Deck 15: Scheduling

ملء الشاشة (f)
exit full mode
سؤال
A well designed high-volume system will minimize _________ inventory and reduce _____________for the product or service.

A)work-in-process, throughput time
B)raw material, storage capacity
C)finished, throughput time
D)work-in-process, storage capacity
E)finished, transportation cost
استخدم زر المسافة أو
up arrow
down arrow
لقلب البطاقة.
سؤال
Which of the following scheduling rules is a global priority rule?

A)first come, first served
B)last come, first served
C)earliest due date
D)shortest processing time
E)slack per remaining operations
سؤال
Which of the following techniques loads jobs without regard to the capacity available to do the work?

A)finite loading
B)infinite loading
C)forward scheduling
D)backward scheduling
E)input/output control
سؤال
Which of the following scheduling techniques determines the earliest possible completion time for a job?

A)finite loading
B)infinite loading
C)forward scheduling
D)backward scheduling
E)input/output control
سؤال
Scheduling in the high-volume environment is typically done through what?

A)priority rules
B)line design and balancing
C)Thompson's rule
D)Simpson's rule
E)Johnson's rule
سؤال
If the schedule shows a 5 day slack between the end of Task A and start of Task B, this means:

A)you must start Task B as soon as Task A ends.
B)Task B start is late.
C)Task A is taking longer to complete.
D)Task A and Task B should be performed concurrently.
E)Task B start can be delayed up to 5 days after Task A's scheduled completion.
سؤال
Slack can be calculated if _______________________.

A)infinite loading and finite loading are used together
B)infinite loading and forward scheduling are used together
C)finite loading and backward scheduling are used together
D)finite loading and forward scheduling are used together
E)forward scheduling and backward scheduling are used together
سؤال
Which of the following scheduling techniques tends to break down over the long term?

A)input/output control
B)infinite loading
C)forward scheduling
D)backward scheduling
E)finite loading
سؤال
Which of the following scheduling techniques can be used to identify resource bottlenecks?

A)finite loading
B)infinite loading
C)forward scheduling
D)backward scheduling
E)input/output control
سؤال
Flow operations can be ________ or ________ operations.

A)intermittent, continuous
B)intermittent, repetitive
C)repetitive, single shot
D)repetitive, continuous
E)single shot, continuous
سؤال
Which of the following techniques determines when the job must begin in order to be completed by the due date?

A)infinite loading
B)finite loading
C)forward scheduling
D)backward scheduling
E)input/output control
سؤال
A progress chart shows the relationship between:

A)a Gantt chart and PERT chart
B)vacation schedule and work schedule
C)forecast and historical performance
D)planned and actual performance
E)planned and actual efficiency
سؤال
Which of the following techniques is used to monitor work flow at individual work centers?

A)infinite loading
B)finite loading
C)forward scheduling
D)backward scheduling
E)input/output control
سؤال
Slim-Quick Inc. produces a variety of nutritional diet products. Management wants to evaluate the performance of Work Center 10, the bottleneck in the packaging line. They are particularly worried about the backlogging problem in the work center. The following input/output report is given.
<strong>Slim-Quick Inc. produces a variety of nutritional diet products. Management wants to evaluate the performance of Work Center 10, the bottleneck in the packaging line. They are particularly worried about the backlogging problem in the work center. The following input/output report is given.     The initial backlog was 100 hours. Based on the above information, calculate the backlog hours of Work Center 10 at the end of period 3.</strong> A)100 B)110 C)140 D)150 E)200 <div style=padding-top: 35px>
<strong>Slim-Quick Inc. produces a variety of nutritional diet products. Management wants to evaluate the performance of Work Center 10, the bottleneck in the packaging line. They are particularly worried about the backlogging problem in the work center. The following input/output report is given.     The initial backlog was 100 hours. Based on the above information, calculate the backlog hours of Work Center 10 at the end of period 3.</strong> A)100 B)110 C)140 D)150 E)200 <div style=padding-top: 35px>
The initial backlog was 100 hours. Based on the above information, calculate the backlog hours of Work Center 10 at the end of period 3.

A)100
B)110
C)140
D)150
E)200
سؤال
Which of the following techniques loads jobs up to a predetermined capacity level?

A)finite loading
B)infinite loading
C)forward scheduling
D)backward scheduling
E)input/output control
سؤال
Quick-Slim Inc. produces a variety of nutritional diet products. Management wants to evaluate the performance of Work Center 10, the bottleneck in the packaging line. The following input report is given.
<strong>Quick-Slim Inc. produces a variety of nutritional diet products. Management wants to evaluate the performance of Work Center 10, the bottleneck in the packaging line. The following input report is given.   Calculate the cumulative deviation of the input at the end of period 3.</strong> A)-20 B)-30 C)10 D)20 E)30 <div style=padding-top: 35px>
Calculate the cumulative deviation of the input at the end of period 3.

A)-20
B)-30
C)10
D)20
E)30
سؤال
Which of the following is not a feature of job-shop operations?

A)a process layout
B)highly skilled employees
C)special-purpose equipment and tooling
D)highly customized products
E)low volume production
سؤال
Which of the following is not a feature of flow operations?

A)a process layout
B)fixed routings
C)special-purpose equipment and tooling
D)high volume production
E)high levels of labor and equipment utilization
سؤال
The two different approaches to load work centers in job-shop scheduling are __________________.

A)load chart and process chart
B)finite loading and infinite loading
C)input control and output control
D)fixed routings and line balancing
E)makespan and linear programming
سؤال
Which of the following is most likely the reason you may have to wait at the doctor's office?

A)infinite loading
B)finite loading
C)forward scheduling
D)backward scheduling
E)none of these answer choices are correct
سؤال
Which of the following is a measure of whether the job is done ahead of, on, or behind schedule?

A)average number of jobs in system
B)mean flow time
C)makespan
D)job tardiness
E)job lateness
سؤال
A measure of response time is:

A)makespan
B)job flow time
C)due date
D)job lateness
E)job schedule time
سؤال
A Dallas firm manufactures dishwashing liquid. The manager wants to evaluate the performance of station 3, the bottleneck in the filling operation. The following output report is given.
<strong>A Dallas firm manufactures dishwashing liquid. The manager wants to evaluate the performance of station 3, the bottleneck in the filling operation. The following output report is given.   Calculate the cumulative deviation of the output at the end of period 3.</strong> A)-20 B)-40 C)10 D)20 E)40 <div style=padding-top: 35px>
Calculate the cumulative deviation of the output at the end of period 3.

A)-20
B)-40
C)10
D)20
E)40
سؤال
Sweet-Dreams Inc. manufactures custom pillows. Five jobs are waiting to be processed. Job A has a flow time of 8 days, job B has a flow time of 10 days, job C has a flow time of 15 days, job D has a flow time of 20 days, and job E has a flow time of 27 days. What is the mean flow time?

A)8 days
B)10 days
C)7 days
D)0 days
E)16 days
سؤال
The following jobs must be processed in the Super Clean motor shop. Assume that the company operates seven days per week. Using FCFS as the priority rule, calculate average job tardiness. <strong>The following jobs must be processed in the Super Clean motor shop. Assume that the company operates seven days per week. Using FCFS as the priority rule, calculate average job tardiness.  </strong> A)0 B)6 C))5 D)-2.833 E)-8 <div style=padding-top: 35px>

A)0
B)6
C))5
D)-2.833
E)-8
سؤال
Heavy Eyes Inc. manufactures custom pillows. Five jobs are waiting to be processed using the SPT priority rule. Their processing times are shown in the following table. What is the mean flow time? <strong>Heavy Eyes Inc. manufactures custom pillows. Five jobs are waiting to be processed using the SPT priority rule. Their processing times are shown in the following table. What is the mean flow time?  </strong> A)57 days B)11.4 days C)17 days D)5)4 days E)27 days <div style=padding-top: 35px>

A)57 days
B)11.4 days
C)17 days
D)5)4 days
E)27 days
سؤال
What does average number of jobs in the system measure?

A)WIP inventory
B)due-date performance
C)makespan
D)job tardiness
E)job lateness
سؤال
A greater number of jobs in the system implies what?

A)a higher work-in-process inventory level and a longer response time
B)a lower work-in-process inventory level and a longer response time
C)a higher work-in-process inventory level and a shorter response time
D)a lower work-in-process inventory level and a shorter response time
E)more jobs will certainly be tardy.
سؤال
If your company is concerned with customer response time you will measure scheduling effectiveness in terms of:

A)job reject rates
B)job profit ratio
C)response time
D)input time
E)makespan
سؤال
What is Period 3's standard hour deviation for Frank's manufacturing firm, based on the following input/output information?
What is Period 3's standard hour deviation for Frank's manufacturing firm, based on the following input/output information?   a)4, -5 b)-3, 2 c)3, -2 d)2, -2 e)-14, 2 Ans d<div style=padding-top: 35px>
a)4, -5
b)-3, 2
c)3, -2
d)2, -2
e)-14, 2
Ans d
سؤال
Using the S/RO rule, which of the following jobs will be scheduled first?

A)the first job that arrives at a work center
B)the job with the least slack per remaining operations
C)the job with the highest slack per remaining operations
D)the job with the smallest ratio of time remaining until due date to process time remaining
E)the job with the largest ratio of time remaining until due date to process time remaining
سؤال
Operation sequencing creates a work center plan based on available _______ and ______.

A)capacity, priorities
B)demand, priorities
C)capacity, demand
D)capacity, rules
E)staff, management
سؤال
What does job flow time measure?

A)the time a job spends in the shop
B)due-date performance
C)the amount of time it takes to finish a batch of jobs
D)job tardiness
E)job lateness
سؤال
Green Inc. manufactures a variety of wooden desks. Five jobs are waiting to be processed using the LPT priority rule. Their processing times are shown in the following table. What is the makespan? <strong>Green Inc. manufactures a variety of wooden desks. Five jobs are waiting to be processed using the LPT priority rule. Their processing times are shown in the following table. What is the makespan?  </strong> A)66 B)13.2 C)27 D)5)4 E)2)4 <div style=padding-top: 35px>

A)66
B)13.2
C)27
D)5)4
E)2)4
سؤال
What does makespan measure?

A)WIP inventory
B)due-date performance
C)the amount of time it takes to finish a batch of jobs
D)job tardiness
E)job lateness
سؤال
Job A is due on day 15, and it is finished on day 12. What is its lateness?

A)-3
B)0
C)3
D)both -3 and 3
E)none of these answer choices are correct
سؤال
Which of the following is not an assumption of priority rules?

A)There is no variability in the setup time.
B)There is no variability in the run time of the job.
C)Multiple jobs are waiting to be processed.
D)Only a single job is waiting to be processed.
E) None of these answer choices are correct.
سؤال
If using CR as the priority rule, which of the following jobs will be scheduled first?

A)the first job arrives at a work center
B)the job with the least slack per remaining operations
C)the job with the highest slack per remaining operations
D)the job with the smallest ratio of time remaining until due date to process time remaining
E)the job with the largest ratio of time remaining until due date to process time remaining
سؤال
Sweet-Dreams Inc. manufactures custom pillows. Five jobs are waiting to be processed using the SPT priority rule. Their processing times are shown in the following table. What is the average number of jobs in the system? <strong>Sweet-Dreams Inc. manufactures custom pillows. Five jobs are waiting to be processed using the SPT priority rule. Their processing times are shown in the following table. What is the average number of jobs in the system?  </strong> A)66 B)13.2 C)27 D)5)4 E)3)38 <div style=padding-top: 35px>

A)66
B)13.2
C)27
D)5)4
E)3)38
سؤال
Which of the following is a measure of how long after the due date the job is completed?

A)job belatedness
B)mean flow time
C)makespan
D)job overdueness
E)job tardiness
سؤال
Consider a production line with five stations. The first station can process a unit in 8 minutes. The second station has two identical machines, each of which can process a unit in 18 minutes (each unit only needs to be processed on one of the two machines). The third station can process a unit in 4 minutes. The fourth station has two different machines, one can process a unit in 5 minutes, and the other one can process a unit in 9 minutes (each unit needs to be processed on both machines). The fifth station can process a unit in 10 minutes. Which station is the bottleneck station?

A)Station 1
B)Station 2
C)Station 3
D)Station 4
E)Station 5
سؤال
What does "negative lateness" mean?

A)The job is finished after its due date.
B)The job is finished on its due date.
C)The job is finished before its due date.
D)The job is not finished.
E)The job has not started.
سؤال
Which of the following scheduling rules is often considered the fairest rule?

A)first come, first served
B)last come, first served
C)earliest due date
D)shortest processing time
E)longest processing time
سؤال
Using the following data, calculate the average job lateness. <strong>Using the following data, calculate the average job lateness.  </strong> A)-2 days B)3 days C)13 days D)-8 days E)1)5 days <div style=padding-top: 35px>

A)-2 days
B)3 days
C)13 days
D)-8 days
E)1)5 days
سؤال
Which of the following scheduling rules minimizes mean job flow time?

A)first come, first served
B)last come, first served
C)earliest due date
D)shortest processing time
E)longest processing time
سؤال
Which of the following statements is not true?

A)An hour lost at a bottleneck is an hour lost forever.
B)An hour lost at a non-bottleneck is just a mirage.
C)Bottlenecks determine throughput and system inventory.
D)The transfer batch does not have to equal the process batch.
E)Lead times are predetermined.
سؤال
Job A is due on day 15, and it is finished on day 12. What is its tardiness?

A)-3
B)0
C)3
D)both -3 and 3
E)none of these answer choices are correct
سؤال
Seven jobs must be scheduled. Each of the jobs must be processed on two machines (A and B)in the same order. The processing times are listed below. According to Johnson's rule, in what order should the jobs be processed? <strong>Seven jobs must be scheduled. Each of the jobs must be processed on two machines (A and B)in the same order. The processing times are listed below. According to Johnson's rule, in what order should the jobs be processed?  </strong> A)A-E-C-G-D-B-F B)A-C-E-G-D-B-F C)F-B-D-G-C-E-A D)F-D-B-G-E-C-A E)G-D-B-F-A-E-C <div style=padding-top: 35px>

A)A-E-C-G-D-B-F
B)A-C-E-G-D-B-F
C)F-B-D-G-C-E-A
D)F-D-B-G-E-C-A
E)G-D-B-F-A-E-C
سؤال
Consider a production line with five stations. Stations one through five can process a unit in 10, 15, 20, 5, and 12 minutes, respectively. What is the maximum throughput per hour?

A)6 units
B)4 units
C)3 units
D)12 units
E)5 units
سؤال
Using the following data, calculate the average job tardiness. <strong>Using the following data, calculate the average job tardiness.  </strong> A)6 days B)1)5 days C)-2 days D)-8 days E)3 days <div style=padding-top: 35px>

A)6 days
B)1)5 days
C)-2 days
D)-8 days
E)3 days
سؤال
Which of the following scheduling rules minimizes the average number of jobs in the system?

A)first come, first served
B)last come, first served
C)earliest due date
D)shortest processing time
E)longest processing time
سؤال
Which of the following sequencing rules is used for minimizing makespan in a two-stage, unidirectional process?

A)FCFS
B)S/RO
C)SPT
D)CR
E)Johnson's rule
سؤال
What is a transfer batch?

A)the quantity of finished goods that can be sold
B)the quantity of items moved at the same time from one resource to the next
C)the quantity of work-in-process inventory
D)the quantity produced at a resource before the resource is switched over to produce another product
E)the quantity of items needed to attain a full truckload (TL)shipping rate
سؤال
The process batch should:

A)match the transfer batch.
B)exceed the transfer batch.
C)be smaller than the transfer batch.
D)be fixed.
E)be variable.
سؤال
What is throughput?

A)the quantity of finished goods that can be sold
B)the quantity of items moved at the same time from one resource to the next
C)the quantity of work-in-process inventory
D)the quantity produced at a resource before the resource is switched over to produce another product
E)the average flow time of the system
سؤال
Which of the following statements is not a valid scheduling principle?

A)Balance the process rather than the flow.
B)Non-bottleneck usage is determined by some other constraint in the system.
C)Usage and activation of a resource are the same.
D)The process batch should be variable.
E)An hour lost at a bottleneck resource is an hour lost forever.
سؤال
Which of the following is mostly like to be an internal resource constraint?

A)increasing market demand
B)raw material shipping problems
C)decreasing market demand
D)no overtime
E)a regular bottleneck in the product process
سؤال
Five jobs must be scheduled. Each of the jobs must be processed on two machines (A and B)in the same order. The processing times are listed below. According to Johnson's rule, in what order should the jobs be processed? <strong>Five jobs must be scheduled. Each of the jobs must be processed on two machines (A and B)in the same order. The processing times are listed below. According to Johnson's rule, in what order should the jobs be processed?  </strong> A)C-B-D-A-E B)C-D-A-E-B C)B-E-A-D-C D)C-A-E-D-B E)C-D-E-B-A <div style=padding-top: 35px>

A)C-B-D-A-E
B)C-D-A-E-B
C)B-E-A-D-C
D)C-A-E-D-B
E)C-D-E-B-A
سؤال
Which of the following is the least effective tactic for managing a bottleneck station?

A)Assign extra workers to the bottleneck station if necessary in order to keep it running.
B)Increase the production rate at the bottleneck station.
C)Inspect items just as soon as they come out of the bottleneck station.
D)Subcontract part of the workload at that station to other companies.
E)Assign your best people to that station to improve efficiency.
سؤال
What is a process batch?

A)the quantity of finished goods that can be sold
B)the quantity of items moved at the same time from one resource to the next
C)the quantity of work-in-process inventory
D)the quantity produced at a resource before the resource is switched over to produce another product
E)the set of machines used to make products
سؤال
A local priority rule sets priority based only on the jobs waiting at that individual work center.
سؤال
In a service organization, a doctor's office is a good example of finite loading.
سؤال
Optimized production technology (OPT)was introduced by Eli ____________________.

A)Goldratt
B)Manning
C)Jefferson
D)Rosenblatt
E)Strasburg
سؤال
The backlog at a work center increases when the work center receives more work than it finishes.
سؤال
Jim-O's fast focus restaurant is opening up a new branch. Based on demand forecast the following service personnel levels are anticipated. What days will employee #1 have off? <strong>Jim-O's fast focus restaurant is opening up a new branch. Based on demand forecast the following service personnel levels are anticipated. What days will employee #1 have off?  </strong> A)Mon - Tue B)Tue - Wed C)Wed - Thur D)Thur - Fri E)Fri - Sat <div style=padding-top: 35px>

A)Mon - Tue
B)Tue - Wed
C)Wed - Thur
D)Thur - Fri
E)Fri - Sat
سؤال
Priority rules are more useful in sequencing jobs in high-volume systems than in low-volume systems.
سؤال
Jim-O's fast focus restaurant is opening up a new branch. Based on demand forecast the following service personnel levels are anticipated. What is the number of employees needed for Thursday-Friday pair? <strong>Jim-O's fast focus restaurant is opening up a new branch. Based on demand forecast the following service personnel levels are anticipated. What is the number of employees needed for Thursday-Friday pair?  </strong> A)7 B)9 C)10 D)11 E)12 <div style=padding-top: 35px>

A)7
B)9
C)10
D)11
E)12
سؤال
If customer service is important to the company, average job lateness is probably a more relevant measurement than average job tardiness.
سؤال
Flow operations are often related to high volume production.
سؤال
Forward scheduling sometimes causes inventory buildup if items are not delivered by the due date.
سؤال
Only Roses Flower Shop currently operates 7 days per week. The staffing needs for each day are shown in the following table. Each of the employees must have two consecutive days off in a week. (Since Monday is used as the first day of the pay week, an employee cannot be off on both Sunday and Monday.) What is the minimum number of employees that needs to be hired? <strong>Only Roses Flower Shop currently operates 7 days per week. The staffing needs for each day are shown in the following table. Each of the employees must have two consecutive days off in a week. (Since Monday is used as the first day of the pay week, an employee cannot be off on both Sunday and Monday.) What is the minimum number of employees that needs to be hired?  </strong> A)5 B)6 C)7 D)8 E)9 <div style=padding-top: 35px>

A)5
B)6
C)7
D)8
E)9
سؤال
A Gantt chart is usually used for a company with low flexibility in both product variation and product volume.
سؤال
Which of the following is mostly like to be a policy constraint?

A)strike at the supplier's plant
B)raw material shipping problems
C)decreasing market demand
D)no overtime
E)a regular bottleneck in the product process
سؤال
If using critical ratio (CR)as the scheduling rule, the job with the smallest ratio of time remaining until due date to the processing time remaining has the lowest priority.
سؤال
Makespan has a link to customer due dates.
سؤال
When were Gantt charts developed?

A)early 1800s
B)early 1900s
C)early 1920s
D)early 1940s
E)early 1960s
سؤال
Makespan is a measure of WIP.
سؤال
Backward scheduling determines the earliest possible completion time for a job.
سؤال
A Gantt chart is a basic scheduling tool for low-volume systems.
سؤال
If using slack per remaining operations (S/RO)as the scheduling rule, the job with the least slack per remaining operations has the highest priority.
فتح الحزمة
قم بالتسجيل لفتح البطاقات في هذه المجموعة!
Unlock Deck
Unlock Deck
1/127
auto play flashcards
العب
simple tutorial
ملء الشاشة (f)
exit full mode
Deck 15: Scheduling
1
A well designed high-volume system will minimize _________ inventory and reduce _____________for the product or service.

A)work-in-process, throughput time
B)raw material, storage capacity
C)finished, throughput time
D)work-in-process, storage capacity
E)finished, transportation cost
A
2
Which of the following scheduling rules is a global priority rule?

A)first come, first served
B)last come, first served
C)earliest due date
D)shortest processing time
E)slack per remaining operations
E
3
Which of the following techniques loads jobs without regard to the capacity available to do the work?

A)finite loading
B)infinite loading
C)forward scheduling
D)backward scheduling
E)input/output control
B
4
Which of the following scheduling techniques determines the earliest possible completion time for a job?

A)finite loading
B)infinite loading
C)forward scheduling
D)backward scheduling
E)input/output control
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
5
Scheduling in the high-volume environment is typically done through what?

A)priority rules
B)line design and balancing
C)Thompson's rule
D)Simpson's rule
E)Johnson's rule
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
6
If the schedule shows a 5 day slack between the end of Task A and start of Task B, this means:

A)you must start Task B as soon as Task A ends.
B)Task B start is late.
C)Task A is taking longer to complete.
D)Task A and Task B should be performed concurrently.
E)Task B start can be delayed up to 5 days after Task A's scheduled completion.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
7
Slack can be calculated if _______________________.

A)infinite loading and finite loading are used together
B)infinite loading and forward scheduling are used together
C)finite loading and backward scheduling are used together
D)finite loading and forward scheduling are used together
E)forward scheduling and backward scheduling are used together
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
8
Which of the following scheduling techniques tends to break down over the long term?

A)input/output control
B)infinite loading
C)forward scheduling
D)backward scheduling
E)finite loading
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
9
Which of the following scheduling techniques can be used to identify resource bottlenecks?

A)finite loading
B)infinite loading
C)forward scheduling
D)backward scheduling
E)input/output control
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
10
Flow operations can be ________ or ________ operations.

A)intermittent, continuous
B)intermittent, repetitive
C)repetitive, single shot
D)repetitive, continuous
E)single shot, continuous
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
11
Which of the following techniques determines when the job must begin in order to be completed by the due date?

A)infinite loading
B)finite loading
C)forward scheduling
D)backward scheduling
E)input/output control
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
12
A progress chart shows the relationship between:

A)a Gantt chart and PERT chart
B)vacation schedule and work schedule
C)forecast and historical performance
D)planned and actual performance
E)planned and actual efficiency
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
13
Which of the following techniques is used to monitor work flow at individual work centers?

A)infinite loading
B)finite loading
C)forward scheduling
D)backward scheduling
E)input/output control
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
14
Slim-Quick Inc. produces a variety of nutritional diet products. Management wants to evaluate the performance of Work Center 10, the bottleneck in the packaging line. They are particularly worried about the backlogging problem in the work center. The following input/output report is given.
<strong>Slim-Quick Inc. produces a variety of nutritional diet products. Management wants to evaluate the performance of Work Center 10, the bottleneck in the packaging line. They are particularly worried about the backlogging problem in the work center. The following input/output report is given.     The initial backlog was 100 hours. Based on the above information, calculate the backlog hours of Work Center 10 at the end of period 3.</strong> A)100 B)110 C)140 D)150 E)200
<strong>Slim-Quick Inc. produces a variety of nutritional diet products. Management wants to evaluate the performance of Work Center 10, the bottleneck in the packaging line. They are particularly worried about the backlogging problem in the work center. The following input/output report is given.     The initial backlog was 100 hours. Based on the above information, calculate the backlog hours of Work Center 10 at the end of period 3.</strong> A)100 B)110 C)140 D)150 E)200
The initial backlog was 100 hours. Based on the above information, calculate the backlog hours of Work Center 10 at the end of period 3.

A)100
B)110
C)140
D)150
E)200
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
15
Which of the following techniques loads jobs up to a predetermined capacity level?

A)finite loading
B)infinite loading
C)forward scheduling
D)backward scheduling
E)input/output control
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
16
Quick-Slim Inc. produces a variety of nutritional diet products. Management wants to evaluate the performance of Work Center 10, the bottleneck in the packaging line. The following input report is given.
<strong>Quick-Slim Inc. produces a variety of nutritional diet products. Management wants to evaluate the performance of Work Center 10, the bottleneck in the packaging line. The following input report is given.   Calculate the cumulative deviation of the input at the end of period 3.</strong> A)-20 B)-30 C)10 D)20 E)30
Calculate the cumulative deviation of the input at the end of period 3.

A)-20
B)-30
C)10
D)20
E)30
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
17
Which of the following is not a feature of job-shop operations?

A)a process layout
B)highly skilled employees
C)special-purpose equipment and tooling
D)highly customized products
E)low volume production
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
18
Which of the following is not a feature of flow operations?

A)a process layout
B)fixed routings
C)special-purpose equipment and tooling
D)high volume production
E)high levels of labor and equipment utilization
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
19
The two different approaches to load work centers in job-shop scheduling are __________________.

A)load chart and process chart
B)finite loading and infinite loading
C)input control and output control
D)fixed routings and line balancing
E)makespan and linear programming
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
20
Which of the following is most likely the reason you may have to wait at the doctor's office?

A)infinite loading
B)finite loading
C)forward scheduling
D)backward scheduling
E)none of these answer choices are correct
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
21
Which of the following is a measure of whether the job is done ahead of, on, or behind schedule?

A)average number of jobs in system
B)mean flow time
C)makespan
D)job tardiness
E)job lateness
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
22
A measure of response time is:

A)makespan
B)job flow time
C)due date
D)job lateness
E)job schedule time
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
23
A Dallas firm manufactures dishwashing liquid. The manager wants to evaluate the performance of station 3, the bottleneck in the filling operation. The following output report is given.
<strong>A Dallas firm manufactures dishwashing liquid. The manager wants to evaluate the performance of station 3, the bottleneck in the filling operation. The following output report is given.   Calculate the cumulative deviation of the output at the end of period 3.</strong> A)-20 B)-40 C)10 D)20 E)40
Calculate the cumulative deviation of the output at the end of period 3.

A)-20
B)-40
C)10
D)20
E)40
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
24
Sweet-Dreams Inc. manufactures custom pillows. Five jobs are waiting to be processed. Job A has a flow time of 8 days, job B has a flow time of 10 days, job C has a flow time of 15 days, job D has a flow time of 20 days, and job E has a flow time of 27 days. What is the mean flow time?

A)8 days
B)10 days
C)7 days
D)0 days
E)16 days
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
25
The following jobs must be processed in the Super Clean motor shop. Assume that the company operates seven days per week. Using FCFS as the priority rule, calculate average job tardiness. <strong>The following jobs must be processed in the Super Clean motor shop. Assume that the company operates seven days per week. Using FCFS as the priority rule, calculate average job tardiness.  </strong> A)0 B)6 C))5 D)-2.833 E)-8

A)0
B)6
C))5
D)-2.833
E)-8
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
26
Heavy Eyes Inc. manufactures custom pillows. Five jobs are waiting to be processed using the SPT priority rule. Their processing times are shown in the following table. What is the mean flow time? <strong>Heavy Eyes Inc. manufactures custom pillows. Five jobs are waiting to be processed using the SPT priority rule. Their processing times are shown in the following table. What is the mean flow time?  </strong> A)57 days B)11.4 days C)17 days D)5)4 days E)27 days

A)57 days
B)11.4 days
C)17 days
D)5)4 days
E)27 days
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
27
What does average number of jobs in the system measure?

A)WIP inventory
B)due-date performance
C)makespan
D)job tardiness
E)job lateness
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
28
A greater number of jobs in the system implies what?

A)a higher work-in-process inventory level and a longer response time
B)a lower work-in-process inventory level and a longer response time
C)a higher work-in-process inventory level and a shorter response time
D)a lower work-in-process inventory level and a shorter response time
E)more jobs will certainly be tardy.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
29
If your company is concerned with customer response time you will measure scheduling effectiveness in terms of:

A)job reject rates
B)job profit ratio
C)response time
D)input time
E)makespan
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
30
What is Period 3's standard hour deviation for Frank's manufacturing firm, based on the following input/output information?
What is Period 3's standard hour deviation for Frank's manufacturing firm, based on the following input/output information?   a)4, -5 b)-3, 2 c)3, -2 d)2, -2 e)-14, 2 Ans d
a)4, -5
b)-3, 2
c)3, -2
d)2, -2
e)-14, 2
Ans d
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
31
Using the S/RO rule, which of the following jobs will be scheduled first?

A)the first job that arrives at a work center
B)the job with the least slack per remaining operations
C)the job with the highest slack per remaining operations
D)the job with the smallest ratio of time remaining until due date to process time remaining
E)the job with the largest ratio of time remaining until due date to process time remaining
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
32
Operation sequencing creates a work center plan based on available _______ and ______.

A)capacity, priorities
B)demand, priorities
C)capacity, demand
D)capacity, rules
E)staff, management
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
33
What does job flow time measure?

A)the time a job spends in the shop
B)due-date performance
C)the amount of time it takes to finish a batch of jobs
D)job tardiness
E)job lateness
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
34
Green Inc. manufactures a variety of wooden desks. Five jobs are waiting to be processed using the LPT priority rule. Their processing times are shown in the following table. What is the makespan? <strong>Green Inc. manufactures a variety of wooden desks. Five jobs are waiting to be processed using the LPT priority rule. Their processing times are shown in the following table. What is the makespan?  </strong> A)66 B)13.2 C)27 D)5)4 E)2)4

A)66
B)13.2
C)27
D)5)4
E)2)4
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
35
What does makespan measure?

A)WIP inventory
B)due-date performance
C)the amount of time it takes to finish a batch of jobs
D)job tardiness
E)job lateness
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
36
Job A is due on day 15, and it is finished on day 12. What is its lateness?

A)-3
B)0
C)3
D)both -3 and 3
E)none of these answer choices are correct
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
37
Which of the following is not an assumption of priority rules?

A)There is no variability in the setup time.
B)There is no variability in the run time of the job.
C)Multiple jobs are waiting to be processed.
D)Only a single job is waiting to be processed.
E) None of these answer choices are correct.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
38
If using CR as the priority rule, which of the following jobs will be scheduled first?

A)the first job arrives at a work center
B)the job with the least slack per remaining operations
C)the job with the highest slack per remaining operations
D)the job with the smallest ratio of time remaining until due date to process time remaining
E)the job with the largest ratio of time remaining until due date to process time remaining
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
39
Sweet-Dreams Inc. manufactures custom pillows. Five jobs are waiting to be processed using the SPT priority rule. Their processing times are shown in the following table. What is the average number of jobs in the system? <strong>Sweet-Dreams Inc. manufactures custom pillows. Five jobs are waiting to be processed using the SPT priority rule. Their processing times are shown in the following table. What is the average number of jobs in the system?  </strong> A)66 B)13.2 C)27 D)5)4 E)3)38

A)66
B)13.2
C)27
D)5)4
E)3)38
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
40
Which of the following is a measure of how long after the due date the job is completed?

A)job belatedness
B)mean flow time
C)makespan
D)job overdueness
E)job tardiness
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
41
Consider a production line with five stations. The first station can process a unit in 8 minutes. The second station has two identical machines, each of which can process a unit in 18 minutes (each unit only needs to be processed on one of the two machines). The third station can process a unit in 4 minutes. The fourth station has two different machines, one can process a unit in 5 minutes, and the other one can process a unit in 9 minutes (each unit needs to be processed on both machines). The fifth station can process a unit in 10 minutes. Which station is the bottleneck station?

A)Station 1
B)Station 2
C)Station 3
D)Station 4
E)Station 5
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
42
What does "negative lateness" mean?

A)The job is finished after its due date.
B)The job is finished on its due date.
C)The job is finished before its due date.
D)The job is not finished.
E)The job has not started.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
43
Which of the following scheduling rules is often considered the fairest rule?

A)first come, first served
B)last come, first served
C)earliest due date
D)shortest processing time
E)longest processing time
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
44
Using the following data, calculate the average job lateness. <strong>Using the following data, calculate the average job lateness.  </strong> A)-2 days B)3 days C)13 days D)-8 days E)1)5 days

A)-2 days
B)3 days
C)13 days
D)-8 days
E)1)5 days
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
45
Which of the following scheduling rules minimizes mean job flow time?

A)first come, first served
B)last come, first served
C)earliest due date
D)shortest processing time
E)longest processing time
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
46
Which of the following statements is not true?

A)An hour lost at a bottleneck is an hour lost forever.
B)An hour lost at a non-bottleneck is just a mirage.
C)Bottlenecks determine throughput and system inventory.
D)The transfer batch does not have to equal the process batch.
E)Lead times are predetermined.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
47
Job A is due on day 15, and it is finished on day 12. What is its tardiness?

A)-3
B)0
C)3
D)both -3 and 3
E)none of these answer choices are correct
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
48
Seven jobs must be scheduled. Each of the jobs must be processed on two machines (A and B)in the same order. The processing times are listed below. According to Johnson's rule, in what order should the jobs be processed? <strong>Seven jobs must be scheduled. Each of the jobs must be processed on two machines (A and B)in the same order. The processing times are listed below. According to Johnson's rule, in what order should the jobs be processed?  </strong> A)A-E-C-G-D-B-F B)A-C-E-G-D-B-F C)F-B-D-G-C-E-A D)F-D-B-G-E-C-A E)G-D-B-F-A-E-C

A)A-E-C-G-D-B-F
B)A-C-E-G-D-B-F
C)F-B-D-G-C-E-A
D)F-D-B-G-E-C-A
E)G-D-B-F-A-E-C
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
49
Consider a production line with five stations. Stations one through five can process a unit in 10, 15, 20, 5, and 12 minutes, respectively. What is the maximum throughput per hour?

A)6 units
B)4 units
C)3 units
D)12 units
E)5 units
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
50
Using the following data, calculate the average job tardiness. <strong>Using the following data, calculate the average job tardiness.  </strong> A)6 days B)1)5 days C)-2 days D)-8 days E)3 days

A)6 days
B)1)5 days
C)-2 days
D)-8 days
E)3 days
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
51
Which of the following scheduling rules minimizes the average number of jobs in the system?

A)first come, first served
B)last come, first served
C)earliest due date
D)shortest processing time
E)longest processing time
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
52
Which of the following sequencing rules is used for minimizing makespan in a two-stage, unidirectional process?

A)FCFS
B)S/RO
C)SPT
D)CR
E)Johnson's rule
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
53
What is a transfer batch?

A)the quantity of finished goods that can be sold
B)the quantity of items moved at the same time from one resource to the next
C)the quantity of work-in-process inventory
D)the quantity produced at a resource before the resource is switched over to produce another product
E)the quantity of items needed to attain a full truckload (TL)shipping rate
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
54
The process batch should:

A)match the transfer batch.
B)exceed the transfer batch.
C)be smaller than the transfer batch.
D)be fixed.
E)be variable.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
55
What is throughput?

A)the quantity of finished goods that can be sold
B)the quantity of items moved at the same time from one resource to the next
C)the quantity of work-in-process inventory
D)the quantity produced at a resource before the resource is switched over to produce another product
E)the average flow time of the system
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
56
Which of the following statements is not a valid scheduling principle?

A)Balance the process rather than the flow.
B)Non-bottleneck usage is determined by some other constraint in the system.
C)Usage and activation of a resource are the same.
D)The process batch should be variable.
E)An hour lost at a bottleneck resource is an hour lost forever.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
57
Which of the following is mostly like to be an internal resource constraint?

A)increasing market demand
B)raw material shipping problems
C)decreasing market demand
D)no overtime
E)a regular bottleneck in the product process
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
58
Five jobs must be scheduled. Each of the jobs must be processed on two machines (A and B)in the same order. The processing times are listed below. According to Johnson's rule, in what order should the jobs be processed? <strong>Five jobs must be scheduled. Each of the jobs must be processed on two machines (A and B)in the same order. The processing times are listed below. According to Johnson's rule, in what order should the jobs be processed?  </strong> A)C-B-D-A-E B)C-D-A-E-B C)B-E-A-D-C D)C-A-E-D-B E)C-D-E-B-A

A)C-B-D-A-E
B)C-D-A-E-B
C)B-E-A-D-C
D)C-A-E-D-B
E)C-D-E-B-A
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
59
Which of the following is the least effective tactic for managing a bottleneck station?

A)Assign extra workers to the bottleneck station if necessary in order to keep it running.
B)Increase the production rate at the bottleneck station.
C)Inspect items just as soon as they come out of the bottleneck station.
D)Subcontract part of the workload at that station to other companies.
E)Assign your best people to that station to improve efficiency.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
60
What is a process batch?

A)the quantity of finished goods that can be sold
B)the quantity of items moved at the same time from one resource to the next
C)the quantity of work-in-process inventory
D)the quantity produced at a resource before the resource is switched over to produce another product
E)the set of machines used to make products
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
61
A local priority rule sets priority based only on the jobs waiting at that individual work center.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
62
In a service organization, a doctor's office is a good example of finite loading.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
63
Optimized production technology (OPT)was introduced by Eli ____________________.

A)Goldratt
B)Manning
C)Jefferson
D)Rosenblatt
E)Strasburg
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
64
The backlog at a work center increases when the work center receives more work than it finishes.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
65
Jim-O's fast focus restaurant is opening up a new branch. Based on demand forecast the following service personnel levels are anticipated. What days will employee #1 have off? <strong>Jim-O's fast focus restaurant is opening up a new branch. Based on demand forecast the following service personnel levels are anticipated. What days will employee #1 have off?  </strong> A)Mon - Tue B)Tue - Wed C)Wed - Thur D)Thur - Fri E)Fri - Sat

A)Mon - Tue
B)Tue - Wed
C)Wed - Thur
D)Thur - Fri
E)Fri - Sat
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
66
Priority rules are more useful in sequencing jobs in high-volume systems than in low-volume systems.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
67
Jim-O's fast focus restaurant is opening up a new branch. Based on demand forecast the following service personnel levels are anticipated. What is the number of employees needed for Thursday-Friday pair? <strong>Jim-O's fast focus restaurant is opening up a new branch. Based on demand forecast the following service personnel levels are anticipated. What is the number of employees needed for Thursday-Friday pair?  </strong> A)7 B)9 C)10 D)11 E)12

A)7
B)9
C)10
D)11
E)12
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
68
If customer service is important to the company, average job lateness is probably a more relevant measurement than average job tardiness.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
69
Flow operations are often related to high volume production.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
70
Forward scheduling sometimes causes inventory buildup if items are not delivered by the due date.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
71
Only Roses Flower Shop currently operates 7 days per week. The staffing needs for each day are shown in the following table. Each of the employees must have two consecutive days off in a week. (Since Monday is used as the first day of the pay week, an employee cannot be off on both Sunday and Monday.) What is the minimum number of employees that needs to be hired? <strong>Only Roses Flower Shop currently operates 7 days per week. The staffing needs for each day are shown in the following table. Each of the employees must have two consecutive days off in a week. (Since Monday is used as the first day of the pay week, an employee cannot be off on both Sunday and Monday.) What is the minimum number of employees that needs to be hired?  </strong> A)5 B)6 C)7 D)8 E)9

A)5
B)6
C)7
D)8
E)9
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
72
A Gantt chart is usually used for a company with low flexibility in both product variation and product volume.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
73
Which of the following is mostly like to be a policy constraint?

A)strike at the supplier's plant
B)raw material shipping problems
C)decreasing market demand
D)no overtime
E)a regular bottleneck in the product process
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
74
If using critical ratio (CR)as the scheduling rule, the job with the smallest ratio of time remaining until due date to the processing time remaining has the lowest priority.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
75
Makespan has a link to customer due dates.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
76
When were Gantt charts developed?

A)early 1800s
B)early 1900s
C)early 1920s
D)early 1940s
E)early 1960s
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
77
Makespan is a measure of WIP.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
78
Backward scheduling determines the earliest possible completion time for a job.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
79
A Gantt chart is a basic scheduling tool for low-volume systems.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
80
If using slack per remaining operations (S/RO)as the scheduling rule, the job with the least slack per remaining operations has the highest priority.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.
فتح الحزمة
k this deck
locked card icon
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 127 في هذه المجموعة.