Deck 9: Project Communication,tracking,and Reporting

ملء الشاشة (f)
exit full mode
سؤال
The Schedule Performance Index SPI)for our project is greater than one 1)and so we would anticipate that all other things being equal,our project will finish ahead of schedule.
استخدم زر المسافة أو
up arrow
down arrow
لقلب البطاقة.
سؤال
Planned value PV)is the planned or budgeted cost of work scheduled for an activity or component of the WBS.
سؤال
Given the advances that have been made in telecommunications and IT technology in general,there is little value or necessity today for Face-to-Face F2F)meetings.
سؤال
If a stakeholder has been judged to adversarial and having a vested interest in the failure of your project,it would probably be wise to keep him/her out of the communication loop.
سؤال
As a project manager,you would be pleased see a Cost Performance Index CPI less than one 1)for your project
سؤال
A good project metric should be understandable,quantifiable,cost effective,proven,and be effective.
سؤال
Generally,the more metrics one adopts,the greater the project control.
سؤال
The Estimate At Completion EAC)is a project metric that can be used to estimate the most likely total or final cost of the project based on the project's performance and any risks that should be considered.
سؤال
All of the project stakeholders should receive exactly the same information regarding the project's progress in order to eliminate any miscommunication.
سؤال
A project metric should be obtained from observable,quantifiable data that allows the team and other stakeholders to gauge the efficiency and effectiveness of the work being done.
سؤال
Earned value provides a performance measurement that tells us how much of the budget we really should have spent for the work completed so far.
سؤال
One attribute of a good project metric is that it should be subjective so that a stakeholder can understand the project manager's personal opinion or insight as to how the project is progressing.
سؤال
Budget At Completion BAC)is the total planned cost of a project.
سؤال
The Expected Time Complete ETC)provides an estimate for completing the scheduled work that remains.
سؤال
The project manager must have a clear picture of how the actual progress or work compares to the baseline plan in order to make well-informed decisions,take appropriate actions,or to make adjustments to the project plan.
سؤال
The purpose of a project review is to not only show evidence that the project work is being completed,but also that the work is being completed according to various standards or agreed upon requirements.
سؤال
The project communications plan may be informal depending on the needs of the project stakeholders and the size of the project.
سؤال
A cost variance CV)can be positive or negative,but never zero.
سؤال
The schedule variance SV)shows the difference between the current progress of the project and its original or planned value.
سؤال
Internet and Web-Based technologies have a significant role to play in communication and collaboration efforts of project teams.
سؤال
Cost Variance CV)= Earned Value - ___________.

A)Budget at Completion BAC)
B)Budgeted cost of remaining work BCRW)
C)Schedule Variance SV)
D)Actual Cost AC)
E)None of the above
سؤال
Earned Value tells us __________

A)how much we actually spent for work completed
B)how much we budgeted to spend at the beginning of the project
C)how much of the budget we have left to spend on the project
D)how much of the budget we really should have spent on the work completed so far
E)None of the above
سؤال
Cost Variance CV)is __________

A)how much we actually spent for work completed
B)how much we budgeted to spend at the beginning of the project
C)how much of the budget we have left to spend on the project
D)how much of the budget we really should have spent on the work completed so far
E)the difference between the estimated cost and how much we have actually spent
سؤال
Expected Time to Completion ETC)is __________

A)how much time it took to complete the work
B)how long we expected the task to take
C)how much time we have left to complete the project
D)how much time it should have taken to complete the task
E)how much longer it will take to complete the project
سؤال
A _________ is a formal or informal meeting that shows evidence of project work that has been completed and work and provides a forum for surfacing issues,problems,decision-making.

A)Budget report
B)Project review
C)Progress report
D)Forecast report
E)News report
سؤال
In Project Communications Management,getting the right information to the right stakeholders in the right format is _____.

A)identify stakeholders
B)plan communications
C)distribute information
D)manage stakeholder expectations
E)report performance
سؤال
If you hired a consulting firm to develop a system which is estimated to take four months to complete with the tasks evenly divided over the four months and you agree to pay for the project with equal monthly installments,those payments would be called:

A)Planned Value PV)
B)Budget At Completion BAC)
C)Actual Cost AC)
D)Earned Value EV)
E)None of the above
سؤال
In Project Communications Management,_____focuses on the collection and dissemination of project ionformation to the various project stakeholders.

A)identify stakeholders
B)plan communications
C)distribute information
D)manage stakeholder expectations
E)report performance
سؤال
In Project Communications Management,identifying people or organizations that have a positive or negative interest in the project's outcome is _____.

A)identify stakeholders
B)plan communications
C)distribute information
D)manage stakeholder expectations
E)report performance
سؤال
If we know the Actual Cost of a WBS component,what other value do we need to know in order to calculate the cost performance index CPI)?

A)Budget at Completion BAC)
B)Budget costs of remaining work BCRW)
C)Schedule Variance SV)
D)Expected Time Complete ETC)
E)Earned Value EV)
سؤال
A _________ describes the present state of the project and provides compares the project's actual progress to the baseline plan.

A)Budget report
B)Status report
C)Progress report
D)Forecast report
E)News report
سؤال
Actual Cost AC)is __________

A)how much we actually spent for work completed
B)how much we budgeted to spend at the beginning of the project
C)how much of the budget we have left to spend on the project
D)how much of the budget we really should have spent on the work completed so far
E)None of the above
سؤال
Budget At Completion BAC)is __________

A)how much we actually spent for work completed
B)how much we budgeted to spend at the beginning of the project
C)how much of the budget we have left to spend on the project
D)how much of the budget we really should have spent on the work completed so far
E)None of the above
سؤال
Schedule Variance SV)is __________

A)how much time it took to complete the work
B)how long we expected the task to take
C)how much time we have left to complete the project
D)how much time it should have taken to complete the task
E)the difference between the current progress and the original schedule
سؤال
Estimate at Completion EAC)is __________

A)how much we actually spent for work completed
B)how much we budgeted to spend at the beginning of the project
C)how much of the budget we have left to spend on the project
D)how much of the budget we really should have spent on the work completed so far
E)how much we spent to complete the project
سؤال
EV-AC =

A)Cost performance index CPI)
B)Scheduled performance index SPI)
C)Cost Variance CV)
D)Minimum funds needed MFN)
E)None of the above
سؤال
In Project Communications Management,providing relevant and timely information to each stakeholder _____.

A)identify stakeholders
B)plan communications
C)distribute information
D)manage stakeholder expectations
E)report performance
سؤال
Barring a change in project scope and given a Cost Performance Index CPI)that is less than 1,the most reasonable inference to draw is that:

A)The project will likely finish earlier than planned.
B)The project will likely finish later than planned.
C)The project will likely cost more than planned.
D)The project will likely cost less than planned.
E)The project will likely be on time and on budget.
سؤال
Barring a change in project scope and given a Schedule Performance Index SPI)that is greater than 1,the most reasonable inference to draw is that:

A)The project will likely finish earlier than planned.
B)The project will likely finish later than planned.
C)The project will likely cost more than planned.
D)The project will likely cost less than planned.
E)The project will likely be on time and on budget.
سؤال
In Project Communications Management,ensuring that clear,consistent,and timely communication satisfies the information needs and that project stakeholder issues are resolved is _____.

A)identify stakeholders
B)plan communications
C)distribute information
D)manage stakeholder expectations
E)report performance
سؤال
A _________ predicts the future status or progress of the project.

A)Budget report
B)Status report
C)Progress report
D)Forecast report
E)News report
سؤال
The total planned cost of the project is computed before the project work begins.This metric is called the:

A)Planned Value PV)
B)Budget At Completion BAC)
C)Actual Cost AC)
D)Expected Time Complete ETC)
E)Estimate at Completion EAC)
سؤال
The cost incurred for completing a scheduled task or WBS component is the

A)Planned Value PV)
B)Budget At Completion BAC)
C)Actual Cost AC)
D)Expected Time Complete ETC)
E)Estimate at Completion EAC)
سؤال
What is the purpose of a project communications plan? What kinds of things should this plan address?
سؤال
Which of the following is not likely a characteristic of a good project metric?:

A)Understandable
B)Quantifiable
C)Cost Effective
D)Subjective
E)High Impact
سؤال
Information distribution includes all of the following EXCEPT:

A)Face-To-Face Meetings
B)Telephone,e-mail,and other wireless devices
C)Web-based technologies
D)Threaded discussion areas
E)All of the above are examples of information distribution
سؤال
Describe the PMBOK area called project communications management.
سؤال
A _________ shows how the scope,features or functionality,or work is being completed over time.

A)Budget report
B)Status report
C)Progress report
D)Forecast report
E)Burndown Chart
سؤال
What is Planned Value PV)?
سؤال
What are project metrics?
سؤال
The metric that provides an estimate of the most likely total or final cost of the project based on the project's performance and any risks that should be considered is the:

A)Planned Value PV)
B)Budget At Completion BAC)
C)Actual Cost AC)
D)Expected Time Complete ETC)
E)Estimate at Completion EAC)
سؤال
The budgeted cost of work scheduled for an activity or component of the WBS is the _____.

A)Planned Value PV)
B)Budget At Completion BAC)
C)Actual Cost AC)
D)Expected Time Complete ETC)
E)Estimate at Completion EAC)
سؤال
What is Budget at Completion BAC)?
سؤال
Why is effective and efficient communication vital to a project?
سؤال
Describe how the SPI and CPI can be used to forecast the final cost of a project.
سؤال
Describe the concept of earned value.
سؤال
A metric that provides an estimate for completing the scheduled work that remains once the project is started is called the

A)Planned Value PV)
B)Budget At Completion BAC)
C)Actual Cost AC)
D)Expected Time Complete ETC)
E)Estimate at Completion EAC)
سؤال
What is Actual Cost AC)?
سؤال
Describe the qualities of a good project metric.
سؤال
Why should a project manager be concerned with monitoring a project's progress?
سؤال
What is a project review and what purpose does it serve?
سؤال
What is a progress report?
سؤال
What is a status report?
فتح الحزمة
قم بالتسجيل لفتح البطاقات في هذه المجموعة!
Unlock Deck
Unlock Deck
1/63
auto play flashcards
العب
simple tutorial
ملء الشاشة (f)
exit full mode
Deck 9: Project Communication,tracking,and Reporting
1
The Schedule Performance Index SPI)for our project is greater than one 1)and so we would anticipate that all other things being equal,our project will finish ahead of schedule.
True
2
Planned value PV)is the planned or budgeted cost of work scheduled for an activity or component of the WBS.
True
3
Given the advances that have been made in telecommunications and IT technology in general,there is little value or necessity today for Face-to-Face F2F)meetings.
False
4
If a stakeholder has been judged to adversarial and having a vested interest in the failure of your project,it would probably be wise to keep him/her out of the communication loop.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
5
As a project manager,you would be pleased see a Cost Performance Index CPI less than one 1)for your project
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
6
A good project metric should be understandable,quantifiable,cost effective,proven,and be effective.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
7
Generally,the more metrics one adopts,the greater the project control.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
8
The Estimate At Completion EAC)is a project metric that can be used to estimate the most likely total or final cost of the project based on the project's performance and any risks that should be considered.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
9
All of the project stakeholders should receive exactly the same information regarding the project's progress in order to eliminate any miscommunication.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
10
A project metric should be obtained from observable,quantifiable data that allows the team and other stakeholders to gauge the efficiency and effectiveness of the work being done.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
11
Earned value provides a performance measurement that tells us how much of the budget we really should have spent for the work completed so far.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
12
One attribute of a good project metric is that it should be subjective so that a stakeholder can understand the project manager's personal opinion or insight as to how the project is progressing.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
13
Budget At Completion BAC)is the total planned cost of a project.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
14
The Expected Time Complete ETC)provides an estimate for completing the scheduled work that remains.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
15
The project manager must have a clear picture of how the actual progress or work compares to the baseline plan in order to make well-informed decisions,take appropriate actions,or to make adjustments to the project plan.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
16
The purpose of a project review is to not only show evidence that the project work is being completed,but also that the work is being completed according to various standards or agreed upon requirements.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
17
The project communications plan may be informal depending on the needs of the project stakeholders and the size of the project.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
18
A cost variance CV)can be positive or negative,but never zero.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
19
The schedule variance SV)shows the difference between the current progress of the project and its original or planned value.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
20
Internet and Web-Based technologies have a significant role to play in communication and collaboration efforts of project teams.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
21
Cost Variance CV)= Earned Value - ___________.

A)Budget at Completion BAC)
B)Budgeted cost of remaining work BCRW)
C)Schedule Variance SV)
D)Actual Cost AC)
E)None of the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
22
Earned Value tells us __________

A)how much we actually spent for work completed
B)how much we budgeted to spend at the beginning of the project
C)how much of the budget we have left to spend on the project
D)how much of the budget we really should have spent on the work completed so far
E)None of the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
23
Cost Variance CV)is __________

A)how much we actually spent for work completed
B)how much we budgeted to spend at the beginning of the project
C)how much of the budget we have left to spend on the project
D)how much of the budget we really should have spent on the work completed so far
E)the difference between the estimated cost and how much we have actually spent
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
24
Expected Time to Completion ETC)is __________

A)how much time it took to complete the work
B)how long we expected the task to take
C)how much time we have left to complete the project
D)how much time it should have taken to complete the task
E)how much longer it will take to complete the project
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
25
A _________ is a formal or informal meeting that shows evidence of project work that has been completed and work and provides a forum for surfacing issues,problems,decision-making.

A)Budget report
B)Project review
C)Progress report
D)Forecast report
E)News report
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
26
In Project Communications Management,getting the right information to the right stakeholders in the right format is _____.

A)identify stakeholders
B)plan communications
C)distribute information
D)manage stakeholder expectations
E)report performance
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
27
If you hired a consulting firm to develop a system which is estimated to take four months to complete with the tasks evenly divided over the four months and you agree to pay for the project with equal monthly installments,those payments would be called:

A)Planned Value PV)
B)Budget At Completion BAC)
C)Actual Cost AC)
D)Earned Value EV)
E)None of the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
28
In Project Communications Management,_____focuses on the collection and dissemination of project ionformation to the various project stakeholders.

A)identify stakeholders
B)plan communications
C)distribute information
D)manage stakeholder expectations
E)report performance
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
29
In Project Communications Management,identifying people or organizations that have a positive or negative interest in the project's outcome is _____.

A)identify stakeholders
B)plan communications
C)distribute information
D)manage stakeholder expectations
E)report performance
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
30
If we know the Actual Cost of a WBS component,what other value do we need to know in order to calculate the cost performance index CPI)?

A)Budget at Completion BAC)
B)Budget costs of remaining work BCRW)
C)Schedule Variance SV)
D)Expected Time Complete ETC)
E)Earned Value EV)
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
31
A _________ describes the present state of the project and provides compares the project's actual progress to the baseline plan.

A)Budget report
B)Status report
C)Progress report
D)Forecast report
E)News report
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
32
Actual Cost AC)is __________

A)how much we actually spent for work completed
B)how much we budgeted to spend at the beginning of the project
C)how much of the budget we have left to spend on the project
D)how much of the budget we really should have spent on the work completed so far
E)None of the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
33
Budget At Completion BAC)is __________

A)how much we actually spent for work completed
B)how much we budgeted to spend at the beginning of the project
C)how much of the budget we have left to spend on the project
D)how much of the budget we really should have spent on the work completed so far
E)None of the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
34
Schedule Variance SV)is __________

A)how much time it took to complete the work
B)how long we expected the task to take
C)how much time we have left to complete the project
D)how much time it should have taken to complete the task
E)the difference between the current progress and the original schedule
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
35
Estimate at Completion EAC)is __________

A)how much we actually spent for work completed
B)how much we budgeted to spend at the beginning of the project
C)how much of the budget we have left to spend on the project
D)how much of the budget we really should have spent on the work completed so far
E)how much we spent to complete the project
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
36
EV-AC =

A)Cost performance index CPI)
B)Scheduled performance index SPI)
C)Cost Variance CV)
D)Minimum funds needed MFN)
E)None of the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
37
In Project Communications Management,providing relevant and timely information to each stakeholder _____.

A)identify stakeholders
B)plan communications
C)distribute information
D)manage stakeholder expectations
E)report performance
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
38
Barring a change in project scope and given a Cost Performance Index CPI)that is less than 1,the most reasonable inference to draw is that:

A)The project will likely finish earlier than planned.
B)The project will likely finish later than planned.
C)The project will likely cost more than planned.
D)The project will likely cost less than planned.
E)The project will likely be on time and on budget.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
39
Barring a change in project scope and given a Schedule Performance Index SPI)that is greater than 1,the most reasonable inference to draw is that:

A)The project will likely finish earlier than planned.
B)The project will likely finish later than planned.
C)The project will likely cost more than planned.
D)The project will likely cost less than planned.
E)The project will likely be on time and on budget.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
40
In Project Communications Management,ensuring that clear,consistent,and timely communication satisfies the information needs and that project stakeholder issues are resolved is _____.

A)identify stakeholders
B)plan communications
C)distribute information
D)manage stakeholder expectations
E)report performance
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
41
A _________ predicts the future status or progress of the project.

A)Budget report
B)Status report
C)Progress report
D)Forecast report
E)News report
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
42
The total planned cost of the project is computed before the project work begins.This metric is called the:

A)Planned Value PV)
B)Budget At Completion BAC)
C)Actual Cost AC)
D)Expected Time Complete ETC)
E)Estimate at Completion EAC)
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
43
The cost incurred for completing a scheduled task or WBS component is the

A)Planned Value PV)
B)Budget At Completion BAC)
C)Actual Cost AC)
D)Expected Time Complete ETC)
E)Estimate at Completion EAC)
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
44
What is the purpose of a project communications plan? What kinds of things should this plan address?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
45
Which of the following is not likely a characteristic of a good project metric?:

A)Understandable
B)Quantifiable
C)Cost Effective
D)Subjective
E)High Impact
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
46
Information distribution includes all of the following EXCEPT:

A)Face-To-Face Meetings
B)Telephone,e-mail,and other wireless devices
C)Web-based technologies
D)Threaded discussion areas
E)All of the above are examples of information distribution
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
47
Describe the PMBOK area called project communications management.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
48
A _________ shows how the scope,features or functionality,or work is being completed over time.

A)Budget report
B)Status report
C)Progress report
D)Forecast report
E)Burndown Chart
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
49
What is Planned Value PV)?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
50
What are project metrics?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
51
The metric that provides an estimate of the most likely total or final cost of the project based on the project's performance and any risks that should be considered is the:

A)Planned Value PV)
B)Budget At Completion BAC)
C)Actual Cost AC)
D)Expected Time Complete ETC)
E)Estimate at Completion EAC)
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
52
The budgeted cost of work scheduled for an activity or component of the WBS is the _____.

A)Planned Value PV)
B)Budget At Completion BAC)
C)Actual Cost AC)
D)Expected Time Complete ETC)
E)Estimate at Completion EAC)
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
53
What is Budget at Completion BAC)?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
54
Why is effective and efficient communication vital to a project?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
55
Describe how the SPI and CPI can be used to forecast the final cost of a project.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
56
Describe the concept of earned value.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
57
A metric that provides an estimate for completing the scheduled work that remains once the project is started is called the

A)Planned Value PV)
B)Budget At Completion BAC)
C)Actual Cost AC)
D)Expected Time Complete ETC)
E)Estimate at Completion EAC)
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
58
What is Actual Cost AC)?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
59
Describe the qualities of a good project metric.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
60
Why should a project manager be concerned with monitoring a project's progress?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
61
What is a project review and what purpose does it serve?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
62
What is a progress report?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
63
What is a status report?
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.
فتح الحزمة
k this deck
locked card icon
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 63 في هذه المجموعة.