Deck 19: CD - Pertcpm Models for Project Management

ملء الشاشة (f)
exit full mode
سؤال
The activities with the longest durations in a project network are called critical activities.
استخدم زر المسافة أو
up arrow
down arrow
لقلب البطاقة.
سؤال
The latest starting time for an activity is equal to the latest finish time minus the duration of the activity.
سؤال
A Gantt chart of a project shows the scheduled start and finish times for activities.
سؤال
The earliest finish time for an activity is equal to the latest finish time minus the duration of the activity.
سؤال
In an Activity-On-Node project network,the nodes are used to separate an activity from each of its immediate predecessors.
سؤال
Projects involve routine activities that are performed repeatedly.
سؤال
If two paths are tied for the longest duration,both would be considered to be critical paths.
سؤال
The project network diagram describes sequential relationships among major activities in a project.
سؤال
An activity in a project network cannot begin until all of the activities leading into that activity have been completed.
سؤال
Project managers must often function in an environment that is beset with uncertainties.
سؤال
In PERT,the path with the fewest activities is referred to as the critical path.
سؤال
The earliest start of an activity is the latest early finish of any immediately preceding activity.
سؤال
An immediate predecessor of an activity must be completed before that activity can begin.
سؤال
The length of the critical path is determined by adding the expected completion times for all the activities in the project.
سؤال
Although PERT and CPM were originally developed for somewhat different types of projects,they are now nearly identical in terms of analysis and procedures.
سؤال
The values assigned to the nodes in a project network are there to identify the precedence relationships.
سؤال
The earliest finish time for an activity is equal to the latest finish time minus the activity slack.
سؤال
In PERT,the project duration will never exceed the expected duration of the critical path.
سؤال
The sum of durations of the longest path in a project network indicates expected project completion time,and the activities are the critical activities.
سؤال
The path in a project network with the average duration is the critical path.
سؤال
A forward pass is the process of moving forward through the project network to determine the latest start times and latest finish times of each activity.
سؤال
The slack of any activity is the amount of time that the activity can be delayed without delaying the completion of the project.
سؤال
The slack of an activity is the difference between the latest finish and the earliest finish times.
سؤال
The PERT three-estimate approach can be used to determine the probability that a project will be completed by a certain time.
سؤال
When making a backward pass through a project network,you must start at the finish node.
سؤال
If an activity is not on the critical path,then the project cannot be delayed if that activity is delayed.
سؤال
Crashing an activity will always reduce the duration of a project.
سؤال
Crashing cannot be accomplished by using different materials than originally planned.
سؤال
PERT/Cost is a systematic procedure to help a project manager bid on a project.
سؤال
In order to determine the probability of timely project completion,it is sometimes necessary to take into account paths other than the critical path.
سؤال
When calculating the probability that a project will finish by a certain time,the approximation that is obtained is usually lower than the true probability.
سؤال
The standard deviation of the critical path is equal to the sum of the standard deviations of all the activities on the critical path.
سؤال
The CPM method provides an excellent procedure for evaluating time-cost tradeoffs.
سؤال
The mean critical path is the path through the project network that would be the critical path if the duration of each activity equals its mean.
سؤال
A manager has decided that an activity has a pessimistic estimate of 15 days,a most-likely estimate of 6 days,and an optimistic estimate of 3 days.The expected duration of this activity is 6 days.
سؤال
If the variance of an activity duration is equal to 1 then all the durations are the same.
سؤال
Activities that are not on the critical path have a slack time equal to zero.
سؤال
The latest finish of an activity is the earliest late start of any immediately preceding activity.
سؤال
Only activities on the critical path are initial candidates for crashing.
سؤال
A normal distribution is usually used to describe the form of the probability distribution of activity durations in the PERT three-estimate approach.
سؤال
There is currently no method that permits activities and their immediate predecessors to overlap.
Multiple Choice Questions
سؤال
Figure <strong>Figure   Given this network: The expected duration of this project is:</strong> A)12. B)17. C)20. D)36. E)77. <div style=padding-top: 35px> Given this network:
The expected duration of this project is:

A)12.
B)17.
C)20.
D)36.
E)77.
سؤال
Figure <strong>Figure   The critical path is:</strong> A)A-E. B)B-F. C)C-D-F. D)C-G. E)there are two critical paths. <div style=padding-top: 35px>
The critical path is:

A)A-E.
B)B-F.
C)C-D-F.
D)C-G.
E)there are two critical paths.
سؤال
PERT/CPM can answer which of the following questions?

A)When do activities need to start and finish to meet a deadline?
B)How much delay can be tolerated for certain activities?
C)Given uncertainties,what is the probability that a project will finish on time?
D)What is the least expensive way to expedite a project to meet a deadline?
E)All of the above.
سؤال
Activity C has an early start time of 8,an early finish time of 12,a latest start time of 13,and a latest finish time of 17.Its slack is:

A)0.
B)1.
C)4.
D)5.
E)9.
سؤال
In a project network the critical path is the sequence of activities which has:

A)the most activities.
B)the fewest activities.
C)the most events.
D)the longest time.
E)the greatest variance.
سؤال
Given this information about activity H: ES = 10,EF = 15,LS = 16,and LF = 21,we can determine that the amount of slack associated with the activity is:

A)0.
B)1.
C)5.
D)6.
E)11.
سؤال
<strong>  Given the portion of the network shown above,what is the earliest finish time for activity D,if the earliest start time of A is 12 and the earliest start time of B is 13?</strong> A)22. B)23. C)24. D)25. E)26. <div style=padding-top: 35px> Given the portion of the network shown above,what is the earliest finish time for activity D,if the earliest start time of A is 12 and the earliest start time of B is 13?

A)22.
B)23.
C)24.
D)25.
E)26.
سؤال
Concerning PERT and CPM:

A)These are two different names for essentially the same technique.
B)CPM tends to focus more on the critical path.
C)PERT gives a better indication of activity slack,CPM a better picture of path slack.
D)Because of its recent discovery,much less is known about CPM that PERT.
E)All of the above are true.
سؤال
A project manager does not need to monitor each individual activity,just the overall project when looking at budget costs.
سؤال
<strong>  Given the portion of the network shown above,what is the latest start time of activity D if the latest finish of activity F is 26 and the latest finish of activity G is 23?</strong> A)3. B)4. C)9. D)10. E)12. <div style=padding-top: 35px> Given the portion of the network shown above,what is the latest start time of activity D if the latest finish of activity F is 26 and the latest finish of activity G is 23?

A)3.
B)4.
C)9.
D)10.
E)12.
سؤال
The earliest start time for an activity is:

A)based on the length of the critical path.
B)determined by the maximum of the earliest finish times of its immediate predecessors.
C)determined by the maximum of the earliest finish times of its immediate successors.
D)the same as the latest start time of its immediate predecessor.
E)None of the above.
سؤال
Figure <strong>Figure   The duration of the critical path is:</strong> A)11 days. B)20 days. C)18 days. D)22 days. E)15 days. <div style=padding-top: 35px>
The duration of the critical path is:

A)11 days.
B)20 days.
C)18 days.
D)22 days.
E)15 days.
سؤال
Once a project is underway,the project manager is responsible for effectively managing:

A)the people.
B)costs.
C)time.
D)a and b.
E)a,b,and c.
سؤال
AON project networks have which of the following advantages over AOA networks?

A)They are easier to construct.
B)They allow the project to be completed faster.
C)They are easier to revise when there are changes in a project.
D)a and c only.
E)b and c only.
سؤال
Figure <strong>Figure   The path with the greatest slack is:</strong> A)A-E. B)B-F. C)C-D-F. D)C-G. E)None of the above. <div style=padding-top: 35px>
The path with the greatest slack is:

A)A-E.
B)B-F.
C)C-D-F.
D)C-G.
E)None of the above.
سؤال
PERT/Cost can be used to monitor budget overruns.
سؤال
In project network analysis,slack refers to the difference between:

A)observed and predicted times.
B)optimistic and pessimistic times.
C)latest finish and latest start times.
D)earliest finish and earliest start times.
E)latest start and earliest start times.
سؤال
Which of the following is not a feature of PERT/CPM?

A)An estimate of how long a project will take.
B)A graphical display of project activities.
C)An indication of crucial activities.
D)An indication of slack time.
E)All are features.
سؤال
A common assumption when using PERT/Cost is that the costs are incurred at a constant rate throughout the duration of an activity.
سؤال
When finding the approximate probability of project duration,it is necessary to know which of the following?

A)The mean and variance of each activity.
B)The mean of each activity on the critical path.
C)The standard deviation of only the activities on the critical path.
D)Each activity's probability of completion.
E)The distribution of activity times.
سؤال
Figure <strong>Figure   (time in days) What is the estimated mean time for project completion?</strong> A)160 days. B)170 days. C)200 days. D)210 days. E)300 days. <div style=padding-top: 35px> (time in days)
What is the estimated mean time for project completion?

A)160 days.
B)170 days.
C)200 days.
D)210 days.
E)300 days.
سؤال
There are four activities on the critical path,and they have standard deviations of 1,2,4,and 2 days.The standard deviation of the critical path is:

A)3 days.
B)5 days.
C)9 days.
D)16 days.
E)25 days.
سؤال
Figure <strong>Figure   (time in days) What is the estimated mean time for project completion?</strong> A)100 days. B)140 days. C)199 days. D)200 days. E)440 days. <div style=padding-top: 35px> (time in days)
What is the estimated mean time for project completion?

A)100 days.
B)140 days.
C)199 days.
D)200 days.
E)440 days.
سؤال
The standard deviation of a path is computed as:

A)the sum of the standard deviations of all activities on the path.
B)the square root of the sum of the standard deviations of all activities on the path.
C)the sum of the variances of all activities on the path.
D)the square root of the sum of the variances of all activities on the path.
E)None of the above.
سؤال
Figure <strong>Figure   Given this network: The path with the greatest slack is:</strong> A)A-E-H. B)B-H. C)A-D-G. D)C-F-H. E)C-I-J. <div style=padding-top: 35px> Given this network:
The path with the greatest slack is:

A)A-E-H.
B)B-H.
C)A-D-G.
D)C-F-H.
E)C-I-J.
سؤال
Figure <strong>Figure   (time in days) What is the estimated mean time for activity E?</strong> A)91 days. B)99 days. C)100 days. D)101 days. E)115 days. <div style=padding-top: 35px> (time in days)
What is the estimated mean time for activity E?

A)91 days.
B)99 days.
C)100 days.
D)101 days.
E)115 days.
سؤال
Activity C in a project network has an optimistic time estimate of five days,a most likely time estimate of seven days,and a pessimistic time estimate of nine days.Its expected duration is approximately:

A)5 days.
B)6 days.
C)7 days.
D)8 days.
E)9 days.
سؤال
There are four activities on the critical path.Coincidentally,their standard deviations are all equal to 4.The standard deviation of the critical path is therefore equal to:

A)2 days.
B)4 days.
C)8 days.
D)16 days.
E)64 days.
سؤال
Figure <strong>Figure   (time in days) What is the probability that this project will be completed within 205 days?</strong> A)0.6826. B)0.8413. C)0.9544. D)0.9772. E)0.9987. <div style=padding-top: 35px> (time in days)
What is the probability that this project will be completed within 205 days?

A)0.6826.
B)0.8413.
C)0.9544.
D)0.9772.
E)0.9987.
سؤال
Figure <strong>Figure   (time in days) What is the estimated slack time for activity A?</strong> A)0 days. B)20 days. C)40 days. D)60 days. E)100 days. <div style=padding-top: 35px> (time in days)
What is the estimated slack time for activity A?

A)0 days.
B)20 days.
C)40 days.
D)60 days.
E)100 days.
سؤال
Figure <strong>Figure   Given this network: The slack for path A-D-H-I is:</strong> A)0. B)3. C)4. D)7. E)8. <div style=padding-top: 35px> Given this network:
The slack for path A-D-H-I is:

A)0.
B)3.
C)4.
D)7.
E)8.
سؤال
Figure <strong>Figure   (time in days) What is the estimated standard deviation in the time for activity E?</strong> A)1 days. B)2 days. C)3 days. D)4 days. E)5 days. <div style=padding-top: 35px> (time in days)
What is the estimated standard deviation in the time for activity E?

A)1 days.
B)2 days.
C)3 days.
D)4 days.
E)5 days.
سؤال
Figure <strong>Figure   (time in days) What is the estimated standard deviation in the time for activity E?</strong> A)2 days. B)3 days. C)4 days. D)16 days. E)24 days. <div style=padding-top: 35px> (time in days)
What is the estimated standard deviation in the time for activity E?

A)2 days.
B)3 days.
C)4 days.
D)16 days.
E)24 days.
سؤال
An activity has an optimistic time estimate of three days,a most likely time estimate of eight days,and a pessimistic time estimate of ten days.The expected duration of this activity is:

A)7.0 days.
B)7.5 days.
C)8.0 days.
D)8.5 days.
E)10.0 days.
سؤال
Figure <strong>Figure   Given this network: The critical path for the network shown is:</strong> A)A-C-G. B)A-D-F-G. C)A-D-H-I. D)B-E-F-G. E)B-E-H-I. <div style=padding-top: 35px> Given this network:
The critical path for the network shown is:

A)A-C-G.
B)A-D-F-G.
C)A-D-H-I.
D)B-E-F-G.
E)B-E-H-I.
سؤال
Figure <strong>Figure   Given this network: The critical path for the network shown is:</strong> A)A-E-H. B)B-H. C)A-D-G. D)C-F-H. E)C-I-J. <div style=padding-top: 35px> Given this network:
The critical path for the network shown is:

A)A-E-H.
B)B-H.
C)A-D-G.
D)C-F-H.
E)C-I-J.
سؤال
An important assumption in PERT calculations is:

A)activity durations are normally distributed.
B)activity durations are independent.
C)a computer will be available to do the calculations.
D)a and b only.
E)a and c only.
سؤال
Figure <strong>Figure   Given this network: The expected duration of this project is:</strong> A)13. B)15. C)20. D)52. E)81. <div style=padding-top: 35px> Given this network:
The expected duration of this project is:

A)13.
B)15.
C)20.
D)52.
E)81.
سؤال
Figure <strong>Figure   (time in days) What is the estimated mean time for activity E?</strong> A)35 days. B)36 days. C)39 days. D)40 days. E)45 days. <div style=padding-top: 35px> (time in days)
What is the estimated mean time for activity E?

A)35 days.
B)36 days.
C)39 days.
D)40 days.
E)45 days.
فتح الحزمة
قم بالتسجيل لفتح البطاقات في هذه المجموعة!
Unlock Deck
Unlock Deck
1/93
auto play flashcards
العب
simple tutorial
ملء الشاشة (f)
exit full mode
Deck 19: CD - Pertcpm Models for Project Management
1
The activities with the longest durations in a project network are called critical activities.
False
2
The latest starting time for an activity is equal to the latest finish time minus the duration of the activity.
True
3
A Gantt chart of a project shows the scheduled start and finish times for activities.
True
4
The earliest finish time for an activity is equal to the latest finish time minus the duration of the activity.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
5
In an Activity-On-Node project network,the nodes are used to separate an activity from each of its immediate predecessors.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
6
Projects involve routine activities that are performed repeatedly.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
7
If two paths are tied for the longest duration,both would be considered to be critical paths.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
8
The project network diagram describes sequential relationships among major activities in a project.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
9
An activity in a project network cannot begin until all of the activities leading into that activity have been completed.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
10
Project managers must often function in an environment that is beset with uncertainties.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
11
In PERT,the path with the fewest activities is referred to as the critical path.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
12
The earliest start of an activity is the latest early finish of any immediately preceding activity.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
13
An immediate predecessor of an activity must be completed before that activity can begin.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
14
The length of the critical path is determined by adding the expected completion times for all the activities in the project.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
15
Although PERT and CPM were originally developed for somewhat different types of projects,they are now nearly identical in terms of analysis and procedures.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
16
The values assigned to the nodes in a project network are there to identify the precedence relationships.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
17
The earliest finish time for an activity is equal to the latest finish time minus the activity slack.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
18
In PERT,the project duration will never exceed the expected duration of the critical path.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
19
The sum of durations of the longest path in a project network indicates expected project completion time,and the activities are the critical activities.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
20
The path in a project network with the average duration is the critical path.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
21
A forward pass is the process of moving forward through the project network to determine the latest start times and latest finish times of each activity.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
22
The slack of any activity is the amount of time that the activity can be delayed without delaying the completion of the project.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
23
The slack of an activity is the difference between the latest finish and the earliest finish times.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
24
The PERT three-estimate approach can be used to determine the probability that a project will be completed by a certain time.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
25
When making a backward pass through a project network,you must start at the finish node.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
26
If an activity is not on the critical path,then the project cannot be delayed if that activity is delayed.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
27
Crashing an activity will always reduce the duration of a project.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
28
Crashing cannot be accomplished by using different materials than originally planned.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
29
PERT/Cost is a systematic procedure to help a project manager bid on a project.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
30
In order to determine the probability of timely project completion,it is sometimes necessary to take into account paths other than the critical path.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
31
When calculating the probability that a project will finish by a certain time,the approximation that is obtained is usually lower than the true probability.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
32
The standard deviation of the critical path is equal to the sum of the standard deviations of all the activities on the critical path.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
33
The CPM method provides an excellent procedure for evaluating time-cost tradeoffs.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
34
The mean critical path is the path through the project network that would be the critical path if the duration of each activity equals its mean.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
35
A manager has decided that an activity has a pessimistic estimate of 15 days,a most-likely estimate of 6 days,and an optimistic estimate of 3 days.The expected duration of this activity is 6 days.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
36
If the variance of an activity duration is equal to 1 then all the durations are the same.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
37
Activities that are not on the critical path have a slack time equal to zero.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
38
The latest finish of an activity is the earliest late start of any immediately preceding activity.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
39
Only activities on the critical path are initial candidates for crashing.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
40
A normal distribution is usually used to describe the form of the probability distribution of activity durations in the PERT three-estimate approach.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
41
There is currently no method that permits activities and their immediate predecessors to overlap.
Multiple Choice Questions
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
42
Figure <strong>Figure   Given this network: The expected duration of this project is:</strong> A)12. B)17. C)20. D)36. E)77. Given this network:
The expected duration of this project is:

A)12.
B)17.
C)20.
D)36.
E)77.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
43
Figure <strong>Figure   The critical path is:</strong> A)A-E. B)B-F. C)C-D-F. D)C-G. E)there are two critical paths.
The critical path is:

A)A-E.
B)B-F.
C)C-D-F.
D)C-G.
E)there are two critical paths.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
44
PERT/CPM can answer which of the following questions?

A)When do activities need to start and finish to meet a deadline?
B)How much delay can be tolerated for certain activities?
C)Given uncertainties,what is the probability that a project will finish on time?
D)What is the least expensive way to expedite a project to meet a deadline?
E)All of the above.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
45
Activity C has an early start time of 8,an early finish time of 12,a latest start time of 13,and a latest finish time of 17.Its slack is:

A)0.
B)1.
C)4.
D)5.
E)9.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
46
In a project network the critical path is the sequence of activities which has:

A)the most activities.
B)the fewest activities.
C)the most events.
D)the longest time.
E)the greatest variance.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
47
Given this information about activity H: ES = 10,EF = 15,LS = 16,and LF = 21,we can determine that the amount of slack associated with the activity is:

A)0.
B)1.
C)5.
D)6.
E)11.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
48
<strong>  Given the portion of the network shown above,what is the earliest finish time for activity D,if the earliest start time of A is 12 and the earliest start time of B is 13?</strong> A)22. B)23. C)24. D)25. E)26. Given the portion of the network shown above,what is the earliest finish time for activity D,if the earliest start time of A is 12 and the earliest start time of B is 13?

A)22.
B)23.
C)24.
D)25.
E)26.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
49
Concerning PERT and CPM:

A)These are two different names for essentially the same technique.
B)CPM tends to focus more on the critical path.
C)PERT gives a better indication of activity slack,CPM a better picture of path slack.
D)Because of its recent discovery,much less is known about CPM that PERT.
E)All of the above are true.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
50
A project manager does not need to monitor each individual activity,just the overall project when looking at budget costs.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
51
<strong>  Given the portion of the network shown above,what is the latest start time of activity D if the latest finish of activity F is 26 and the latest finish of activity G is 23?</strong> A)3. B)4. C)9. D)10. E)12. Given the portion of the network shown above,what is the latest start time of activity D if the latest finish of activity F is 26 and the latest finish of activity G is 23?

A)3.
B)4.
C)9.
D)10.
E)12.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
52
The earliest start time for an activity is:

A)based on the length of the critical path.
B)determined by the maximum of the earliest finish times of its immediate predecessors.
C)determined by the maximum of the earliest finish times of its immediate successors.
D)the same as the latest start time of its immediate predecessor.
E)None of the above.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
53
Figure <strong>Figure   The duration of the critical path is:</strong> A)11 days. B)20 days. C)18 days. D)22 days. E)15 days.
The duration of the critical path is:

A)11 days.
B)20 days.
C)18 days.
D)22 days.
E)15 days.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
54
Once a project is underway,the project manager is responsible for effectively managing:

A)the people.
B)costs.
C)time.
D)a and b.
E)a,b,and c.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
55
AON project networks have which of the following advantages over AOA networks?

A)They are easier to construct.
B)They allow the project to be completed faster.
C)They are easier to revise when there are changes in a project.
D)a and c only.
E)b and c only.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
56
Figure <strong>Figure   The path with the greatest slack is:</strong> A)A-E. B)B-F. C)C-D-F. D)C-G. E)None of the above.
The path with the greatest slack is:

A)A-E.
B)B-F.
C)C-D-F.
D)C-G.
E)None of the above.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
57
PERT/Cost can be used to monitor budget overruns.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
58
In project network analysis,slack refers to the difference between:

A)observed and predicted times.
B)optimistic and pessimistic times.
C)latest finish and latest start times.
D)earliest finish and earliest start times.
E)latest start and earliest start times.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
59
Which of the following is not a feature of PERT/CPM?

A)An estimate of how long a project will take.
B)A graphical display of project activities.
C)An indication of crucial activities.
D)An indication of slack time.
E)All are features.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
60
A common assumption when using PERT/Cost is that the costs are incurred at a constant rate throughout the duration of an activity.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
61
When finding the approximate probability of project duration,it is necessary to know which of the following?

A)The mean and variance of each activity.
B)The mean of each activity on the critical path.
C)The standard deviation of only the activities on the critical path.
D)Each activity's probability of completion.
E)The distribution of activity times.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
62
Figure <strong>Figure   (time in days) What is the estimated mean time for project completion?</strong> A)160 days. B)170 days. C)200 days. D)210 days. E)300 days. (time in days)
What is the estimated mean time for project completion?

A)160 days.
B)170 days.
C)200 days.
D)210 days.
E)300 days.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
63
There are four activities on the critical path,and they have standard deviations of 1,2,4,and 2 days.The standard deviation of the critical path is:

A)3 days.
B)5 days.
C)9 days.
D)16 days.
E)25 days.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
64
Figure <strong>Figure   (time in days) What is the estimated mean time for project completion?</strong> A)100 days. B)140 days. C)199 days. D)200 days. E)440 days. (time in days)
What is the estimated mean time for project completion?

A)100 days.
B)140 days.
C)199 days.
D)200 days.
E)440 days.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
65
The standard deviation of a path is computed as:

A)the sum of the standard deviations of all activities on the path.
B)the square root of the sum of the standard deviations of all activities on the path.
C)the sum of the variances of all activities on the path.
D)the square root of the sum of the variances of all activities on the path.
E)None of the above.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
66
Figure <strong>Figure   Given this network: The path with the greatest slack is:</strong> A)A-E-H. B)B-H. C)A-D-G. D)C-F-H. E)C-I-J. Given this network:
The path with the greatest slack is:

A)A-E-H.
B)B-H.
C)A-D-G.
D)C-F-H.
E)C-I-J.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
67
Figure <strong>Figure   (time in days) What is the estimated mean time for activity E?</strong> A)91 days. B)99 days. C)100 days. D)101 days. E)115 days. (time in days)
What is the estimated mean time for activity E?

A)91 days.
B)99 days.
C)100 days.
D)101 days.
E)115 days.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
68
Activity C in a project network has an optimistic time estimate of five days,a most likely time estimate of seven days,and a pessimistic time estimate of nine days.Its expected duration is approximately:

A)5 days.
B)6 days.
C)7 days.
D)8 days.
E)9 days.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
69
There are four activities on the critical path.Coincidentally,their standard deviations are all equal to 4.The standard deviation of the critical path is therefore equal to:

A)2 days.
B)4 days.
C)8 days.
D)16 days.
E)64 days.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
70
Figure <strong>Figure   (time in days) What is the probability that this project will be completed within 205 days?</strong> A)0.6826. B)0.8413. C)0.9544. D)0.9772. E)0.9987. (time in days)
What is the probability that this project will be completed within 205 days?

A)0.6826.
B)0.8413.
C)0.9544.
D)0.9772.
E)0.9987.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
71
Figure <strong>Figure   (time in days) What is the estimated slack time for activity A?</strong> A)0 days. B)20 days. C)40 days. D)60 days. E)100 days. (time in days)
What is the estimated slack time for activity A?

A)0 days.
B)20 days.
C)40 days.
D)60 days.
E)100 days.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
72
Figure <strong>Figure   Given this network: The slack for path A-D-H-I is:</strong> A)0. B)3. C)4. D)7. E)8. Given this network:
The slack for path A-D-H-I is:

A)0.
B)3.
C)4.
D)7.
E)8.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
73
Figure <strong>Figure   (time in days) What is the estimated standard deviation in the time for activity E?</strong> A)1 days. B)2 days. C)3 days. D)4 days. E)5 days. (time in days)
What is the estimated standard deviation in the time for activity E?

A)1 days.
B)2 days.
C)3 days.
D)4 days.
E)5 days.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
74
Figure <strong>Figure   (time in days) What is the estimated standard deviation in the time for activity E?</strong> A)2 days. B)3 days. C)4 days. D)16 days. E)24 days. (time in days)
What is the estimated standard deviation in the time for activity E?

A)2 days.
B)3 days.
C)4 days.
D)16 days.
E)24 days.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
75
An activity has an optimistic time estimate of three days,a most likely time estimate of eight days,and a pessimistic time estimate of ten days.The expected duration of this activity is:

A)7.0 days.
B)7.5 days.
C)8.0 days.
D)8.5 days.
E)10.0 days.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
76
Figure <strong>Figure   Given this network: The critical path for the network shown is:</strong> A)A-C-G. B)A-D-F-G. C)A-D-H-I. D)B-E-F-G. E)B-E-H-I. Given this network:
The critical path for the network shown is:

A)A-C-G.
B)A-D-F-G.
C)A-D-H-I.
D)B-E-F-G.
E)B-E-H-I.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
77
Figure <strong>Figure   Given this network: The critical path for the network shown is:</strong> A)A-E-H. B)B-H. C)A-D-G. D)C-F-H. E)C-I-J. Given this network:
The critical path for the network shown is:

A)A-E-H.
B)B-H.
C)A-D-G.
D)C-F-H.
E)C-I-J.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
78
An important assumption in PERT calculations is:

A)activity durations are normally distributed.
B)activity durations are independent.
C)a computer will be available to do the calculations.
D)a and b only.
E)a and c only.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
79
Figure <strong>Figure   Given this network: The expected duration of this project is:</strong> A)13. B)15. C)20. D)52. E)81. Given this network:
The expected duration of this project is:

A)13.
B)15.
C)20.
D)52.
E)81.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
80
Figure <strong>Figure   (time in days) What is the estimated mean time for activity E?</strong> A)35 days. B)36 days. C)39 days. D)40 days. E)45 days. (time in days)
What is the estimated mean time for activity E?

A)35 days.
B)36 days.
C)39 days.
D)40 days.
E)45 days.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.
فتح الحزمة
k this deck
locked card icon
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 93 في هذه المجموعة.