within the bill of materials, component B is considered to be

A)Level 0.
B)Level 1.
C)Level 2.
سؤال
A company has decided to outsource the production of key components for its main product to suppliers.What affect will this have on the product's bill of materials?

A)None.
B)The bill of materials will be wider.
C)The bill of materials will be deeper.
D)The bill of materials will be flatter.
سؤال
Demand-driven MRP:

A)Compares materials and capacity requirements within a single firm.
B)Extends planning across the supply chain.
C)Focuses on distribution planning.
D)Is also called advanced planning and scheduling
سؤال
An MRP Schedule is as follows.What are the net requirements in Week 2? <strong>An MRP Schedule is as follows.What are the net requirements in Week 2?  </strong> A)0. B)20 units. C)30 units. D)50 units. <div style=padding-top: 35px>

A)0.
B)20 units.
C)30 units.
D)50 units.
سؤال
The available capacity of a worker, machine, work center or facility during a specific period of time is compared against the capacity needed for a specific work schedule in a:

A)Load profile.
B)Capacity profile.
C)Infinite load
D)DRP
سؤال
The planned order releases in week 5 are 100 units.Each unit must be processed for 5 minutes at the work station.If the available capacity at the work station is one hour:

A)Overtime will be needed.
B)Delivery lead times should be increased.
C)The work station is underloaded.
D)An order backlog will be created
سؤال
Distribution requirements planning:

A)Uses logic that starts at the manufacturing plant and works forward toward the customer.
B)Includes only firm orders in its calculations.
C)Uses logic similar to MRP, beginning at the point closes to the customer.
D)Is normally not included as a module in ERP software.
سؤال
Which of the following information is NOT contained in a MRP secondary report?

A)Cost.
B)Inventory levels.
C)Schedule attainment.
D)Planned order releases.
فتح الحزمة
قم بالتسجيل لفتح البطاقات في هذه المجموعة!
Unlock Deck
Unlock Deck
1/48
auto play flashcards
العب
simple tutorial
ملء الشاشة (f)
exit full mode
Deck 13: Sales and Operations Planning
1
A master production schedule shows the following information: <strong>A master production schedule shows the following information:   Using a lot-for-lot rule, what is the MSP quantity for week 4?</strong> A)500 B)400 C)450 D)50 Using a lot-for-lot rule, what is the MSP quantity for week 4?

A)500
B)400
C)450
D)50
500
2
End item A is made by assembling 2 of part B and 3 of part C.Part C is made from 2 of component D and 2 of component E.Component D is considered to be a:

A)Level 0.
B)Level 1 input.
C)Level 2 input.
D)Level 3 input.
Level 2 input.
3
If the cumulative lead time is 8 weeks, to be feasible the MPS planning horizon must be:

A)Exactly 8 weeks.
B)At least 8 weeks.
C)Less than 8 weeks.
D)At least 16 weeks.
At least 8 weeks.
4
Materials requirement planning (MRP) systems are used primarily to:

A)Plan orders.
B)Plan lead time.
C)Plan amounts of end items to produce.
D)Plan distribution.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
5
The positioning and replenishment of finished goods inventories at the retail level can be determined using:

A)MRP.
B)CRP.
C)DRP.
D)RFID.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
6
Jones Company uses widgets as component parts.In a particular week it has gross requirements for 250 units of widgets, beginning inventory of 50 widgets, and scheduled receipts of 350 widgets.Available inventory for the next period is:

A)650.
B)50.
C)250.
D)150.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
7
Significant changes in an MPS quantity several weeks into the planning horizon can:

A)Make the MRP more accurate.
B)Cause inconsistencies in the MRP.
C)Reduce stockouts.
D)Increase safety stock.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
8
Constant changing of the master schedule and the resulting changes in the requirements for components is referred to as:

A)Master schedule dynamics.
B)System nervousness.
C)Bad planning.
D)MRP failure.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
9
Planning for which of the following products would see the LEAST benefit from the use of an MRP system?

A)Microwave ovens
B)Mobile phones
C)Shampoo
D)Power lawnmowers
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
10
MRP is a process that would be most applicable in which situation?

A)Planning requirements for repair parts for production equipment in a manufacturing plant.
B)Planning requirements for safety stocks of finished goods in a distribution center.
C)Planning requirements for bicycle seats in a bicycle production plant.
D)None of these.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
11
A master production schedule shows the following information: <strong>A master production schedule shows the following information:   What is the available to promise for period 2?</strong> A)0. B)-20. C)20. D)None of these. What is the available to promise for period 2?

A)0.
B)-20.
C)20.
D)None of these.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
12
A bill-of-materials file contains:

A)Invoices for materials that must be paid in this period.
B)Lists of materials required to produce end item products.
C)Accounts payable for materials.
D)None of these.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
13
A master production schedule shows the following information: <strong>A master production schedule shows the following information:   Using a lot-for-lot rule, what is the MPS quantity for period 1?</strong> A)90 B)80 C)100 D)40 Using a lot-for-lot rule, what is the MPS quantity for period 1?

A)90
B)80
C)100
D)40
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
14
Using the BOM, if 2 units of A are needed, how many used of K will be required? Assume that there is no on-hand inventory of any items. <strong>Using the BOM, if 2 units of A are needed, how many used of K will be required? Assume that there is no on-hand inventory of any items.  </strong> A)16 B)34 C)52 D)104

A)16
B)34
C)52
D)104
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
15
The quantities of end items to be completed in each time period into the future is shown in a(n):

A)MRP.
B)MPS.
C)BOM.
D)ERP.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
16
An MRP record for a motor is shown in the following table. <strong>An MRP record for a motor is shown in the following table.   What is the planned order release for week 4?</strong> A)0 B)10,000 C)8,000 D)6,000 What is the planned order release for week 4?

A)0
B)10,000
C)8,000
D)6,000
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
17
Which of the following is NOT an input into the MRP?

A)Bill of materials
B)Inventory records file
C)Master production schedule
D)Planned order release
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
18
Which of the following is NOT included in the information about the inventory records file for an item?

A)Safety stock
B)Preferred order quantity
C)Net requirements
D)Lead time
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
19
A master production schedule shows the following information: <strong>A master production schedule shows the following information:   Based on the information in the MPS, what is the amount that is available to promise in week 4?</strong> A)1,200 B)700 C)500 D)1,500 Based on the information in the MPS, what is the amount that is available to promise in week 4?

A)1,200
B)700
C)500
D)1,500
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
20
The longest lead time path in the BOM is the:

A)Time bucket.
B)Planning horizon.
C)Time window.
D)Cumulative lead time.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
21
All of the following are outputs from an MRP system EXCEPT:

A)Order releases.
B)Change orders.
C)Forecasts.
D)Exception reports.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
22
Which of the following would benefit the most from MRP:

A)Gasoline production.
B)Building of a new bridge.
C)Production of vacuum cleaners.
D)Production of aluminum soft drink cans
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
23
Capacity requirements planning does all of the following EXCEPT:

A)Determines if a work center has the capacity to implement the MRP plan.
B)Uses planned order releases and scheduled receipts to estimate work center loads.
C)Develops a load profile.
D)Recalculates the MRP plan.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
24
Zanda Company is looking for a requirements planning system to help plan replenishment of its finished goods throughout its network of distribution centers.The type of system Zanda should consider is known as:

A)CRP.
B)DRP.
C)MRP.
D)ERP.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
25
Which of the following is NOT an input to an MRP system?

A)Order releases.
B)Actual orders.
C)Inventory receipts.
D)Bill of materials.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
26
Benefits of ERP systems include all of the following EXCEPT:

A)Easy implementation.
B)Fewer data entry errors.
C)More informed business decisions.
D)Improved customer service.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
27
The following table shows capacity requirements data for making Blodgetts. <strong>The following table shows capacity requirements data for making Blodgetts.   A load profile would show:</strong> A)Load above capacity in periods 3 and 5. B)Load below capacity in periods 1 and 3. C)Load is exactly equal to capacity in period 5. D)None of these. A load profile would show:

A)Load above capacity in periods 3 and 5.
B)Load below capacity in periods 1 and 3.
C)Load is exactly equal to capacity in period 5.
D)None of these.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
28
An MPS shows:

A)The number of each type of part that is needed to make the final product.
B)The change orders that are required.
C)The quantities of end items to be completed in each time period.
D)The scheduled releases for all parts and components.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
29
If the planning horizon is 12 weeks, the cumulative lead time must be:

A)Greater than 12 weeks.
B)Exactly equal to 12 weeks.
C)Greater than 6 weeks.
D)Less than or equal to 12 weeks.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
30
Software that consolidates all of the business planning systems and data throughout an organization is:

A)MPS.
B)MRP.
C)DRP.
D)ERP.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
31
A detailed description of an "end item" along with a list of all of its raw materials, parts, and subassemblies is shown in a:

A)MPS
B)Planning horizon.
C)BOM.
D)DRP.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
32
A master production schedule shows the beginning inventory is 200 units, the forecast is 600 units and the actual customer orders is 500 units.Using a lot-for-lot rule, what is the MPS quantity for period 1?

A)400
B)300
C)600
D)500
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
33
A master production schedule shows the beginning inventory is 100 units, the forecast is 250 units and actual customer orders are 400 units.Using a lot-for-lot rule, what is the MPS quantity for period 1?

A)150
B)250
C)300
D)400
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
34
A master production schedule shows the beginning inventory is 50 units, the forecast is 200 units and actual customer orders are 220 units.What is the quantity that is available to promise in period 1?

A)50
B)150
C)170
D)0
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
35
The entire time period covered by the MPS is the:

A)Time bucket.
B)Cumulative lead time.
C)Planning horizon.
D)Production schedule.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
36
The primary purpose of an MRP system is to:

A)Develop forecasts.
B)Plan transportation and deliveries.
C)Schedule personnel.
D)Match supply and demand
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
37
A master production schedule shows the beginning inventory is 50 units, the forecast is 80 unitsand actual customer orders are 70 units.Using a lot-for-lot rule, what is the MPS quantity for period 1?

A)30
B)80
C)70
D)20
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
38
The following table shows capacity requirements data for making table tops. <strong>The following table shows capacity requirements data for making table tops.   Which of the following is TRUE?</strong> A)Overtime is needed in day 1. B)Capacity exactly meets demand in day 5. C)All of the excess demand in days 4 and 5 can be shifted to day 3. D)New machines are needed. Which of the following is TRUE?

A)Overtime is needed in day 1.
B)Capacity exactly meets demand in day 5.
C)All of the excess demand in days 4 and 5 can be shifted to day 3.
D)New machines are needed.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
39
A master production schedule shows the beginning inventory is 40 units, the forecast is 100 units and actual customer orders are 80 units.What is the quantity that is available to promise in period 1?

A)40
B)80
C)100
D)60
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
40
Advanced planning and scheduling systems:

A)Use a simpler logic than the logic used in MRP.
B)Consolidate all business planning systems and data throughout an organization.
C)Integrate materials and capacity planning into one system.
D)All of these.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
41
An end item A is made by assembling 4 of component B and 1 of component C.Component B is made from 2 of part D and 4 of part E.Within the bill of materials, component B is considered to be

A)Level 0.
B)Level 1.
C)Level 2.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
42
A company has decided to outsource the production of key components for its main product to suppliers.What affect will this have on the product's bill of materials?

A)None.
B)The bill of materials will be wider.
C)The bill of materials will be deeper.
D)The bill of materials will be flatter.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
43
Demand-driven MRP:

A)Compares materials and capacity requirements within a single firm.
B)Extends planning across the supply chain.
C)Focuses on distribution planning.
D)Is also called advanced planning and scheduling
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
44
An MRP Schedule is as follows.What are the net requirements in Week 2? <strong>An MRP Schedule is as follows.What are the net requirements in Week 2?  </strong> A)0. B)20 units. C)30 units. D)50 units.

A)0.
B)20 units.
C)30 units.
D)50 units.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
45
The available capacity of a worker, machine, work center or facility during a specific period of time is compared against the capacity needed for a specific work schedule in a:

A)Load profile.
B)Capacity profile.
C)Infinite load
D)DRP
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
46
The planned order releases in week 5 are 100 units.Each unit must be processed for 5 minutes at the work station.If the available capacity at the work station is one hour:

A)Overtime will be needed.
B)Delivery lead times should be increased.
C)The work station is underloaded.
D)An order backlog will be created
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
47
Distribution requirements planning:

A)Uses logic that starts at the manufacturing plant and works forward toward the customer.
B)Includes only firm orders in its calculations.
C)Uses logic similar to MRP, beginning at the point closes to the customer.
D)Is normally not included as a module in ERP software.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
48
Which of the following information is NOT contained in a MRP secondary report?

A)Cost.
B)Inventory levels.
C)Schedule attainment.
D)Planned order releases.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.
فتح الحزمة
k this deck
locked card icon
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 48 في هذه المجموعة.