Deck 22: Workcenter Scheduling

ملء الشاشة (f)
exit full mode
سؤال
A backward schedule tells when an order must be started in order to be done by a specific date.
استخدم زر المسافة أو
up arrow
down arrow
لقلب البطاقة.
سؤال
Under the STR/OP sequencing priority rule, orders with the jobs with the longest STR/OP are run first.
سؤال
The FCFS priority rule used in sequencing production jobs will always result in a better solution than the LCFS rule.
سؤال
In infinite loading, no consideration is given directly to whether there is sufficient capacity at the resources required to complete the work, nor is the actual sequence of the work as done by each resource in the work center considered.
سؤال
Shop-floor control (or production activity control) can involve reviewing the status and controlling the progress of orders as they are being worked on.
سؤال
Theoretically, all schedules are feasible when finite loading is used.
سؤال
A work center is a physical area of the business in which productive resources are organized and work is completed.
سؤال
The objective of Johnson's rule for job sequencing is to minimize flow time from the beginning of the first job until the completion of the last job.
سؤال
The assignment method of job sequencing is a special case of the transportation method of linear programming.
سؤال
Using the random order or "whim" priority rule to sequence production jobs means that supervisors or operators select whichever job they feel like running.
سؤال
Priority rules are the rules used to obtain a job sequence in production scheduling.
سؤال
In production scheduling, the process of determining which job to start first on some machine or in some work center is known as sequencing or priority sequencing.
سؤال
A system that "backward schedules" is designed to determine and report the earliest date an order can be completed.
سؤال
Shop-floor control (or production activity control) can involve expediting late and critical orders.
سؤال
Initiating performance of scheduled work is commonly termed "dispatching" of orders.
سؤال
In finite loading, no consideration is given directly to whether there is sufficient capacity at the resources required to complete the work, nor is the actual sequence of the work as done by each resource in the work center considered.
سؤال
The LCFS and Johnson's priority rules are basically the same except LCFS uses due dates as a major determiner of job sequence.
سؤال
Johnson's rule, a priority rule used in sequencing production jobs, is used only in production situations where we are dealing with one machine or one stage of production activity.
سؤال
A shop-floor control system is a system that uses data from the shop floor as well as data processing files to maintain and communicate status information on shop orders and work centers.
سؤال
The textbook underscores the importance of scheduling with the phrase "workflow equals cash flow, and scheduling lies at the heart of the process."
سؤال
For a high-volume type of manufacturing, which of the following is the typical production scheduling approach?

A)Finite backward scheduling
B)Finite forward scheduling
C)Infinite forward scheduling
D)Infinite backward scheduling
E)Assignment method
سؤال
Scheduling hourly work times using the "first-hour principle" ensures that no excess labor will be used during the work shift.
سؤال
Which of the following is not a standard measure of schedule performance that can be used to evaluate priority rules?

A)The schedule quality index
B)Minimizing the time a job spends in the process
C)Minimizing work-in-process inventory
D)Minimizing idle time of machines or workers
E)Meeting due dates of customers
سؤال
For a continuous-process type of manufacturing, which of the following is the typical production scheduling approach?

A)Finite forward scheduling
B)Finite backward scheduling
C)Infinite forward scheduling
D)Infinite backward scheduling
E)Shortest due date
سؤال
One of the principles of work center scheduling is to match work center input information to what the worker can actually do.
سؤال
When work is assigned to a work center based on what is needed over time it is called which of the following?

A)Infinite loading
B)Finite loading
C)Machine-limited
D)Labor-limited
E)Johnson's rule
سؤال
For a low-volume job shop type of manufacturing, which of the following is the typical production scheduling approach?

A)Finite forward scheduling
B)Finite backward scheduling
C)Infinite backward scheduling
D)Infinite forward scheduling
E)Soonest due date
سؤال
For a mid-volume type of manufacturing, which of the following is the typical production scheduling approach?

A)Finite forward scheduling
B)Finite backward scheduling
C)Infinite forward scheduling
D)Infinite backward scheduling
E)Precision forward scheduling
سؤال
Which of the following is not a way in which a work center can be organized?

A)According to function in a work center configuration
B)According to function in an assembly line
C)By product in assembly line
D)As a group technology cell (GT cell)
E)By product in a flow operation
سؤال
One of the principles of work center scheduling is that once started, a job should not be interrupted.
سؤال
One of the principles of work center scheduling is that the effectiveness of any shop should be measured by speed of flow through the shop.
سؤال
MES and SES are acronyms for "manufacturing environment scheduler" and "service environment scheduler" systems, respectively.
سؤال
Which of the following is not a function performed in scheduling and controlling an operation?

A)Allocating orders and equipment
B)Setting priorities and sequencing jobs
C)Allocating personnel to work centers
D)Expediting late orders
E)Reporting bottleneck operations
سؤال
A material requirements planning system is an example of which of the following scheduling systems?

A)Infinite loading, backward scheduling
B)Finite loading, backward scheduling
C)Infinite loading, forward scheduling
D)Finite loading, forward scheduling
E)None of these
سؤال
When work is scheduled in detail using the setup and run time required for each order, then theoretically all schedules will be feasible.
سؤال
When work has been scheduled in a shop that does not have sufficient resources to complete the schedule on time, the system that generated the schedule is called which of the following?

A)Infinite loading
B)Machine-limited
C)Finite loading
D)Labor-limited
E)Constrained
سؤال
One of the principles of work center scheduling is that, while certainty of standards, routings, and so forth is not entirely possible in a shop, certainty should always be an objective to work toward.
سؤال
The objectives of work center scheduling include which of the following?

A)Minimizing worker alienation
B)Providing variety to workforce
C)Following all the priority rules
D)Avoiding tradeoffs
E)Minimizing setup costs
سؤال
Which of the following is not an objective of work center scheduling?

A)Meeting due dates
B)Providing time for quality at the source
C)Minimizing setup time or cost
D)Minimizing work-in-process inventory
E)Minimizing lead time
سؤال
When work is scheduled in detail using the setup and run time required for each order, it is called which of the following?

A)Infinite loading
B)Finite loading
C)Machine-limited
D)Labor-limited
E)Johnson's rule
سؤال
Assume there are five jobs (i.e., A, B, C, D, and E) that need to be sequenced in a production schedule.The remaining operating time necessary for completion of job A is 4 days (i.e., job A will take 4 more days to complete), B will take 7 days, C will take 8 days, D will take 2 days, and E will take 5 days.All jobs are available now and the time now is 0.Using SOT rule sequence the jobs and find the schedule (single machine scheduling problem).What is the completion time of job B as per your schedule?

A)2
B)6
C)26
D)11
E)18
سؤال
Which of the following priority rules used in scheduling the sequence of production is calculated as the time remaining before the due date minus the remaining processing time, with the smallest value being run first?

A)STR
B)CR
C)SOT
D)LCFS
E)EDD
سؤال
Which of the following is not one of the major functions of shop-floor control?

A)Measure efficiency, utilization, and productivity of manpower and machines.
B)Assign a priority to each shop order.
C)Load machine hours into workstations.
D)Track WIP quantity by location by shop order to accounting.
E)Convey shop order status information to the office.
سؤال
Which of the following might be a status and exception report used in shop-floor control?

A)Absentee report
B)Quality failure report
C)Shortage lists
D)Expediting report
E)Union activity report
سؤال
Assume there are five jobs (i.e., A, B, C, D, and E) that need to be sequenced in a production schedule.The remaining operating time necessary for completion of job A is 3 days (i.e., job A will take 3 more days to complete), B will take 9 days, C will take 6 days, D will take 5 days and E will take 8 days.Which job should be scheduled last if using the SOT priority rule for job sequencing?

A)A
B)B
C)C
D)D
E)E
سؤال
The assignment method is useful in solving scheduling problems that have which of the following characteristics?

A)There are n jobs to be distributed to n machines or workers.
B)Each job can only be done on one particular machine.
C)Speed and efficiency are important.
D)The objective is to minimize cost and lateness of delivery.
E)The jobs have to go through more than one process.
سؤال
Assume there are five jobs (i.e., A, B, C, D, and E) that need to be sequenced in a production schedule.The remaining operating time necessary for completion of job A is 4 days (i.e., job A will take 4 more days to complete), B will take 7 days, C will take 8 days, D will take 2 days, and E will take 5 days.Which job should be scheduled first if you use the SOT priority rule for job sequencing?

A)A
B)B
C)C
D)D
E)E
سؤال
Which of the following is one of the major functions of shop-floor control?

A)Observing the priorities set for each shop order
B)Keeping work-in-process inventory out of the way
C)Conveying shop-order status information to the office
D)Controlling cost and materials waste
E)Keeping the workforce fully utilized
سؤال
Which of the following priority rules used in scheduling the sequence of production is calculated as the slack time remaining in the schedule divided by the number of remaining operations, with the smallest value being run first?

A)STR
B)Johnson's
C)STR/OP
D)LCFS
E)FCFS
سؤال
Assume you are sequencing jobs using Johnson's rule.A particular job requires 3 hours to assemble and then is followed by 2 hours in the painting department.Which of the following is where you would schedule this job?

A)As early as possible in the unfilled job sequence.
B)As late as possible in the unfilled job sequence.
C)The schedule would depend on the due date.
D)Does not matter.
E)Johnson's rule does not apply.
سؤال
Which of the following priority rule will minimize the average flow time of jobs and also perform well in other measures such as average lateness

A)STR
B)CR
C)SOT
D)LCFS
E)EDD
سؤال
Which of the following is not a priority rule used to schedule the sequence of jobs in a production operation?

A)First-come, first-served
B)Shortest operating time
C)Last-in, first-out
D)Critical ratio
E)Slack-time-remaining per operation
سؤال
Which of the following is a principle of work center scheduling?

A)Once started, a job can and should be finished even if unavoidably interrupted.
B)Reschedule every day.
C)Achieve certainty in standards and routings.
D)Give work centers less to do then their maximum.
E)Assign the first worker to all of the days that require staffing.
سؤال
Assume you are sequencing jobs using Johnson's rule.There are three jobs called A, B and C.The first step in assembling and the second step is painting. Job A requires 3 hours to assemble and 6 hours to paint.Job B requires 7 hours to assemble and 2 hours to paint.Job C requires 4 hours to assemble and 1 hour to paint.The objective is to minimize the total processing time of all jobs, using Johnson's rule.What is the correct sequence to process the jobs?

A)A - C - B
B)B - C - A
C)B - A - C
D)A - B - C
E)C - B - A
سؤال
Assume there are five jobs (i.e., A, B, C, D, and E) that need to be sequenced in a production schedule.The remaining operating time necessary for completion of job A is 3 days (i.e., job A will take 3 more days to complete), B will take 9 days, C will take 6 days, D will take 5 days and E will take 8 days.In what order will these jobs be scheduled if using the SOT priority rule for job sequencing?

A)A-B-D-E-C
B)A-D-C-E-B
C)D-C-A-B-E
D)B-E-C-D-A
E)E-D-A-B-C
سؤال
Which of the following is a tool of shop-floor control?

A)The hours worked per employee report
B)The anticipated delay report
C)The permanent work-in-process report
D)Time and motion studies
E)Product and process control report
سؤال
A job has 10 days of processing time left to do before completion, and today is the 5th day of the month.If the job is due on the 15th day of the month, what is its critical ratio?

A)3
B)2
C)1
D)0.8
E)- 0.8
سؤال
A job has 5 days of processing time left to do before completion, and today is the 10th day of the month.If the job is due on the 14th day of the month, what is its critical ratio?

A)5
B)2
C)0.8
D)0.5
E)0.1
سؤال
Which of the following is a priority rule used to schedule the sequence of jobs in a production operation?

A)Last-come, first-served
B)Last complaint first
C)First on hand first
D)Longest slack time first
E)Parts on hand first
سؤال
Assume you are sequencing jobs using Johnson's rule.A particular job requires 7 hours to assemble and then is followed by 8 hours in the painting department.Which of the following is where you would schedule this job?

A)As early as possible in the unfilled job sequence.
B)As late as possible in the unfilled job sequence.
C)The schedule would depend on the due date.
D)Does not matter.
E)Johnson's Rule does not apply.
سؤال
Assume you are sequencing jobs using Johnson's rule.There are three jobs called A, B and C.The first step in assembling and the second step is painting. Job A requires 3 hours to assemble and 6 hours to paint.Job B requires 7 hours to assemble and 2 hours to paint.Job C requires 4 hours to assemble and 1 hour to paint.The objective is to minimize the total processing time of all jobs, using Johnson's rule.What is the completion time of the last job in the sequence in the second step (painting)?

A)14
B)15
C)9
D)12
E)10
فتح الحزمة
قم بالتسجيل لفتح البطاقات في هذه المجموعة!
Unlock Deck
Unlock Deck
1/61
auto play flashcards
العب
simple tutorial
ملء الشاشة (f)
exit full mode
Deck 22: Workcenter Scheduling
1
A backward schedule tells when an order must be started in order to be done by a specific date.
True
2
Under the STR/OP sequencing priority rule, orders with the jobs with the longest STR/OP are run first.
False
3
The FCFS priority rule used in sequencing production jobs will always result in a better solution than the LCFS rule.
False
4
In infinite loading, no consideration is given directly to whether there is sufficient capacity at the resources required to complete the work, nor is the actual sequence of the work as done by each resource in the work center considered.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
5
Shop-floor control (or production activity control) can involve reviewing the status and controlling the progress of orders as they are being worked on.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
6
Theoretically, all schedules are feasible when finite loading is used.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
7
A work center is a physical area of the business in which productive resources are organized and work is completed.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
8
The objective of Johnson's rule for job sequencing is to minimize flow time from the beginning of the first job until the completion of the last job.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
9
The assignment method of job sequencing is a special case of the transportation method of linear programming.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
10
Using the random order or "whim" priority rule to sequence production jobs means that supervisors or operators select whichever job they feel like running.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
11
Priority rules are the rules used to obtain a job sequence in production scheduling.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
12
In production scheduling, the process of determining which job to start first on some machine or in some work center is known as sequencing or priority sequencing.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
13
A system that "backward schedules" is designed to determine and report the earliest date an order can be completed.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
14
Shop-floor control (or production activity control) can involve expediting late and critical orders.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
15
Initiating performance of scheduled work is commonly termed "dispatching" of orders.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
16
In finite loading, no consideration is given directly to whether there is sufficient capacity at the resources required to complete the work, nor is the actual sequence of the work as done by each resource in the work center considered.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
17
The LCFS and Johnson's priority rules are basically the same except LCFS uses due dates as a major determiner of job sequence.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
18
Johnson's rule, a priority rule used in sequencing production jobs, is used only in production situations where we are dealing with one machine or one stage of production activity.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
19
A shop-floor control system is a system that uses data from the shop floor as well as data processing files to maintain and communicate status information on shop orders and work centers.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
20
The textbook underscores the importance of scheduling with the phrase "workflow equals cash flow, and scheduling lies at the heart of the process."
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
21
For a high-volume type of manufacturing, which of the following is the typical production scheduling approach?

A)Finite backward scheduling
B)Finite forward scheduling
C)Infinite forward scheduling
D)Infinite backward scheduling
E)Assignment method
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
22
Scheduling hourly work times using the "first-hour principle" ensures that no excess labor will be used during the work shift.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
23
Which of the following is not a standard measure of schedule performance that can be used to evaluate priority rules?

A)The schedule quality index
B)Minimizing the time a job spends in the process
C)Minimizing work-in-process inventory
D)Minimizing idle time of machines or workers
E)Meeting due dates of customers
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
24
For a continuous-process type of manufacturing, which of the following is the typical production scheduling approach?

A)Finite forward scheduling
B)Finite backward scheduling
C)Infinite forward scheduling
D)Infinite backward scheduling
E)Shortest due date
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
25
One of the principles of work center scheduling is to match work center input information to what the worker can actually do.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
26
When work is assigned to a work center based on what is needed over time it is called which of the following?

A)Infinite loading
B)Finite loading
C)Machine-limited
D)Labor-limited
E)Johnson's rule
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
27
For a low-volume job shop type of manufacturing, which of the following is the typical production scheduling approach?

A)Finite forward scheduling
B)Finite backward scheduling
C)Infinite backward scheduling
D)Infinite forward scheduling
E)Soonest due date
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
28
For a mid-volume type of manufacturing, which of the following is the typical production scheduling approach?

A)Finite forward scheduling
B)Finite backward scheduling
C)Infinite forward scheduling
D)Infinite backward scheduling
E)Precision forward scheduling
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
29
Which of the following is not a way in which a work center can be organized?

A)According to function in a work center configuration
B)According to function in an assembly line
C)By product in assembly line
D)As a group technology cell (GT cell)
E)By product in a flow operation
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
30
One of the principles of work center scheduling is that once started, a job should not be interrupted.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
31
One of the principles of work center scheduling is that the effectiveness of any shop should be measured by speed of flow through the shop.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
32
MES and SES are acronyms for "manufacturing environment scheduler" and "service environment scheduler" systems, respectively.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
33
Which of the following is not a function performed in scheduling and controlling an operation?

A)Allocating orders and equipment
B)Setting priorities and sequencing jobs
C)Allocating personnel to work centers
D)Expediting late orders
E)Reporting bottleneck operations
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
34
A material requirements planning system is an example of which of the following scheduling systems?

A)Infinite loading, backward scheduling
B)Finite loading, backward scheduling
C)Infinite loading, forward scheduling
D)Finite loading, forward scheduling
E)None of these
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
35
When work is scheduled in detail using the setup and run time required for each order, then theoretically all schedules will be feasible.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
36
When work has been scheduled in a shop that does not have sufficient resources to complete the schedule on time, the system that generated the schedule is called which of the following?

A)Infinite loading
B)Machine-limited
C)Finite loading
D)Labor-limited
E)Constrained
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
37
One of the principles of work center scheduling is that, while certainty of standards, routings, and so forth is not entirely possible in a shop, certainty should always be an objective to work toward.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
38
The objectives of work center scheduling include which of the following?

A)Minimizing worker alienation
B)Providing variety to workforce
C)Following all the priority rules
D)Avoiding tradeoffs
E)Minimizing setup costs
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
39
Which of the following is not an objective of work center scheduling?

A)Meeting due dates
B)Providing time for quality at the source
C)Minimizing setup time or cost
D)Minimizing work-in-process inventory
E)Minimizing lead time
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
40
When work is scheduled in detail using the setup and run time required for each order, it is called which of the following?

A)Infinite loading
B)Finite loading
C)Machine-limited
D)Labor-limited
E)Johnson's rule
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
41
Assume there are five jobs (i.e., A, B, C, D, and E) that need to be sequenced in a production schedule.The remaining operating time necessary for completion of job A is 4 days (i.e., job A will take 4 more days to complete), B will take 7 days, C will take 8 days, D will take 2 days, and E will take 5 days.All jobs are available now and the time now is 0.Using SOT rule sequence the jobs and find the schedule (single machine scheduling problem).What is the completion time of job B as per your schedule?

A)2
B)6
C)26
D)11
E)18
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
42
Which of the following priority rules used in scheduling the sequence of production is calculated as the time remaining before the due date minus the remaining processing time, with the smallest value being run first?

A)STR
B)CR
C)SOT
D)LCFS
E)EDD
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
43
Which of the following is not one of the major functions of shop-floor control?

A)Measure efficiency, utilization, and productivity of manpower and machines.
B)Assign a priority to each shop order.
C)Load machine hours into workstations.
D)Track WIP quantity by location by shop order to accounting.
E)Convey shop order status information to the office.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
44
Which of the following might be a status and exception report used in shop-floor control?

A)Absentee report
B)Quality failure report
C)Shortage lists
D)Expediting report
E)Union activity report
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
45
Assume there are five jobs (i.e., A, B, C, D, and E) that need to be sequenced in a production schedule.The remaining operating time necessary for completion of job A is 3 days (i.e., job A will take 3 more days to complete), B will take 9 days, C will take 6 days, D will take 5 days and E will take 8 days.Which job should be scheduled last if using the SOT priority rule for job sequencing?

A)A
B)B
C)C
D)D
E)E
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
46
The assignment method is useful in solving scheduling problems that have which of the following characteristics?

A)There are n jobs to be distributed to n machines or workers.
B)Each job can only be done on one particular machine.
C)Speed and efficiency are important.
D)The objective is to minimize cost and lateness of delivery.
E)The jobs have to go through more than one process.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
47
Assume there are five jobs (i.e., A, B, C, D, and E) that need to be sequenced in a production schedule.The remaining operating time necessary for completion of job A is 4 days (i.e., job A will take 4 more days to complete), B will take 7 days, C will take 8 days, D will take 2 days, and E will take 5 days.Which job should be scheduled first if you use the SOT priority rule for job sequencing?

A)A
B)B
C)C
D)D
E)E
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
48
Which of the following is one of the major functions of shop-floor control?

A)Observing the priorities set for each shop order
B)Keeping work-in-process inventory out of the way
C)Conveying shop-order status information to the office
D)Controlling cost and materials waste
E)Keeping the workforce fully utilized
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
49
Which of the following priority rules used in scheduling the sequence of production is calculated as the slack time remaining in the schedule divided by the number of remaining operations, with the smallest value being run first?

A)STR
B)Johnson's
C)STR/OP
D)LCFS
E)FCFS
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
50
Assume you are sequencing jobs using Johnson's rule.A particular job requires 3 hours to assemble and then is followed by 2 hours in the painting department.Which of the following is where you would schedule this job?

A)As early as possible in the unfilled job sequence.
B)As late as possible in the unfilled job sequence.
C)The schedule would depend on the due date.
D)Does not matter.
E)Johnson's rule does not apply.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
51
Which of the following priority rule will minimize the average flow time of jobs and also perform well in other measures such as average lateness

A)STR
B)CR
C)SOT
D)LCFS
E)EDD
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
52
Which of the following is not a priority rule used to schedule the sequence of jobs in a production operation?

A)First-come, first-served
B)Shortest operating time
C)Last-in, first-out
D)Critical ratio
E)Slack-time-remaining per operation
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
53
Which of the following is a principle of work center scheduling?

A)Once started, a job can and should be finished even if unavoidably interrupted.
B)Reschedule every day.
C)Achieve certainty in standards and routings.
D)Give work centers less to do then their maximum.
E)Assign the first worker to all of the days that require staffing.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
54
Assume you are sequencing jobs using Johnson's rule.There are three jobs called A, B and C.The first step in assembling and the second step is painting. Job A requires 3 hours to assemble and 6 hours to paint.Job B requires 7 hours to assemble and 2 hours to paint.Job C requires 4 hours to assemble and 1 hour to paint.The objective is to minimize the total processing time of all jobs, using Johnson's rule.What is the correct sequence to process the jobs?

A)A - C - B
B)B - C - A
C)B - A - C
D)A - B - C
E)C - B - A
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
55
Assume there are five jobs (i.e., A, B, C, D, and E) that need to be sequenced in a production schedule.The remaining operating time necessary for completion of job A is 3 days (i.e., job A will take 3 more days to complete), B will take 9 days, C will take 6 days, D will take 5 days and E will take 8 days.In what order will these jobs be scheduled if using the SOT priority rule for job sequencing?

A)A-B-D-E-C
B)A-D-C-E-B
C)D-C-A-B-E
D)B-E-C-D-A
E)E-D-A-B-C
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
56
Which of the following is a tool of shop-floor control?

A)The hours worked per employee report
B)The anticipated delay report
C)The permanent work-in-process report
D)Time and motion studies
E)Product and process control report
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
57
A job has 10 days of processing time left to do before completion, and today is the 5th day of the month.If the job is due on the 15th day of the month, what is its critical ratio?

A)3
B)2
C)1
D)0.8
E)- 0.8
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
58
A job has 5 days of processing time left to do before completion, and today is the 10th day of the month.If the job is due on the 14th day of the month, what is its critical ratio?

A)5
B)2
C)0.8
D)0.5
E)0.1
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
59
Which of the following is a priority rule used to schedule the sequence of jobs in a production operation?

A)Last-come, first-served
B)Last complaint first
C)First on hand first
D)Longest slack time first
E)Parts on hand first
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
60
Assume you are sequencing jobs using Johnson's rule.A particular job requires 7 hours to assemble and then is followed by 8 hours in the painting department.Which of the following is where you would schedule this job?

A)As early as possible in the unfilled job sequence.
B)As late as possible in the unfilled job sequence.
C)The schedule would depend on the due date.
D)Does not matter.
E)Johnson's Rule does not apply.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
61
Assume you are sequencing jobs using Johnson's rule.There are three jobs called A, B and C.The first step in assembling and the second step is painting. Job A requires 3 hours to assemble and 6 hours to paint.Job B requires 7 hours to assemble and 2 hours to paint.Job C requires 4 hours to assemble and 1 hour to paint.The objective is to minimize the total processing time of all jobs, using Johnson's rule.What is the completion time of the last job in the sequence in the second step (painting)?

A)14
B)15
C)9
D)12
E)10
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.
فتح الحزمة
k this deck
locked card icon
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 61 في هذه المجموعة.