Deck 18: Project Management

ملء الشاشة (f)
exit full mode
سؤال
When the beta probability distribution is used to characterize uncertain activity times, the distribution of the project completion time will also have a beta probability distribution.
استخدم زر المسافة أو
up arrow
down arrow
لقلب البطاقة.
سؤال
A slack of (-2) means the project is ahead of schedule by two time periods.
سؤال
Project managers need to be specialists, not generalists.
سؤال
The Critical Path Method (CPM) allows for an evaluation of uncertainty in project completion times.
سؤال
Activity times must be estimated from historical data of similar work tasks to provide realism for a project.
سؤال
With the Activity-On-Node (AON) network, the nodes define the precedence relationships and the arcs define the work activities.
سؤال
Using a beta probability distribution to characterize uncertain activity times is practical because it allows managers to use judgmental estimates to identify the distribution.
سؤال
Because the preparation of annual reports is done on a repeating basis, project management techniques are not appropriate.
سؤال
A statement of work would be developed in the "Organize" step of the project life cycle.
سؤال
In a matrix organization, functional managers may be reluctant to provide the resources and employees, and the employees assigned to projects may relegate a project to a lower priority than their daily functional job.
سؤال
All activities on the critical path have a zero slack time.
سؤال
The early start time for an activity is computed by finding the largest early finish time of all immediate predecessors.
سؤال
The critical path is the sequence of activities that takes the longest time.
سؤال
In most organizations, projects cut across organizational boundaries, making it difficult to implement projects exclusively within functional departments.
سؤال
Immediate predecessors are activities that must be completed immediately before an activity may start.
سؤال
To compute the critical path, we assign all nodes in the network an earliest starting time of zero.
سؤال
Strong leadership is an impediment to project management success because of the team-based nature of most projects.
سؤال
Project management objectives revolved around on-time and budget performance.
سؤال
Crashing refers to the process of shortening selected activity times in order to reduce the overall project completion time.
سؤال
A Gantt chart is a useful tool for allocating limited resources among project activities.
سؤال
Which step in the project management process would involve determining time estimates for activities?

A)Project definition
B)Resource planning
C)Project scheduling
D)Project control
سؤال
Which of the following is not considered a project?

A)Writing and implementing a computer program
B)Introducing a new product
C)Production of soft drinks
D)Building a bridge
سؤال
The slack for an activity is equal to its latest finish time minus its earliest start time.
سؤال
The county government has decided to redo the street you live on and plans to block the street off which causes you and your neighbor's considerable inconvenience. The project has three parallel paths defined as follows: (i) path A-B-C-H to install street lights and electrical wiring that takes 16 days, (ii) path A-D-E-H to install sidewalks with handicap capabilities that takes 22 days, and (iii) path A-F-G-H to repave the street including storm drains that takes 30 days. Which one of the following statements is true?

A)The expected duration of the project is 30 + 22 + 16 = 68 days.
B)Path A-B-C-H is the critical path.
C)Path A-D-E-H has the most slack time.
D)Path A-F-G-H is the critical path.
سؤال
A project has three paths. A-B-C has a length of 25 days. A-D-C has a length of 15 days. Finally, A-E-C has a length of 20 days. Which one of the following statements is true?

A)A-D-C is the critical path.
B)A-B-C has the most slack.
C)The expected duration of this project is 25 days.
D)The expected duration of this project is 25 + 15 + 20 = 60 days.
سؤال
A type of organization which "loans" resources to projects while still maintaining control over them is called

A)Pure project structure
B)Pure functional structure
C)Matrix structure
D)Product structure
سؤال
Which step in the project management process would involve developing alternative plans in anticipation of problems that might arise?

A)Project definition
B)Resource planning
C)Project scheduling
D)Project control
سؤال
In which stage in the project life cycle would critical path calculations be performed?

A)Define
B)Plan
C)Organize
D)Control
سؤال
Which of the following is not an assumption of the critical path method?

A)Activities are independent of one another
B)Activity time estimates are stable
C)Activity times are characterized by a beta probability distribution
D)Once an activity is started it continues uninterrupted until completion
سؤال
Which statement is true regarding activities not on the critical path?

A)Usually cannot be delayed
B)Have less slack than activities on the critical path
C)Can delay a project if they are highly variable
D)Are used to crash project completion times
سؤال
We should not crash activities on the critical path.
سؤال
Which is incorrect regarding the critical path?

A)Shortest time to complete a project
B)Longest time to complete a project
C)Project path with 0 slack
D)Delays in activities will delay the project
سؤال
Which of the following is incorrect regarding time/cost trade-offs?

A)The relationship between time and cost is proportional
B)Some activities cannot be crashed
C)The minimum cost can be found by crashing all activities as much as possible
D)Crashing priority is based on the amount of uncertainty in activity times
سؤال
Slack in an activity is computed as

A)ES -LS
B)EF - LF
C)LS - ES
D)LS - EF
سؤال
When finding the earliest finish (EF) time for an activity with two or more predecessor activities, the largest EF among the predecessor activities is used to calculate the EF for that activity.
سؤال
In which stage in the project life cycle would a Gantt chart be used?

A)Define
B)Plan
C)Organize
D)Control
سؤال
Which of the following is not a stage in the project life cycle?

A)Define
B)Organize
C)Improve
D)Close
سؤال
In which stage in the project life cycle would crashing likely be performed?

A)Define
B)Plan
C)Organize
D)Control
سؤال
A type of organization that can result in inefficiencies because of duplication of resources across the organization is called

A)Pure project structure
B)Pure functional structure
C)Matrix structure
D)Product structure
سؤال
Which of the following is least related to Program Evaluation and Review Technique (PERT)?

A)Beta distribution
B)Variance
C)Most probable time
D)Crashing
سؤال
Define critical path and explain how it is identified once a project schedule is calculated.
سؤال
A company has a PERT project with path b-d-e-g-i that has these activity time estimates in days: A company has a PERT project with path b-d-e-g-i that has these activity time estimates in days:   a.What is the expected duration for activity e? b.What is the variance for activity b? c.What is the standard deviation of the path?<div style=padding-top: 35px>
a.What is the expected duration for activity e?
b.What is the variance for activity b?
c.What is the standard deviation of the path?
سؤال
You are in charge of the "advertising program" for the Boston Red Sox baseball team during their spring training in Fort Myers, Florida. You have defined the advertising program as a project with the following characteristics. The goal is to fill all stadium seats during the spring training season. You are in charge of the advertising program for the Boston Red Sox baseball team during their spring training in Fort Myers, Florida. You have defined the advertising program as a project with the following characteristics. The goal is to fill all stadium seats during the spring training season.   a.What is the earliest completion time for this project? b.What is the largest amount of slack that any activity has in this project? c.If activity C is delayed three weeks, what is the revised earliest project completion time? d.For the original CPM problem, what is the minimum number of activities that would have to be crashed in order to reduce the project's earliest completion time by two weeks assuming all activity crash costs per week are the same and all activities can be crashed?<div style=padding-top: 35px>
a.What is the earliest completion time for this project?
b.What is the largest amount of slack that any activity has in this project?
c.If activity C is delayed three weeks, what is the revised earliest project completion time?
d.For the original CPM problem, what is the minimum number of activities that would have to be crashed in order to reduce the project's earliest completion time by two weeks assuming all activity crash costs per week are the same and all activities can be crashed?
سؤال
Explain the role of the project managers and some principles for success.
سؤال
You are responsible for managing an advertising and promotion project with the following activities (times are given in weeks). You are responsible for managing an advertising and promotion project with the following activities (times are given in weeks).   a.What is the critical path and expected completion time for this project? b.Which activity has the largest slack, and how large is that slack? c.What is the probability that the project will be completed within 16 weeks? d.If the expected time (not the most likely time) for activity B is changed to 18 weeks from 11 weeks, by how many weeks will the project's expected completion time increase?<div style=padding-top: 35px>
a.What is the critical path and expected completion time for this project?
b.Which activity has the largest slack, and how large is that slack?
c.What is the probability that the project will be completed within 16 weeks?
d.If the expected time (not the most likely time) for activity B is changed to 18 weeks from 11 weeks, by how many weeks will the project's expected completion time increase?
سؤال
Data regarding the activities for a project are presented below. The times are in weeks. The critical path for this project is A - D - H - I - J - K. Data regarding the activities for a project are presented below. The times are in weeks. The critical path for this project is A - D - H - I - J - K.   a.Determine the standard deviation of the critical path. b.Determine the probability of completing the project in 38 weeks or less. c.What is the probability of completing the project in 32 weeks or less?<div style=padding-top: 35px>
a.Determine the standard deviation of the critical path.
b.Determine the probability of completing the project in 38 weeks or less.
c.What is the probability of completing the project in 32 weeks or less?
سؤال
Consider the project network and data shown below: Consider the project network and data shown below:     a.Determine the critical path and the project completion time. b.Determine the crash cost per week for all activities c.Which activities need to be crashed to reduce the project's completion time by 4 weeks? How much does this cost?<div style=padding-top: 35px> Consider the project network and data shown below:     a.Determine the critical path and the project completion time. b.Determine the crash cost per week for all activities c.Which activities need to be crashed to reduce the project's completion time by 4 weeks? How much does this cost?<div style=padding-top: 35px>
a.Determine the critical path and the project completion time.
b.Determine the crash cost per week for all activities
c.Which activities need to be crashed to reduce the project's completion time by 4 weeks? How much does this cost?
سؤال
Describe how a project fits into each of the three common organizational structures.
سؤال
Explain the three time estimates used to characterize uncertainty of activity times in the Program Evaluation and Review Technique (PERT) procedure.
سؤال
Describe the four major steps in the project-planning process.
سؤال
The following network shows all the major activities on the circles (nodes). Each node contains time estimates in weeks. The following network shows all the major activities on the circles (nodes). Each node contains time estimates in weeks.   Complete the following table.  <div style=padding-top: 35px> Complete the following table. The following network shows all the major activities on the circles (nodes). Each node contains time estimates in weeks.   Complete the following table.  <div style=padding-top: 35px>
سؤال
The following network shows the activities on the circles or nodes. Time estimates are in weeks. The following network shows the activities on the circles or nodes. Time estimates are in weeks.   Complete the following table:  <div style=padding-top: 35px> Complete the following table: The following network shows the activities on the circles or nodes. Time estimates are in weeks.   Complete the following table:  <div style=padding-top: 35px>
سؤال
Consider the project network and data shown below: Consider the project network and data shown below:     a.Determine the critical path. b.If management wants the project done in one less month, which activity should they crash?<div style=padding-top: 35px> Consider the project network and data shown below:     a.Determine the critical path. b.If management wants the project done in one less month, which activity should they crash?<div style=padding-top: 35px>
a.Determine the critical path.
b.If management wants the project done in one less month, which activity should they crash?
سؤال
List at least six principal factors (contributors) to project success.
سؤال
The network below represents a project being analyzed by the Critical Path Method. The network below represents a project being analyzed by the Critical Path Method.   a.What activity must be on the critical path, regardless of activity durations? b.What is the duration of path A-B-E-H-J? c.What is the critical path of this network? d.What is the length of the critical path?<div style=padding-top: 35px>
a.What activity must be on the critical path, regardless of activity durations?
b.What is the duration of path A-B-E-H-J?
c.What is the critical path of this network?
d.What is the length of the critical path?
سؤال
Explain the stages of the project life cycle.
سؤال
Explain the purpose of Gantt charts.
سؤال
A company has used PERT for a project and wants to minimize the probability of overrunning a contract deadline of 30 weeks. Three paths of concern in the PERT network have these mean durations and variances in weeks: A company has used PERT for a project and wants to minimize the probability of overrunning a contract deadline of 30 weeks. Three paths of concern in the PERT network have these mean durations and variances in weeks:   a.What is the Z-score for path 1? b.What is the probability of path 2 overrunning the deadline?<div style=padding-top: 35px>
a.What is the Z-score for path 1?
b.What is the probability of path 2 overrunning the deadline?
سؤال
Define a project. Give some non-manufacturing or non-construction examples.
سؤال
An electrical contracting company has been awarded a government contract to install lighting fixtures on a major highway. They want to use a horizontal bar chart to plan the schedule for the contract with work to begin on January 1 and assuming four weeks per month. The company has established the following project activities, their precedence relationships, and their estimated normal times: An electrical contracting company has been awarded a government contract to install lighting fixtures on a major highway. They want to use a horizontal bar chart to plan the schedule for the contract with work to begin on January 1 and assuming four weeks per month. The company has established the following project activities, their precedence relationships, and their estimated normal times:   a.When does activity d begin? b.When does activity f end?<div style=padding-top: 35px>
a.When does activity d begin?
b.When does activity f end?
فتح الحزمة
قم بالتسجيل لفتح البطاقات في هذه المجموعة!
Unlock Deck
Unlock Deck
1/60
auto play flashcards
العب
simple tutorial
ملء الشاشة (f)
exit full mode
Deck 18: Project Management
1
When the beta probability distribution is used to characterize uncertain activity times, the distribution of the project completion time will also have a beta probability distribution.
False
2
A slack of (-2) means the project is ahead of schedule by two time periods.
False
3
Project managers need to be specialists, not generalists.
False
4
The Critical Path Method (CPM) allows for an evaluation of uncertainty in project completion times.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
5
Activity times must be estimated from historical data of similar work tasks to provide realism for a project.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
6
With the Activity-On-Node (AON) network, the nodes define the precedence relationships and the arcs define the work activities.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
7
Using a beta probability distribution to characterize uncertain activity times is practical because it allows managers to use judgmental estimates to identify the distribution.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
8
Because the preparation of annual reports is done on a repeating basis, project management techniques are not appropriate.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
9
A statement of work would be developed in the "Organize" step of the project life cycle.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
10
In a matrix organization, functional managers may be reluctant to provide the resources and employees, and the employees assigned to projects may relegate a project to a lower priority than their daily functional job.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
11
All activities on the critical path have a zero slack time.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
12
The early start time for an activity is computed by finding the largest early finish time of all immediate predecessors.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
13
The critical path is the sequence of activities that takes the longest time.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
14
In most organizations, projects cut across organizational boundaries, making it difficult to implement projects exclusively within functional departments.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
15
Immediate predecessors are activities that must be completed immediately before an activity may start.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
16
To compute the critical path, we assign all nodes in the network an earliest starting time of zero.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
17
Strong leadership is an impediment to project management success because of the team-based nature of most projects.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
18
Project management objectives revolved around on-time and budget performance.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
19
Crashing refers to the process of shortening selected activity times in order to reduce the overall project completion time.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
20
A Gantt chart is a useful tool for allocating limited resources among project activities.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
21
Which step in the project management process would involve determining time estimates for activities?

A)Project definition
B)Resource planning
C)Project scheduling
D)Project control
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
22
Which of the following is not considered a project?

A)Writing and implementing a computer program
B)Introducing a new product
C)Production of soft drinks
D)Building a bridge
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
23
The slack for an activity is equal to its latest finish time minus its earliest start time.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
24
The county government has decided to redo the street you live on and plans to block the street off which causes you and your neighbor's considerable inconvenience. The project has three parallel paths defined as follows: (i) path A-B-C-H to install street lights and electrical wiring that takes 16 days, (ii) path A-D-E-H to install sidewalks with handicap capabilities that takes 22 days, and (iii) path A-F-G-H to repave the street including storm drains that takes 30 days. Which one of the following statements is true?

A)The expected duration of the project is 30 + 22 + 16 = 68 days.
B)Path A-B-C-H is the critical path.
C)Path A-D-E-H has the most slack time.
D)Path A-F-G-H is the critical path.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
25
A project has three paths. A-B-C has a length of 25 days. A-D-C has a length of 15 days. Finally, A-E-C has a length of 20 days. Which one of the following statements is true?

A)A-D-C is the critical path.
B)A-B-C has the most slack.
C)The expected duration of this project is 25 days.
D)The expected duration of this project is 25 + 15 + 20 = 60 days.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
26
A type of organization which "loans" resources to projects while still maintaining control over them is called

A)Pure project structure
B)Pure functional structure
C)Matrix structure
D)Product structure
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
27
Which step in the project management process would involve developing alternative plans in anticipation of problems that might arise?

A)Project definition
B)Resource planning
C)Project scheduling
D)Project control
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
28
In which stage in the project life cycle would critical path calculations be performed?

A)Define
B)Plan
C)Organize
D)Control
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
29
Which of the following is not an assumption of the critical path method?

A)Activities are independent of one another
B)Activity time estimates are stable
C)Activity times are characterized by a beta probability distribution
D)Once an activity is started it continues uninterrupted until completion
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
30
Which statement is true regarding activities not on the critical path?

A)Usually cannot be delayed
B)Have less slack than activities on the critical path
C)Can delay a project if they are highly variable
D)Are used to crash project completion times
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
31
We should not crash activities on the critical path.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
32
Which is incorrect regarding the critical path?

A)Shortest time to complete a project
B)Longest time to complete a project
C)Project path with 0 slack
D)Delays in activities will delay the project
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
33
Which of the following is incorrect regarding time/cost trade-offs?

A)The relationship between time and cost is proportional
B)Some activities cannot be crashed
C)The minimum cost can be found by crashing all activities as much as possible
D)Crashing priority is based on the amount of uncertainty in activity times
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
34
Slack in an activity is computed as

A)ES -LS
B)EF - LF
C)LS - ES
D)LS - EF
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
35
When finding the earliest finish (EF) time for an activity with two or more predecessor activities, the largest EF among the predecessor activities is used to calculate the EF for that activity.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
36
In which stage in the project life cycle would a Gantt chart be used?

A)Define
B)Plan
C)Organize
D)Control
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
37
Which of the following is not a stage in the project life cycle?

A)Define
B)Organize
C)Improve
D)Close
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
38
In which stage in the project life cycle would crashing likely be performed?

A)Define
B)Plan
C)Organize
D)Control
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
39
A type of organization that can result in inefficiencies because of duplication of resources across the organization is called

A)Pure project structure
B)Pure functional structure
C)Matrix structure
D)Product structure
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
40
Which of the following is least related to Program Evaluation and Review Technique (PERT)?

A)Beta distribution
B)Variance
C)Most probable time
D)Crashing
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
41
Define critical path and explain how it is identified once a project schedule is calculated.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
42
A company has a PERT project with path b-d-e-g-i that has these activity time estimates in days: A company has a PERT project with path b-d-e-g-i that has these activity time estimates in days:   a.What is the expected duration for activity e? b.What is the variance for activity b? c.What is the standard deviation of the path?
a.What is the expected duration for activity e?
b.What is the variance for activity b?
c.What is the standard deviation of the path?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
43
You are in charge of the "advertising program" for the Boston Red Sox baseball team during their spring training in Fort Myers, Florida. You have defined the advertising program as a project with the following characteristics. The goal is to fill all stadium seats during the spring training season. You are in charge of the advertising program for the Boston Red Sox baseball team during their spring training in Fort Myers, Florida. You have defined the advertising program as a project with the following characteristics. The goal is to fill all stadium seats during the spring training season.   a.What is the earliest completion time for this project? b.What is the largest amount of slack that any activity has in this project? c.If activity C is delayed three weeks, what is the revised earliest project completion time? d.For the original CPM problem, what is the minimum number of activities that would have to be crashed in order to reduce the project's earliest completion time by two weeks assuming all activity crash costs per week are the same and all activities can be crashed?
a.What is the earliest completion time for this project?
b.What is the largest amount of slack that any activity has in this project?
c.If activity C is delayed three weeks, what is the revised earliest project completion time?
d.For the original CPM problem, what is the minimum number of activities that would have to be crashed in order to reduce the project's earliest completion time by two weeks assuming all activity crash costs per week are the same and all activities can be crashed?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
44
Explain the role of the project managers and some principles for success.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
45
You are responsible for managing an advertising and promotion project with the following activities (times are given in weeks). You are responsible for managing an advertising and promotion project with the following activities (times are given in weeks).   a.What is the critical path and expected completion time for this project? b.Which activity has the largest slack, and how large is that slack? c.What is the probability that the project will be completed within 16 weeks? d.If the expected time (not the most likely time) for activity B is changed to 18 weeks from 11 weeks, by how many weeks will the project's expected completion time increase?
a.What is the critical path and expected completion time for this project?
b.Which activity has the largest slack, and how large is that slack?
c.What is the probability that the project will be completed within 16 weeks?
d.If the expected time (not the most likely time) for activity B is changed to 18 weeks from 11 weeks, by how many weeks will the project's expected completion time increase?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
46
Data regarding the activities for a project are presented below. The times are in weeks. The critical path for this project is A - D - H - I - J - K. Data regarding the activities for a project are presented below. The times are in weeks. The critical path for this project is A - D - H - I - J - K.   a.Determine the standard deviation of the critical path. b.Determine the probability of completing the project in 38 weeks or less. c.What is the probability of completing the project in 32 weeks or less?
a.Determine the standard deviation of the critical path.
b.Determine the probability of completing the project in 38 weeks or less.
c.What is the probability of completing the project in 32 weeks or less?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
47
Consider the project network and data shown below: Consider the project network and data shown below:     a.Determine the critical path and the project completion time. b.Determine the crash cost per week for all activities c.Which activities need to be crashed to reduce the project's completion time by 4 weeks? How much does this cost? Consider the project network and data shown below:     a.Determine the critical path and the project completion time. b.Determine the crash cost per week for all activities c.Which activities need to be crashed to reduce the project's completion time by 4 weeks? How much does this cost?
a.Determine the critical path and the project completion time.
b.Determine the crash cost per week for all activities
c.Which activities need to be crashed to reduce the project's completion time by 4 weeks? How much does this cost?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
48
Describe how a project fits into each of the three common organizational structures.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
49
Explain the three time estimates used to characterize uncertainty of activity times in the Program Evaluation and Review Technique (PERT) procedure.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
50
Describe the four major steps in the project-planning process.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
51
The following network shows all the major activities on the circles (nodes). Each node contains time estimates in weeks. The following network shows all the major activities on the circles (nodes). Each node contains time estimates in weeks.   Complete the following table.  Complete the following table. The following network shows all the major activities on the circles (nodes). Each node contains time estimates in weeks.   Complete the following table.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
52
The following network shows the activities on the circles or nodes. Time estimates are in weeks. The following network shows the activities on the circles or nodes. Time estimates are in weeks.   Complete the following table:  Complete the following table: The following network shows the activities on the circles or nodes. Time estimates are in weeks.   Complete the following table:
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
53
Consider the project network and data shown below: Consider the project network and data shown below:     a.Determine the critical path. b.If management wants the project done in one less month, which activity should they crash? Consider the project network and data shown below:     a.Determine the critical path. b.If management wants the project done in one less month, which activity should they crash?
a.Determine the critical path.
b.If management wants the project done in one less month, which activity should they crash?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
54
List at least six principal factors (contributors) to project success.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
55
The network below represents a project being analyzed by the Critical Path Method. The network below represents a project being analyzed by the Critical Path Method.   a.What activity must be on the critical path, regardless of activity durations? b.What is the duration of path A-B-E-H-J? c.What is the critical path of this network? d.What is the length of the critical path?
a.What activity must be on the critical path, regardless of activity durations?
b.What is the duration of path A-B-E-H-J?
c.What is the critical path of this network?
d.What is the length of the critical path?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
56
Explain the stages of the project life cycle.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
57
Explain the purpose of Gantt charts.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
58
A company has used PERT for a project and wants to minimize the probability of overrunning a contract deadline of 30 weeks. Three paths of concern in the PERT network have these mean durations and variances in weeks: A company has used PERT for a project and wants to minimize the probability of overrunning a contract deadline of 30 weeks. Three paths of concern in the PERT network have these mean durations and variances in weeks:   a.What is the Z-score for path 1? b.What is the probability of path 2 overrunning the deadline?
a.What is the Z-score for path 1?
b.What is the probability of path 2 overrunning the deadline?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
59
Define a project. Give some non-manufacturing or non-construction examples.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
60
An electrical contracting company has been awarded a government contract to install lighting fixtures on a major highway. They want to use a horizontal bar chart to plan the schedule for the contract with work to begin on January 1 and assuming four weeks per month. The company has established the following project activities, their precedence relationships, and their estimated normal times: An electrical contracting company has been awarded a government contract to install lighting fixtures on a major highway. They want to use a horizontal bar chart to plan the schedule for the contract with work to begin on January 1 and assuming four weeks per month. The company has established the following project activities, their precedence relationships, and their estimated normal times:   a.When does activity d begin? b.When does activity f end?
a.When does activity d begin?
b.When does activity f end?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.
فتح الحزمة
k this deck
locked card icon
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 60 في هذه المجموعة.