Deck 14: Managing Projects

ملء الشاشة (f)
exit full mode
سؤال
An expectation that a new building's foundation would be poured and cured by the end of the year is an example of a(n):

A)activity.
B)scope.
C)milestone.
D)precedence.
استخدم زر المسافة أو
up arrow
down arrow
لقلب البطاقة.
سؤال
In what ways are projects distinct from typical business activities?
سؤال
During the ________, project planners identify how to accomplish the work, how to organize for the project, and the key personnel and resources needed.
سؤال
A performance or time target for each major group of activities in a project is a(n)________.
سؤال
Execution of the project's constituent activities begins in the project's:

A)planning phase.
B)concept phase.
C)post-completion phase.
D)performance phase.
سؤال
A project is a temporary undertaking designed to create a unique, product, service or results.
سؤال
The Triskaidekaphobia Project is starting its tenth week and the Gantt chart appears below. Which of these statements about the project is incorrect? <strong>The Triskaidekaphobia Project is starting its tenth week and the Gantt chart appears below. Which of these statements about the project is incorrect?  </strong> A)The critical path is BCEF. B)Five of the activities are complete. C)Activity D had one week of slack. D)The project is behind schedule. <div style=padding-top: 35px>

A)The critical path is BCEF.
B)Five of the activities are complete.
C)Activity D had one week of slack.
D)The project is behind schedule.
سؤال
This Gantt chart can be used to show: <strong>This Gantt chart can be used to show:  </strong> A)activity D must come before activity C. B)activity F can be done at the same time as D. C)activity E can begin as soon as activity A is complete. D)activities D and B can be done simultaneously. <div style=padding-top: 35px>

A)activity D must come before activity C.
B)activity F can be done at the same time as D.
C)activity E can begin as soon as activity A is complete.
D)activities D and B can be done simultaneously.
سؤال
One of the primary characteristics of projects as a form of work is the movement of personnel from project to project.
سؤال
Discuss the recent business trends that have increased the attention and interest in project management skills.
سؤال
In what way are projects and typical business activities similar?

A)For most companies, projects and typical business activities can be described as routine.
B)Both projects and typical business activities have a defined ending point at which time they are complete.
C)Projects and routine business activities require significant levels of cross-functional and interorganizational coordination.
D)The successful completion of projects and business activities is essential to a firm's competitive position.
سؤال
Performance or time targets for each major group of activities in a project are set during the planning phase of a project.
سؤال
There are more resources required during the performance phase of a project than the project definition phase.
سؤال
Key points in a project, such as when a major activity or phase should be completed, are referred to as lodestones.
سؤال
PERT is an acronym meaning:

A)Project Evaluation and Review Technique.
B)Project Execution and Review Technique.
C)Program Evaluation and Review Technique.
D)Plan Estimation and Review Technique.
سؤال
Project planners develop a broad definition of what the project is and what its scope will be during the:

A)concept phase.
B)project definition phase.
C)planning phase.
D)performance phase.
سؤال
The actual work gets done during the ________ phase of a project.
سؤال
What are the phases of a project and the activities within each?
سؤال
The budget estimates made during the concept phase are usually accurate to within:

A)20 percent.
B)30 percent.
C)40 percent.
D)50 percent.
سؤال
In the project definition phase, project planners identify, among other tasks, how to accomplish the work and how to organize for the project.
سؤال
The tablet unearthed by the archaeologist revealed an ancient culture's project plan. However, the sands of time had erased much of the information that the table once contained. Use this fragmentary record to unlock the ancient project's secrets and answer the following question(s).
 Activity  Predecessors  Time  ES  EF  LS  LF  A 712 B 8 C  A 1320 D  A 1112 E  B 1417 F  B 11 G  D, E 6 H  C 20 K  F 29 L G,H,K9\begin{array} { | c | c | c | c | c | c | c | } \hline \text { Activity } & \text { Predecessors } & \text { Time } & \text { ES } & \text { EF } & \text { LS } & \text { LF } \\\hline \text { A } & \cdots & 7 & & & & 12 \\\hline \text { B } & \cdots & 8 & & & & \\\hline \text { C } & \text { A } & & & & 13 & 20 \\\hline \text { D } & \text { A } & 11 & & & 12 & \\\hline \text { E } & \text { B } & & & 14 & 17 & \\\hline \text { F } & \text { B } & 11 & & & & \\\hline \text { G } & \text { D, E } & 6 & & & & \\\hline \text { H } & \text { C } & & & & 20 & \\\hline \text { K } & \text { F } & & & 29 & & \\\hline \text { L } & G , H , K & 9 & & & & \\\hline\end{array}

-Refer to the scenario above. What is the earliest start time for activity H?

A)Week 14
B)Week 15
C)Week 16
D)Week 17
سؤال
A Gantt chart provides both a planning function and a control function.
سؤال
A hatmaker, fresh off a very successful showing at Lidzapalooza is excited about the prospects of providing the finest chapeaus to meet the needs of his energized customer base in the coming year. He and his space designer have identified seven activities that are necessary to expand his small shop. For the sake of simplicity, and to avoid giving away any trade secrets, the activities have been identified by letters A-G. The activities, their time estimates, and the precedence requirements are listed in the table immediately below. Use this scenario to answer the following question(s).
 Activity  Predecessors  Time (weeks)  A 7 B  A 6 C  A 10 D  C 12 E  B, C 5 F  D, E 11 G  F 8\begin{array} { | c | c | c | } \hline \text { Activity } & \text { Predecessors } & \text { Time (weeks) } \\\hline \text { A } & - & 7 \\\hline \text { B } & \text { A } & 6 \\\hline \text { C } & \text { A } & 10 \\\hline \text { D } & \text { C } & 12 \\\hline \text { E } & \text { B, C } & 5 \\\hline \text { F } & \text { D, E } & 11 \\\hline \text { G } & \text { F } & 8 \\\hline\end{array}

-Refer to the scenario above. Which of these statements is BEST?

A)Only four of these activities have zero slack.
B)The late finish of D minus the latest finish of C is less than the slack of B.
C)B's latest start plus its slack equals F's latest finish.
D)The sum of the latest start times for activities A through E is less than the sum of the latest start times for F and G.
سؤال
A Gantt chart explicitly shows precedence requirements for a project's constituent activities.
سؤال
A project is composed of 6 activities that have durations and precedence requirements shown in the table. Which of these activities is NOT on the critical path?  Activity  Length  Predecessor  A 5 B 7 A  C 4 A  D 7 B,C  E 7 B  F 6 D, E \begin{array} { | c | c | c | } \hline \text { Activity } & \text { Length } & \text { Predecessor } \\\hline \text { A } & 5 & \cdots \\\hline \text { B } & 7 & \text { A } \\\hline \text { C } & 4 & \text { A } \\\hline \text { D } & 7 & \text { B,C } \\\hline \text { E } & 7 & \text { B } \\\hline \text { F } & 6 & \text { D, E } \\\hline\end{array}

A)A
B)B
C)C
D)D
سؤال
Construction of the cattery could be distilled to eight distinct steps, from the official groundbreaking ceremony to the cutting of the litterbox ribbon. The activities, their durations and predecessors are shown in the table below. Use this scenario to answer the following question(s).
 Activity  Predecessors  Time (weeks)  A 10 B  A 8 C  A 7 D  C 11 E  D 12 F  B 11 G  E, F 6 H  E, F 9\begin{array} { | c | c | c | } \hline \text { Activity } & \text { Predecessors } & \text { Time (weeks) } \\\hline \text { A } & \cdots & 10 \\\hline \text { B } & \text { A } & 8 \\\hline \text { C } & \text { A } & 7 \\\hline \text { D } & \text { C } & 11 \\\hline \text { E } & \text { D } & 12 \\\hline \text { F } & \text { B } & 11 \\\hline \text { G } & \text { E, F } & 6 \\\hline \text { H } & \text { E, F } & 9 \\\hline\end{array}

-Refer to the scenario above. The fastest the project can be completed is:

A)49 weeks
B)46 weeks
C)38 weeks
D)35 weeks
سؤال
Construction of the cattery could be distilled to eight distinct steps, from the official groundbreaking ceremony to the cutting of the litterbox ribbon. The activities, their durations and predecessors are shown in the table below. Use this scenario to answer the following question(s).
 Activity  Predecessors  Time (weeks)  A 10 B  A 8 C  A 7 D  C 11 E  D 12 F  B 11 G  E, F 6 H  E, F 9\begin{array} { | c | c | c | } \hline \text { Activity } & \text { Predecessors } & \text { Time (weeks) } \\\hline \text { A } & \cdots & 10 \\\hline \text { B } & \text { A } & 8 \\\hline \text { C } & \text { A } & 7 \\\hline \text { D } & \text { C } & 11 \\\hline \text { E } & \text { D } & 12 \\\hline \text { F } & \text { B } & 11 \\\hline \text { G } & \text { E, F } & 6 \\\hline \text { H } & \text { E, F } & 9 \\\hline\end{array}

-Refer to the scenario above. Which of these activities has the least slack?

A)E
B)B
C)G
D)F
سؤال
Program evaluation and review technique, PERT, is a network-based technique in which there are multiple time estimates for each activity.
سؤال
Most project management software represents a project in AON format.
سؤال
Construction of the cattery could be distilled to eight distinct steps, from the official groundbreaking ceremony to the cutting of the litterbox ribbon. The activities, their durations and predecessors are shown in the table below. Use this scenario to answer the following question(s).
 Activity  Predecessors  Time (weeks)  A 10 B  A 8 C  A 7 D  C 11 E  D 12 F  B 11 G  E, F 6 H  E, F 9\begin{array} { | c | c | c | } \hline \text { Activity } & \text { Predecessors } & \text { Time (weeks) } \\\hline \text { A } & \cdots & 10 \\\hline \text { B } & \text { A } & 8 \\\hline \text { C } & \text { A } & 7 \\\hline \text { D } & \text { C } & 11 \\\hline \text { E } & \text { D } & 12 \\\hline \text { F } & \text { B } & 11 \\\hline \text { G } & \text { E, F } & 6 \\\hline \text { H } & \text { E, F } & 9 \\\hline\end{array}

-Refer to the scenario above. What is the slack for activity G?

A)4 weeks
B)3 weeks
C)2 weeks
D)1 week
سؤال
Construction of the cattery could be distilled to eight distinct steps, from the official groundbreaking ceremony to the cutting of the litterbox ribbon. The activities, their durations and predecessors are shown in the table below. Use this scenario to answer the following question.  Activity  Predecessors  Time (weeks)  A 10 B  A 8 C  A 7 D  C 11 E  D 12 F  B 11 G  E, F 6 H  E, F 9\begin{array} { | c | c | c | } \hline \text { Activity } & \text { Predecessors } & \text { Time (weeks) } \\\hline \text { A } & \cdots & 10 \\\hline \text { B } & \text { A } & 8 \\\hline \text { C } & \text { A } & 7 \\\hline \text { D } & \text { C } & 11 \\\hline \text { E } & \text { D } & 12 \\\hline \text { F } & \text { B } & 11 \\\hline \text { G } & \text { E, F } & 6 \\\hline \text { H } & \text { E, F } & 9 \\\hline\end{array} Refer to the scenario above. One activity has identical earliest finish and latest start times. What is the common number for this unusual activity?

A)17
B)18
C)21
D)29
سؤال
The tablet unearthed by the archaeologist revealed an ancient culture's project plan. However, the sands of time had erased much of the information that the table once contained. Use this fragmentary record to unlock the ancient project's secrets and answer the following question(s).
 Activity  Predecessors  Time  ES  EF  LS  LF  A 712 B 8 C  A 1320 D  A 1112 E  B 1417 F  B 11 G  D, E 6 H  C 20 K  F 29 L G,H,K9\begin{array} { | c | c | c | c | c | c | c | } \hline \text { Activity } & \text { Predecessors } & \text { Time } & \text { ES } & \text { EF } & \text { LS } & \text { LF } \\\hline \text { A } & \cdots & 7 & & & & 12 \\\hline \text { B } & \cdots & 8 & & & & \\\hline \text { C } & \text { A } & & & & 13 & 20 \\\hline \text { D } & \text { A } & 11 & & & 12 & \\\hline \text { E } & \text { B } & & & 14 & 17 & \\\hline \text { F } & \text { B } & 11 & & & & \\\hline \text { G } & \text { D, E } & 6 & & & & \\\hline \text { H } & \text { C } & & & & 20 & \\\hline \text { K } & \text { F } & & & 29 & & \\\hline \text { L } & G , H , K & 9 & & & & \\\hline\end{array}

-Refer to the scenario above. What is the duration of activity H?

A)7 weeks
B)8 weeks
C)9 weeks
D)10 weeks
سؤال
The tablet unearthed by the archaeologist revealed an ancient culture's project plan. However, the sands of time had erased much of the information that the table once contained. Use this fragmentary record to unlock the ancient project's secrets and answer the following question(s).
 Activity  Predecessors  Time  ES  EF  LS  LF  A 712 B 8 C  A 1320 D  A 1112 E  B 1417 F  B 11 G  D, E 6 H  C 20 K  F 29 L G,H,K9\begin{array} { | c | c | c | c | c | c | c | } \hline \text { Activity } & \text { Predecessors } & \text { Time } & \text { ES } & \text { EF } & \text { LS } & \text { LF } \\\hline \text { A } & \cdots & 7 & & & & 12 \\\hline \text { B } & \cdots & 8 & & & & \\\hline \text { C } & \text { A } & & & & 13 & 20 \\\hline \text { D } & \text { A } & 11 & & & 12 & \\\hline \text { E } & \text { B } & & & 14 & 17 & \\\hline \text { F } & \text { B } & 11 & & & & \\\hline \text { G } & \text { D, E } & 6 & & & & \\\hline \text { H } & \text { C } & & & & 20 & \\\hline \text { K } & \text { F } & & & 29 & & \\\hline \text { L } & G , H , K & 9 & & & & \\\hline\end{array}

-Refer to the scenario above. What is the latest start time for activity K?

A)Week 20
B)Week 19
C)Week 18
D)Week 17
سؤال
What is the latest that activity B can start if A lasts 35 days, B lasts 5, days C lasts 6 days, and D lasts 7 days? <strong>What is the latest that activity B can start if A lasts 35 days, B lasts 5, days C lasts 6 days, and D lasts 7 days?  </strong> A)35 B)36 C)40 D)41 <div style=padding-top: 35px>

A)35
B)36
C)40
D)41
سؤال
A hatmaker, fresh off a very successful showing at Lidzapalooza is excited about the prospects of providing the finest chapeaus to meet the needs of his energized customer base in the coming year. He and his space designer have identified seven activities that are necessary to expand his small shop. For the sake of simplicity, and to avoid giving away any trade secrets, the activities have been identified by letters A-G. The activities, their time estimates, and the precedence requirements are listed in the table immediately below. Use this scenario to answer the following question(s).
 Activity  Predecessors  Time (weeks)  A 7 B  A 6 C  A 10 D  C 12 E  B, C 5 F  D, E 11 G  F 8\begin{array} { | c | c | c | } \hline \text { Activity } & \text { Predecessors } & \text { Time (weeks) } \\\hline \text { A } & - & 7 \\\hline \text { B } & \text { A } & 6 \\\hline \text { C } & \text { A } & 10 \\\hline \text { D } & \text { C } & 12 \\\hline \text { E } & \text { B, C } & 5 \\\hline \text { F } & \text { D, E } & 11 \\\hline \text { G } & \text { F } & 8 \\\hline\end{array}

-Refer to the scenario above. Which of these activities has slack?

A)G
B)E
C)F
D)D
سؤال
What is the latest that activity D can start if A lasts 5 days, B lasts 7 days, C lasts 4 days, D lasts 5 days, E lasts 7 days, and F is 6 days long? <strong>What is the latest that activity D can start if A lasts 5 days, B lasts 7 days, C lasts 4 days, D lasts 5 days, E lasts 7 days, and F is 6 days long?  </strong> A)14 B)15 C)16 D)17 <div style=padding-top: 35px>

A)14
B)15
C)16
D)17
سؤال
The tablet unearthed by the archaeologist revealed an ancient culture's project plan. However, the sands of time had erased much of the information that the table once contained. Use this fragmentary record to unlock the ancient project's secrets and answer the following question(s).
 Activity  Predecessors  Time  ES  EF  LS  LF  A 712 B 8 C  A 1320 D  A 1112 E  B 1417 F  B 11 G  D, E 6 H  C 20 K  F 29 L G,H,K9\begin{array} { | c | c | c | c | c | c | c | } \hline \text { Activity } & \text { Predecessors } & \text { Time } & \text { ES } & \text { EF } & \text { LS } & \text { LF } \\\hline \text { A } & \cdots & 7 & & & & 12 \\\hline \text { B } & \cdots & 8 & & & & \\\hline \text { C } & \text { A } & & & & 13 & 20 \\\hline \text { D } & \text { A } & 11 & & & 12 & \\\hline \text { E } & \text { B } & & & 14 & 17 & \\\hline \text { F } & \text { B } & 11 & & & & \\\hline \text { G } & \text { D, E } & 6 & & & & \\\hline \text { H } & \text { C } & & & & 20 & \\\hline \text { K } & \text { F } & & & 29 & & \\\hline \text { L } & G , H , K & 9 & & & & \\\hline\end{array}

-Refer to the scenario above. What is the earliest finish time for activity G?

A)Week 21
B)Week 22
C)Week 23
D)Week 24
سؤال
What is the fastest completion time of the project with activity lengths (in days)and precedence requirements as shown in the table?  Activity  Length  Predecessor  A 15 B 7 A  C 4 A  D 8 B, C \begin{array} { | c | c | c | } \hline \text { Activity } & \text { Length } & \text { Predecessor } \\\hline \text { A } & 15 & \cdots \\\hline \text { B } & 7 & \text { A } \\\hline \text { C } & 4 & \text { A } \\\hline \text { D } & 8 & \text { B, C } \\\hline\end{array}

A)22
B)25
C)27
D)30
سؤال
Which of the activities in this project has the greatest amount of slack?  Activity  Length  Predecessor  A 7 B 4 A  C 8 A  D 3B,C E 2B F 8 D, E \begin{array} { | c | c | c | } \hline \text { Activity } & \text { Length } & \text { Predecessor } \\\hline \text { A } & 7 & \cdots \\\hline \text { B } & 4 & \text { A } \\\hline \text { C } & 8 & \text { A } \\\hline \text { D } & 3 & B , C \\\hline \text { E } & 2 & B \\\hline \text { F } & 8 & \text { D, E } \\\hline\end{array}

A)B
B)C
C)D
D)E
سؤال
The tablet unearthed by the archaeologist revealed an ancient culture's project plan. However, the sands of time had erased much of the information that the table once contained. Use this fragmentary record to unlock the ancient project's secrets and answer the following question(s).
 Activity  Predecessors  Time  ES  EF  LS  LF  A 712 B 8 C  A 1320 D  A 1112 E  B 1417 F  B 11 G  D, E 6 H  C 20 K  F 29 L G,H,K9\begin{array} { | c | c | c | c | c | c | c | } \hline \text { Activity } & \text { Predecessors } & \text { Time } & \text { ES } & \text { EF } & \text { LS } & \text { LF } \\\hline \text { A } & \cdots & 7 & & & & 12 \\\hline \text { B } & \cdots & 8 & & & & \\\hline \text { C } & \text { A } & & & & 13 & 20 \\\hline \text { D } & \text { A } & 11 & & & 12 & \\\hline \text { E } & \text { B } & & & 14 & 17 & \\\hline \text { F } & \text { B } & 11 & & & & \\\hline \text { G } & \text { D, E } & 6 & & & & \\\hline \text { H } & \text { C } & & & & 20 & \\\hline \text { K } & \text { F } & & & 29 & & \\\hline \text { L } & G , H , K & 9 & & & & \\\hline\end{array}

-Refer to the scenario above. The project's duration is:

A)32 weeks.
B)33 weeks.
C)36 weeks.
D)38 weeks.
سؤال
The earliest start time of an activity is dependent on the earliest finish time of its immediate predecessors.
سؤال
The longest path in a network from the start of a project to the end of a project is the ________.
سؤال
An activity's duration added to its earliest start time yields the ________.
سؤال
The earliest finish time of an activity is always later than its latest start time.
سؤال
The university president concocts a thirteen-step sinister plan to lower morale to zero during his last year in office. The duration of each step (in days)and the required predecessor(s)are displayed in the table.
The university president concocts a thirteen-step sinister plan to lower morale to zero during his last year in office. The duration of each step (in days)and the required predecessor(s)are displayed in the table.   What are the early and late start and finish times for this morale-lowering project?<div style=padding-top: 35px> What are the early and late start and finish times for this morale-lowering project?
سؤال
A hatmaker, fresh off a very successful showing at Lidzapalooza is excited about the prospects of providing the finest chapeaus to meet the needs of his energized customer base in the coming year. He and his space designer have identified seven activities that are necessary to expand his small shop. For the sake of simplicity, and to avoid giving away any trade secrets, the activities have been identified by letters A-G. The activities, their time estimates, and the precedence requirements structure are listed in the table immediately below. Use this table to answer the following question.
A hatmaker, fresh off a very successful showing at Lidzapalooza is excited about the prospects of providing the finest chapeaus to meet the needs of his energized customer base in the coming year. He and his space designer have identified seven activities that are necessary to expand his small shop. For the sake of simplicity, and to avoid giving away any trade secrets, the activities have been identified by letters A-G. The activities, their time estimates, and the precedence requirements structure are listed in the table immediately below. Use this table to answer the following question.   Refer to the scenario above. What are the earliest and latest start and finish times for all of these activities?<div style=padding-top: 35px> Refer to the scenario above. What are the earliest and latest start and finish times for all of these activities?
سؤال
The earliest finish time is calculated by adding the activity's duration to the predecessor's earliest finish time.
سؤال
A hatmaker, fresh off a very successful showing at Lidzapalooza is excited about the prospects of providing the finest chapeaus (hats, for those of you without a thesaurus)to meet the needs of his energized customer base in the coming year. He and his space designer have identified seven activities that are necessary to expand his small shop. For the sake of simplicity, and to avoid giving away any trade secrets, the activities have been identified by letters A-G. The activities, their time estimates, and the precedence requirements structure are listed in the table immediately below. Use this table to answer the following question(s).
A hatmaker, fresh off a very successful showing at Lidzapalooza is excited about the prospects of providing the finest chapeaus (hats, for those of you without a thesaurus)to meet the needs of his energized customer base in the coming year. He and his space designer have identified seven activities that are necessary to expand his small shop. For the sake of simplicity, and to avoid giving away any trade secrets, the activities have been identified by letters A-G. The activities, their time estimates, and the precedence requirements structure are listed in the table immediately below. Use this table to answer the following question(s).   Refer to the scenario above. Develop a Gantt chart for this project and indicate the finish times for each activity.<div style=padding-top: 35px>
Refer to the scenario above. Develop a Gantt chart for this project and indicate the finish times for each activity.
سؤال
A forward pass through a network is used to determine the earliest start times and earliest finish times for each project activity.
سؤال
Complete this table containing earliest and latest start times and activity lengths.
Complete this table containing earliest and latest start times and activity lengths.  <div style=padding-top: 35px>
سؤال
Given the earliest and latest finish times for each of these activities, what are the activity lengths?
Given the earliest and latest finish times for each of these activities, what are the activity lengths?  <div style=padding-top: 35px>
سؤال
For critical path activities, slack is equal to ________.
سؤال
A critical path is composed entirely of critical activities.
سؤال
Construction of the cattery could be distilled to eight distinct steps, from the official groundbreaking ceremony to the cutting of the litterbox ribbon. The activities, their durations and predecessors are shown in the table below. Determine earliest and latest start and finish times for all of the activities.
Construction of the cattery could be distilled to eight distinct steps, from the official groundbreaking ceremony to the cutting of the litterbox ribbon. The activities, their durations and predecessors are shown in the table below. Determine earliest and latest start and finish times for all of the activities.  <div style=padding-top: 35px>
سؤال
A project is composed of the twelve activities shown in the table. What are the earliest and latest start times for each of these activities?
A project is composed of the twelve activities shown in the table. What are the earliest and latest start times for each of these activities?  <div style=padding-top: 35px>
سؤال
A Gantt chart can be used for project planning and also project ________ .
سؤال
A hatmaker, fresh off a very successful showing at Lidzapalooza is excited about the prospects of providing the finest chapeaus (hats, for those of you without a thesaurus)to meet the needs of his energized customer base in the coming year. He and his space designer have identified seven activities that are necessary to expand his small shop. For the sake of simplicity, and to avoid giving away any trade secrets, the activities have been identified by letters A-G. The activities, their time estimates, and the precedence requirements structure are listed in the table immediately below. Use this table to answer the following question(s).
A hatmaker, fresh off a very successful showing at Lidzapalooza is excited about the prospects of providing the finest chapeaus (hats, for those of you without a thesaurus)to meet the needs of his energized customer base in the coming year. He and his space designer have identified seven activities that are necessary to expand his small shop. For the sake of simplicity, and to avoid giving away any trade secrets, the activities have been identified by letters A-G. The activities, their time estimates, and the precedence requirements structure are listed in the table immediately below. Use this table to answer the following question(s).   Refer to the scenario above. Develop a Gantt chart for this project and indicate the finish times for each activity.<div style=padding-top: 35px>
Refer to the scenario above. Develop a Gantt chart for this project and indicate the finish times for each activity.
سؤال
Activities on the critical path may have positive or negative slack as long as the overall slack time of the critical path is zero.
سؤال
The tablet unearthed by the archaeologist revealed an ancient culture's project plan, however the sands of time had erased much of the information that the table once contained. Unlock the ancient project's secrets by completing all of the information missing from this fragmentary record.
The tablet unearthed by the archaeologist revealed an ancient culture's project plan, however the sands of time had erased much of the information that the table once contained. Unlock the ancient project's secrets by completing all of the information missing from this fragmentary record.  <div style=padding-top: 35px>
سؤال
A(n)________ is a graphical tool used to show a project's progress as time elapses.
سؤال
The professional organization that serves the needs of project management professionals is ________.
سؤال
Which of these needs does the Guide to the Project Management Body of Knowledge NOT serve?

A)It provides a common language for discussing project management issues.
B)It provides a blueprint for ISO certification of the project management process.
C)It identifies and disseminates generally accepted project management knowledge and practices.
D)It serves as a basic reference source for project management.
سؤال
The Guide to the Project Management Body of Knowledge (PMBOK®)is divided into two main parts, the various business processes that organizations follow in carrying out projects and the nine knowledge areas applicable to nearly all projects.
سؤال
Describe some of the key features and advantages of project management software.
The university president concocts a thirteen-step sinister plan to lower morale to zero during his last year in office. The duration of each step (in days)and the required predecessor(s)are displayed in the table.
Describe some of the key features and advantages of project management software. The university president concocts a thirteen-step sinister plan to lower morale to zero during his last year in office. The duration of each step (in days)and the required predecessor(s)are displayed in the table.   Identify the activities that have slack and the amount of slack each has for this morale-lowering project?<div style=padding-top: 35px>
Identify the activities that have slack and the amount of slack each has for this morale-lowering project?
سؤال
Describe some of the key features and advantages of project management software.
The university president concocts a thirteen-step sinister plan to lower morale to zero during his last year in office. The duration of each step (in days)and the required predecessor(s)are displayed in the table.
Describe some of the key features and advantages of project management software. The university president concocts a thirteen-step sinister plan to lower morale to zero during his last year in office. The duration of each step (in days)and the required predecessor(s)are displayed in the table.   What is the critical path for this morale-lowering project?<div style=padding-top: 35px>
What is the critical path for this morale-lowering project?
فتح الحزمة
قم بالتسجيل لفتح البطاقات في هذه المجموعة!
Unlock Deck
Unlock Deck
1/65
auto play flashcards
العب
simple tutorial
ملء الشاشة (f)
exit full mode
Deck 14: Managing Projects
1
An expectation that a new building's foundation would be poured and cured by the end of the year is an example of a(n):

A)activity.
B)scope.
C)milestone.
D)precedence.
milestone.
2
In what ways are projects distinct from typical business activities?
Projects are distinct from typical business activities in four ways. First, projects are nonroutine. Second, the nonroutine nature of a project makes it very difficult to manage. Third, projects typically require significant levels of cross-functional and interorganizational coordination. Fourth, projects have a defined ending point at which time the project is complete.
3
During the ________, project planners identify how to accomplish the work, how to organize for the project, and the key personnel and resources needed.
project definition phase
4
A performance or time target for each major group of activities in a project is a(n)________.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
5
Execution of the project's constituent activities begins in the project's:

A)planning phase.
B)concept phase.
C)post-completion phase.
D)performance phase.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
6
A project is a temporary undertaking designed to create a unique, product, service or results.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
7
The Triskaidekaphobia Project is starting its tenth week and the Gantt chart appears below. Which of these statements about the project is incorrect? <strong>The Triskaidekaphobia Project is starting its tenth week and the Gantt chart appears below. Which of these statements about the project is incorrect?  </strong> A)The critical path is BCEF. B)Five of the activities are complete. C)Activity D had one week of slack. D)The project is behind schedule.

A)The critical path is BCEF.
B)Five of the activities are complete.
C)Activity D had one week of slack.
D)The project is behind schedule.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
8
This Gantt chart can be used to show: <strong>This Gantt chart can be used to show:  </strong> A)activity D must come before activity C. B)activity F can be done at the same time as D. C)activity E can begin as soon as activity A is complete. D)activities D and B can be done simultaneously.

A)activity D must come before activity C.
B)activity F can be done at the same time as D.
C)activity E can begin as soon as activity A is complete.
D)activities D and B can be done simultaneously.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
9
One of the primary characteristics of projects as a form of work is the movement of personnel from project to project.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
10
Discuss the recent business trends that have increased the attention and interest in project management skills.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
11
In what way are projects and typical business activities similar?

A)For most companies, projects and typical business activities can be described as routine.
B)Both projects and typical business activities have a defined ending point at which time they are complete.
C)Projects and routine business activities require significant levels of cross-functional and interorganizational coordination.
D)The successful completion of projects and business activities is essential to a firm's competitive position.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
12
Performance or time targets for each major group of activities in a project are set during the planning phase of a project.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
13
There are more resources required during the performance phase of a project than the project definition phase.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
14
Key points in a project, such as when a major activity or phase should be completed, are referred to as lodestones.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
15
PERT is an acronym meaning:

A)Project Evaluation and Review Technique.
B)Project Execution and Review Technique.
C)Program Evaluation and Review Technique.
D)Plan Estimation and Review Technique.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
16
Project planners develop a broad definition of what the project is and what its scope will be during the:

A)concept phase.
B)project definition phase.
C)planning phase.
D)performance phase.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
17
The actual work gets done during the ________ phase of a project.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
18
What are the phases of a project and the activities within each?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
19
The budget estimates made during the concept phase are usually accurate to within:

A)20 percent.
B)30 percent.
C)40 percent.
D)50 percent.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
20
In the project definition phase, project planners identify, among other tasks, how to accomplish the work and how to organize for the project.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
21
The tablet unearthed by the archaeologist revealed an ancient culture's project plan. However, the sands of time had erased much of the information that the table once contained. Use this fragmentary record to unlock the ancient project's secrets and answer the following question(s).
 Activity  Predecessors  Time  ES  EF  LS  LF  A 712 B 8 C  A 1320 D  A 1112 E  B 1417 F  B 11 G  D, E 6 H  C 20 K  F 29 L G,H,K9\begin{array} { | c | c | c | c | c | c | c | } \hline \text { Activity } & \text { Predecessors } & \text { Time } & \text { ES } & \text { EF } & \text { LS } & \text { LF } \\\hline \text { A } & \cdots & 7 & & & & 12 \\\hline \text { B } & \cdots & 8 & & & & \\\hline \text { C } & \text { A } & & & & 13 & 20 \\\hline \text { D } & \text { A } & 11 & & & 12 & \\\hline \text { E } & \text { B } & & & 14 & 17 & \\\hline \text { F } & \text { B } & 11 & & & & \\\hline \text { G } & \text { D, E } & 6 & & & & \\\hline \text { H } & \text { C } & & & & 20 & \\\hline \text { K } & \text { F } & & & 29 & & \\\hline \text { L } & G , H , K & 9 & & & & \\\hline\end{array}

-Refer to the scenario above. What is the earliest start time for activity H?

A)Week 14
B)Week 15
C)Week 16
D)Week 17
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
22
A Gantt chart provides both a planning function and a control function.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
23
A hatmaker, fresh off a very successful showing at Lidzapalooza is excited about the prospects of providing the finest chapeaus to meet the needs of his energized customer base in the coming year. He and his space designer have identified seven activities that are necessary to expand his small shop. For the sake of simplicity, and to avoid giving away any trade secrets, the activities have been identified by letters A-G. The activities, their time estimates, and the precedence requirements are listed in the table immediately below. Use this scenario to answer the following question(s).
 Activity  Predecessors  Time (weeks)  A 7 B  A 6 C  A 10 D  C 12 E  B, C 5 F  D, E 11 G  F 8\begin{array} { | c | c | c | } \hline \text { Activity } & \text { Predecessors } & \text { Time (weeks) } \\\hline \text { A } & - & 7 \\\hline \text { B } & \text { A } & 6 \\\hline \text { C } & \text { A } & 10 \\\hline \text { D } & \text { C } & 12 \\\hline \text { E } & \text { B, C } & 5 \\\hline \text { F } & \text { D, E } & 11 \\\hline \text { G } & \text { F } & 8 \\\hline\end{array}

-Refer to the scenario above. Which of these statements is BEST?

A)Only four of these activities have zero slack.
B)The late finish of D minus the latest finish of C is less than the slack of B.
C)B's latest start plus its slack equals F's latest finish.
D)The sum of the latest start times for activities A through E is less than the sum of the latest start times for F and G.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
24
A Gantt chart explicitly shows precedence requirements for a project's constituent activities.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
25
A project is composed of 6 activities that have durations and precedence requirements shown in the table. Which of these activities is NOT on the critical path?  Activity  Length  Predecessor  A 5 B 7 A  C 4 A  D 7 B,C  E 7 B  F 6 D, E \begin{array} { | c | c | c | } \hline \text { Activity } & \text { Length } & \text { Predecessor } \\\hline \text { A } & 5 & \cdots \\\hline \text { B } & 7 & \text { A } \\\hline \text { C } & 4 & \text { A } \\\hline \text { D } & 7 & \text { B,C } \\\hline \text { E } & 7 & \text { B } \\\hline \text { F } & 6 & \text { D, E } \\\hline\end{array}

A)A
B)B
C)C
D)D
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
26
Construction of the cattery could be distilled to eight distinct steps, from the official groundbreaking ceremony to the cutting of the litterbox ribbon. The activities, their durations and predecessors are shown in the table below. Use this scenario to answer the following question(s).
 Activity  Predecessors  Time (weeks)  A 10 B  A 8 C  A 7 D  C 11 E  D 12 F  B 11 G  E, F 6 H  E, F 9\begin{array} { | c | c | c | } \hline \text { Activity } & \text { Predecessors } & \text { Time (weeks) } \\\hline \text { A } & \cdots & 10 \\\hline \text { B } & \text { A } & 8 \\\hline \text { C } & \text { A } & 7 \\\hline \text { D } & \text { C } & 11 \\\hline \text { E } & \text { D } & 12 \\\hline \text { F } & \text { B } & 11 \\\hline \text { G } & \text { E, F } & 6 \\\hline \text { H } & \text { E, F } & 9 \\\hline\end{array}

-Refer to the scenario above. The fastest the project can be completed is:

A)49 weeks
B)46 weeks
C)38 weeks
D)35 weeks
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
27
Construction of the cattery could be distilled to eight distinct steps, from the official groundbreaking ceremony to the cutting of the litterbox ribbon. The activities, their durations and predecessors are shown in the table below. Use this scenario to answer the following question(s).
 Activity  Predecessors  Time (weeks)  A 10 B  A 8 C  A 7 D  C 11 E  D 12 F  B 11 G  E, F 6 H  E, F 9\begin{array} { | c | c | c | } \hline \text { Activity } & \text { Predecessors } & \text { Time (weeks) } \\\hline \text { A } & \cdots & 10 \\\hline \text { B } & \text { A } & 8 \\\hline \text { C } & \text { A } & 7 \\\hline \text { D } & \text { C } & 11 \\\hline \text { E } & \text { D } & 12 \\\hline \text { F } & \text { B } & 11 \\\hline \text { G } & \text { E, F } & 6 \\\hline \text { H } & \text { E, F } & 9 \\\hline\end{array}

-Refer to the scenario above. Which of these activities has the least slack?

A)E
B)B
C)G
D)F
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
28
Program evaluation and review technique, PERT, is a network-based technique in which there are multiple time estimates for each activity.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
29
Most project management software represents a project in AON format.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
30
Construction of the cattery could be distilled to eight distinct steps, from the official groundbreaking ceremony to the cutting of the litterbox ribbon. The activities, their durations and predecessors are shown in the table below. Use this scenario to answer the following question(s).
 Activity  Predecessors  Time (weeks)  A 10 B  A 8 C  A 7 D  C 11 E  D 12 F  B 11 G  E, F 6 H  E, F 9\begin{array} { | c | c | c | } \hline \text { Activity } & \text { Predecessors } & \text { Time (weeks) } \\\hline \text { A } & \cdots & 10 \\\hline \text { B } & \text { A } & 8 \\\hline \text { C } & \text { A } & 7 \\\hline \text { D } & \text { C } & 11 \\\hline \text { E } & \text { D } & 12 \\\hline \text { F } & \text { B } & 11 \\\hline \text { G } & \text { E, F } & 6 \\\hline \text { H } & \text { E, F } & 9 \\\hline\end{array}

-Refer to the scenario above. What is the slack for activity G?

A)4 weeks
B)3 weeks
C)2 weeks
D)1 week
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
31
Construction of the cattery could be distilled to eight distinct steps, from the official groundbreaking ceremony to the cutting of the litterbox ribbon. The activities, their durations and predecessors are shown in the table below. Use this scenario to answer the following question.  Activity  Predecessors  Time (weeks)  A 10 B  A 8 C  A 7 D  C 11 E  D 12 F  B 11 G  E, F 6 H  E, F 9\begin{array} { | c | c | c | } \hline \text { Activity } & \text { Predecessors } & \text { Time (weeks) } \\\hline \text { A } & \cdots & 10 \\\hline \text { B } & \text { A } & 8 \\\hline \text { C } & \text { A } & 7 \\\hline \text { D } & \text { C } & 11 \\\hline \text { E } & \text { D } & 12 \\\hline \text { F } & \text { B } & 11 \\\hline \text { G } & \text { E, F } & 6 \\\hline \text { H } & \text { E, F } & 9 \\\hline\end{array} Refer to the scenario above. One activity has identical earliest finish and latest start times. What is the common number for this unusual activity?

A)17
B)18
C)21
D)29
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
32
The tablet unearthed by the archaeologist revealed an ancient culture's project plan. However, the sands of time had erased much of the information that the table once contained. Use this fragmentary record to unlock the ancient project's secrets and answer the following question(s).
 Activity  Predecessors  Time  ES  EF  LS  LF  A 712 B 8 C  A 1320 D  A 1112 E  B 1417 F  B 11 G  D, E 6 H  C 20 K  F 29 L G,H,K9\begin{array} { | c | c | c | c | c | c | c | } \hline \text { Activity } & \text { Predecessors } & \text { Time } & \text { ES } & \text { EF } & \text { LS } & \text { LF } \\\hline \text { A } & \cdots & 7 & & & & 12 \\\hline \text { B } & \cdots & 8 & & & & \\\hline \text { C } & \text { A } & & & & 13 & 20 \\\hline \text { D } & \text { A } & 11 & & & 12 & \\\hline \text { E } & \text { B } & & & 14 & 17 & \\\hline \text { F } & \text { B } & 11 & & & & \\\hline \text { G } & \text { D, E } & 6 & & & & \\\hline \text { H } & \text { C } & & & & 20 & \\\hline \text { K } & \text { F } & & & 29 & & \\\hline \text { L } & G , H , K & 9 & & & & \\\hline\end{array}

-Refer to the scenario above. What is the duration of activity H?

A)7 weeks
B)8 weeks
C)9 weeks
D)10 weeks
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
33
The tablet unearthed by the archaeologist revealed an ancient culture's project plan. However, the sands of time had erased much of the information that the table once contained. Use this fragmentary record to unlock the ancient project's secrets and answer the following question(s).
 Activity  Predecessors  Time  ES  EF  LS  LF  A 712 B 8 C  A 1320 D  A 1112 E  B 1417 F  B 11 G  D, E 6 H  C 20 K  F 29 L G,H,K9\begin{array} { | c | c | c | c | c | c | c | } \hline \text { Activity } & \text { Predecessors } & \text { Time } & \text { ES } & \text { EF } & \text { LS } & \text { LF } \\\hline \text { A } & \cdots & 7 & & & & 12 \\\hline \text { B } & \cdots & 8 & & & & \\\hline \text { C } & \text { A } & & & & 13 & 20 \\\hline \text { D } & \text { A } & 11 & & & 12 & \\\hline \text { E } & \text { B } & & & 14 & 17 & \\\hline \text { F } & \text { B } & 11 & & & & \\\hline \text { G } & \text { D, E } & 6 & & & & \\\hline \text { H } & \text { C } & & & & 20 & \\\hline \text { K } & \text { F } & & & 29 & & \\\hline \text { L } & G , H , K & 9 & & & & \\\hline\end{array}

-Refer to the scenario above. What is the latest start time for activity K?

A)Week 20
B)Week 19
C)Week 18
D)Week 17
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
34
What is the latest that activity B can start if A lasts 35 days, B lasts 5, days C lasts 6 days, and D lasts 7 days? <strong>What is the latest that activity B can start if A lasts 35 days, B lasts 5, days C lasts 6 days, and D lasts 7 days?  </strong> A)35 B)36 C)40 D)41

A)35
B)36
C)40
D)41
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
35
A hatmaker, fresh off a very successful showing at Lidzapalooza is excited about the prospects of providing the finest chapeaus to meet the needs of his energized customer base in the coming year. He and his space designer have identified seven activities that are necessary to expand his small shop. For the sake of simplicity, and to avoid giving away any trade secrets, the activities have been identified by letters A-G. The activities, their time estimates, and the precedence requirements are listed in the table immediately below. Use this scenario to answer the following question(s).
 Activity  Predecessors  Time (weeks)  A 7 B  A 6 C  A 10 D  C 12 E  B, C 5 F  D, E 11 G  F 8\begin{array} { | c | c | c | } \hline \text { Activity } & \text { Predecessors } & \text { Time (weeks) } \\\hline \text { A } & - & 7 \\\hline \text { B } & \text { A } & 6 \\\hline \text { C } & \text { A } & 10 \\\hline \text { D } & \text { C } & 12 \\\hline \text { E } & \text { B, C } & 5 \\\hline \text { F } & \text { D, E } & 11 \\\hline \text { G } & \text { F } & 8 \\\hline\end{array}

-Refer to the scenario above. Which of these activities has slack?

A)G
B)E
C)F
D)D
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
36
What is the latest that activity D can start if A lasts 5 days, B lasts 7 days, C lasts 4 days, D lasts 5 days, E lasts 7 days, and F is 6 days long? <strong>What is the latest that activity D can start if A lasts 5 days, B lasts 7 days, C lasts 4 days, D lasts 5 days, E lasts 7 days, and F is 6 days long?  </strong> A)14 B)15 C)16 D)17

A)14
B)15
C)16
D)17
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
37
The tablet unearthed by the archaeologist revealed an ancient culture's project plan. However, the sands of time had erased much of the information that the table once contained. Use this fragmentary record to unlock the ancient project's secrets and answer the following question(s).
 Activity  Predecessors  Time  ES  EF  LS  LF  A 712 B 8 C  A 1320 D  A 1112 E  B 1417 F  B 11 G  D, E 6 H  C 20 K  F 29 L G,H,K9\begin{array} { | c | c | c | c | c | c | c | } \hline \text { Activity } & \text { Predecessors } & \text { Time } & \text { ES } & \text { EF } & \text { LS } & \text { LF } \\\hline \text { A } & \cdots & 7 & & & & 12 \\\hline \text { B } & \cdots & 8 & & & & \\\hline \text { C } & \text { A } & & & & 13 & 20 \\\hline \text { D } & \text { A } & 11 & & & 12 & \\\hline \text { E } & \text { B } & & & 14 & 17 & \\\hline \text { F } & \text { B } & 11 & & & & \\\hline \text { G } & \text { D, E } & 6 & & & & \\\hline \text { H } & \text { C } & & & & 20 & \\\hline \text { K } & \text { F } & & & 29 & & \\\hline \text { L } & G , H , K & 9 & & & & \\\hline\end{array}

-Refer to the scenario above. What is the earliest finish time for activity G?

A)Week 21
B)Week 22
C)Week 23
D)Week 24
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
38
What is the fastest completion time of the project with activity lengths (in days)and precedence requirements as shown in the table?  Activity  Length  Predecessor  A 15 B 7 A  C 4 A  D 8 B, C \begin{array} { | c | c | c | } \hline \text { Activity } & \text { Length } & \text { Predecessor } \\\hline \text { A } & 15 & \cdots \\\hline \text { B } & 7 & \text { A } \\\hline \text { C } & 4 & \text { A } \\\hline \text { D } & 8 & \text { B, C } \\\hline\end{array}

A)22
B)25
C)27
D)30
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
39
Which of the activities in this project has the greatest amount of slack?  Activity  Length  Predecessor  A 7 B 4 A  C 8 A  D 3B,C E 2B F 8 D, E \begin{array} { | c | c | c | } \hline \text { Activity } & \text { Length } & \text { Predecessor } \\\hline \text { A } & 7 & \cdots \\\hline \text { B } & 4 & \text { A } \\\hline \text { C } & 8 & \text { A } \\\hline \text { D } & 3 & B , C \\\hline \text { E } & 2 & B \\\hline \text { F } & 8 & \text { D, E } \\\hline\end{array}

A)B
B)C
C)D
D)E
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
40
The tablet unearthed by the archaeologist revealed an ancient culture's project plan. However, the sands of time had erased much of the information that the table once contained. Use this fragmentary record to unlock the ancient project's secrets and answer the following question(s).
 Activity  Predecessors  Time  ES  EF  LS  LF  A 712 B 8 C  A 1320 D  A 1112 E  B 1417 F  B 11 G  D, E 6 H  C 20 K  F 29 L G,H,K9\begin{array} { | c | c | c | c | c | c | c | } \hline \text { Activity } & \text { Predecessors } & \text { Time } & \text { ES } & \text { EF } & \text { LS } & \text { LF } \\\hline \text { A } & \cdots & 7 & & & & 12 \\\hline \text { B } & \cdots & 8 & & & & \\\hline \text { C } & \text { A } & & & & 13 & 20 \\\hline \text { D } & \text { A } & 11 & & & 12 & \\\hline \text { E } & \text { B } & & & 14 & 17 & \\\hline \text { F } & \text { B } & 11 & & & & \\\hline \text { G } & \text { D, E } & 6 & & & & \\\hline \text { H } & \text { C } & & & & 20 & \\\hline \text { K } & \text { F } & & & 29 & & \\\hline \text { L } & G , H , K & 9 & & & & \\\hline\end{array}

-Refer to the scenario above. The project's duration is:

A)32 weeks.
B)33 weeks.
C)36 weeks.
D)38 weeks.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
41
The earliest start time of an activity is dependent on the earliest finish time of its immediate predecessors.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
42
The longest path in a network from the start of a project to the end of a project is the ________.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
43
An activity's duration added to its earliest start time yields the ________.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
44
The earliest finish time of an activity is always later than its latest start time.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
45
The university president concocts a thirteen-step sinister plan to lower morale to zero during his last year in office. The duration of each step (in days)and the required predecessor(s)are displayed in the table.
The university president concocts a thirteen-step sinister plan to lower morale to zero during his last year in office. The duration of each step (in days)and the required predecessor(s)are displayed in the table.   What are the early and late start and finish times for this morale-lowering project? What are the early and late start and finish times for this morale-lowering project?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
46
A hatmaker, fresh off a very successful showing at Lidzapalooza is excited about the prospects of providing the finest chapeaus to meet the needs of his energized customer base in the coming year. He and his space designer have identified seven activities that are necessary to expand his small shop. For the sake of simplicity, and to avoid giving away any trade secrets, the activities have been identified by letters A-G. The activities, their time estimates, and the precedence requirements structure are listed in the table immediately below. Use this table to answer the following question.
A hatmaker, fresh off a very successful showing at Lidzapalooza is excited about the prospects of providing the finest chapeaus to meet the needs of his energized customer base in the coming year. He and his space designer have identified seven activities that are necessary to expand his small shop. For the sake of simplicity, and to avoid giving away any trade secrets, the activities have been identified by letters A-G. The activities, their time estimates, and the precedence requirements structure are listed in the table immediately below. Use this table to answer the following question.   Refer to the scenario above. What are the earliest and latest start and finish times for all of these activities? Refer to the scenario above. What are the earliest and latest start and finish times for all of these activities?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
47
The earliest finish time is calculated by adding the activity's duration to the predecessor's earliest finish time.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
48
A hatmaker, fresh off a very successful showing at Lidzapalooza is excited about the prospects of providing the finest chapeaus (hats, for those of you without a thesaurus)to meet the needs of his energized customer base in the coming year. He and his space designer have identified seven activities that are necessary to expand his small shop. For the sake of simplicity, and to avoid giving away any trade secrets, the activities have been identified by letters A-G. The activities, their time estimates, and the precedence requirements structure are listed in the table immediately below. Use this table to answer the following question(s).
A hatmaker, fresh off a very successful showing at Lidzapalooza is excited about the prospects of providing the finest chapeaus (hats, for those of you without a thesaurus)to meet the needs of his energized customer base in the coming year. He and his space designer have identified seven activities that are necessary to expand his small shop. For the sake of simplicity, and to avoid giving away any trade secrets, the activities have been identified by letters A-G. The activities, their time estimates, and the precedence requirements structure are listed in the table immediately below. Use this table to answer the following question(s).   Refer to the scenario above. Develop a Gantt chart for this project and indicate the finish times for each activity.
Refer to the scenario above. Develop a Gantt chart for this project and indicate the finish times for each activity.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
49
A forward pass through a network is used to determine the earliest start times and earliest finish times for each project activity.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
50
Complete this table containing earliest and latest start times and activity lengths.
Complete this table containing earliest and latest start times and activity lengths.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
51
Given the earliest and latest finish times for each of these activities, what are the activity lengths?
Given the earliest and latest finish times for each of these activities, what are the activity lengths?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
52
For critical path activities, slack is equal to ________.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
53
A critical path is composed entirely of critical activities.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
54
Construction of the cattery could be distilled to eight distinct steps, from the official groundbreaking ceremony to the cutting of the litterbox ribbon. The activities, their durations and predecessors are shown in the table below. Determine earliest and latest start and finish times for all of the activities.
Construction of the cattery could be distilled to eight distinct steps, from the official groundbreaking ceremony to the cutting of the litterbox ribbon. The activities, their durations and predecessors are shown in the table below. Determine earliest and latest start and finish times for all of the activities.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
55
A project is composed of the twelve activities shown in the table. What are the earliest and latest start times for each of these activities?
A project is composed of the twelve activities shown in the table. What are the earliest and latest start times for each of these activities?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
56
A Gantt chart can be used for project planning and also project ________ .
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
57
A hatmaker, fresh off a very successful showing at Lidzapalooza is excited about the prospects of providing the finest chapeaus (hats, for those of you without a thesaurus)to meet the needs of his energized customer base in the coming year. He and his space designer have identified seven activities that are necessary to expand his small shop. For the sake of simplicity, and to avoid giving away any trade secrets, the activities have been identified by letters A-G. The activities, their time estimates, and the precedence requirements structure are listed in the table immediately below. Use this table to answer the following question(s).
A hatmaker, fresh off a very successful showing at Lidzapalooza is excited about the prospects of providing the finest chapeaus (hats, for those of you without a thesaurus)to meet the needs of his energized customer base in the coming year. He and his space designer have identified seven activities that are necessary to expand his small shop. For the sake of simplicity, and to avoid giving away any trade secrets, the activities have been identified by letters A-G. The activities, their time estimates, and the precedence requirements structure are listed in the table immediately below. Use this table to answer the following question(s).   Refer to the scenario above. Develop a Gantt chart for this project and indicate the finish times for each activity.
Refer to the scenario above. Develop a Gantt chart for this project and indicate the finish times for each activity.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
58
Activities on the critical path may have positive or negative slack as long as the overall slack time of the critical path is zero.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
59
The tablet unearthed by the archaeologist revealed an ancient culture's project plan, however the sands of time had erased much of the information that the table once contained. Unlock the ancient project's secrets by completing all of the information missing from this fragmentary record.
The tablet unearthed by the archaeologist revealed an ancient culture's project plan, however the sands of time had erased much of the information that the table once contained. Unlock the ancient project's secrets by completing all of the information missing from this fragmentary record.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
60
A(n)________ is a graphical tool used to show a project's progress as time elapses.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
61
The professional organization that serves the needs of project management professionals is ________.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
62
Which of these needs does the Guide to the Project Management Body of Knowledge NOT serve?

A)It provides a common language for discussing project management issues.
B)It provides a blueprint for ISO certification of the project management process.
C)It identifies and disseminates generally accepted project management knowledge and practices.
D)It serves as a basic reference source for project management.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
63
The Guide to the Project Management Body of Knowledge (PMBOK®)is divided into two main parts, the various business processes that organizations follow in carrying out projects and the nine knowledge areas applicable to nearly all projects.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
64
Describe some of the key features and advantages of project management software.
The university president concocts a thirteen-step sinister plan to lower morale to zero during his last year in office. The duration of each step (in days)and the required predecessor(s)are displayed in the table.
Describe some of the key features and advantages of project management software. The university president concocts a thirteen-step sinister plan to lower morale to zero during his last year in office. The duration of each step (in days)and the required predecessor(s)are displayed in the table.   Identify the activities that have slack and the amount of slack each has for this morale-lowering project?
Identify the activities that have slack and the amount of slack each has for this morale-lowering project?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 65 في هذه المجموعة.
فتح الحزمة
k this deck
65
Describe some of the key features and advantages of project management software.
The university president concocts a thirteen-step sinister plan to lower morale to zero during his last year in office. The duration of each step (in days)and the required predecessor(s)are displayed in the table.
Describe some of the key features and advantages of project management software. The university president concocts a thirteen-step sinister plan to lower morale to zero during his last year in office. The duration of each step (in days)and the required predecessor(s)are displayed in the table.   What is the critical path for this morale-lowering project?
What is the critical path for this morale-lowering project?