Jude is in charge of the advertising program for the Boston Red Sox baseball team during their spring training in Fort Myers, Florida. He has defined the advertising program as a project with the following characteristics. The goal is to fill all stadium seats during the spring training season or he may not have this job next year-the pressure is on!
 Activity  Immediate  Predecessor(s)  Activity Time  in weeks  A  None 1 B  None 1 C  A 4 D  B 5 E  C, D 5 F  E 3 G  F 2\begin{array}{|c|c|c|}\hline \text { Activity } & \begin{array}{c}\text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array}{c}\text { Activity Time } \\\text { in weeks }\end{array} \\\hline \text { A } & \text { None } & 1 \\\hline \text { B } & \text { None } & 1 \\\hline \text { C } & \text { A } & 4 \\\hline \text { D } & \text { B } & 5 \\\hline \text { E } & \text { C, D } & 5 \\\hline \text { F } & \text { E } & 3 \\\hline \text { G } & \text { F } & 2 \\\hline\end{array}

-The largest amount of slack that any activity has in this project is:

A) 1 week.
B) 2 weeks.
C) 3 weeks.
D) 4 weeks.
استخدم زر المسافة أو
up arrow
down arrow
لقلب البطاقة.
سؤال
Consider the following project network. Time estimates are in weeks.  <strong>Consider the following project network. Time estimates are in weeks.   Complete the following table and questions :  \begin{array} { | c | l | l | l | l | l | l | l | } \hline \text { Activity } & \text { Time } & \text { Earliest Start } & \text { Earliest Finish } & \text { Latest Start } & \text { Latest Finish } & \text { Slack } & \text { On Critical Path? } \\ \hline \text { A } & & & & & & & \\ \hline \text { B } & & & & & & & \\ \hline \text { C } & & & & & & & \\ \hline \text { D } & & & & & & & \\ \hline \text { E } & & & & & & & \\ \hline \text { F } & & & & & & \\ \hline \end{array}   \begin{array}{|c|c|c|c|c|c|c|c|} \hline \text { Activity } & \text { Duration } & \text { ES } & \text { EF } & \text { LS } & \text { LF } & \text { Slack } & \begin{array}{c} \text { On } \\ \text { CP? } \end{array} \\ \hline \text { A } & 2 & 0 & 2 & 0 & 2 & 0 & \text { yes } \\ \hline \text { B } & 4 & 2 & 6 & 2 & 6 & 0 & \text { yes } \\ \hline \text { C } & 5 & 6 & 11 & 6 & 11 & 0 & \text { yes } \\ \hline \text { D } & 4 & 11 & 15 & 11 & 15 & 0 & \text { yes } \\ \hline \text { E } & 6 & 2 & 8 & 9 & 15 & 7 & \text { no } \\ \hline \text { F } & 7 & 15 & 22 & 15 & 22 & 0 & \text { yes } \\ \hline \end{array}   -In the previous project network, the latest finish for activity B is:</strong> A) 5. B) 6. C) 7. D) 8. <div style=padding-top: 35px>  Complete the following table and questions :  Activity  Time  Earliest Start  Earliest Finish  Latest Start  Latest Finish  Slack  On Critical Path?  A  B  C  D  E  F \begin{array} { | c | l | l | l | l | l | l | l | } \hline \text { Activity } & \text { Time } & \text { Earliest Start } & \text { Earliest Finish } & \text { Latest Start } & \text { Latest Finish } & \text { Slack } & \text { On Critical Path? } \\\hline \text { A } & & & & & & & \\\hline \text { B } & & & & & & & \\\hline \text { C } & & & & & & & \\\hline \text { D } & & & & & & & \\\hline \text { E } & & & & & & & \\\hline \text { F } & & & & & & \\\hline\end{array}  Activity  Duration  ES  EF  LS  LF  Slack  On  CP?  A 202020 yes  B 426260 yes  C 56116110 yes  D 4111511150 yes  E 6289157 no  F 7152215220 yes \begin{array}{|c|c|c|c|c|c|c|c|}\hline \text { Activity } & \text { Duration } & \text { ES } & \text { EF } & \text { LS } & \text { LF } & \text { Slack } & \begin{array}{c}\text { On } \\\text { CP? }\end{array} \\\hline \text { A } & 2 & 0 & 2 & 0 & 2 & 0 & \text { yes } \\\hline \text { B } & 4 & 2 & 6 & 2 & 6 & 0 & \text { yes } \\\hline \text { C } & 5 & 6 & 11 & 6 & 11 & 0 & \text { yes } \\\hline \text { D } & 4 & 11 & 15 & 11 & 15 & 0 & \text { yes } \\\hline \text { E } & 6 & 2 & 8 & 9 & 15 & 7 & \text { no } \\\hline \text { F } & 7 & 15 & 22 & 15 & 22 & 0 & \text { yes } \\\hline\end{array}

-In the previous project network, the latest finish for activity B is:

A) 5.
B) 6.
C) 7.
D) 8.
سؤال
Jude is in charge of the advertising program for the Boston Red Sox baseball team during their spring training in Fort Myers, Florida. He has defined the advertising program as a project with the following characteristics. The goal is to fill all stadium seats during the spring training season or he may not have this job next year-the pressure is on!
 Activity  Immediate  Predecessor(s)  Activity Time  in weeks  A  None 1 B  None 1 C  A 4 D  B 5 E  C, D 5 F  E 3 G  F 2\begin{array}{|c|c|c|}\hline \text { Activity } & \begin{array}{c}\text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array}{c}\text { Activity Time } \\\text { in weeks }\end{array} \\\hline \text { A } & \text { None } & 1 \\\hline \text { B } & \text { None } & 1 \\\hline \text { C } & \text { A } & 4 \\\hline \text { D } & \text { B } & 5 \\\hline \text { E } & \text { C, D } & 5 \\\hline \text { F } & \text { E } & 3 \\\hline \text { G } & \text { F } & 2 \\\hline\end{array}

-The most likely activities to share resources with critical path activities are:

A) Activities A and B.
B) Activities E and A.
C) Activities A and C.
D) Activities B and D.
سؤال
Consider the following project network. Time estimates are in weeks.  <strong>Consider the following project network. Time estimates are in weeks.   Complete the following table and questions :  \begin{array} { | c | l | l | l | l | l | l | l | } \hline \text { Activity } & \text { Time } & \text { Earliest Start } & \text { Earliest Finish } & \text { Latest Start } & \text { Latest Finish } & \text { Slack } & \text { On Critical Path? } \\ \hline \text { A } & & & & & & & \\ \hline \text { B } & & & & & & & \\ \hline \text { C } & & & & & & & \\ \hline \text { D } & & & & & & & \\ \hline \text { E } & & & & & & & \\ \hline \text { F } & & & & & & \\ \hline \end{array}   \begin{array}{|c|c|c|c|c|c|c|c|} \hline \text { Activity } & \text { Duration } & \text { ES } & \text { EF } & \text { LS } & \text { LF } & \text { Slack } & \begin{array}{c} \text { On } \\ \text { CP? } \end{array} \\ \hline \text { A } & 2 & 0 & 2 & 0 & 2 & 0 & \text { yes } \\ \hline \text { B } & 4 & 2 & 6 & 2 & 6 & 0 & \text { yes } \\ \hline \text { C } & 5 & 6 & 11 & 6 & 11 & 0 & \text { yes } \\ \hline \text { D } & 4 & 11 & 15 & 11 & 15 & 0 & \text { yes } \\ \hline \text { E } & 6 & 2 & 8 & 9 & 15 & 7 & \text { no } \\ \hline \text { F } & 7 & 15 & 22 & 15 & 22 & 0 & \text { yes } \\ \hline \end{array}   -Slack for activity E is:</strong> A) less than 4. B) between 4 and 6. C) between 6 and 8. D) greater than 8. <div style=padding-top: 35px>  Complete the following table and questions :  Activity  Time  Earliest Start  Earliest Finish  Latest Start  Latest Finish  Slack  On Critical Path?  A  B  C  D  E  F \begin{array} { | c | l | l | l | l | l | l | l | } \hline \text { Activity } & \text { Time } & \text { Earliest Start } & \text { Earliest Finish } & \text { Latest Start } & \text { Latest Finish } & \text { Slack } & \text { On Critical Path? } \\\hline \text { A } & & & & & & & \\\hline \text { B } & & & & & & & \\\hline \text { C } & & & & & & & \\\hline \text { D } & & & & & & & \\\hline \text { E } & & & & & & & \\\hline \text { F } & & & & & & \\\hline\end{array}  Activity  Duration  ES  EF  LS  LF  Slack  On  CP?  A 202020 yes  B 426260 yes  C 56116110 yes  D 4111511150 yes  E 6289157 no  F 7152215220 yes \begin{array}{|c|c|c|c|c|c|c|c|}\hline \text { Activity } & \text { Duration } & \text { ES } & \text { EF } & \text { LS } & \text { LF } & \text { Slack } & \begin{array}{c}\text { On } \\\text { CP? }\end{array} \\\hline \text { A } & 2 & 0 & 2 & 0 & 2 & 0 & \text { yes } \\\hline \text { B } & 4 & 2 & 6 & 2 & 6 & 0 & \text { yes } \\\hline \text { C } & 5 & 6 & 11 & 6 & 11 & 0 & \text { yes } \\\hline \text { D } & 4 & 11 & 15 & 11 & 15 & 0 & \text { yes } \\\hline \text { E } & 6 & 2 & 8 & 9 & 15 & 7 & \text { no } \\\hline \text { F } & 7 & 15 & 22 & 15 & 22 & 0 & \text { yes } \\\hline\end{array}

-Slack for activity E is:

A) less than 4.
B) between 4 and 6.
C) between 6 and 8.
D) greater than 8.
سؤال
Which one of the following is NOT a major project management decision area?

A) Revenue
B) Cost
C) Time
D) Resources
سؤال
Which one of the following skills contributes to project success?

A) Lack of data accuracy and integrity
B) Clear communication channels
C) Ill-defined project objectives
D) Inability to resolve conflicts
سؤال
Which of the following is NOT a stage in the project life cycle?

A) Define
B) Organize
C) Improve
D) Close
سؤال
The Baker county government has decided to redo the street and plans to block the street off which causes considerable inconvenience to people. The critical path method (CPM) project has three sequential (in series, that is "i" is first, then "ii" and finally "iii.") paths defined as follows: (i) path A-B-C-H to install street lights and electrical wiring that takes 10 days, (ii) path G-J-K-L to install sidewalks with handicap capabilities that takes 20 days, and (iii) path U-V-Z-W to repave the street including storm drains that takes 8 days. Which one of the following statements is true?

A) The expected duration of the project is 10 + 20 + 8 = 38 days.
B) The expected duration of the project is 20 days.
C) The normal time is inversely related to the crash time.
D) The three sub-system precedent relationships are in parallel.
سؤال
_____ is the sequence of activities that takes the longest time and defines the total project completion time.

A) Project Evaluation and Review Technique
B) The critical path
C) The crash time
D) Project nodes network
سؤال
Consider the following project network. Time estimates are in weeks.  <strong>Consider the following project network. Time estimates are in weeks.   Complete the following table and questions :  \begin{array} { | c | l | l | l | l | l | l | l | } \hline \text { Activity } & \text { Time } & \text { Earliest Start } & \text { Earliest Finish } & \text { Latest Start } & \text { Latest Finish } & \text { Slack } & \text { On Critical Path? } \\ \hline \text { A } & & & & & & & \\ \hline \text { B } & & & & & & & \\ \hline \text { C } & & & & & & & \\ \hline \text { D } & & & & & & & \\ \hline \text { E } & & & & & & & \\ \hline \text { F } & & & & & & \\ \hline \end{array}   \begin{array}{|c|c|c|c|c|c|c|c|} \hline \text { Activity } & \text { Duration } & \text { ES } & \text { EF } & \text { LS } & \text { LF } & \text { Slack } & \begin{array}{c} \text { On } \\ \text { CP? } \end{array} \\ \hline \text { A } & 2 & 0 & 2 & 0 & 2 & 0 & \text { yes } \\ \hline \text { B } & 4 & 2 & 6 & 2 & 6 & 0 & \text { yes } \\ \hline \text { C } & 5 & 6 & 11 & 6 & 11 & 0 & \text { yes } \\ \hline \text { D } & 4 & 11 & 15 & 11 & 15 & 0 & \text { yes } \\ \hline \text { E } & 6 & 2 & 8 & 9 & 15 & 7 & \text { no } \\ \hline \text { F } & 7 & 15 & 22 & 15 & 22 & 0 & \text { yes } \\ \hline \end{array}   -In the previous project network, the critical path activities are:</strong> A) A,B, and C. B) A,B,C,D, and F. C) A,B,D, and F. D) B,C,D, and F. <div style=padding-top: 35px>  Complete the following table and questions :  Activity  Time  Earliest Start  Earliest Finish  Latest Start  Latest Finish  Slack  On Critical Path?  A  B  C  D  E  F \begin{array} { | c | l | l | l | l | l | l | l | } \hline \text { Activity } & \text { Time } & \text { Earliest Start } & \text { Earliest Finish } & \text { Latest Start } & \text { Latest Finish } & \text { Slack } & \text { On Critical Path? } \\\hline \text { A } & & & & & & & \\\hline \text { B } & & & & & & & \\\hline \text { C } & & & & & & & \\\hline \text { D } & & & & & & & \\\hline \text { E } & & & & & & & \\\hline \text { F } & & & & & & \\\hline\end{array}  Activity  Duration  ES  EF  LS  LF  Slack  On  CP?  A 202020 yes  B 426260 yes  C 56116110 yes  D 4111511150 yes  E 6289157 no  F 7152215220 yes \begin{array}{|c|c|c|c|c|c|c|c|}\hline \text { Activity } & \text { Duration } & \text { ES } & \text { EF } & \text { LS } & \text { LF } & \text { Slack } & \begin{array}{c}\text { On } \\\text { CP? }\end{array} \\\hline \text { A } & 2 & 0 & 2 & 0 & 2 & 0 & \text { yes } \\\hline \text { B } & 4 & 2 & 6 & 2 & 6 & 0 & \text { yes } \\\hline \text { C } & 5 & 6 & 11 & 6 & 11 & 0 & \text { yes } \\\hline \text { D } & 4 & 11 & 15 & 11 & 15 & 0 & \text { yes } \\\hline \text { E } & 6 & 2 & 8 & 9 & 15 & 7 & \text { no } \\\hline \text { F } & 7 & 15 & 22 & 15 & 22 & 0 & \text { yes } \\\hline\end{array}

-In the previous project network, the critical path activities are:

A) A,B, and C.
B) A,B,C,D, and F.
C) A,B,D, and F.
D) B,C,D, and F.
سؤال
A Gantt chart is:

A) a useful tool for depicting a schedule graphically.
B) a chart that enables the project manager to know what activities should be performed at a given time.
C) a chart that can be used to monitor daily progress of a project so that corrective action can be taken when necessary.
D) All of the above
سؤال
The county government has decided to redo the street and plans to block the street off which causes considerable inconvenience to people. The project has three parallel paths defined as follows: (i) path A-B-C-H to install street lights and electrical wiring that takes 16 days, (ii) path A-D-E-H to install sidewalks with handicap capabilities that takes 22 days, and (iii) path A-F-G-H to repave the street including storm drains that takes 30 days. Which one of the following statements is TRUE?

A) The expected duration of the project is 30 + 22 + 16 = 68 days.
B) Path A-B-C-H is the critical path.
C) Path A-D-E-H has the largest slack time.
D) Path A-F-G-H is the critical path.
سؤال
In which stage of the project life cycle would a project schedule be developed?

A) Define
B) Plan
C) Organize
D) Control
سؤال
Slack in an activity is computed as:

A) ES - LS.
B) EF - LF.
C) LS - ES.
D) LS - EF.
سؤال
Jude is in charge of the advertising program for the Boston Red Sox baseball team during their spring training in Fort Myers, Florida. He has defined the advertising program as a project with the following characteristics. The goal is to fill all stadium seats during the spring training season or he may not have this job next year-the pressure is on!
 Activity  Immediate  Predecessor(s)  Activity Time  in weeks  A  None 1 B  None 1 C  A 4 D  B 5 E  C, D 5 F  E 3 G  F 2\begin{array}{|c|c|c|}\hline \text { Activity } & \begin{array}{c}\text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array}{c}\text { Activity Time } \\\text { in weeks }\end{array} \\\hline \text { A } & \text { None } & 1 \\\hline \text { B } & \text { None } & 1 \\\hline \text { C } & \text { A } & 4 \\\hline \text { D } & \text { B } & 5 \\\hline \text { E } & \text { C, D } & 5 \\\hline \text { F } & \text { E } & 3 \\\hline \text { G } & \text { F } & 2 \\\hline\end{array}

-The earliest completion time for this project is:

A) 12 weeks.
B) 13 weeks.
C) 14 weeks.
D) 16 weeks.
سؤال
A project has three parallel paths. A-B-C has a length of 25 days. A-D-C has a length of 15 days. Finally, A-E-C has a length of 20 days. Which one of the following statements is TRUE?

A) A-D-C is the critical path.
B) A-B-C has the most slack.
C) The expected duration of this project is 25 days.
D) The expected duration of this project is 25 + 15 + 20 = 60 days.
سؤال
Which of the following is NOT considered a project?

A) Writing and implementing a computer program
B) Introducing a new product
C) Production of soft drinks
D) Building a bridge
سؤال
The critical path method (CPM) work breakdown structure consists of all of the following EXCEPT:

A) the number and definition of each project activity.
B) the normal time to complete each activity.
C) the immediate predecessors (i.e., the precedent relationships).
D) the probabilities of completing each activity.
سؤال
Jude is in charge of the advertising program for the Boston Red Sox baseball team during their spring training in Fort Myers, Florida. He has defined the advertising program as a project with the following characteristics. The goal is to fill all stadium seats during the spring training season or he may not have this job next year-the pressure is on!
 Activity  Immediate  Predecessor(s)  Activity Time  in weeks  A  None 1 B  None 1 C  A 4 D  B 5 E  C, D 5 F  E 3 G  F 2\begin{array}{|c|c|c|}\hline \text { Activity } & \begin{array}{c}\text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array}{c}\text { Activity Time } \\\text { in weeks }\end{array} \\\hline \text { A } & \text { None } & 1 \\\hline \text { B } & \text { None } & 1 \\\hline \text { C } & \text { A } & 4 \\\hline \text { D } & \text { B } & 5 \\\hline \text { E } & \text { C, D } & 5 \\\hline \text { F } & \text { E } & 3 \\\hline \text { G } & \text { F } & 2 \\\hline\end{array}

-If activity C is delayed by 2 weeks, then the revised earliest project completion time is:

A) 13 weeks.
B) 14 weeks.
C) 15 weeks.
D) 17 weeks.
سؤال
Shea is in charge of the "advertising program" for the Boston Red Sox baseball team during their spring training in Fort Myers, Florida. She has defined the advertising program as a project with the following characteristics. The goal is to fill all stadium seats during the spring training season or she may not have the same job next year-the pressure is on!
 Activity  Immediate  Predecessor(s)  Activity Time  in weeks  A  None 1 B  A 2 C  A 3 D  A, B 4 E  C, D 3 F  D, E 2\begin{array}{|c|c|c|}\hline \text { Activity } & \begin{array}{c}\text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array}{c}\text { Activity Time } \\\text { in weeks }\end{array} \\\hline \text { A } & \text { None } & 1 \\\hline \text { B } & \text { A } & 2 \\\hline \text { C } & \text { A } & 3 \\\hline \text { D } & \text { A, B } & 4 \\\hline \text { E } & \text { C, D } & 3 \\\hline \text { F } & \text { D, E } & 2 \\\hline\end{array}

-The earliest completion time for this project is:

A) 9 weeks.
B) 10 weeks.
C) 11 weeks.
D) 12 weeks.
سؤال
You are responsible for managing an advertising project with the following activities (times are given in weeks).
 Immediate  Normal Time  Crash Time  Normal  Crash  Activity  Predecessor  (Weeks)  (Weeks)  Cost ($) Cost ($) A  none 32$14,000$16,500 B  none 66$5,500$5,500 C  none 21$6,000$8,000 D  A, B 53$7,500$14,500 E  C 21$9,000$10,500 F  A 76$15,000$18,000 G  D. E F 43$8,400$10,000\begin{array}{cccccc}&\text { Immediate } & \text { Normal Time } & \text { Crash Time } & \text { Normal } & \text { Crash } \\\text { Activity }&\text { Predecessor } & \text { (Weeks) } & \text { (Weeks) } & \text { Cost }(\$) & \text { Cost }(\$)\\\hline\text { A } & \text { none } & 3 & 2 & \$ 14,000 & \$ 16,500 \\\text { B } & \text { none } & 6 & 6 & \$ 5,500 & \$ 5,500 \\\text { C } & \text { none } & 2 & 1 & \$ 6,000 & \$ 8,000 \\\text { D } & \text { A, B } & 5 & 3 & \$ 7,500 & \$ 14,500 \\\text { E } & \text { C } & 2 & 1 & \$ 9,000 & \$ 10,500 \\\text { F } & \text { A } & 7 & 6 & \$ 15,000 & \$ 18,000 \\\text { G } & \text { D. E F } & 4 & 3 & \$ 8,400 & \$ 10,000\end{array} Draw the project network here. BLANK SPACES

-The project completion time is _____.

A) 12 weeks
B) 13 weeks
C) 14 weeks
D) 15 weeks
سؤال
Shea is in charge of the "advertising program" for the Boston Red Sox baseball team during their spring training in Fort Myers, Florida. She has defined the advertising program as a project with the following characteristics. The goal is to fill all stadium seats during the spring training season or she may not have the same job next year-the pressure is on!
 Activity  Immediate  Predecessor(s)  Activity Time  in weeks  A  None 1 B  A 2 C  A 3 D  A, B 4 E  C, D 3 F  D, E 2\begin{array}{|c|c|c|}\hline \text { Activity } & \begin{array}{c}\text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array}{c}\text { Activity Time } \\\text { in weeks }\end{array} \\\hline \text { A } & \text { None } & 1 \\\hline \text { B } & \text { A } & 2 \\\hline \text { C } & \text { A } & 3 \\\hline \text { D } & \text { A, B } & 4 \\\hline \text { E } & \text { C, D } & 3 \\\hline \text { F } & \text { D, E } & 2 \\\hline\end{array}

-For the original critical path method problem, the minimum number of activities that would have to be crashed in order to reduce the project's earliest completion time by two weeks assuming all activity crash costs per week are the same and all activities can be crashed is:

A) one activity.
B) two activities.
C) three activities.
D) four activities.
سؤال
Which is NOT true of the critical path?

A) The activities on the critical path take the shortest time to complete.
B) The activities on the critical path define the total project completion time.
C) It is the project path with zero slack.
D) The delays in critical path activities will delay the project.
سؤال
You are responsible for managing a project with the following activities (times are given in weeks):
 Immediate  Normal Time  Crash Time  Normal  Crash  Activity  Predecessor  (Weeks)  (Weeks)  Cost ($) Cost ($) A  none 32$14,000$16,500 B  none 66$5,500$5,500 C  none 21$6,000$8,000 D  A 53$7,500$14,500 E  C 21$9,000$10,500 F  A 76$15,000$18,000 G  B. D. E. F 43$8,400$10,000\begin{array}{cccccc}&\text { Immediate } & \text { Normal Time } & \text { Crash Time } & \text { Normal } & \text { Crash } \\\text { Activity }&\text { Predecessor } & \text { (Weeks) } & \text { (Weeks) } & \text { Cost }(\$) & \text { Cost }(\$)\\\hline\text { A } & \text { none } & 3 & 2 & \$ 14,000 & \$ 16,500 \\\text { B } & \text { none } & 6 & 6 & \$ 5,500 & \$ 5,500 \\\text { C } & \text { none } & 2 & 1 & \$ 6,000 & \$ 8,000 \\\text { D } & \text { A } & 5 & 3 & \$ 7,500 & \$ 14,500 \\\text { E } & \text { C } & 2 & 1 & \$ 9,000 & \$ 10,500 \\\text { F } & \text { A } & 7 & 6 & \$ 15,000 & \$ 18,000 \\\text { G } & \text { B. D. E. F } & 4 & 3 & \$ 8,400 & \$ 10,000\end{array}

-What activity should one crash to reduce the project completion time by two weeks at minimum crash costs?

A) A and F.
B) A and G.
C) A and E.
D) G and F.
سؤال
You are responsible for managing a project with the following activities (times are given in weeks):
 Immediate  Normal Time  Crash Time  Normal  Crash  Activity  Predecessor  (Weeks)  (Weeks)  Cost ($) Cost ($) A  none 32$14,000$16,500 B  none 66$5,500$5,500 C  none 21$6,000$8,000 D  A 53$7,500$14,500 E  C 21$9,000$10,500 F  A 76$15,000$18,000 G  B. D. E. F 43$8,400$10,000\begin{array}{cccccc}&\text { Immediate } & \text { Normal Time } & \text { Crash Time } & \text { Normal } & \text { Crash } \\\text { Activity }&\text { Predecessor } & \text { (Weeks) } & \text { (Weeks) } & \text { Cost }(\$) & \text { Cost }(\$)\\\hline\text { A } & \text { none } & 3 & 2 & \$ 14,000 & \$ 16,500 \\\text { B } & \text { none } & 6 & 6 & \$ 5,500 & \$ 5,500 \\\text { C } & \text { none } & 2 & 1 & \$ 6,000 & \$ 8,000 \\\text { D } & \text { A } & 5 & 3 & \$ 7,500 & \$ 14,500 \\\text { E } & \text { C } & 2 & 1 & \$ 9,000 & \$ 10,500 \\\text { F } & \text { A } & 7 & 6 & \$ 15,000 & \$ 18,000 \\\text { G } & \text { B. D. E. F } & 4 & 3 & \$ 8,400 & \$ 10,000\end{array}

-If activity D is delayed by 2 weeks, which one of the following statements is TRUE?

A) There are now two critical paths in the network.
B) The slack time for activity D changes to 1 week.
C) The project completion time is still 12 weeks.
D) The project completion time becomes 16 weeks.
سؤال
Which of the following is true of project scheduling using the critical path method?

A) Activity crash time is greater than normal time.
B) Crash cost per time period is assumed to be non-linear.
C) Gantt charts are built using activity ES, EF, LS, and LF times.
D) Gantt charts assume a beta probability distribution.
سؤال
Brian is assigned his first project. If things go well, he should get promoted. The CEO is aware of this project, so he has a chance for high visibility. His first task is to define the work break down structure by interviewing project activity managers, and the firm's friendly, yet boring accountants, to get "good estimates" of project activity times and costs. For Activity Z, the crash cost per week is _____, given the following data: normal time = 5 weeks, crash time = 2, normal cost = $7,560, and crash cost = $17,365.

A) less than or equal to $1,000 per week
B) more than $1,000 but less than or equal to $2,500
C) more than $2,500 but less than or equal to $3,000
D) more than $3,000 but less than or equal to $3,500
سؤال
You are responsible for managing an advertising project with the following activities (times are given in weeks).
 Immediate  Normal Time  Crash Time  Normal  Crash  Activity  Predecessor  (Weeks)  (Weeks)  Cost ($) Cost ($) A  none 32$14,000$16,500 B  none 66$5,500$5,500 C  none 21$6,000$8,000 D  A, B 53$7,500$14,500 E  C 21$9,000$10,500 F  A 76$15,000$18,000 G  D. E F 43$8,400$10,000\begin{array}{cccccc}&\text { Immediate } & \text { Normal Time } & \text { Crash Time } & \text { Normal } & \text { Crash } \\\text { Activity }&\text { Predecessor } & \text { (Weeks) } & \text { (Weeks) } & \text { Cost }(\$) & \text { Cost }(\$)\\\hline\text { A } & \text { none } & 3 & 2 & \$ 14,000 & \$ 16,500 \\\text { B } & \text { none } & 6 & 6 & \$ 5,500 & \$ 5,500 \\\text { C } & \text { none } & 2 & 1 & \$ 6,000 & \$ 8,000 \\\text { D } & \text { A, B } & 5 & 3 & \$ 7,500 & \$ 14,500 \\\text { E } & \text { C } & 2 & 1 & \$ 9,000 & \$ 10,500 \\\text { F } & \text { A } & 7 & 6 & \$ 15,000 & \$ 18,000 \\\text { G } & \text { D. E F } & 4 & 3 & \$ 8,400 & \$ 10,000\end{array} Draw the project network here. BLANK SPACES

-What activity should one crash to reduce the project completion time by two weeks at minimum crash costs?

A) A and F, each by one week
B) A and D, each by one week
C) C and D, each by one week
D) D and G, each by one week
سؤال
Which of the following is NOT an assumption of the critical path method?

A) Activities are independent of one another.
B) Activity time estimates are stable.
C) Activity times are characterized by a beta probability distribution.
D) Once an activity is started, it continues uninterrupted until completion.
سؤال
You are responsible for managing a project with the following activities (times are given in weeks):
 Immediate  Normal Time  Crash Time  Normal  Crash  Activity  Predecessor  (Weeks)  (Weeks)  Cost ($) Cost ($) A  none 32$14,000$16,500 B  none 66$5,500$5,500 C  none 21$6,000$8,000 D  A 53$7,500$14,500 E  C 21$9,000$10,500 F  A 76$15,000$18,000 G  B. D. E. F 43$8,400$10,000\begin{array}{cccccc}&\text { Immediate } & \text { Normal Time } & \text { Crash Time } & \text { Normal } & \text { Crash } \\\text { Activity }&\text { Predecessor } & \text { (Weeks) } & \text { (Weeks) } & \text { Cost }(\$) & \text { Cost }(\$)\\\hline\text { A } & \text { none } & 3 & 2 & \$ 14,000 & \$ 16,500 \\\text { B } & \text { none } & 6 & 6 & \$ 5,500 & \$ 5,500 \\\text { C } & \text { none } & 2 & 1 & \$ 6,000 & \$ 8,000 \\\text { D } & \text { A } & 5 & 3 & \$ 7,500 & \$ 14,500 \\\text { E } & \text { C } & 2 & 1 & \$ 9,000 & \$ 10,500 \\\text { F } & \text { A } & 7 & 6 & \$ 15,000 & \$ 18,000 \\\text { G } & \text { B. D. E. F } & 4 & 3 & \$ 8,400 & \$ 10,000\end{array}

-What is the total project (normal plus crash) cost?

A) Less than or equal to $60,000
B) Greater than $60,000 but less than or equal to $65,000
C) Greater than $65,000 but less than or equal to $70,000
D) Greater than $70,000
سؤال
You are responsible for managing an advertising project with the following activities (times are given in weeks).
 Immediate  Normal Time  Crash Time  Normal  Crash  Activity  Predecessor  (Weeks)  (Weeks)  Cost ($) Cost ($) A  none 32$14,000$16,500 B  none 66$5,500$5,500 C  none 21$6,000$8,000 D  A, B 53$7,500$14,500 E  C 21$9,000$10,500 F  A 76$15,000$18,000 G  D. E F 43$8,400$10,000\begin{array}{cccccc}&\text { Immediate } & \text { Normal Time } & \text { Crash Time } & \text { Normal } & \text { Crash } \\\text { Activity }&\text { Predecessor } & \text { (Weeks) } & \text { (Weeks) } & \text { Cost }(\$) & \text { Cost }(\$)\\\hline\text { A } & \text { none } & 3 & 2 & \$ 14,000 & \$ 16,500 \\\text { B } & \text { none } & 6 & 6 & \$ 5,500 & \$ 5,500 \\\text { C } & \text { none } & 2 & 1 & \$ 6,000 & \$ 8,000 \\\text { D } & \text { A, B } & 5 & 3 & \$ 7,500 & \$ 14,500 \\\text { E } & \text { C } & 2 & 1 & \$ 9,000 & \$ 10,500 \\\text { F } & \text { A } & 7 & 6 & \$ 15,000 & \$ 18,000 \\\text { G } & \text { D. E F } & 4 & 3 & \$ 8,400 & \$ 10,000\end{array} Draw the project network here. BLANK SPACES

-What is the critical path for this project?

A) A-D-G
B) A-F-G
C) B-D-G
D) C-E-G
سؤال
You are responsible for managing a project with the following activities (times are given in weeks):
 Immediate  Normal Time  Crash Time  Normal  Crash  Activity  Predecessor  (Weeks)  (Weeks)  Cost ($) Cost ($) A  none 32$14,000$16,500 B  none 66$5,500$5,500 C  none 21$6,000$8,000 D  A 53$7,500$14,500 E  C 21$9,000$10,500 F  A 76$15,000$18,000 G  B. D. E. F 43$8,400$10,000\begin{array}{cccccc}&\text { Immediate } & \text { Normal Time } & \text { Crash Time } & \text { Normal } & \text { Crash } \\\text { Activity }&\text { Predecessor } & \text { (Weeks) } & \text { (Weeks) } & \text { Cost }(\$) & \text { Cost }(\$)\\\hline\text { A } & \text { none } & 3 & 2 & \$ 14,000 & \$ 16,500 \\\text { B } & \text { none } & 6 & 6 & \$ 5,500 & \$ 5,500 \\\text { C } & \text { none } & 2 & 1 & \$ 6,000 & \$ 8,000 \\\text { D } & \text { A } & 5 & 3 & \$ 7,500 & \$ 14,500 \\\text { E } & \text { C } & 2 & 1 & \$ 9,000 & \$ 10,500 \\\text { F } & \text { A } & 7 & 6 & \$ 15,000 & \$ 18,000 \\\text { G } & \text { B. D. E. F } & 4 & 3 & \$ 8,400 & \$ 10,000\end{array}

-Which of the following activities has the largest amount of slack?

A) Activity A
B) Activity B
C) Activity C
D) Activity D
سؤال
You are responsible for managing an advertising project with the following activities (times are given in weeks).
 Immediate  Normal Time  Crash Time  Normal  Crash  Activity  Predecessor  (Weeks)  (Weeks)  Cost ($) Cost ($) A  none 32$14,000$16,500 B  none 66$5,500$5,500 C  none 21$6,000$8,000 D  A, B 53$7,500$14,500 E  C 21$9,000$10,500 F  A 76$15,000$18,000 G  D. E F 43$8,400$10,000\begin{array}{cccccc}&\text { Immediate } & \text { Normal Time } & \text { Crash Time } & \text { Normal } & \text { Crash } \\\text { Activity }&\text { Predecessor } & \text { (Weeks) } & \text { (Weeks) } & \text { Cost }(\$) & \text { Cost }(\$)\\\hline\text { A } & \text { none } & 3 & 2 & \$ 14,000 & \$ 16,500 \\\text { B } & \text { none } & 6 & 6 & \$ 5,500 & \$ 5,500 \\\text { C } & \text { none } & 2 & 1 & \$ 6,000 & \$ 8,000 \\\text { D } & \text { A, B } & 5 & 3 & \$ 7,500 & \$ 14,500 \\\text { E } & \text { C } & 2 & 1 & \$ 9,000 & \$ 10,500 \\\text { F } & \text { A } & 7 & 6 & \$ 15,000 & \$ 18,000 \\\text { G } & \text { D. E F } & 4 & 3 & \$ 8,400 & \$ 10,000\end{array} Draw the project network here. BLANK SPACES

-If activity D is delayed by 2 weeks, which one of the following statements is TRUE?

A) There are now two critical paths in the network.
B) The slack time for activity D changes to 1 week.
C) The project completion time is still 14 weeks.
D) The project completion time becomes 18 weeks.
سؤال
You are responsible for managing a project with the following activities (times are given in weeks):
 Immediate  Normal Time  Crash Time  Normal  Crash  Activity  Predecessor  (Weeks)  (Weeks)  Cost ($) Cost ($) A  none 32$14,000$16,500 B  none 66$5,500$5,500 C  none 21$6,000$8,000 D  A 53$7,500$14,500 E  C 21$9,000$10,500 F  A 76$15,000$18,000 G  B. D. E. F 43$8,400$10,000\begin{array}{cccccc}&\text { Immediate } & \text { Normal Time } & \text { Crash Time } & \text { Normal } & \text { Crash } \\\text { Activity }&\text { Predecessor } & \text { (Weeks) } & \text { (Weeks) } & \text { Cost }(\$) & \text { Cost }(\$)\\\hline\text { A } & \text { none } & 3 & 2 & \$ 14,000 & \$ 16,500 \\\text { B } & \text { none } & 6 & 6 & \$ 5,500 & \$ 5,500 \\\text { C } & \text { none } & 2 & 1 & \$ 6,000 & \$ 8,000 \\\text { D } & \text { A } & 5 & 3 & \$ 7,500 & \$ 14,500 \\\text { E } & \text { C } & 2 & 1 & \$ 9,000 & \$ 10,500 \\\text { F } & \text { A } & 7 & 6 & \$ 15,000 & \$ 18,000 \\\text { G } & \text { B. D. E. F } & 4 & 3 & \$ 8,400 & \$ 10,000\end{array}

-What is the critical path and expected completion time for this project?

A) B-D-G; 12 weeks
B) A-D-G; 12 weeks
C) B-G; 10 weeks
D) A-F-G; 14 weeks
سؤال
Shea is in charge of the "advertising program" for the Boston Red Sox baseball team during their spring training in Fort Myers, Florida. She has defined the advertising program as a project with the following characteristics. The goal is to fill all stadium seats during the spring training season or she may not have the same job next year-the pressure is on!
 Activity  Immediate  Predecessor(s)  Activity Time  in weeks  A  None 1 B  A 2 C  A 3 D  A, B 4 E  C, D 3 F  D, E 2\begin{array}{|c|c|c|}\hline \text { Activity } & \begin{array}{c}\text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array}{c}\text { Activity Time } \\\text { in weeks }\end{array} \\\hline \text { A } & \text { None } & 1 \\\hline \text { B } & \text { A } & 2 \\\hline \text { C } & \text { A } & 3 \\\hline \text { D } & \text { A, B } & 4 \\\hline \text { E } & \text { C, D } & 3 \\\hline \text { F } & \text { D, E } & 2 \\\hline\end{array}

-If activity C is delayed by three weeks, the revised earliest project completion time is:

A) 9 weeks.
B) 10 weeks.
C) 11 weeks.
D) 12 weeks.
سؤال
You are responsible for managing an advertising project with the following activities (times are given in weeks).
 Immediate  Normal Time  Crash Time  Normal  Crash  Activity  Predecessor  (Weeks)  (Weeks)  Cost ($) Cost ($) A  none 32$14,000$16,500 B  none 66$5,500$5,500 C  none 21$6,000$8,000 D  A, B 53$7,500$14,500 E  C 21$9,000$10,500 F  A 76$15,000$18,000 G  D. E F 43$8,400$10,000\begin{array}{cccccc}&\text { Immediate } & \text { Normal Time } & \text { Crash Time } & \text { Normal } & \text { Crash } \\\text { Activity }&\text { Predecessor } & \text { (Weeks) } & \text { (Weeks) } & \text { Cost }(\$) & \text { Cost }(\$)\\\hline\text { A } & \text { none } & 3 & 2 & \$ 14,000 & \$ 16,500 \\\text { B } & \text { none } & 6 & 6 & \$ 5,500 & \$ 5,500 \\\text { C } & \text { none } & 2 & 1 & \$ 6,000 & \$ 8,000 \\\text { D } & \text { A, B } & 5 & 3 & \$ 7,500 & \$ 14,500 \\\text { E } & \text { C } & 2 & 1 & \$ 9,000 & \$ 10,500 \\\text { F } & \text { A } & 7 & 6 & \$ 15,000 & \$ 18,000 \\\text { G } & \text { D. E F } & 4 & 3 & \$ 8,400 & \$ 10,000\end{array} Draw the project network here. BLANK SPACES

-Which of the following activities has the largest amount of slack?

A) Activity A
B) Activity B
C) Activity C
D) Activity D
سؤال
Which one of the following statements about the critical path method (CPM) is TRUE?

A) The activity time estimates are accurate and stable.
B) Activities are dependent on each other.
C) Activities can be interrupted before completion.
D) The project schedule defines a correct sequence of work in terms of technology and workflow.
سؤال
Which one of the following statements about critical path method (CPM) is TRUE?

A) Crashing an activity refers to increasing its normal time.
B) Crashing an activity refers to decreasing its normal time possibly up to its limit.
C) Crashing a project requires revised immediate predecessor relationships.
D) Crashing a project is a tradeoff between revenue and costs.
سؤال
Shea is in charge of the "advertising program" for the Boston Red Sox baseball team during their spring training in Fort Myers, Florida. She has defined the advertising program as a project with the following characteristics. The goal is to fill all stadium seats during the spring training season or she may not have the same job next year-the pressure is on!
 Activity  Immediate  Predecessor(s)  Activity Time  in weeks  A  None 1 B  A 2 C  A 3 D  A, B 4 E  C, D 3 F  D, E 2\begin{array}{|c|c|c|}\hline \text { Activity } & \begin{array}{c}\text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array}{c}\text { Activity Time } \\\text { in weeks }\end{array} \\\hline \text { A } & \text { None } & 1 \\\hline \text { B } & \text { A } & 2 \\\hline \text { C } & \text { A } & 3 \\\hline \text { D } & \text { A, B } & 4 \\\hline \text { E } & \text { C, D } & 3 \\\hline \text { F } & \text { D, E } & 2 \\\hline\end{array}

-The largest amount of slack that any activity has in this project is:

A) 1 week.
B) 2 weeks.
C) 3 weeks.
D) 4 weeks.
سؤال
Which of the following statements is TRUE of the activities not on the critical path?

A) These activities usually cannot be delayed.
B) These activities have less slack than activities on the critical path.
C) These activities can become part of the critical path if delayed long enough.
D) These activities have uncertain times.
سؤال
Which of the following is LEAST relevant to Program Evaluation and Review Technique (PERT)?

A) Beta distribution
B) Variance of activity time
C) Most probable time
D) Constant activity time
سؤال
Which of the following forms part of Program Evaluation and Review Technique (PERT)?

A) Beta distribution
B) Variance
C) Most probable time
D) All of above are related to PERT
سؤال
A high definition television manufacturer in Asia wants to develop a new smart television as fast as possible using Program Evaluation and Review Technique (PERT) and must complete the design and testing work first. The objective is to be the first to market the most innovative smart television on the planet and capture the first adopter market share. The manufacturer has determined the following activities, precedence relationships, and time estimates in days for the project:
 Immediate  Optimistic  Most Likely  Pessimistic  Activity  Predecessors totmtp\hlinea none 467 ba123ca555 d b7912eb248fcd6910\begin{array}{rcccr}& \text { Immediate } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\\text { Activity } & \text { Predecessors } & t_{o} & t_{m} & t_{p}\\\hlinea & \text { none } & 4 & 6 & 7 \\\mathrm{~b} & \mathrm{a} & 1 & 2 & 3 \\\mathrm{c} & \mathrm{a} & 5 & 5 & 5 \\\mathrm{~d} & \mathrm{~b} & 7 & 9 & 12 \\\mathrm{e} & \mathrm{b} & 2 & 4 & 8 \\\mathrm{f} & \mathrm{c} d & 6 & 9 & 10\end{array} Solutions are at the end of questions

-The expected variance of Activity A is _____.

A) less than or equal to 0.5 days
B) greater than 0.5 but less than or equal to 1.0 day
C) greater than 1.0 but less than or equal to 1.5 days
D) greater than 1.5 days
سؤال
Ayben is responsible for managing an advertising and promotion project using Program Evaluation and Review Technique (PERT) with the following activities (times are given in weeks).
 Project  Immediate  Optimistic  Most Likely  Pessimistic  Expected  Activity  Activity  Predecessor(s)  Time  Time  Time  Time  Variance  A  none 2514 B  none 81114 C  A 579 D  A 6912 E  B, C, D 135\begin{array}{|c|c|c|c|c|c|c|}\hline\text { Project } & \text { Immediate } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } & \text { Expected } & \text { Activity } \\\hline \text { Activity } & \text { Predecessor(s) } & \text { Time } & \text { Time } & \text { Time } & \text { Time } & \text { Variance } \\\hline\\\hline \text { A } & \text { none } & 2 & 5 & 14 \\\hline \text { B } & \text { none } & 8 & 11 & 14 \\\hline \text { C } & \text { A } & 5 & 7 & 9 \\\hline \text { D } & \text { A } & 6 & 9 & 12 \\\hline \text { E } & \text { B, C, D } & 1 & 3 & 5 \\\hline\end{array} Draw the project network here. BLANK SPACES
 PERT Exam Question #52 to #55 \text { PERT Exam Question \#52 to \#55 }
 Activity  OT  MLT  PT  ET  AV  A 25146.004.00 B 8111411.001.00 C 5797.000.44 D 69129.001.00 F 1353.000.44\begin{array}{cccccc}\text { Activity } & \text { OT } & \text { MLT } & \text { PT } & \text { ET } & \text { AV } \\\text { A } & 2 & 5 & 14 & 6.00 & 4.00 \\\text { B } & 8 & 11 & 14 & 11.00 & 1.00 \\\text { C } & 5 & 7 & 9 & 7.00 & 0.44 \\\text { D } & 6 & 9 & 12 & 9.00 & 1.00 \\\text { F } & 1 & 3 & 5 & 3.00 & 0.44\end{array}

-Using the table for the advertising and promotion project, which activity has the largest slack, and how large is that slack?

A) Activity C; 5 weeks
B) Activity A; 6 weeks
C) Activity B; 4 weeks
D) Activity E; 3 weeks
سؤال
Rose is in charge of the advertising program for Proctor & Gamble's new laundry detergent. She has defined the advertising program as a project with the following characteristics. The goal is to complete the project on time and within budget, or she may not have this job next year-the pressure is on!
 Activity  Immediate  Predecessor(s)  Normal  Time  in weeks  Crash Time  in weeks  Normal Cost  Crash Cost  A  None 22$15,000$15,000 B  None 11$12,000$12,000 C  A, B 53$18,000$24,000 D  A, B 42$12,000$16,000 E  C, D 21$22,000$23,500 F  D 43$32,000$36,000 G  E, F 32$19,000$20,000\begin{array}{|c|c|c|c|c|c|}\hline\text { Activity } & \begin{array}{c}\text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array}{c}\text { Normal } \\\text { Time } \\\text { in weeks }\end{array} & \begin{array}{c}\text { Crash Time } \\\text { in weeks }\end{array} & \text { Normal Cost } & \text { Crash Cost } \\\hline \text { A } & \text { None } & 2 & 2 & \$ 15,000 & \$ 15,000 \\\hline \text { B } & \text { None } & 1 & 1 & \$ 12,000 & \$ 12,000 \\\hline \text { C } & \text { A, B } & 5 & 3 & \$ 18,000 & \$ 24,000 \\\hline \text { D } & \text { A, B } & 4 & 2 & \$ 12,000 & \$ 16,000 \\\hline \text { E } & \text { C, D } & 2 & 1 & \$ 22,000 & \$ 23,500 \\\hline \text { F } & \text { D } & 4 & 3 & \$ 32,000 & \$ 36,000 \\\hline \text { G } & \text { E, F } & 3 & 2 & \$ 19,000 & \$ 20,000 \\\hline\end{array} Draw the project network in the space below if you want. BLANK SPACES

-The total minimum crash cost only for the project to achieve a two-week earlier completion time from the original project completion time is:

A) less than $1,000.
B) more than $1,000 but less than or equal to $2,000.
C) more than $2,000 but less than or equal to $3,000.
D) more than $3,000 but less than or equal to $4,000.
سؤال
A high definition television manufacturer in Asia wants to develop a new smart television as fast as possible using Program Evaluation and Review Technique (PERT) and must complete the design and testing work first. The objective is to be the first to market the most innovative smart television on the planet and capture the first adopter market share. The manufacturer has determined the following activities, precedence relationships, and time estimates in days for the project:
 Immediate  Optimistic  Most Likely  Pessimistic  Activity  Predecessors totmtp\hlinea none 467 ba123ca555 d b7912eb248fcd6910\begin{array}{rcccr}& \text { Immediate } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\\text { Activity } & \text { Predecessors } & t_{o} & t_{m} & t_{p}\\\hlinea & \text { none } & 4 & 6 & 7 \\\mathrm{~b} & \mathrm{a} & 1 & 2 & 3 \\\mathrm{c} & \mathrm{a} & 5 & 5 & 5 \\\mathrm{~d} & \mathrm{~b} & 7 & 9 & 12 \\\mathrm{e} & \mathrm{b} & 2 & 4 & 8 \\\mathrm{f} & \mathrm{c} d & 6 & 9 & 10\end{array} Solutions are at the end of questions

-The expected duration of Activity A is _____.

A) Less than or equal to 2 days
B) Greater than 2 but less than or equal to 4 days
C) Greater than 4 but less than or equal to 6 days
D) Greater than 6 days
سؤال
Rose is in charge of the advertising program for Proctor & Gamble's new laundry detergent. She has defined the advertising program as a project with the following characteristics. The goal is to complete the project on time and within budget, or she may not have this job next year-the pressure is on!
 Activity  Immediate  Predecessor(s)  Normal  Time  in weeks  Crash Time  in weeks  Normal Cost  Crash Cost  A  None 22$15,000$15,000 B  None 11$12,000$12,000 C  A, B 53$18,000$24,000 D  A, B 42$12,000$16,000 E  C, D 21$22,000$23,500 F  D 43$32,000$36,000 G  E, F 32$19,000$20,000\begin{array}{|c|c|c|c|c|c|}\hline\text { Activity } & \begin{array}{c}\text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array}{c}\text { Normal } \\\text { Time } \\\text { in weeks }\end{array} & \begin{array}{c}\text { Crash Time } \\\text { in weeks }\end{array} & \text { Normal Cost } & \text { Crash Cost } \\\hline \text { A } & \text { None } & 2 & 2 & \$ 15,000 & \$ 15,000 \\\hline \text { B } & \text { None } & 1 & 1 & \$ 12,000 & \$ 12,000 \\\hline \text { C } & \text { A, B } & 5 & 3 & \$ 18,000 & \$ 24,000 \\\hline \text { D } & \text { A, B } & 4 & 2 & \$ 12,000 & \$ 16,000 \\\hline \text { E } & \text { C, D } & 2 & 1 & \$ 22,000 & \$ 23,500 \\\hline \text { F } & \text { D } & 4 & 3 & \$ 32,000 & \$ 36,000 \\\hline \text { G } & \text { E, F } & 3 & 2 & \$ 19,000 & \$ 20,000 \\\hline\end{array} Draw the project network in the space below if you want. BLANK SPACES

-If activity D is delayed by 2 weeks, the revised earliest project completion time is:

A) 11 weeks.
B) 12 weeks.
C) 13 weeks.
D) 15 weeks.
سؤال
Rose is in charge of the advertising program for Proctor & Gamble's new laundry detergent. She has defined the advertising program as a project with the following characteristics. The goal is to complete the project on time and within budget, or she may not have this job next year-the pressure is on!
 Activity  Immediate  Predecessor(s)  Normal  Time  in weeks  Crash Time  in weeks  Normal Cost  Crash Cost  A  None 22$15,000$15,000 B  None 11$12,000$12,000 C  A, B 53$18,000$24,000 D  A, B 42$12,000$16,000 E  C, D 21$22,000$23,500 F  D 43$32,000$36,000 G  E, F 32$19,000$20,000\begin{array}{|c|c|c|c|c|c|}\hline\text { Activity } & \begin{array}{c}\text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array}{c}\text { Normal } \\\text { Time } \\\text { in weeks }\end{array} & \begin{array}{c}\text { Crash Time } \\\text { in weeks }\end{array} & \text { Normal Cost } & \text { Crash Cost } \\\hline \text { A } & \text { None } & 2 & 2 & \$ 15,000 & \$ 15,000 \\\hline \text { B } & \text { None } & 1 & 1 & \$ 12,000 & \$ 12,000 \\\hline \text { C } & \text { A, B } & 5 & 3 & \$ 18,000 & \$ 24,000 \\\hline \text { D } & \text { A, B } & 4 & 2 & \$ 12,000 & \$ 16,000 \\\hline \text { E } & \text { C, D } & 2 & 1 & \$ 22,000 & \$ 23,500 \\\hline \text { F } & \text { D } & 4 & 3 & \$ 32,000 & \$ 36,000 \\\hline \text { G } & \text { E, F } & 3 & 2 & \$ 19,000 & \$ 20,000 \\\hline\end{array} Draw the project network in the space below if you want. BLANK SPACES

-The earliest completion time for this project is:

A) 11 weeks.
B) 12 weeks.
C) 13 weeks.
D) 14 weeks.
سؤال
Rose is in charge of the advertising program for Proctor & Gamble's new laundry detergent. She has defined the advertising program as a project with the following characteristics. The goal is to complete the project on time and within budget, or she may not have this job next year-the pressure is on!
 Activity  Immediate  Predecessor(s)  Normal  Time  in weeks  Crash Time  in weeks  Normal Cost  Crash Cost  A  None 22$15,000$15,000 B  None 11$12,000$12,000 C  A, B 53$18,000$24,000 D  A, B 42$12,000$16,000 E  C, D 21$22,000$23,500 F  D 43$32,000$36,000 G  E, F 32$19,000$20,000\begin{array}{|c|c|c|c|c|c|}\hline\text { Activity } & \begin{array}{c}\text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array}{c}\text { Normal } \\\text { Time } \\\text { in weeks }\end{array} & \begin{array}{c}\text { Crash Time } \\\text { in weeks }\end{array} & \text { Normal Cost } & \text { Crash Cost } \\\hline \text { A } & \text { None } & 2 & 2 & \$ 15,000 & \$ 15,000 \\\hline \text { B } & \text { None } & 1 & 1 & \$ 12,000 & \$ 12,000 \\\hline \text { C } & \text { A, B } & 5 & 3 & \$ 18,000 & \$ 24,000 \\\hline \text { D } & \text { A, B } & 4 & 2 & \$ 12,000 & \$ 16,000 \\\hline \text { E } & \text { C, D } & 2 & 1 & \$ 22,000 & \$ 23,500 \\\hline \text { F } & \text { D } & 4 & 3 & \$ 32,000 & \$ 36,000 \\\hline \text { G } & \text { E, F } & 3 & 2 & \$ 19,000 & \$ 20,000 \\\hline\end{array} Draw the project network in the space below if you want. BLANK SPACES

-Britt is managing this project, and his bossRose gives him $5,000 to speed up the original completion time (i.e., project improvement dollars). The best action is to:

A) spend it on activity G first.
B) spend it on activity F first.
C) spent it on activity C first.
D) spend one-half of it on activity C and one-half on activity E.
سؤال
Ayben is responsible for managing an advertising and promotion project using Program Evaluation and Review Technique (PERT) with the following activities (times are given in weeks).
 Project  Immediate  Optimistic  Most Likely  Pessimistic  Expected  Activity  Activity  Predecessor(s)  Time  Time  Time  Time  Variance  A  none 2514 B  none 81114 C  A 579 D  A 6912 E  B, C, D 135\begin{array}{|c|c|c|c|c|c|c|}\hline\text { Project } & \text { Immediate } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } & \text { Expected } & \text { Activity } \\\hline \text { Activity } & \text { Predecessor(s) } & \text { Time } & \text { Time } & \text { Time } & \text { Time } & \text { Variance } \\\hline\\\hline \text { A } & \text { none } & 2 & 5 & 14 \\\hline \text { B } & \text { none } & 8 & 11 & 14 \\\hline \text { C } & \text { A } & 5 & 7 & 9 \\\hline \text { D } & \text { A } & 6 & 9 & 12 \\\hline \text { E } & \text { B, C, D } & 1 & 3 & 5 \\\hline\end{array} Draw the project network here. BLANK SPACES
 PERT Exam Question #52 to #55 \text { PERT Exam Question \#52 to \#55 }
 Activity  OT  MLT  PT  ET  AV  A 25146.004.00 B 8111411.001.00 C 5797.000.44 D 69129.001.00 F 1353.000.44\begin{array}{cccccc}\text { Activity } & \text { OT } & \text { MLT } & \text { PT } & \text { ET } & \text { AV } \\\text { A } & 2 & 5 & 14 & 6.00 & 4.00 \\\text { B } & 8 & 11 & 14 & 11.00 & 1.00 \\\text { C } & 5 & 7 & 9 & 7.00 & 0.44 \\\text { D } & 6 & 9 & 12 & 9.00 & 1.00 \\\text { F } & 1 & 3 & 5 & 3.00 & 0.44\end{array}

-Using the table for the advertising and promotion project, if the expected time (not the most likely time) for activity B is changed to 18 weeks, by how many weeks will the project's expected completion time increase?

A) It will not change.
B) It will increase by 1 week.
C) It will increase by 2 weeks.
D) It will increase by 3 weeks.
سؤال
A high definition television manufacturer in Asia wants to develop a new smart television as fast as possible using Program Evaluation and Review Technique (PERT) and must complete the design and testing work first. The objective is to be the first to market the most innovative smart television on the planet and capture the first adopter market share. The manufacturer has determined the following activities, precedence relationships, and time estimates in days for the project:
 Immediate  Optimistic  Most Likely  Pessimistic  Activity  Predecessors totmtp\hlinea none 467 ba123ca555 d b7912eb248fcd6910\begin{array}{rcccr}& \text { Immediate } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\\text { Activity } & \text { Predecessors } & t_{o} & t_{m} & t_{p}\\\hlinea & \text { none } & 4 & 6 & 7 \\\mathrm{~b} & \mathrm{a} & 1 & 2 & 3 \\\mathrm{c} & \mathrm{a} & 5 & 5 & 5 \\\mathrm{~d} & \mathrm{~b} & 7 & 9 & 12 \\\mathrm{e} & \mathrm{b} & 2 & 4 & 8 \\\mathrm{f} & \mathrm{c} d & 6 & 9 & 10\end{array} Solutions are at the end of questions

-There are _____ possible paths in this project network.

A) one
B) two
C) three
D) four
سؤال
Which of the following is NOT true of time/cost trade-offs?

A) The relationship between time and cost is proportional and assumed to be linear.
B) Some activities cannot be crashed.
C) Crash time is less than normal time.
D) Crashing priority is based on the amount of uncertainty in activity times.
سؤال
Ayben is responsible for managing an advertising and promotion project using Program Evaluation and Review Technique (PERT) with the following activities (times are given in weeks).
 Project  Immediate  Optimistic  Most Likely  Pessimistic  Expected  Activity  Activity  Predecessor(s)  Time  Time  Time  Time  Variance  A  none 2514 B  none 81114 C  A 579 D  A 6912 E  B, C, D 135\begin{array}{|c|c|c|c|c|c|c|}\hline\text { Project } & \text { Immediate } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } & \text { Expected } & \text { Activity } \\\hline \text { Activity } & \text { Predecessor(s) } & \text { Time } & \text { Time } & \text { Time } & \text { Time } & \text { Variance } \\\hline\\\hline \text { A } & \text { none } & 2 & 5 & 14 \\\hline \text { B } & \text { none } & 8 & 11 & 14 \\\hline \text { C } & \text { A } & 5 & 7 & 9 \\\hline \text { D } & \text { A } & 6 & 9 & 12 \\\hline \text { E } & \text { B, C, D } & 1 & 3 & 5 \\\hline\end{array} Draw the project network here. BLANK SPACES
 PERT Exam Question #52 to #55 \text { PERT Exam Question \#52 to \#55 }
 Activity  OT  MLT  PT  ET  AV  A 25146.004.00 B 8111411.001.00 C 5797.000.44 D 69129.001.00 F 1353.000.44\begin{array}{cccccc}\text { Activity } & \text { OT } & \text { MLT } & \text { PT } & \text { ET } & \text { AV } \\\text { A } & 2 & 5 & 14 & 6.00 & 4.00 \\\text { B } & 8 & 11 & 14 & 11.00 & 1.00 \\\text { C } & 5 & 7 & 9 & 7.00 & 0.44 \\\text { D } & 6 & 9 & 12 & 9.00 & 1.00 \\\text { F } & 1 & 3 & 5 & 3.00 & 0.44\end{array}

-Using the table for the advertising and promotion project, what is the critical path and expected completion time for this project?

A) A-D-E; 17 weeks
B) A-C-E; 16 weeks
C) B-E; 14 weeks
D) A-D-E; 18 weeks
سؤال
A high definition television manufacturer in Asia wants to develop a new smart television as fast as possible using Program Evaluation and Review Technique (PERT) and must complete the design and testing work first. The objective is to be the first to market the most innovative smart television on the planet and capture the first adopter market share. The manufacturer has determined the following activities, precedence relationships, and time estimates in days for the project:
 Immediate  Optimistic  Most Likely  Pessimistic  Activity  Predecessors totmtp\hlinea none 467 ba123ca555 d b7912eb248fcd6910\begin{array}{rcccr}& \text { Immediate } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\\text { Activity } & \text { Predecessors } & t_{o} & t_{m} & t_{p}\\\hlinea & \text { none } & 4 & 6 & 7 \\\mathrm{~b} & \mathrm{a} & 1 & 2 & 3 \\\mathrm{c} & \mathrm{a} & 5 & 5 & 5 \\\mathrm{~d} & \mathrm{~b} & 7 & 9 & 12 \\\mathrm{e} & \mathrm{b} & 2 & 4 & 8 \\\mathrm{f} & \mathrm{c} d & 6 & 9 & 10\end{array} Solutions are at the end of questions

-What is the critical path

A) A-B-E
B) A-C-F
C) A-C-D-F
D) A-B-D-F
سؤال
Rose is in charge of the advertising program for Proctor & Gamble's new laundry detergent. She has defined the advertising program as a project with the following characteristics. The goal is to complete the project on time and within budget, or she may not have this job next year-the pressure is on!
 Activity  Immediate  Predecessor(s)  Normal  Time  in weeks  Crash Time  in weeks  Normal Cost  Crash Cost  A  None 22$15,000$15,000 B  None 11$12,000$12,000 C  A, B 53$18,000$24,000 D  A, B 42$12,000$16,000 E  C, D 21$22,000$23,500 F  D 43$32,000$36,000 G  E, F 32$19,000$20,000\begin{array}{|c|c|c|c|c|c|}\hline\text { Activity } & \begin{array}{c}\text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array}{c}\text { Normal } \\\text { Time } \\\text { in weeks }\end{array} & \begin{array}{c}\text { Crash Time } \\\text { in weeks }\end{array} & \text { Normal Cost } & \text { Crash Cost } \\\hline \text { A } & \text { None } & 2 & 2 & \$ 15,000 & \$ 15,000 \\\hline \text { B } & \text { None } & 1 & 1 & \$ 12,000 & \$ 12,000 \\\hline \text { C } & \text { A, B } & 5 & 3 & \$ 18,000 & \$ 24,000 \\\hline \text { D } & \text { A, B } & 4 & 2 & \$ 12,000 & \$ 16,000 \\\hline \text { E } & \text { C, D } & 2 & 1 & \$ 22,000 & \$ 23,500 \\\hline \text { F } & \text { D } & 4 & 3 & \$ 32,000 & \$ 36,000 \\\hline \text { G } & \text { E, F } & 3 & 2 & \$ 19,000 & \$ 20,000 \\\hline\end{array} Draw the project network in the space below if you want. BLANK SPACES

-Which activity should one crash to complete the project two weeks earlier than the original project completion time to minimize total crash costs?

A) Activity G by 1 week
B) Activity G by 1 week and activity D by 1 week
C) Activity D by 2 weeks
D) Activity D by 1 week and activity F by 1 week
سؤال
Ayben is responsible for managing an advertising and promotion project using Program Evaluation and Review Technique (PERT) with the following activities (times are given in weeks).
 Project  Immediate  Optimistic  Most Likely  Pessimistic  Expected  Activity  Activity  Predecessor(s)  Time  Time  Time  Time  Variance  A  none 2514 B  none 81114 C  A 579 D  A 6912 E  B, C, D 135\begin{array}{|c|c|c|c|c|c|c|}\hline\text { Project } & \text { Immediate } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } & \text { Expected } & \text { Activity } \\\hline \text { Activity } & \text { Predecessor(s) } & \text { Time } & \text { Time } & \text { Time } & \text { Time } & \text { Variance } \\\hline\\\hline \text { A } & \text { none } & 2 & 5 & 14 \\\hline \text { B } & \text { none } & 8 & 11 & 14 \\\hline \text { C } & \text { A } & 5 & 7 & 9 \\\hline \text { D } & \text { A } & 6 & 9 & 12 \\\hline \text { E } & \text { B, C, D } & 1 & 3 & 5 \\\hline\end{array} Draw the project network here. BLANK SPACES
 PERT Exam Question #52 to #55 \text { PERT Exam Question \#52 to \#55 }
 Activity  OT  MLT  PT  ET  AV  A 25146.004.00 B 8111411.001.00 C 5797.000.44 D 69129.001.00 F 1353.000.44\begin{array}{cccccc}\text { Activity } & \text { OT } & \text { MLT } & \text { PT } & \text { ET } & \text { AV } \\\text { A } & 2 & 5 & 14 & 6.00 & 4.00 \\\text { B } & 8 & 11 & 14 & 11.00 & 1.00 \\\text { C } & 5 & 7 & 9 & 7.00 & 0.44 \\\text { D } & 6 & 9 & 12 & 9.00 & 1.00 \\\text { F } & 1 & 3 & 5 & 3.00 & 0.44\end{array}

-Using the table for the advertising and promotion project, what is the probability percentage that the project will be completed within 16 weeks?

A) Less than or equal to 20%
B) Greater than 20% but less than or equal to 40%
C) Greater than 40% but less than or equal to 60%
D) Greater than 60%
سؤال
Rose is in charge of the advertising program for Proctor & Gamble's new laundry detergent. She has defined the advertising program as a project with the following characteristics. The goal is to complete the project on time and within budget, or she may not have this job next year-the pressure is on!
 Activity  Immediate  Predecessor(s)  Normal  Time  in weeks  Crash Time  in weeks  Normal Cost  Crash Cost  A  None 22$15,000$15,000 B  None 11$12,000$12,000 C  A, B 53$18,000$24,000 D  A, B 42$12,000$16,000 E  C, D 21$22,000$23,500 F  D 43$32,000$36,000 G  E, F 32$19,000$20,000\begin{array}{|c|c|c|c|c|c|}\hline\text { Activity } & \begin{array}{c}\text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array}{c}\text { Normal } \\\text { Time } \\\text { in weeks }\end{array} & \begin{array}{c}\text { Crash Time } \\\text { in weeks }\end{array} & \text { Normal Cost } & \text { Crash Cost } \\\hline \text { A } & \text { None } & 2 & 2 & \$ 15,000 & \$ 15,000 \\\hline \text { B } & \text { None } & 1 & 1 & \$ 12,000 & \$ 12,000 \\\hline \text { C } & \text { A, B } & 5 & 3 & \$ 18,000 & \$ 24,000 \\\hline \text { D } & \text { A, B } & 4 & 2 & \$ 12,000 & \$ 16,000 \\\hline \text { E } & \text { C, D } & 2 & 1 & \$ 22,000 & \$ 23,500 \\\hline \text { F } & \text { D } & 4 & 3 & \$ 32,000 & \$ 36,000 \\\hline \text { G } & \text { E, F } & 3 & 2 & \$ 19,000 & \$ 20,000 \\\hline\end{array} Draw the project network in the space below if you want. BLANK SPACES

-The largest amount of slack that any activity has in this project is:

A) 1 week.
B) 2 weeks.
C) 3 weeks.
D) 4 weeks.
سؤال
You are responsible for managing an advertising project with the following activities (times are given in weeks).
 Immediate  Normal Time  Crash Time  Normal  Crash  Activity  Predecessor  (Weeks)  (Weeks)  Cost ($) Cost ($) A  none 32$14,000$16,500 B  none 66$5,500$5,500 C  none 21$6,000$8,000 D  A, B 53$7,500$14,500 E  C 21$9,000$10,500 F  A 76$15,000$18,000 G  D. E F 43$8,400$10,000\begin{array}{cccccc}&\text { Immediate } & \text { Normal Time } & \text { Crash Time } & \text { Normal } & \text { Crash } \\\text { Activity }&\text { Predecessor } & \text { (Weeks) } & \text { (Weeks) } & \text { Cost }(\$) & \text { Cost }(\$)\\\hline\text { A } & \text { none } & 3 & 2 & \$ 14,000 & \$ 16,500 \\\text { B } & \text { none } & 6 & 6 & \$ 5,500 & \$ 5,500 \\\text { C } & \text { none } & 2 & 1 & \$ 6,000 & \$ 8,000 \\\text { D } & \text { A, B } & 5 & 3 & \$ 7,500 & \$ 14,500 \\\text { E } & \text { C } & 2 & 1 & \$ 9,000 & \$ 10,500 \\\text { F } & \text { A } & 7 & 6 & \$ 15,000 & \$ 18,000 \\\text { G } & \text { D. E F } & 4 & 3 & \$ 8,400 & \$ 10,000\end{array} Draw the project network here. BLANK SPACES

-What is the total project (normal plus crash) cost?

A) Less than or equal to $60,000
B) Greater than $60,000 but less than or equal to $65,000
C) Greater than $65,000 but less than or equal to $70,000
D) Greater than $70,000
سؤال
Which of the following terms is least related to Program Evaluation and Review Technique (PERT)?

A) Beta distribution
B) Variance
C) Most probable time
D) Crashing
سؤال
Rose is in charge of the advertising program for Proctor & Gamble's new laundry detergent. She has defined the advertising program as a project with the following characteristics. The goal is to complete the project on time and within budget, or she may not have this job next year-the pressure is on!
 Activity  Immediate  Predecessor(s)  Normal  Time  in weeks  Crash Time  in weeks  Normal Cost  Crash Cost  A  None 22$15,000$15,000 B  None 11$12,000$12,000 C  A, B 53$18,000$24,000 D  A, B 42$12,000$16,000 E  C, D 21$22,000$23,500 F  D 43$32,000$36,000 G  E, F 32$19,000$20,000\begin{array}{|c|c|c|c|c|c|}\hline\text { Activity } & \begin{array}{c}\text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array}{c}\text { Normal } \\\text { Time } \\\text { in weeks }\end{array} & \begin{array}{c}\text { Crash Time } \\\text { in weeks }\end{array} & \text { Normal Cost } & \text { Crash Cost } \\\hline \text { A } & \text { None } & 2 & 2 & \$ 15,000 & \$ 15,000 \\\hline \text { B } & \text { None } & 1 & 1 & \$ 12,000 & \$ 12,000 \\\hline \text { C } & \text { A, B } & 5 & 3 & \$ 18,000 & \$ 24,000 \\\hline \text { D } & \text { A, B } & 4 & 2 & \$ 12,000 & \$ 16,000 \\\hline \text { E } & \text { C, D } & 2 & 1 & \$ 22,000 & \$ 23,500 \\\hline \text { F } & \text { D } & 4 & 3 & \$ 32,000 & \$ 36,000 \\\hline \text { G } & \text { E, F } & 3 & 2 & \$ 19,000 & \$ 20,000 \\\hline\end{array} Draw the project network in the space below if you want. BLANK SPACES

-The total normal cost of the project is:

A) less than $50,000.
B) more than $50,000 but less than or equal to $75,000.
C) more than $75,000 but less than or equal to $100,000.
D) more than $125,000.
سؤال
In the Activity-On-Node (AON) network, the nodes define the precedence relationships, and the arcs define the work activities.
سؤال
Activity times are always estimated from historical data of similar work tasks to provide realism for a project.
سؤال
Preparation of annual reports does not require project management techniques.
سؤال
Strong leadership is an impediment to project management success because of the team-based nature of most projects.
سؤال
A high definition television manufacturer in Asia wants to develop a new smart television as fast as possible using Program Evaluation and Review Technique (PERT) and must complete the design and testing work first. The objective is to be the first to market the most innovative smart television on the planet and capture the first adopter market share. The manufacturer has determined the following activities, precedence relationships, and time estimates in days for the project:
 Immediate  Optimistic  Most Likely  Pessimistic  Activity  Predecessors totmtp\hlinea none 467 ba123ca555 d b7912eb248fcd6910\begin{array}{rcccr}& \text { Immediate } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\\text { Activity } & \text { Predecessors } & t_{o} & t_{m} & t_{p}\\\hlinea & \text { none } & 4 & 6 & 7 \\\mathrm{~b} & \mathrm{a} & 1 & 2 & 3 \\\mathrm{c} & \mathrm{a} & 5 & 5 & 5 \\\mathrm{~d} & \mathrm{~b} & 7 & 9 & 12 \\\mathrm{e} & \mathrm{b} & 2 & 4 & 8 \\\mathrm{f} & \mathrm{c} d & 6 & 9 & 10\end{array} Solutions are at the end of questions

-The probability that the project will take longer than 28 weeks to complete is _____.

A) less than or equal to 0.1
B) greater than 0.1 but less than or equal to 0.3
C) greater than 0.3 but less than or equal to 0.6
D) greater than 0.6 but less than or equal to 0.9
سؤال
In most organizations, projects cut across organizational boundaries, making it difficult to implement projects exclusively within functional departments.
سؤال
Which one of the following statements about Project Evaluation and Review Technique (PERT) is TRUE?

A) The expected time is given and not computed using formulas.
B) The probability of completing the project on time is 0 when the project target completion time equals the expected time.
C) The normal probability distribution is not used in PERT methods.
D) The variance in project duration is given by the sum of the variances of the critical path activities.
سؤال
All activities on the critical path have a zero slack time.
سؤال
Immediate predecessors are activities that must be completed immediately before an activity may start.
سؤال
The early start time for an activity is computed by finding the largest early finish time of all immediate predecessors.
سؤال
To compute the critical path, all nodes in the network are assigned an earliest starting time of zero.
سؤال
Project managers need to be specialists, not generalists.
سؤال
A high definition television manufacturer in Asia wants to develop a new smart television as fast as possible using Program Evaluation and Review Technique (PERT) and must complete the design and testing work first. The objective is to be the first to market the most innovative smart television on the planet and capture the first adopter market share. The manufacturer has determined the following activities, precedence relationships, and time estimates in days for the project:
 Immediate  Optimistic  Most Likely  Pessimistic  Activity  Predecessors totmtp\hlinea none 467 ba123ca555 d b7912eb248fcd6910\begin{array}{rcccr}& \text { Immediate } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\\text { Activity } & \text { Predecessors } & t_{o} & t_{m} & t_{p}\\\hlinea & \text { none } & 4 & 6 & 7 \\\mathrm{~b} & \mathrm{a} & 1 & 2 & 3 \\\mathrm{c} & \mathrm{a} & 5 & 5 & 5 \\\mathrm{~d} & \mathrm{~b} & 7 & 9 & 12 \\\mathrm{e} & \mathrm{b} & 2 & 4 & 8 \\\mathrm{f} & \mathrm{c} d & 6 & 9 & 10\end{array} Solutions are at the end of questions

-What is the slack time for Activity B?

A) Zero days
B) Greater than zero but less than or equal to 1.0 days
C) Greater than 1.0 but less than or equal to 2.0 days
D) Greater than 2.0 days
سؤال
A Gantt chart is a useful tool for allocating limited resources among project activities.
سؤال
Project management objectives revolve around time and budget.
سؤال
A high definition television manufacturer in Asia wants to develop a new smart television as fast as possible using Program Evaluation and Review Technique (PERT) and must complete the design and testing work first. The objective is to be the first to market the most innovative smart television on the planet and capture the first adopter market share. The manufacturer has determined the following activities, precedence relationships, and time estimates in days for the project:
 Immediate  Optimistic  Most Likely  Pessimistic  Activity  Predecessors totmtp\hlinea none 467 ba123ca555 d b7912eb248fcd6910\begin{array}{rcccr}& \text { Immediate } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\\text { Activity } & \text { Predecessors } & t_{o} & t_{m} & t_{p}\\\hlinea & \text { none } & 4 & 6 & 7 \\\mathrm{~b} & \mathrm{a} & 1 & 2 & 3 \\\mathrm{c} & \mathrm{a} & 5 & 5 & 5 \\\mathrm{~d} & \mathrm{~b} & 7 & 9 & 12 \\\mathrm{e} & \mathrm{b} & 2 & 4 & 8 \\\mathrm{f} & \mathrm{c} d & 6 & 9 & 10\end{array} Solutions are at the end of questions

-The standard deviation (not variance) of the critical path in days is _____.

A) less than or equal to 1.0 days
B) greater than 1.0 but less than or equal to 2.0 days
C) greater than 2.0 but less than or equal to 3.0 days
D) greater than 3.0 days
سؤال
A slack of 2 means the project is ahead of schedule by two time periods.
سؤال
A statement of work would be developed in the "organize" step of the project life cycle.
سؤال
A high definition television manufacturer in Asia wants to develop a new smart television as fast as possible using Program Evaluation and Review Technique (PERT) and must complete the design and testing work first. The objective is to be the first to market the most innovative smart television on the planet and capture the first adopter market share. The manufacturer has determined the following activities, precedence relationships, and time estimates in days for the project:
 Immediate  Optimistic  Most Likely  Pessimistic  Activity  Predecessors totmtp\hlinea none 467 ba123ca555 d b7912eb248fcd6910\begin{array}{rcccr}& \text { Immediate } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\\text { Activity } & \text { Predecessors } & t_{o} & t_{m} & t_{p}\\\hlinea & \text { none } & 4 & 6 & 7 \\\mathrm{~b} & \mathrm{a} & 1 & 2 & 3 \\\mathrm{c} & \mathrm{a} & 5 & 5 & 5 \\\mathrm{~d} & \mathrm{~b} & 7 & 9 & 12 \\\mathrm{e} & \mathrm{b} & 2 & 4 & 8 \\\mathrm{f} & \mathrm{c} d & 6 & 9 & 10\end{array} Solutions are at the end of questions

-The expected duration of the critical path in days is _____.

A) less than or equal to 20 days
B) greater than 20 but less than or equal to 25 days
C) greater than 25 but less than or equal to 30 days
D) greater than 30 days
سؤال
The critical path is the sequence of activities that takes the longest time.
فتح الحزمة
قم بالتسجيل لفتح البطاقات في هذه المجموعة!
Unlock Deck
Unlock Deck
1/108
auto play flashcards
العب
simple tutorial
ملء الشاشة (f)
exit full mode
Deck 18: Project Management
1
Jude is in charge of the advertising program for the Boston Red Sox baseball team during their spring training in Fort Myers, Florida. He has defined the advertising program as a project with the following characteristics. The goal is to fill all stadium seats during the spring training season or he may not have this job next year-the pressure is on!
 Activity  Immediate  Predecessor(s)  Activity Time  in weeks  A  None 1 B  None 1 C  A 4 D  B 5 E  C, D 5 F  E 3 G  F 2\begin{array}{|c|c|c|}\hline \text { Activity } & \begin{array}{c}\text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array}{c}\text { Activity Time } \\\text { in weeks }\end{array} \\\hline \text { A } & \text { None } & 1 \\\hline \text { B } & \text { None } & 1 \\\hline \text { C } & \text { A } & 4 \\\hline \text { D } & \text { B } & 5 \\\hline \text { E } & \text { C, D } & 5 \\\hline \text { F } & \text { E } & 3 \\\hline \text { G } & \text { F } & 2 \\\hline\end{array}

-The largest amount of slack that any activity has in this project is:

A) 1 week.
B) 2 weeks.
C) 3 weeks.
D) 4 weeks.
1 week.
2
Consider the following project network. Time estimates are in weeks.  <strong>Consider the following project network. Time estimates are in weeks.   Complete the following table and questions :  \begin{array} { | c | l | l | l | l | l | l | l | } \hline \text { Activity } & \text { Time } & \text { Earliest Start } & \text { Earliest Finish } & \text { Latest Start } & \text { Latest Finish } & \text { Slack } & \text { On Critical Path? } \\ \hline \text { A } & & & & & & & \\ \hline \text { B } & & & & & & & \\ \hline \text { C } & & & & & & & \\ \hline \text { D } & & & & & & & \\ \hline \text { E } & & & & & & & \\ \hline \text { F } & & & & & & \\ \hline \end{array}   \begin{array}{|c|c|c|c|c|c|c|c|} \hline \text { Activity } & \text { Duration } & \text { ES } & \text { EF } & \text { LS } & \text { LF } & \text { Slack } & \begin{array}{c} \text { On } \\ \text { CP? } \end{array} \\ \hline \text { A } & 2 & 0 & 2 & 0 & 2 & 0 & \text { yes } \\ \hline \text { B } & 4 & 2 & 6 & 2 & 6 & 0 & \text { yes } \\ \hline \text { C } & 5 & 6 & 11 & 6 & 11 & 0 & \text { yes } \\ \hline \text { D } & 4 & 11 & 15 & 11 & 15 & 0 & \text { yes } \\ \hline \text { E } & 6 & 2 & 8 & 9 & 15 & 7 & \text { no } \\ \hline \text { F } & 7 & 15 & 22 & 15 & 22 & 0 & \text { yes } \\ \hline \end{array}   -In the previous project network, the latest finish for activity B is:</strong> A) 5. B) 6. C) 7. D) 8.  Complete the following table and questions :  Activity  Time  Earliest Start  Earliest Finish  Latest Start  Latest Finish  Slack  On Critical Path?  A  B  C  D  E  F \begin{array} { | c | l | l | l | l | l | l | l | } \hline \text { Activity } & \text { Time } & \text { Earliest Start } & \text { Earliest Finish } & \text { Latest Start } & \text { Latest Finish } & \text { Slack } & \text { On Critical Path? } \\\hline \text { A } & & & & & & & \\\hline \text { B } & & & & & & & \\\hline \text { C } & & & & & & & \\\hline \text { D } & & & & & & & \\\hline \text { E } & & & & & & & \\\hline \text { F } & & & & & & \\\hline\end{array}  Activity  Duration  ES  EF  LS  LF  Slack  On  CP?  A 202020 yes  B 426260 yes  C 56116110 yes  D 4111511150 yes  E 6289157 no  F 7152215220 yes \begin{array}{|c|c|c|c|c|c|c|c|}\hline \text { Activity } & \text { Duration } & \text { ES } & \text { EF } & \text { LS } & \text { LF } & \text { Slack } & \begin{array}{c}\text { On } \\\text { CP? }\end{array} \\\hline \text { A } & 2 & 0 & 2 & 0 & 2 & 0 & \text { yes } \\\hline \text { B } & 4 & 2 & 6 & 2 & 6 & 0 & \text { yes } \\\hline \text { C } & 5 & 6 & 11 & 6 & 11 & 0 & \text { yes } \\\hline \text { D } & 4 & 11 & 15 & 11 & 15 & 0 & \text { yes } \\\hline \text { E } & 6 & 2 & 8 & 9 & 15 & 7 & \text { no } \\\hline \text { F } & 7 & 15 & 22 & 15 & 22 & 0 & \text { yes } \\\hline\end{array}

-In the previous project network, the latest finish for activity B is:

A) 5.
B) 6.
C) 7.
D) 8.
6.
3
Jude is in charge of the advertising program for the Boston Red Sox baseball team during their spring training in Fort Myers, Florida. He has defined the advertising program as a project with the following characteristics. The goal is to fill all stadium seats during the spring training season or he may not have this job next year-the pressure is on!
 Activity  Immediate  Predecessor(s)  Activity Time  in weeks  A  None 1 B  None 1 C  A 4 D  B 5 E  C, D 5 F  E 3 G  F 2\begin{array}{|c|c|c|}\hline \text { Activity } & \begin{array}{c}\text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array}{c}\text { Activity Time } \\\text { in weeks }\end{array} \\\hline \text { A } & \text { None } & 1 \\\hline \text { B } & \text { None } & 1 \\\hline \text { C } & \text { A } & 4 \\\hline \text { D } & \text { B } & 5 \\\hline \text { E } & \text { C, D } & 5 \\\hline \text { F } & \text { E } & 3 \\\hline \text { G } & \text { F } & 2 \\\hline\end{array}

-The most likely activities to share resources with critical path activities are:

A) Activities A and B.
B) Activities E and A.
C) Activities A and C.
D) Activities B and D.
Activities A and C.
4
Consider the following project network. Time estimates are in weeks.  <strong>Consider the following project network. Time estimates are in weeks.   Complete the following table and questions :  \begin{array} { | c | l | l | l | l | l | l | l | } \hline \text { Activity } & \text { Time } & \text { Earliest Start } & \text { Earliest Finish } & \text { Latest Start } & \text { Latest Finish } & \text { Slack } & \text { On Critical Path? } \\ \hline \text { A } & & & & & & & \\ \hline \text { B } & & & & & & & \\ \hline \text { C } & & & & & & & \\ \hline \text { D } & & & & & & & \\ \hline \text { E } & & & & & & & \\ \hline \text { F } & & & & & & \\ \hline \end{array}   \begin{array}{|c|c|c|c|c|c|c|c|} \hline \text { Activity } & \text { Duration } & \text { ES } & \text { EF } & \text { LS } & \text { LF } & \text { Slack } & \begin{array}{c} \text { On } \\ \text { CP? } \end{array} \\ \hline \text { A } & 2 & 0 & 2 & 0 & 2 & 0 & \text { yes } \\ \hline \text { B } & 4 & 2 & 6 & 2 & 6 & 0 & \text { yes } \\ \hline \text { C } & 5 & 6 & 11 & 6 & 11 & 0 & \text { yes } \\ \hline \text { D } & 4 & 11 & 15 & 11 & 15 & 0 & \text { yes } \\ \hline \text { E } & 6 & 2 & 8 & 9 & 15 & 7 & \text { no } \\ \hline \text { F } & 7 & 15 & 22 & 15 & 22 & 0 & \text { yes } \\ \hline \end{array}   -Slack for activity E is:</strong> A) less than 4. B) between 4 and 6. C) between 6 and 8. D) greater than 8.  Complete the following table and questions :  Activity  Time  Earliest Start  Earliest Finish  Latest Start  Latest Finish  Slack  On Critical Path?  A  B  C  D  E  F \begin{array} { | c | l | l | l | l | l | l | l | } \hline \text { Activity } & \text { Time } & \text { Earliest Start } & \text { Earliest Finish } & \text { Latest Start } & \text { Latest Finish } & \text { Slack } & \text { On Critical Path? } \\\hline \text { A } & & & & & & & \\\hline \text { B } & & & & & & & \\\hline \text { C } & & & & & & & \\\hline \text { D } & & & & & & & \\\hline \text { E } & & & & & & & \\\hline \text { F } & & & & & & \\\hline\end{array}  Activity  Duration  ES  EF  LS  LF  Slack  On  CP?  A 202020 yes  B 426260 yes  C 56116110 yes  D 4111511150 yes  E 6289157 no  F 7152215220 yes \begin{array}{|c|c|c|c|c|c|c|c|}\hline \text { Activity } & \text { Duration } & \text { ES } & \text { EF } & \text { LS } & \text { LF } & \text { Slack } & \begin{array}{c}\text { On } \\\text { CP? }\end{array} \\\hline \text { A } & 2 & 0 & 2 & 0 & 2 & 0 & \text { yes } \\\hline \text { B } & 4 & 2 & 6 & 2 & 6 & 0 & \text { yes } \\\hline \text { C } & 5 & 6 & 11 & 6 & 11 & 0 & \text { yes } \\\hline \text { D } & 4 & 11 & 15 & 11 & 15 & 0 & \text { yes } \\\hline \text { E } & 6 & 2 & 8 & 9 & 15 & 7 & \text { no } \\\hline \text { F } & 7 & 15 & 22 & 15 & 22 & 0 & \text { yes } \\\hline\end{array}

-Slack for activity E is:

A) less than 4.
B) between 4 and 6.
C) between 6 and 8.
D) greater than 8.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
5
Which one of the following is NOT a major project management decision area?

A) Revenue
B) Cost
C) Time
D) Resources
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
6
Which one of the following skills contributes to project success?

A) Lack of data accuracy and integrity
B) Clear communication channels
C) Ill-defined project objectives
D) Inability to resolve conflicts
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
7
Which of the following is NOT a stage in the project life cycle?

A) Define
B) Organize
C) Improve
D) Close
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
8
The Baker county government has decided to redo the street and plans to block the street off which causes considerable inconvenience to people. The critical path method (CPM) project has three sequential (in series, that is "i" is first, then "ii" and finally "iii.") paths defined as follows: (i) path A-B-C-H to install street lights and electrical wiring that takes 10 days, (ii) path G-J-K-L to install sidewalks with handicap capabilities that takes 20 days, and (iii) path U-V-Z-W to repave the street including storm drains that takes 8 days. Which one of the following statements is true?

A) The expected duration of the project is 10 + 20 + 8 = 38 days.
B) The expected duration of the project is 20 days.
C) The normal time is inversely related to the crash time.
D) The three sub-system precedent relationships are in parallel.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
9
_____ is the sequence of activities that takes the longest time and defines the total project completion time.

A) Project Evaluation and Review Technique
B) The critical path
C) The crash time
D) Project nodes network
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
10
Consider the following project network. Time estimates are in weeks.  <strong>Consider the following project network. Time estimates are in weeks.   Complete the following table and questions :  \begin{array} { | c | l | l | l | l | l | l | l | } \hline \text { Activity } & \text { Time } & \text { Earliest Start } & \text { Earliest Finish } & \text { Latest Start } & \text { Latest Finish } & \text { Slack } & \text { On Critical Path? } \\ \hline \text { A } & & & & & & & \\ \hline \text { B } & & & & & & & \\ \hline \text { C } & & & & & & & \\ \hline \text { D } & & & & & & & \\ \hline \text { E } & & & & & & & \\ \hline \text { F } & & & & & & \\ \hline \end{array}   \begin{array}{|c|c|c|c|c|c|c|c|} \hline \text { Activity } & \text { Duration } & \text { ES } & \text { EF } & \text { LS } & \text { LF } & \text { Slack } & \begin{array}{c} \text { On } \\ \text { CP? } \end{array} \\ \hline \text { A } & 2 & 0 & 2 & 0 & 2 & 0 & \text { yes } \\ \hline \text { B } & 4 & 2 & 6 & 2 & 6 & 0 & \text { yes } \\ \hline \text { C } & 5 & 6 & 11 & 6 & 11 & 0 & \text { yes } \\ \hline \text { D } & 4 & 11 & 15 & 11 & 15 & 0 & \text { yes } \\ \hline \text { E } & 6 & 2 & 8 & 9 & 15 & 7 & \text { no } \\ \hline \text { F } & 7 & 15 & 22 & 15 & 22 & 0 & \text { yes } \\ \hline \end{array}   -In the previous project network, the critical path activities are:</strong> A) A,B, and C. B) A,B,C,D, and F. C) A,B,D, and F. D) B,C,D, and F.  Complete the following table and questions :  Activity  Time  Earliest Start  Earliest Finish  Latest Start  Latest Finish  Slack  On Critical Path?  A  B  C  D  E  F \begin{array} { | c | l | l | l | l | l | l | l | } \hline \text { Activity } & \text { Time } & \text { Earliest Start } & \text { Earliest Finish } & \text { Latest Start } & \text { Latest Finish } & \text { Slack } & \text { On Critical Path? } \\\hline \text { A } & & & & & & & \\\hline \text { B } & & & & & & & \\\hline \text { C } & & & & & & & \\\hline \text { D } & & & & & & & \\\hline \text { E } & & & & & & & \\\hline \text { F } & & & & & & \\\hline\end{array}  Activity  Duration  ES  EF  LS  LF  Slack  On  CP?  A 202020 yes  B 426260 yes  C 56116110 yes  D 4111511150 yes  E 6289157 no  F 7152215220 yes \begin{array}{|c|c|c|c|c|c|c|c|}\hline \text { Activity } & \text { Duration } & \text { ES } & \text { EF } & \text { LS } & \text { LF } & \text { Slack } & \begin{array}{c}\text { On } \\\text { CP? }\end{array} \\\hline \text { A } & 2 & 0 & 2 & 0 & 2 & 0 & \text { yes } \\\hline \text { B } & 4 & 2 & 6 & 2 & 6 & 0 & \text { yes } \\\hline \text { C } & 5 & 6 & 11 & 6 & 11 & 0 & \text { yes } \\\hline \text { D } & 4 & 11 & 15 & 11 & 15 & 0 & \text { yes } \\\hline \text { E } & 6 & 2 & 8 & 9 & 15 & 7 & \text { no } \\\hline \text { F } & 7 & 15 & 22 & 15 & 22 & 0 & \text { yes } \\\hline\end{array}

-In the previous project network, the critical path activities are:

A) A,B, and C.
B) A,B,C,D, and F.
C) A,B,D, and F.
D) B,C,D, and F.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
11
A Gantt chart is:

A) a useful tool for depicting a schedule graphically.
B) a chart that enables the project manager to know what activities should be performed at a given time.
C) a chart that can be used to monitor daily progress of a project so that corrective action can be taken when necessary.
D) All of the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
12
The county government has decided to redo the street and plans to block the street off which causes considerable inconvenience to people. The project has three parallel paths defined as follows: (i) path A-B-C-H to install street lights and electrical wiring that takes 16 days, (ii) path A-D-E-H to install sidewalks with handicap capabilities that takes 22 days, and (iii) path A-F-G-H to repave the street including storm drains that takes 30 days. Which one of the following statements is TRUE?

A) The expected duration of the project is 30 + 22 + 16 = 68 days.
B) Path A-B-C-H is the critical path.
C) Path A-D-E-H has the largest slack time.
D) Path A-F-G-H is the critical path.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
13
In which stage of the project life cycle would a project schedule be developed?

A) Define
B) Plan
C) Organize
D) Control
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
14
Slack in an activity is computed as:

A) ES - LS.
B) EF - LF.
C) LS - ES.
D) LS - EF.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
15
Jude is in charge of the advertising program for the Boston Red Sox baseball team during their spring training in Fort Myers, Florida. He has defined the advertising program as a project with the following characteristics. The goal is to fill all stadium seats during the spring training season or he may not have this job next year-the pressure is on!
 Activity  Immediate  Predecessor(s)  Activity Time  in weeks  A  None 1 B  None 1 C  A 4 D  B 5 E  C, D 5 F  E 3 G  F 2\begin{array}{|c|c|c|}\hline \text { Activity } & \begin{array}{c}\text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array}{c}\text { Activity Time } \\\text { in weeks }\end{array} \\\hline \text { A } & \text { None } & 1 \\\hline \text { B } & \text { None } & 1 \\\hline \text { C } & \text { A } & 4 \\\hline \text { D } & \text { B } & 5 \\\hline \text { E } & \text { C, D } & 5 \\\hline \text { F } & \text { E } & 3 \\\hline \text { G } & \text { F } & 2 \\\hline\end{array}

-The earliest completion time for this project is:

A) 12 weeks.
B) 13 weeks.
C) 14 weeks.
D) 16 weeks.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
16
A project has three parallel paths. A-B-C has a length of 25 days. A-D-C has a length of 15 days. Finally, A-E-C has a length of 20 days. Which one of the following statements is TRUE?

A) A-D-C is the critical path.
B) A-B-C has the most slack.
C) The expected duration of this project is 25 days.
D) The expected duration of this project is 25 + 15 + 20 = 60 days.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
17
Which of the following is NOT considered a project?

A) Writing and implementing a computer program
B) Introducing a new product
C) Production of soft drinks
D) Building a bridge
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
18
The critical path method (CPM) work breakdown structure consists of all of the following EXCEPT:

A) the number and definition of each project activity.
B) the normal time to complete each activity.
C) the immediate predecessors (i.e., the precedent relationships).
D) the probabilities of completing each activity.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
19
Jude is in charge of the advertising program for the Boston Red Sox baseball team during their spring training in Fort Myers, Florida. He has defined the advertising program as a project with the following characteristics. The goal is to fill all stadium seats during the spring training season or he may not have this job next year-the pressure is on!
 Activity  Immediate  Predecessor(s)  Activity Time  in weeks  A  None 1 B  None 1 C  A 4 D  B 5 E  C, D 5 F  E 3 G  F 2\begin{array}{|c|c|c|}\hline \text { Activity } & \begin{array}{c}\text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array}{c}\text { Activity Time } \\\text { in weeks }\end{array} \\\hline \text { A } & \text { None } & 1 \\\hline \text { B } & \text { None } & 1 \\\hline \text { C } & \text { A } & 4 \\\hline \text { D } & \text { B } & 5 \\\hline \text { E } & \text { C, D } & 5 \\\hline \text { F } & \text { E } & 3 \\\hline \text { G } & \text { F } & 2 \\\hline\end{array}

-If activity C is delayed by 2 weeks, then the revised earliest project completion time is:

A) 13 weeks.
B) 14 weeks.
C) 15 weeks.
D) 17 weeks.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
20
Shea is in charge of the "advertising program" for the Boston Red Sox baseball team during their spring training in Fort Myers, Florida. She has defined the advertising program as a project with the following characteristics. The goal is to fill all stadium seats during the spring training season or she may not have the same job next year-the pressure is on!
 Activity  Immediate  Predecessor(s)  Activity Time  in weeks  A  None 1 B  A 2 C  A 3 D  A, B 4 E  C, D 3 F  D, E 2\begin{array}{|c|c|c|}\hline \text { Activity } & \begin{array}{c}\text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array}{c}\text { Activity Time } \\\text { in weeks }\end{array} \\\hline \text { A } & \text { None } & 1 \\\hline \text { B } & \text { A } & 2 \\\hline \text { C } & \text { A } & 3 \\\hline \text { D } & \text { A, B } & 4 \\\hline \text { E } & \text { C, D } & 3 \\\hline \text { F } & \text { D, E } & 2 \\\hline\end{array}

-The earliest completion time for this project is:

A) 9 weeks.
B) 10 weeks.
C) 11 weeks.
D) 12 weeks.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
21
You are responsible for managing an advertising project with the following activities (times are given in weeks).
 Immediate  Normal Time  Crash Time  Normal  Crash  Activity  Predecessor  (Weeks)  (Weeks)  Cost ($) Cost ($) A  none 32$14,000$16,500 B  none 66$5,500$5,500 C  none 21$6,000$8,000 D  A, B 53$7,500$14,500 E  C 21$9,000$10,500 F  A 76$15,000$18,000 G  D. E F 43$8,400$10,000\begin{array}{cccccc}&\text { Immediate } & \text { Normal Time } & \text { Crash Time } & \text { Normal } & \text { Crash } \\\text { Activity }&\text { Predecessor } & \text { (Weeks) } & \text { (Weeks) } & \text { Cost }(\$) & \text { Cost }(\$)\\\hline\text { A } & \text { none } & 3 & 2 & \$ 14,000 & \$ 16,500 \\\text { B } & \text { none } & 6 & 6 & \$ 5,500 & \$ 5,500 \\\text { C } & \text { none } & 2 & 1 & \$ 6,000 & \$ 8,000 \\\text { D } & \text { A, B } & 5 & 3 & \$ 7,500 & \$ 14,500 \\\text { E } & \text { C } & 2 & 1 & \$ 9,000 & \$ 10,500 \\\text { F } & \text { A } & 7 & 6 & \$ 15,000 & \$ 18,000 \\\text { G } & \text { D. E F } & 4 & 3 & \$ 8,400 & \$ 10,000\end{array} Draw the project network here. BLANK SPACES

-The project completion time is _____.

A) 12 weeks
B) 13 weeks
C) 14 weeks
D) 15 weeks
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
22
Shea is in charge of the "advertising program" for the Boston Red Sox baseball team during their spring training in Fort Myers, Florida. She has defined the advertising program as a project with the following characteristics. The goal is to fill all stadium seats during the spring training season or she may not have the same job next year-the pressure is on!
 Activity  Immediate  Predecessor(s)  Activity Time  in weeks  A  None 1 B  A 2 C  A 3 D  A, B 4 E  C, D 3 F  D, E 2\begin{array}{|c|c|c|}\hline \text { Activity } & \begin{array}{c}\text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array}{c}\text { Activity Time } \\\text { in weeks }\end{array} \\\hline \text { A } & \text { None } & 1 \\\hline \text { B } & \text { A } & 2 \\\hline \text { C } & \text { A } & 3 \\\hline \text { D } & \text { A, B } & 4 \\\hline \text { E } & \text { C, D } & 3 \\\hline \text { F } & \text { D, E } & 2 \\\hline\end{array}

-For the original critical path method problem, the minimum number of activities that would have to be crashed in order to reduce the project's earliest completion time by two weeks assuming all activity crash costs per week are the same and all activities can be crashed is:

A) one activity.
B) two activities.
C) three activities.
D) four activities.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
23
Which is NOT true of the critical path?

A) The activities on the critical path take the shortest time to complete.
B) The activities on the critical path define the total project completion time.
C) It is the project path with zero slack.
D) The delays in critical path activities will delay the project.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
24
You are responsible for managing a project with the following activities (times are given in weeks):
 Immediate  Normal Time  Crash Time  Normal  Crash  Activity  Predecessor  (Weeks)  (Weeks)  Cost ($) Cost ($) A  none 32$14,000$16,500 B  none 66$5,500$5,500 C  none 21$6,000$8,000 D  A 53$7,500$14,500 E  C 21$9,000$10,500 F  A 76$15,000$18,000 G  B. D. E. F 43$8,400$10,000\begin{array}{cccccc}&\text { Immediate } & \text { Normal Time } & \text { Crash Time } & \text { Normal } & \text { Crash } \\\text { Activity }&\text { Predecessor } & \text { (Weeks) } & \text { (Weeks) } & \text { Cost }(\$) & \text { Cost }(\$)\\\hline\text { A } & \text { none } & 3 & 2 & \$ 14,000 & \$ 16,500 \\\text { B } & \text { none } & 6 & 6 & \$ 5,500 & \$ 5,500 \\\text { C } & \text { none } & 2 & 1 & \$ 6,000 & \$ 8,000 \\\text { D } & \text { A } & 5 & 3 & \$ 7,500 & \$ 14,500 \\\text { E } & \text { C } & 2 & 1 & \$ 9,000 & \$ 10,500 \\\text { F } & \text { A } & 7 & 6 & \$ 15,000 & \$ 18,000 \\\text { G } & \text { B. D. E. F } & 4 & 3 & \$ 8,400 & \$ 10,000\end{array}

-What activity should one crash to reduce the project completion time by two weeks at minimum crash costs?

A) A and F.
B) A and G.
C) A and E.
D) G and F.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
25
You are responsible for managing a project with the following activities (times are given in weeks):
 Immediate  Normal Time  Crash Time  Normal  Crash  Activity  Predecessor  (Weeks)  (Weeks)  Cost ($) Cost ($) A  none 32$14,000$16,500 B  none 66$5,500$5,500 C  none 21$6,000$8,000 D  A 53$7,500$14,500 E  C 21$9,000$10,500 F  A 76$15,000$18,000 G  B. D. E. F 43$8,400$10,000\begin{array}{cccccc}&\text { Immediate } & \text { Normal Time } & \text { Crash Time } & \text { Normal } & \text { Crash } \\\text { Activity }&\text { Predecessor } & \text { (Weeks) } & \text { (Weeks) } & \text { Cost }(\$) & \text { Cost }(\$)\\\hline\text { A } & \text { none } & 3 & 2 & \$ 14,000 & \$ 16,500 \\\text { B } & \text { none } & 6 & 6 & \$ 5,500 & \$ 5,500 \\\text { C } & \text { none } & 2 & 1 & \$ 6,000 & \$ 8,000 \\\text { D } & \text { A } & 5 & 3 & \$ 7,500 & \$ 14,500 \\\text { E } & \text { C } & 2 & 1 & \$ 9,000 & \$ 10,500 \\\text { F } & \text { A } & 7 & 6 & \$ 15,000 & \$ 18,000 \\\text { G } & \text { B. D. E. F } & 4 & 3 & \$ 8,400 & \$ 10,000\end{array}

-If activity D is delayed by 2 weeks, which one of the following statements is TRUE?

A) There are now two critical paths in the network.
B) The slack time for activity D changes to 1 week.
C) The project completion time is still 12 weeks.
D) The project completion time becomes 16 weeks.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
26
Which of the following is true of project scheduling using the critical path method?

A) Activity crash time is greater than normal time.
B) Crash cost per time period is assumed to be non-linear.
C) Gantt charts are built using activity ES, EF, LS, and LF times.
D) Gantt charts assume a beta probability distribution.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
27
Brian is assigned his first project. If things go well, he should get promoted. The CEO is aware of this project, so he has a chance for high visibility. His first task is to define the work break down structure by interviewing project activity managers, and the firm's friendly, yet boring accountants, to get "good estimates" of project activity times and costs. For Activity Z, the crash cost per week is _____, given the following data: normal time = 5 weeks, crash time = 2, normal cost = $7,560, and crash cost = $17,365.

A) less than or equal to $1,000 per week
B) more than $1,000 but less than or equal to $2,500
C) more than $2,500 but less than or equal to $3,000
D) more than $3,000 but less than or equal to $3,500
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
28
You are responsible for managing an advertising project with the following activities (times are given in weeks).
 Immediate  Normal Time  Crash Time  Normal  Crash  Activity  Predecessor  (Weeks)  (Weeks)  Cost ($) Cost ($) A  none 32$14,000$16,500 B  none 66$5,500$5,500 C  none 21$6,000$8,000 D  A, B 53$7,500$14,500 E  C 21$9,000$10,500 F  A 76$15,000$18,000 G  D. E F 43$8,400$10,000\begin{array}{cccccc}&\text { Immediate } & \text { Normal Time } & \text { Crash Time } & \text { Normal } & \text { Crash } \\\text { Activity }&\text { Predecessor } & \text { (Weeks) } & \text { (Weeks) } & \text { Cost }(\$) & \text { Cost }(\$)\\\hline\text { A } & \text { none } & 3 & 2 & \$ 14,000 & \$ 16,500 \\\text { B } & \text { none } & 6 & 6 & \$ 5,500 & \$ 5,500 \\\text { C } & \text { none } & 2 & 1 & \$ 6,000 & \$ 8,000 \\\text { D } & \text { A, B } & 5 & 3 & \$ 7,500 & \$ 14,500 \\\text { E } & \text { C } & 2 & 1 & \$ 9,000 & \$ 10,500 \\\text { F } & \text { A } & 7 & 6 & \$ 15,000 & \$ 18,000 \\\text { G } & \text { D. E F } & 4 & 3 & \$ 8,400 & \$ 10,000\end{array} Draw the project network here. BLANK SPACES

-What activity should one crash to reduce the project completion time by two weeks at minimum crash costs?

A) A and F, each by one week
B) A and D, each by one week
C) C and D, each by one week
D) D and G, each by one week
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
29
Which of the following is NOT an assumption of the critical path method?

A) Activities are independent of one another.
B) Activity time estimates are stable.
C) Activity times are characterized by a beta probability distribution.
D) Once an activity is started, it continues uninterrupted until completion.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
30
You are responsible for managing a project with the following activities (times are given in weeks):
 Immediate  Normal Time  Crash Time  Normal  Crash  Activity  Predecessor  (Weeks)  (Weeks)  Cost ($) Cost ($) A  none 32$14,000$16,500 B  none 66$5,500$5,500 C  none 21$6,000$8,000 D  A 53$7,500$14,500 E  C 21$9,000$10,500 F  A 76$15,000$18,000 G  B. D. E. F 43$8,400$10,000\begin{array}{cccccc}&\text { Immediate } & \text { Normal Time } & \text { Crash Time } & \text { Normal } & \text { Crash } \\\text { Activity }&\text { Predecessor } & \text { (Weeks) } & \text { (Weeks) } & \text { Cost }(\$) & \text { Cost }(\$)\\\hline\text { A } & \text { none } & 3 & 2 & \$ 14,000 & \$ 16,500 \\\text { B } & \text { none } & 6 & 6 & \$ 5,500 & \$ 5,500 \\\text { C } & \text { none } & 2 & 1 & \$ 6,000 & \$ 8,000 \\\text { D } & \text { A } & 5 & 3 & \$ 7,500 & \$ 14,500 \\\text { E } & \text { C } & 2 & 1 & \$ 9,000 & \$ 10,500 \\\text { F } & \text { A } & 7 & 6 & \$ 15,000 & \$ 18,000 \\\text { G } & \text { B. D. E. F } & 4 & 3 & \$ 8,400 & \$ 10,000\end{array}

-What is the total project (normal plus crash) cost?

A) Less than or equal to $60,000
B) Greater than $60,000 but less than or equal to $65,000
C) Greater than $65,000 but less than or equal to $70,000
D) Greater than $70,000
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
31
You are responsible for managing an advertising project with the following activities (times are given in weeks).
 Immediate  Normal Time  Crash Time  Normal  Crash  Activity  Predecessor  (Weeks)  (Weeks)  Cost ($) Cost ($) A  none 32$14,000$16,500 B  none 66$5,500$5,500 C  none 21$6,000$8,000 D  A, B 53$7,500$14,500 E  C 21$9,000$10,500 F  A 76$15,000$18,000 G  D. E F 43$8,400$10,000\begin{array}{cccccc}&\text { Immediate } & \text { Normal Time } & \text { Crash Time } & \text { Normal } & \text { Crash } \\\text { Activity }&\text { Predecessor } & \text { (Weeks) } & \text { (Weeks) } & \text { Cost }(\$) & \text { Cost }(\$)\\\hline\text { A } & \text { none } & 3 & 2 & \$ 14,000 & \$ 16,500 \\\text { B } & \text { none } & 6 & 6 & \$ 5,500 & \$ 5,500 \\\text { C } & \text { none } & 2 & 1 & \$ 6,000 & \$ 8,000 \\\text { D } & \text { A, B } & 5 & 3 & \$ 7,500 & \$ 14,500 \\\text { E } & \text { C } & 2 & 1 & \$ 9,000 & \$ 10,500 \\\text { F } & \text { A } & 7 & 6 & \$ 15,000 & \$ 18,000 \\\text { G } & \text { D. E F } & 4 & 3 & \$ 8,400 & \$ 10,000\end{array} Draw the project network here. BLANK SPACES

-What is the critical path for this project?

A) A-D-G
B) A-F-G
C) B-D-G
D) C-E-G
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
32
You are responsible for managing a project with the following activities (times are given in weeks):
 Immediate  Normal Time  Crash Time  Normal  Crash  Activity  Predecessor  (Weeks)  (Weeks)  Cost ($) Cost ($) A  none 32$14,000$16,500 B  none 66$5,500$5,500 C  none 21$6,000$8,000 D  A 53$7,500$14,500 E  C 21$9,000$10,500 F  A 76$15,000$18,000 G  B. D. E. F 43$8,400$10,000\begin{array}{cccccc}&\text { Immediate } & \text { Normal Time } & \text { Crash Time } & \text { Normal } & \text { Crash } \\\text { Activity }&\text { Predecessor } & \text { (Weeks) } & \text { (Weeks) } & \text { Cost }(\$) & \text { Cost }(\$)\\\hline\text { A } & \text { none } & 3 & 2 & \$ 14,000 & \$ 16,500 \\\text { B } & \text { none } & 6 & 6 & \$ 5,500 & \$ 5,500 \\\text { C } & \text { none } & 2 & 1 & \$ 6,000 & \$ 8,000 \\\text { D } & \text { A } & 5 & 3 & \$ 7,500 & \$ 14,500 \\\text { E } & \text { C } & 2 & 1 & \$ 9,000 & \$ 10,500 \\\text { F } & \text { A } & 7 & 6 & \$ 15,000 & \$ 18,000 \\\text { G } & \text { B. D. E. F } & 4 & 3 & \$ 8,400 & \$ 10,000\end{array}

-Which of the following activities has the largest amount of slack?

A) Activity A
B) Activity B
C) Activity C
D) Activity D
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
33
You are responsible for managing an advertising project with the following activities (times are given in weeks).
 Immediate  Normal Time  Crash Time  Normal  Crash  Activity  Predecessor  (Weeks)  (Weeks)  Cost ($) Cost ($) A  none 32$14,000$16,500 B  none 66$5,500$5,500 C  none 21$6,000$8,000 D  A, B 53$7,500$14,500 E  C 21$9,000$10,500 F  A 76$15,000$18,000 G  D. E F 43$8,400$10,000\begin{array}{cccccc}&\text { Immediate } & \text { Normal Time } & \text { Crash Time } & \text { Normal } & \text { Crash } \\\text { Activity }&\text { Predecessor } & \text { (Weeks) } & \text { (Weeks) } & \text { Cost }(\$) & \text { Cost }(\$)\\\hline\text { A } & \text { none } & 3 & 2 & \$ 14,000 & \$ 16,500 \\\text { B } & \text { none } & 6 & 6 & \$ 5,500 & \$ 5,500 \\\text { C } & \text { none } & 2 & 1 & \$ 6,000 & \$ 8,000 \\\text { D } & \text { A, B } & 5 & 3 & \$ 7,500 & \$ 14,500 \\\text { E } & \text { C } & 2 & 1 & \$ 9,000 & \$ 10,500 \\\text { F } & \text { A } & 7 & 6 & \$ 15,000 & \$ 18,000 \\\text { G } & \text { D. E F } & 4 & 3 & \$ 8,400 & \$ 10,000\end{array} Draw the project network here. BLANK SPACES

-If activity D is delayed by 2 weeks, which one of the following statements is TRUE?

A) There are now two critical paths in the network.
B) The slack time for activity D changes to 1 week.
C) The project completion time is still 14 weeks.
D) The project completion time becomes 18 weeks.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
34
You are responsible for managing a project with the following activities (times are given in weeks):
 Immediate  Normal Time  Crash Time  Normal  Crash  Activity  Predecessor  (Weeks)  (Weeks)  Cost ($) Cost ($) A  none 32$14,000$16,500 B  none 66$5,500$5,500 C  none 21$6,000$8,000 D  A 53$7,500$14,500 E  C 21$9,000$10,500 F  A 76$15,000$18,000 G  B. D. E. F 43$8,400$10,000\begin{array}{cccccc}&\text { Immediate } & \text { Normal Time } & \text { Crash Time } & \text { Normal } & \text { Crash } \\\text { Activity }&\text { Predecessor } & \text { (Weeks) } & \text { (Weeks) } & \text { Cost }(\$) & \text { Cost }(\$)\\\hline\text { A } & \text { none } & 3 & 2 & \$ 14,000 & \$ 16,500 \\\text { B } & \text { none } & 6 & 6 & \$ 5,500 & \$ 5,500 \\\text { C } & \text { none } & 2 & 1 & \$ 6,000 & \$ 8,000 \\\text { D } & \text { A } & 5 & 3 & \$ 7,500 & \$ 14,500 \\\text { E } & \text { C } & 2 & 1 & \$ 9,000 & \$ 10,500 \\\text { F } & \text { A } & 7 & 6 & \$ 15,000 & \$ 18,000 \\\text { G } & \text { B. D. E. F } & 4 & 3 & \$ 8,400 & \$ 10,000\end{array}

-What is the critical path and expected completion time for this project?

A) B-D-G; 12 weeks
B) A-D-G; 12 weeks
C) B-G; 10 weeks
D) A-F-G; 14 weeks
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
35
Shea is in charge of the "advertising program" for the Boston Red Sox baseball team during their spring training in Fort Myers, Florida. She has defined the advertising program as a project with the following characteristics. The goal is to fill all stadium seats during the spring training season or she may not have the same job next year-the pressure is on!
 Activity  Immediate  Predecessor(s)  Activity Time  in weeks  A  None 1 B  A 2 C  A 3 D  A, B 4 E  C, D 3 F  D, E 2\begin{array}{|c|c|c|}\hline \text { Activity } & \begin{array}{c}\text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array}{c}\text { Activity Time } \\\text { in weeks }\end{array} \\\hline \text { A } & \text { None } & 1 \\\hline \text { B } & \text { A } & 2 \\\hline \text { C } & \text { A } & 3 \\\hline \text { D } & \text { A, B } & 4 \\\hline \text { E } & \text { C, D } & 3 \\\hline \text { F } & \text { D, E } & 2 \\\hline\end{array}

-If activity C is delayed by three weeks, the revised earliest project completion time is:

A) 9 weeks.
B) 10 weeks.
C) 11 weeks.
D) 12 weeks.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
36
You are responsible for managing an advertising project with the following activities (times are given in weeks).
 Immediate  Normal Time  Crash Time  Normal  Crash  Activity  Predecessor  (Weeks)  (Weeks)  Cost ($) Cost ($) A  none 32$14,000$16,500 B  none 66$5,500$5,500 C  none 21$6,000$8,000 D  A, B 53$7,500$14,500 E  C 21$9,000$10,500 F  A 76$15,000$18,000 G  D. E F 43$8,400$10,000\begin{array}{cccccc}&\text { Immediate } & \text { Normal Time } & \text { Crash Time } & \text { Normal } & \text { Crash } \\\text { Activity }&\text { Predecessor } & \text { (Weeks) } & \text { (Weeks) } & \text { Cost }(\$) & \text { Cost }(\$)\\\hline\text { A } & \text { none } & 3 & 2 & \$ 14,000 & \$ 16,500 \\\text { B } & \text { none } & 6 & 6 & \$ 5,500 & \$ 5,500 \\\text { C } & \text { none } & 2 & 1 & \$ 6,000 & \$ 8,000 \\\text { D } & \text { A, B } & 5 & 3 & \$ 7,500 & \$ 14,500 \\\text { E } & \text { C } & 2 & 1 & \$ 9,000 & \$ 10,500 \\\text { F } & \text { A } & 7 & 6 & \$ 15,000 & \$ 18,000 \\\text { G } & \text { D. E F } & 4 & 3 & \$ 8,400 & \$ 10,000\end{array} Draw the project network here. BLANK SPACES

-Which of the following activities has the largest amount of slack?

A) Activity A
B) Activity B
C) Activity C
D) Activity D
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
37
Which one of the following statements about the critical path method (CPM) is TRUE?

A) The activity time estimates are accurate and stable.
B) Activities are dependent on each other.
C) Activities can be interrupted before completion.
D) The project schedule defines a correct sequence of work in terms of technology and workflow.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
38
Which one of the following statements about critical path method (CPM) is TRUE?

A) Crashing an activity refers to increasing its normal time.
B) Crashing an activity refers to decreasing its normal time possibly up to its limit.
C) Crashing a project requires revised immediate predecessor relationships.
D) Crashing a project is a tradeoff between revenue and costs.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
39
Shea is in charge of the "advertising program" for the Boston Red Sox baseball team during their spring training in Fort Myers, Florida. She has defined the advertising program as a project with the following characteristics. The goal is to fill all stadium seats during the spring training season or she may not have the same job next year-the pressure is on!
 Activity  Immediate  Predecessor(s)  Activity Time  in weeks  A  None 1 B  A 2 C  A 3 D  A, B 4 E  C, D 3 F  D, E 2\begin{array}{|c|c|c|}\hline \text { Activity } & \begin{array}{c}\text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array}{c}\text { Activity Time } \\\text { in weeks }\end{array} \\\hline \text { A } & \text { None } & 1 \\\hline \text { B } & \text { A } & 2 \\\hline \text { C } & \text { A } & 3 \\\hline \text { D } & \text { A, B } & 4 \\\hline \text { E } & \text { C, D } & 3 \\\hline \text { F } & \text { D, E } & 2 \\\hline\end{array}

-The largest amount of slack that any activity has in this project is:

A) 1 week.
B) 2 weeks.
C) 3 weeks.
D) 4 weeks.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
40
Which of the following statements is TRUE of the activities not on the critical path?

A) These activities usually cannot be delayed.
B) These activities have less slack than activities on the critical path.
C) These activities can become part of the critical path if delayed long enough.
D) These activities have uncertain times.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
41
Which of the following is LEAST relevant to Program Evaluation and Review Technique (PERT)?

A) Beta distribution
B) Variance of activity time
C) Most probable time
D) Constant activity time
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
42
Which of the following forms part of Program Evaluation and Review Technique (PERT)?

A) Beta distribution
B) Variance
C) Most probable time
D) All of above are related to PERT
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
43
A high definition television manufacturer in Asia wants to develop a new smart television as fast as possible using Program Evaluation and Review Technique (PERT) and must complete the design and testing work first. The objective is to be the first to market the most innovative smart television on the planet and capture the first adopter market share. The manufacturer has determined the following activities, precedence relationships, and time estimates in days for the project:
 Immediate  Optimistic  Most Likely  Pessimistic  Activity  Predecessors totmtp\hlinea none 467 ba123ca555 d b7912eb248fcd6910\begin{array}{rcccr}& \text { Immediate } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\\text { Activity } & \text { Predecessors } & t_{o} & t_{m} & t_{p}\\\hlinea & \text { none } & 4 & 6 & 7 \\\mathrm{~b} & \mathrm{a} & 1 & 2 & 3 \\\mathrm{c} & \mathrm{a} & 5 & 5 & 5 \\\mathrm{~d} & \mathrm{~b} & 7 & 9 & 12 \\\mathrm{e} & \mathrm{b} & 2 & 4 & 8 \\\mathrm{f} & \mathrm{c} d & 6 & 9 & 10\end{array} Solutions are at the end of questions

-The expected variance of Activity A is _____.

A) less than or equal to 0.5 days
B) greater than 0.5 but less than or equal to 1.0 day
C) greater than 1.0 but less than or equal to 1.5 days
D) greater than 1.5 days
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
44
Ayben is responsible for managing an advertising and promotion project using Program Evaluation and Review Technique (PERT) with the following activities (times are given in weeks).
 Project  Immediate  Optimistic  Most Likely  Pessimistic  Expected  Activity  Activity  Predecessor(s)  Time  Time  Time  Time  Variance  A  none 2514 B  none 81114 C  A 579 D  A 6912 E  B, C, D 135\begin{array}{|c|c|c|c|c|c|c|}\hline\text { Project } & \text { Immediate } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } & \text { Expected } & \text { Activity } \\\hline \text { Activity } & \text { Predecessor(s) } & \text { Time } & \text { Time } & \text { Time } & \text { Time } & \text { Variance } \\\hline\\\hline \text { A } & \text { none } & 2 & 5 & 14 \\\hline \text { B } & \text { none } & 8 & 11 & 14 \\\hline \text { C } & \text { A } & 5 & 7 & 9 \\\hline \text { D } & \text { A } & 6 & 9 & 12 \\\hline \text { E } & \text { B, C, D } & 1 & 3 & 5 \\\hline\end{array} Draw the project network here. BLANK SPACES
 PERT Exam Question #52 to #55 \text { PERT Exam Question \#52 to \#55 }
 Activity  OT  MLT  PT  ET  AV  A 25146.004.00 B 8111411.001.00 C 5797.000.44 D 69129.001.00 F 1353.000.44\begin{array}{cccccc}\text { Activity } & \text { OT } & \text { MLT } & \text { PT } & \text { ET } & \text { AV } \\\text { A } & 2 & 5 & 14 & 6.00 & 4.00 \\\text { B } & 8 & 11 & 14 & 11.00 & 1.00 \\\text { C } & 5 & 7 & 9 & 7.00 & 0.44 \\\text { D } & 6 & 9 & 12 & 9.00 & 1.00 \\\text { F } & 1 & 3 & 5 & 3.00 & 0.44\end{array}

-Using the table for the advertising and promotion project, which activity has the largest slack, and how large is that slack?

A) Activity C; 5 weeks
B) Activity A; 6 weeks
C) Activity B; 4 weeks
D) Activity E; 3 weeks
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
45
Rose is in charge of the advertising program for Proctor & Gamble's new laundry detergent. She has defined the advertising program as a project with the following characteristics. The goal is to complete the project on time and within budget, or she may not have this job next year-the pressure is on!
 Activity  Immediate  Predecessor(s)  Normal  Time  in weeks  Crash Time  in weeks  Normal Cost  Crash Cost  A  None 22$15,000$15,000 B  None 11$12,000$12,000 C  A, B 53$18,000$24,000 D  A, B 42$12,000$16,000 E  C, D 21$22,000$23,500 F  D 43$32,000$36,000 G  E, F 32$19,000$20,000\begin{array}{|c|c|c|c|c|c|}\hline\text { Activity } & \begin{array}{c}\text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array}{c}\text { Normal } \\\text { Time } \\\text { in weeks }\end{array} & \begin{array}{c}\text { Crash Time } \\\text { in weeks }\end{array} & \text { Normal Cost } & \text { Crash Cost } \\\hline \text { A } & \text { None } & 2 & 2 & \$ 15,000 & \$ 15,000 \\\hline \text { B } & \text { None } & 1 & 1 & \$ 12,000 & \$ 12,000 \\\hline \text { C } & \text { A, B } & 5 & 3 & \$ 18,000 & \$ 24,000 \\\hline \text { D } & \text { A, B } & 4 & 2 & \$ 12,000 & \$ 16,000 \\\hline \text { E } & \text { C, D } & 2 & 1 & \$ 22,000 & \$ 23,500 \\\hline \text { F } & \text { D } & 4 & 3 & \$ 32,000 & \$ 36,000 \\\hline \text { G } & \text { E, F } & 3 & 2 & \$ 19,000 & \$ 20,000 \\\hline\end{array} Draw the project network in the space below if you want. BLANK SPACES

-The total minimum crash cost only for the project to achieve a two-week earlier completion time from the original project completion time is:

A) less than $1,000.
B) more than $1,000 but less than or equal to $2,000.
C) more than $2,000 but less than or equal to $3,000.
D) more than $3,000 but less than or equal to $4,000.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
46
A high definition television manufacturer in Asia wants to develop a new smart television as fast as possible using Program Evaluation and Review Technique (PERT) and must complete the design and testing work first. The objective is to be the first to market the most innovative smart television on the planet and capture the first adopter market share. The manufacturer has determined the following activities, precedence relationships, and time estimates in days for the project:
 Immediate  Optimistic  Most Likely  Pessimistic  Activity  Predecessors totmtp\hlinea none 467 ba123ca555 d b7912eb248fcd6910\begin{array}{rcccr}& \text { Immediate } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\\text { Activity } & \text { Predecessors } & t_{o} & t_{m} & t_{p}\\\hlinea & \text { none } & 4 & 6 & 7 \\\mathrm{~b} & \mathrm{a} & 1 & 2 & 3 \\\mathrm{c} & \mathrm{a} & 5 & 5 & 5 \\\mathrm{~d} & \mathrm{~b} & 7 & 9 & 12 \\\mathrm{e} & \mathrm{b} & 2 & 4 & 8 \\\mathrm{f} & \mathrm{c} d & 6 & 9 & 10\end{array} Solutions are at the end of questions

-The expected duration of Activity A is _____.

A) Less than or equal to 2 days
B) Greater than 2 but less than or equal to 4 days
C) Greater than 4 but less than or equal to 6 days
D) Greater than 6 days
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
47
Rose is in charge of the advertising program for Proctor & Gamble's new laundry detergent. She has defined the advertising program as a project with the following characteristics. The goal is to complete the project on time and within budget, or she may not have this job next year-the pressure is on!
 Activity  Immediate  Predecessor(s)  Normal  Time  in weeks  Crash Time  in weeks  Normal Cost  Crash Cost  A  None 22$15,000$15,000 B  None 11$12,000$12,000 C  A, B 53$18,000$24,000 D  A, B 42$12,000$16,000 E  C, D 21$22,000$23,500 F  D 43$32,000$36,000 G  E, F 32$19,000$20,000\begin{array}{|c|c|c|c|c|c|}\hline\text { Activity } & \begin{array}{c}\text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array}{c}\text { Normal } \\\text { Time } \\\text { in weeks }\end{array} & \begin{array}{c}\text { Crash Time } \\\text { in weeks }\end{array} & \text { Normal Cost } & \text { Crash Cost } \\\hline \text { A } & \text { None } & 2 & 2 & \$ 15,000 & \$ 15,000 \\\hline \text { B } & \text { None } & 1 & 1 & \$ 12,000 & \$ 12,000 \\\hline \text { C } & \text { A, B } & 5 & 3 & \$ 18,000 & \$ 24,000 \\\hline \text { D } & \text { A, B } & 4 & 2 & \$ 12,000 & \$ 16,000 \\\hline \text { E } & \text { C, D } & 2 & 1 & \$ 22,000 & \$ 23,500 \\\hline \text { F } & \text { D } & 4 & 3 & \$ 32,000 & \$ 36,000 \\\hline \text { G } & \text { E, F } & 3 & 2 & \$ 19,000 & \$ 20,000 \\\hline\end{array} Draw the project network in the space below if you want. BLANK SPACES

-If activity D is delayed by 2 weeks, the revised earliest project completion time is:

A) 11 weeks.
B) 12 weeks.
C) 13 weeks.
D) 15 weeks.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
48
Rose is in charge of the advertising program for Proctor & Gamble's new laundry detergent. She has defined the advertising program as a project with the following characteristics. The goal is to complete the project on time and within budget, or she may not have this job next year-the pressure is on!
 Activity  Immediate  Predecessor(s)  Normal  Time  in weeks  Crash Time  in weeks  Normal Cost  Crash Cost  A  None 22$15,000$15,000 B  None 11$12,000$12,000 C  A, B 53$18,000$24,000 D  A, B 42$12,000$16,000 E  C, D 21$22,000$23,500 F  D 43$32,000$36,000 G  E, F 32$19,000$20,000\begin{array}{|c|c|c|c|c|c|}\hline\text { Activity } & \begin{array}{c}\text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array}{c}\text { Normal } \\\text { Time } \\\text { in weeks }\end{array} & \begin{array}{c}\text { Crash Time } \\\text { in weeks }\end{array} & \text { Normal Cost } & \text { Crash Cost } \\\hline \text { A } & \text { None } & 2 & 2 & \$ 15,000 & \$ 15,000 \\\hline \text { B } & \text { None } & 1 & 1 & \$ 12,000 & \$ 12,000 \\\hline \text { C } & \text { A, B } & 5 & 3 & \$ 18,000 & \$ 24,000 \\\hline \text { D } & \text { A, B } & 4 & 2 & \$ 12,000 & \$ 16,000 \\\hline \text { E } & \text { C, D } & 2 & 1 & \$ 22,000 & \$ 23,500 \\\hline \text { F } & \text { D } & 4 & 3 & \$ 32,000 & \$ 36,000 \\\hline \text { G } & \text { E, F } & 3 & 2 & \$ 19,000 & \$ 20,000 \\\hline\end{array} Draw the project network in the space below if you want. BLANK SPACES

-The earliest completion time for this project is:

A) 11 weeks.
B) 12 weeks.
C) 13 weeks.
D) 14 weeks.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
49
Rose is in charge of the advertising program for Proctor & Gamble's new laundry detergent. She has defined the advertising program as a project with the following characteristics. The goal is to complete the project on time and within budget, or she may not have this job next year-the pressure is on!
 Activity  Immediate  Predecessor(s)  Normal  Time  in weeks  Crash Time  in weeks  Normal Cost  Crash Cost  A  None 22$15,000$15,000 B  None 11$12,000$12,000 C  A, B 53$18,000$24,000 D  A, B 42$12,000$16,000 E  C, D 21$22,000$23,500 F  D 43$32,000$36,000 G  E, F 32$19,000$20,000\begin{array}{|c|c|c|c|c|c|}\hline\text { Activity } & \begin{array}{c}\text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array}{c}\text { Normal } \\\text { Time } \\\text { in weeks }\end{array} & \begin{array}{c}\text { Crash Time } \\\text { in weeks }\end{array} & \text { Normal Cost } & \text { Crash Cost } \\\hline \text { A } & \text { None } & 2 & 2 & \$ 15,000 & \$ 15,000 \\\hline \text { B } & \text { None } & 1 & 1 & \$ 12,000 & \$ 12,000 \\\hline \text { C } & \text { A, B } & 5 & 3 & \$ 18,000 & \$ 24,000 \\\hline \text { D } & \text { A, B } & 4 & 2 & \$ 12,000 & \$ 16,000 \\\hline \text { E } & \text { C, D } & 2 & 1 & \$ 22,000 & \$ 23,500 \\\hline \text { F } & \text { D } & 4 & 3 & \$ 32,000 & \$ 36,000 \\\hline \text { G } & \text { E, F } & 3 & 2 & \$ 19,000 & \$ 20,000 \\\hline\end{array} Draw the project network in the space below if you want. BLANK SPACES

-Britt is managing this project, and his bossRose gives him $5,000 to speed up the original completion time (i.e., project improvement dollars). The best action is to:

A) spend it on activity G first.
B) spend it on activity F first.
C) spent it on activity C first.
D) spend one-half of it on activity C and one-half on activity E.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
50
Ayben is responsible for managing an advertising and promotion project using Program Evaluation and Review Technique (PERT) with the following activities (times are given in weeks).
 Project  Immediate  Optimistic  Most Likely  Pessimistic  Expected  Activity  Activity  Predecessor(s)  Time  Time  Time  Time  Variance  A  none 2514 B  none 81114 C  A 579 D  A 6912 E  B, C, D 135\begin{array}{|c|c|c|c|c|c|c|}\hline\text { Project } & \text { Immediate } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } & \text { Expected } & \text { Activity } \\\hline \text { Activity } & \text { Predecessor(s) } & \text { Time } & \text { Time } & \text { Time } & \text { Time } & \text { Variance } \\\hline\\\hline \text { A } & \text { none } & 2 & 5 & 14 \\\hline \text { B } & \text { none } & 8 & 11 & 14 \\\hline \text { C } & \text { A } & 5 & 7 & 9 \\\hline \text { D } & \text { A } & 6 & 9 & 12 \\\hline \text { E } & \text { B, C, D } & 1 & 3 & 5 \\\hline\end{array} Draw the project network here. BLANK SPACES
 PERT Exam Question #52 to #55 \text { PERT Exam Question \#52 to \#55 }
 Activity  OT  MLT  PT  ET  AV  A 25146.004.00 B 8111411.001.00 C 5797.000.44 D 69129.001.00 F 1353.000.44\begin{array}{cccccc}\text { Activity } & \text { OT } & \text { MLT } & \text { PT } & \text { ET } & \text { AV } \\\text { A } & 2 & 5 & 14 & 6.00 & 4.00 \\\text { B } & 8 & 11 & 14 & 11.00 & 1.00 \\\text { C } & 5 & 7 & 9 & 7.00 & 0.44 \\\text { D } & 6 & 9 & 12 & 9.00 & 1.00 \\\text { F } & 1 & 3 & 5 & 3.00 & 0.44\end{array}

-Using the table for the advertising and promotion project, if the expected time (not the most likely time) for activity B is changed to 18 weeks, by how many weeks will the project's expected completion time increase?

A) It will not change.
B) It will increase by 1 week.
C) It will increase by 2 weeks.
D) It will increase by 3 weeks.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
51
A high definition television manufacturer in Asia wants to develop a new smart television as fast as possible using Program Evaluation and Review Technique (PERT) and must complete the design and testing work first. The objective is to be the first to market the most innovative smart television on the planet and capture the first adopter market share. The manufacturer has determined the following activities, precedence relationships, and time estimates in days for the project:
 Immediate  Optimistic  Most Likely  Pessimistic  Activity  Predecessors totmtp\hlinea none 467 ba123ca555 d b7912eb248fcd6910\begin{array}{rcccr}& \text { Immediate } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\\text { Activity } & \text { Predecessors } & t_{o} & t_{m} & t_{p}\\\hlinea & \text { none } & 4 & 6 & 7 \\\mathrm{~b} & \mathrm{a} & 1 & 2 & 3 \\\mathrm{c} & \mathrm{a} & 5 & 5 & 5 \\\mathrm{~d} & \mathrm{~b} & 7 & 9 & 12 \\\mathrm{e} & \mathrm{b} & 2 & 4 & 8 \\\mathrm{f} & \mathrm{c} d & 6 & 9 & 10\end{array} Solutions are at the end of questions

-There are _____ possible paths in this project network.

A) one
B) two
C) three
D) four
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
52
Which of the following is NOT true of time/cost trade-offs?

A) The relationship between time and cost is proportional and assumed to be linear.
B) Some activities cannot be crashed.
C) Crash time is less than normal time.
D) Crashing priority is based on the amount of uncertainty in activity times.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
53
Ayben is responsible for managing an advertising and promotion project using Program Evaluation and Review Technique (PERT) with the following activities (times are given in weeks).
 Project  Immediate  Optimistic  Most Likely  Pessimistic  Expected  Activity  Activity  Predecessor(s)  Time  Time  Time  Time  Variance  A  none 2514 B  none 81114 C  A 579 D  A 6912 E  B, C, D 135\begin{array}{|c|c|c|c|c|c|c|}\hline\text { Project } & \text { Immediate } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } & \text { Expected } & \text { Activity } \\\hline \text { Activity } & \text { Predecessor(s) } & \text { Time } & \text { Time } & \text { Time } & \text { Time } & \text { Variance } \\\hline\\\hline \text { A } & \text { none } & 2 & 5 & 14 \\\hline \text { B } & \text { none } & 8 & 11 & 14 \\\hline \text { C } & \text { A } & 5 & 7 & 9 \\\hline \text { D } & \text { A } & 6 & 9 & 12 \\\hline \text { E } & \text { B, C, D } & 1 & 3 & 5 \\\hline\end{array} Draw the project network here. BLANK SPACES
 PERT Exam Question #52 to #55 \text { PERT Exam Question \#52 to \#55 }
 Activity  OT  MLT  PT  ET  AV  A 25146.004.00 B 8111411.001.00 C 5797.000.44 D 69129.001.00 F 1353.000.44\begin{array}{cccccc}\text { Activity } & \text { OT } & \text { MLT } & \text { PT } & \text { ET } & \text { AV } \\\text { A } & 2 & 5 & 14 & 6.00 & 4.00 \\\text { B } & 8 & 11 & 14 & 11.00 & 1.00 \\\text { C } & 5 & 7 & 9 & 7.00 & 0.44 \\\text { D } & 6 & 9 & 12 & 9.00 & 1.00 \\\text { F } & 1 & 3 & 5 & 3.00 & 0.44\end{array}

-Using the table for the advertising and promotion project, what is the critical path and expected completion time for this project?

A) A-D-E; 17 weeks
B) A-C-E; 16 weeks
C) B-E; 14 weeks
D) A-D-E; 18 weeks
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
54
A high definition television manufacturer in Asia wants to develop a new smart television as fast as possible using Program Evaluation and Review Technique (PERT) and must complete the design and testing work first. The objective is to be the first to market the most innovative smart television on the planet and capture the first adopter market share. The manufacturer has determined the following activities, precedence relationships, and time estimates in days for the project:
 Immediate  Optimistic  Most Likely  Pessimistic  Activity  Predecessors totmtp\hlinea none 467 ba123ca555 d b7912eb248fcd6910\begin{array}{rcccr}& \text { Immediate } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\\text { Activity } & \text { Predecessors } & t_{o} & t_{m} & t_{p}\\\hlinea & \text { none } & 4 & 6 & 7 \\\mathrm{~b} & \mathrm{a} & 1 & 2 & 3 \\\mathrm{c} & \mathrm{a} & 5 & 5 & 5 \\\mathrm{~d} & \mathrm{~b} & 7 & 9 & 12 \\\mathrm{e} & \mathrm{b} & 2 & 4 & 8 \\\mathrm{f} & \mathrm{c} d & 6 & 9 & 10\end{array} Solutions are at the end of questions

-What is the critical path

A) A-B-E
B) A-C-F
C) A-C-D-F
D) A-B-D-F
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
55
Rose is in charge of the advertising program for Proctor & Gamble's new laundry detergent. She has defined the advertising program as a project with the following characteristics. The goal is to complete the project on time and within budget, or she may not have this job next year-the pressure is on!
 Activity  Immediate  Predecessor(s)  Normal  Time  in weeks  Crash Time  in weeks  Normal Cost  Crash Cost  A  None 22$15,000$15,000 B  None 11$12,000$12,000 C  A, B 53$18,000$24,000 D  A, B 42$12,000$16,000 E  C, D 21$22,000$23,500 F  D 43$32,000$36,000 G  E, F 32$19,000$20,000\begin{array}{|c|c|c|c|c|c|}\hline\text { Activity } & \begin{array}{c}\text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array}{c}\text { Normal } \\\text { Time } \\\text { in weeks }\end{array} & \begin{array}{c}\text { Crash Time } \\\text { in weeks }\end{array} & \text { Normal Cost } & \text { Crash Cost } \\\hline \text { A } & \text { None } & 2 & 2 & \$ 15,000 & \$ 15,000 \\\hline \text { B } & \text { None } & 1 & 1 & \$ 12,000 & \$ 12,000 \\\hline \text { C } & \text { A, B } & 5 & 3 & \$ 18,000 & \$ 24,000 \\\hline \text { D } & \text { A, B } & 4 & 2 & \$ 12,000 & \$ 16,000 \\\hline \text { E } & \text { C, D } & 2 & 1 & \$ 22,000 & \$ 23,500 \\\hline \text { F } & \text { D } & 4 & 3 & \$ 32,000 & \$ 36,000 \\\hline \text { G } & \text { E, F } & 3 & 2 & \$ 19,000 & \$ 20,000 \\\hline\end{array} Draw the project network in the space below if you want. BLANK SPACES

-Which activity should one crash to complete the project two weeks earlier than the original project completion time to minimize total crash costs?

A) Activity G by 1 week
B) Activity G by 1 week and activity D by 1 week
C) Activity D by 2 weeks
D) Activity D by 1 week and activity F by 1 week
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
56
Ayben is responsible for managing an advertising and promotion project using Program Evaluation and Review Technique (PERT) with the following activities (times are given in weeks).
 Project  Immediate  Optimistic  Most Likely  Pessimistic  Expected  Activity  Activity  Predecessor(s)  Time  Time  Time  Time  Variance  A  none 2514 B  none 81114 C  A 579 D  A 6912 E  B, C, D 135\begin{array}{|c|c|c|c|c|c|c|}\hline\text { Project } & \text { Immediate } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } & \text { Expected } & \text { Activity } \\\hline \text { Activity } & \text { Predecessor(s) } & \text { Time } & \text { Time } & \text { Time } & \text { Time } & \text { Variance } \\\hline\\\hline \text { A } & \text { none } & 2 & 5 & 14 \\\hline \text { B } & \text { none } & 8 & 11 & 14 \\\hline \text { C } & \text { A } & 5 & 7 & 9 \\\hline \text { D } & \text { A } & 6 & 9 & 12 \\\hline \text { E } & \text { B, C, D } & 1 & 3 & 5 \\\hline\end{array} Draw the project network here. BLANK SPACES
 PERT Exam Question #52 to #55 \text { PERT Exam Question \#52 to \#55 }
 Activity  OT  MLT  PT  ET  AV  A 25146.004.00 B 8111411.001.00 C 5797.000.44 D 69129.001.00 F 1353.000.44\begin{array}{cccccc}\text { Activity } & \text { OT } & \text { MLT } & \text { PT } & \text { ET } & \text { AV } \\\text { A } & 2 & 5 & 14 & 6.00 & 4.00 \\\text { B } & 8 & 11 & 14 & 11.00 & 1.00 \\\text { C } & 5 & 7 & 9 & 7.00 & 0.44 \\\text { D } & 6 & 9 & 12 & 9.00 & 1.00 \\\text { F } & 1 & 3 & 5 & 3.00 & 0.44\end{array}

-Using the table for the advertising and promotion project, what is the probability percentage that the project will be completed within 16 weeks?

A) Less than or equal to 20%
B) Greater than 20% but less than or equal to 40%
C) Greater than 40% but less than or equal to 60%
D) Greater than 60%
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
57
Rose is in charge of the advertising program for Proctor & Gamble's new laundry detergent. She has defined the advertising program as a project with the following characteristics. The goal is to complete the project on time and within budget, or she may not have this job next year-the pressure is on!
 Activity  Immediate  Predecessor(s)  Normal  Time  in weeks  Crash Time  in weeks  Normal Cost  Crash Cost  A  None 22$15,000$15,000 B  None 11$12,000$12,000 C  A, B 53$18,000$24,000 D  A, B 42$12,000$16,000 E  C, D 21$22,000$23,500 F  D 43$32,000$36,000 G  E, F 32$19,000$20,000\begin{array}{|c|c|c|c|c|c|}\hline\text { Activity } & \begin{array}{c}\text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array}{c}\text { Normal } \\\text { Time } \\\text { in weeks }\end{array} & \begin{array}{c}\text { Crash Time } \\\text { in weeks }\end{array} & \text { Normal Cost } & \text { Crash Cost } \\\hline \text { A } & \text { None } & 2 & 2 & \$ 15,000 & \$ 15,000 \\\hline \text { B } & \text { None } & 1 & 1 & \$ 12,000 & \$ 12,000 \\\hline \text { C } & \text { A, B } & 5 & 3 & \$ 18,000 & \$ 24,000 \\\hline \text { D } & \text { A, B } & 4 & 2 & \$ 12,000 & \$ 16,000 \\\hline \text { E } & \text { C, D } & 2 & 1 & \$ 22,000 & \$ 23,500 \\\hline \text { F } & \text { D } & 4 & 3 & \$ 32,000 & \$ 36,000 \\\hline \text { G } & \text { E, F } & 3 & 2 & \$ 19,000 & \$ 20,000 \\\hline\end{array} Draw the project network in the space below if you want. BLANK SPACES

-The largest amount of slack that any activity has in this project is:

A) 1 week.
B) 2 weeks.
C) 3 weeks.
D) 4 weeks.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
58
You are responsible for managing an advertising project with the following activities (times are given in weeks).
 Immediate  Normal Time  Crash Time  Normal  Crash  Activity  Predecessor  (Weeks)  (Weeks)  Cost ($) Cost ($) A  none 32$14,000$16,500 B  none 66$5,500$5,500 C  none 21$6,000$8,000 D  A, B 53$7,500$14,500 E  C 21$9,000$10,500 F  A 76$15,000$18,000 G  D. E F 43$8,400$10,000\begin{array}{cccccc}&\text { Immediate } & \text { Normal Time } & \text { Crash Time } & \text { Normal } & \text { Crash } \\\text { Activity }&\text { Predecessor } & \text { (Weeks) } & \text { (Weeks) } & \text { Cost }(\$) & \text { Cost }(\$)\\\hline\text { A } & \text { none } & 3 & 2 & \$ 14,000 & \$ 16,500 \\\text { B } & \text { none } & 6 & 6 & \$ 5,500 & \$ 5,500 \\\text { C } & \text { none } & 2 & 1 & \$ 6,000 & \$ 8,000 \\\text { D } & \text { A, B } & 5 & 3 & \$ 7,500 & \$ 14,500 \\\text { E } & \text { C } & 2 & 1 & \$ 9,000 & \$ 10,500 \\\text { F } & \text { A } & 7 & 6 & \$ 15,000 & \$ 18,000 \\\text { G } & \text { D. E F } & 4 & 3 & \$ 8,400 & \$ 10,000\end{array} Draw the project network here. BLANK SPACES

-What is the total project (normal plus crash) cost?

A) Less than or equal to $60,000
B) Greater than $60,000 but less than or equal to $65,000
C) Greater than $65,000 but less than or equal to $70,000
D) Greater than $70,000
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
59
Which of the following terms is least related to Program Evaluation and Review Technique (PERT)?

A) Beta distribution
B) Variance
C) Most probable time
D) Crashing
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
60
Rose is in charge of the advertising program for Proctor & Gamble's new laundry detergent. She has defined the advertising program as a project with the following characteristics. The goal is to complete the project on time and within budget, or she may not have this job next year-the pressure is on!
 Activity  Immediate  Predecessor(s)  Normal  Time  in weeks  Crash Time  in weeks  Normal Cost  Crash Cost  A  None 22$15,000$15,000 B  None 11$12,000$12,000 C  A, B 53$18,000$24,000 D  A, B 42$12,000$16,000 E  C, D 21$22,000$23,500 F  D 43$32,000$36,000 G  E, F 32$19,000$20,000\begin{array}{|c|c|c|c|c|c|}\hline\text { Activity } & \begin{array}{c}\text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array}{c}\text { Normal } \\\text { Time } \\\text { in weeks }\end{array} & \begin{array}{c}\text { Crash Time } \\\text { in weeks }\end{array} & \text { Normal Cost } & \text { Crash Cost } \\\hline \text { A } & \text { None } & 2 & 2 & \$ 15,000 & \$ 15,000 \\\hline \text { B } & \text { None } & 1 & 1 & \$ 12,000 & \$ 12,000 \\\hline \text { C } & \text { A, B } & 5 & 3 & \$ 18,000 & \$ 24,000 \\\hline \text { D } & \text { A, B } & 4 & 2 & \$ 12,000 & \$ 16,000 \\\hline \text { E } & \text { C, D } & 2 & 1 & \$ 22,000 & \$ 23,500 \\\hline \text { F } & \text { D } & 4 & 3 & \$ 32,000 & \$ 36,000 \\\hline \text { G } & \text { E, F } & 3 & 2 & \$ 19,000 & \$ 20,000 \\\hline\end{array} Draw the project network in the space below if you want. BLANK SPACES

-The total normal cost of the project is:

A) less than $50,000.
B) more than $50,000 but less than or equal to $75,000.
C) more than $75,000 but less than or equal to $100,000.
D) more than $125,000.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
61
In the Activity-On-Node (AON) network, the nodes define the precedence relationships, and the arcs define the work activities.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
62
Activity times are always estimated from historical data of similar work tasks to provide realism for a project.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
63
Preparation of annual reports does not require project management techniques.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
64
Strong leadership is an impediment to project management success because of the team-based nature of most projects.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
65
A high definition television manufacturer in Asia wants to develop a new smart television as fast as possible using Program Evaluation and Review Technique (PERT) and must complete the design and testing work first. The objective is to be the first to market the most innovative smart television on the planet and capture the first adopter market share. The manufacturer has determined the following activities, precedence relationships, and time estimates in days for the project:
 Immediate  Optimistic  Most Likely  Pessimistic  Activity  Predecessors totmtp\hlinea none 467 ba123ca555 d b7912eb248fcd6910\begin{array}{rcccr}& \text { Immediate } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\\text { Activity } & \text { Predecessors } & t_{o} & t_{m} & t_{p}\\\hlinea & \text { none } & 4 & 6 & 7 \\\mathrm{~b} & \mathrm{a} & 1 & 2 & 3 \\\mathrm{c} & \mathrm{a} & 5 & 5 & 5 \\\mathrm{~d} & \mathrm{~b} & 7 & 9 & 12 \\\mathrm{e} & \mathrm{b} & 2 & 4 & 8 \\\mathrm{f} & \mathrm{c} d & 6 & 9 & 10\end{array} Solutions are at the end of questions

-The probability that the project will take longer than 28 weeks to complete is _____.

A) less than or equal to 0.1
B) greater than 0.1 but less than or equal to 0.3
C) greater than 0.3 but less than or equal to 0.6
D) greater than 0.6 but less than or equal to 0.9
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
66
In most organizations, projects cut across organizational boundaries, making it difficult to implement projects exclusively within functional departments.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
67
Which one of the following statements about Project Evaluation and Review Technique (PERT) is TRUE?

A) The expected time is given and not computed using formulas.
B) The probability of completing the project on time is 0 when the project target completion time equals the expected time.
C) The normal probability distribution is not used in PERT methods.
D) The variance in project duration is given by the sum of the variances of the critical path activities.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
68
All activities on the critical path have a zero slack time.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
69
Immediate predecessors are activities that must be completed immediately before an activity may start.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
70
The early start time for an activity is computed by finding the largest early finish time of all immediate predecessors.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
71
To compute the critical path, all nodes in the network are assigned an earliest starting time of zero.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
72
Project managers need to be specialists, not generalists.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
73
A high definition television manufacturer in Asia wants to develop a new smart television as fast as possible using Program Evaluation and Review Technique (PERT) and must complete the design and testing work first. The objective is to be the first to market the most innovative smart television on the planet and capture the first adopter market share. The manufacturer has determined the following activities, precedence relationships, and time estimates in days for the project:
 Immediate  Optimistic  Most Likely  Pessimistic  Activity  Predecessors totmtp\hlinea none 467 ba123ca555 d b7912eb248fcd6910\begin{array}{rcccr}& \text { Immediate } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\\text { Activity } & \text { Predecessors } & t_{o} & t_{m} & t_{p}\\\hlinea & \text { none } & 4 & 6 & 7 \\\mathrm{~b} & \mathrm{a} & 1 & 2 & 3 \\\mathrm{c} & \mathrm{a} & 5 & 5 & 5 \\\mathrm{~d} & \mathrm{~b} & 7 & 9 & 12 \\\mathrm{e} & \mathrm{b} & 2 & 4 & 8 \\\mathrm{f} & \mathrm{c} d & 6 & 9 & 10\end{array} Solutions are at the end of questions

-What is the slack time for Activity B?

A) Zero days
B) Greater than zero but less than or equal to 1.0 days
C) Greater than 1.0 but less than or equal to 2.0 days
D) Greater than 2.0 days
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
74
A Gantt chart is a useful tool for allocating limited resources among project activities.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
75
Project management objectives revolve around time and budget.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
76
A high definition television manufacturer in Asia wants to develop a new smart television as fast as possible using Program Evaluation and Review Technique (PERT) and must complete the design and testing work first. The objective is to be the first to market the most innovative smart television on the planet and capture the first adopter market share. The manufacturer has determined the following activities, precedence relationships, and time estimates in days for the project:
 Immediate  Optimistic  Most Likely  Pessimistic  Activity  Predecessors totmtp\hlinea none 467 ba123ca555 d b7912eb248fcd6910\begin{array}{rcccr}& \text { Immediate } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\\text { Activity } & \text { Predecessors } & t_{o} & t_{m} & t_{p}\\\hlinea & \text { none } & 4 & 6 & 7 \\\mathrm{~b} & \mathrm{a} & 1 & 2 & 3 \\\mathrm{c} & \mathrm{a} & 5 & 5 & 5 \\\mathrm{~d} & \mathrm{~b} & 7 & 9 & 12 \\\mathrm{e} & \mathrm{b} & 2 & 4 & 8 \\\mathrm{f} & \mathrm{c} d & 6 & 9 & 10\end{array} Solutions are at the end of questions

-The standard deviation (not variance) of the critical path in days is _____.

A) less than or equal to 1.0 days
B) greater than 1.0 but less than or equal to 2.0 days
C) greater than 2.0 but less than or equal to 3.0 days
D) greater than 3.0 days
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
77
A slack of 2 means the project is ahead of schedule by two time periods.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
78
A statement of work would be developed in the "organize" step of the project life cycle.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
79
A high definition television manufacturer in Asia wants to develop a new smart television as fast as possible using Program Evaluation and Review Technique (PERT) and must complete the design and testing work first. The objective is to be the first to market the most innovative smart television on the planet and capture the first adopter market share. The manufacturer has determined the following activities, precedence relationships, and time estimates in days for the project:
 Immediate  Optimistic  Most Likely  Pessimistic  Activity  Predecessors totmtp\hlinea none 467 ba123ca555 d b7912eb248fcd6910\begin{array}{rcccr}& \text { Immediate } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\\text { Activity } & \text { Predecessors } & t_{o} & t_{m} & t_{p}\\\hlinea & \text { none } & 4 & 6 & 7 \\\mathrm{~b} & \mathrm{a} & 1 & 2 & 3 \\\mathrm{c} & \mathrm{a} & 5 & 5 & 5 \\\mathrm{~d} & \mathrm{~b} & 7 & 9 & 12 \\\mathrm{e} & \mathrm{b} & 2 & 4 & 8 \\\mathrm{f} & \mathrm{c} d & 6 & 9 & 10\end{array} Solutions are at the end of questions

-The expected duration of the critical path in days is _____.

A) less than or equal to 20 days
B) greater than 20 but less than or equal to 25 days
C) greater than 25 but less than or equal to 30 days
D) greater than 30 days
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
80
The critical path is the sequence of activities that takes the longest time.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.
فتح الحزمة
k this deck
locked card icon
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 108 في هذه المجموعة.