Deck 9: Cost Accounting Systems

ملء الشاشة (f)
exit full mode
سؤال
Which of these is not a source document for job costing?

A)Materials requisition record
B)Labour hours/time sheets record
C)Invoice for factory expense
D)The marketing manager's expense sheet
استخدم زر المسافة أو
up arrow
down arrow
لقلب البطاقة.
سؤال
Predetermined overhead rates are necessary for how many of the following reasons?
.Actual overheads are not incurred evenly over the period
.Product costs need to be calculated promptly for decision- making
.Overhead cannot be traced directly to products because of its indirect nature

A)0
B)1
C)2
D)3
سؤال
Magenta Ltd uses a job order costing system and applies factory overhead,based on direct labour hours,at a rate of $2 per direct labour hour.The data relating to production for last period is: Magenta Ltd uses a job order costing system and applies factory overhead,based on direct labour hours,at a rate of $2 per direct labour hour.The data relating to production for last period is:  <div style=padding-top: 35px>
سؤال
The Pike Supply Company distributes overhead based on direct labour dollars.The estimated manufacturing overhead for the year was $484,000 and the estimated direct labour dollars for the year were $110,000.Indicate the amount of underapplied or overapplied overhead if actual direct labour was $118,000 and actual manufacturing overhead was $497,400:

A)$21,800 underapplied
B)$21,800 overapplied
C)$15,000 overapplied
D)$15,000 underapplied
سؤال
G Repair Services uses job order costing.At the end of the month the following information was available:  Job X-1  Job X-2  Job X-3  Direct materials $50$60$30 Direct labour $20$30$10\begin{array} { l l l l } & \text { Job X-1 } & \text { Job X-2 } & \text { Job X-3 } \\\text { Direct materials } & \$ 50 & \$ 60 & \$ 30 \\\text { Direct labour } & \$ 20 & \$ 30 & \$ 10\end{array} Actual overhead costs are $100.Overhead is applied on the basis of 200% of direct labour costs.Jobs X-1 and X-2 have been completed and sold.Job X-3 is not yet complete.At month-end the work in process inventory balance is:

A)$320
B)$260
C)$60
D)$40
سؤال
Which of these is not a section of a cost of production report?

A)Physical flow schedule
B)Costs to be accounted for
C)Costs accounted for
D)GST summary
سؤال
Port Manufacturing uses the weighted-average method of computing equivalent units of production.For beginning work in process there were 9000 units 30% complete as to materials and conversion costs.For ending work in process there were 5000 units 60% complete as to materials and conversion costs.13 000 units were completed during the year.Determine the equivalent units of production.

A)16 000
B)19 300
C)20 000
D)22 300
سؤال
Equivalent units are:

A)The number of whole units represented by the finished units plus the partly completed units
B)The number of whole units represented by the finished units
C)The units represented by the total manufacturing costs for the period
D)The units that would have been produced under optimum circumstances
سؤال
Smith Co started 40 000 units into production during the current period and completed 28 000.The other 12 000 units were 30% complete as to conversion costs at the end of the period.Total costs were $60 000 for material and $36 000 for conversion costs.
Material is added at the beginning of the production process.Unit raw material and conversion costs for the period were: Smith Co started 40 000 units into production during the current period and completed 28 000.The other 12 000 units were 30% complete as to conversion costs at the end of the period.Total costs were $60 000 for material and $36 000 for conversion costs. Material is added at the beginning of the production process.Unit raw material and conversion costs for the period were:  <div style=padding-top: 35px>
سؤال
In 2011,Brunswick Plumbing Supplies planned the following:
Factory overhead costs $180,000
Direct labour costs 15,000 hours at $8.00 per hour) $120,000
Machine Hours 48,000
Direct material costs $108,000
The predetermined overhead rate is based on direct labour hours and planned production during 2011 is 12,000 units.The estimated cost per unit produced is:

A)$24.00
B)$44.00
C)$34.00
D)$26.00
سؤال
 Beginning balance Job No 58$18,800 Direct Materials issued to job in the current period $30,600 Direct Labour charged to job in the current period $24,500 Manufacturing overhead applied in the current period $40,100 Total number of units produced by Job 58 30,000 What is the unit cost for Job 58?\begin{array}{l}\begin{array} { l c } \text { Beginning balance Job No } 58 \quad \mid & \$ 18,800 \\\text { Direct Materials issued to job in the current period } & \$ 30,600 \\\text { Direct Labour charged to job in the current period } & \$ 24,500 \\\text { Manufacturing overhead applied in the current period } & \$ 40,100 \\\text { Total number of units produced by Job 58 } & 30,000\end{array}\\\text { What is the unit cost for Job } 58 ?\end{array}

A)$3.85
B)$3.80
C)$4.00
D)$3.91
سؤال
Manufacturing costs assigned to inventory should appear on the income statement in the period in which:

A)The goods are completed
B)Cash is collected for the goods sold
C)The sale of goods is recorded
D)The purchase order to manufacture the goods is received
سؤال
The statement concerning the job cost order that is incorrect is:

A)It provides an itemised list of all costs charged to a particular job
B)Orders for incomplete jobs serve as a subsidiary ledger for the work in process account
C)It traces all costs to jobs
D)The control number assigned to each job is recorded on the job order
سؤال
Black Cat Limited supplies the following information.Manufacturing overhead is applied on the basis of direct labour hours.
 on the basis of direct labour hours.  Estimated manufacturing overhead costs $2,295,000 Estimated direct labour hours 340,000 Actual direct labour hours 348,000 Actual manufacturing overhead costs $2,357,000\begin{array}{l}\text { on the basis of direct labour hours. }\\\begin{array} { l r } \text { Estimated manufacturing overhead costs } & \$ 2,295,000 \\\text { Estimated direct labour hours } & 340,000 \\\text { Actual direct labour hours } & 348,000 \\\text { Actual manufacturing overhead costs } & \$ 2,357,000\end{array}\end{array}
Compute the amount of overapplied or underapplied overhead.

A)$8,800 underapplied
B)$8,000 overapplied
C)$8,000 underapplied
D)$8 800 overapplied
سؤال
Which most accurately describes the flow of costs through the accounting system?

A)Purchases,to Finished Goods,to Work in Process
B)Work in Process,to Cost of sales
C)Factory overhead applied,to Work in Process,to Finished Goods
D)Purchases,to Factory overhead,to Cost of sales
سؤال
For 2011 The Iron Works planned the following: For 2011 The Iron Works planned the following:  <div style=padding-top: 35px>
سؤال
Petlyn Pty Ltd applies overhead to completed jobs using a predetermined rate of 60% of direct labour costs.If Job No 22 shows $9,000 of factory overhead applied,how much was the direct labour cost of the job?

A)$5,400
B)$12,000
C)$15,000
D)$14,400
سؤال
The Work in Process account of Village Manufacturing shows a balance of $42 000 at the end of an accounting period.The job cost orders of the two uncompleted jobs show charges of $15 000 and $7000 for materials used and charges of $10 000 and $5000 for direct labour used.From this information it appears that the company is using a predetermined overhead rate as a percentage of direct labour costs,of:

A)13.5%
B)50.0%
C)33.3%
D)300%
سؤال
Small Budget Production uses a predetermined overhead rate based upon direct labour hours.The firm has the following budgeted and actual data for the current year: Small Budget Production uses a predetermined overhead rate based upon direct labour hours.The firm has the following budgeted and actual data for the current year:  <div style=padding-top: 35px>
سؤال
Which best describes the set of costs that are debited directly to work in process inventory?

A)Actual direct materials,actual direct labour,actual overhead
B)Actual indirect materials,actual direct labour,applied overhead
C)Actual indirect materials,actual indirect labour,actual overhead
D)Actual direct materials,actual direct labour,applied overhead
سؤال
When a job is completed,the costs recorded on its job cost order are totalled and the amount debited/credite d__________ to finished goods inventory.
سؤال
The correct statement concerning cost accounting for service type businesses is:

A)Cost information is needed for different reasons in a service business than in a manufacturing business
B)The cost object is normally activities
C)Actual costs rather than budgeted costs are used to determine overhead application rates
D)To determine the rate at which direct labour costs are applied to a particular job a labour cost per hour is developed for each employee.
سؤال
The two types of cost accounting systems are j______ costing and p________ costing.
سؤال
The combined cost of direct labour and factory overhead incurred in converting raw materials into finished goods is known as c________________ cost.
سؤال
In an 'ideal' just-in-time processing plant,the inventories held are:

A)Direct materials
B)Work in process
C)Finished goods
D)Supplies of packaging
سؤال
It is incorrect concerning Activity-Based Costing [ABC] that:

A)Production processes are broken down into activities
B)Cost drivers are used to assign costs between activities
C)The use of cost drivers allows management to apply overhead more accurately to products with different production requirements
D)It is now used by firms much more commonly than traditional costing
سؤال
Which of these inputs are debited to a work -in-process account with a process costing system?

A)Direct materials and direct labour
B)Direct labour and factory overhead applied
C)Direct materials,direct labour and factory overhead applied
D)Direct materials and factory overhead applied
سؤال
Equivalent units of production measures:

A)The number of partial jobs completed in the period
B)The production level which could have been achieved under optimum circumstances
C)The number of full units that could have been completely produced with the effort expended
D)The number of jobs started but not completed in the period
سؤال
Which of these differs between job order and process costing?

A)Basic purpose
B)Focal point for cost accumulation
C)Tracing of direct costs and allocation of indirect costs
D)Cost flows
سؤال
The correct statement concerning process costing is:

A)The type of production is heterogeneous
B)The flow of products is separated by jobs
C)The control document is a cost of production report
D)Record keeping is more detailed than for job costing
سؤال
Something that is not a feature of just-in-time processing is:

A)Strict quality control
B)A steady,reliable supply of raw materials and labour
C)A variable demand from customers
D)Efficiency in the production process
سؤال
The flow of goods in a firm that uses process costing is,work in process at the start 5000 units ½ complete,units started 54,000,units finished 50,000,work in process end of period 9000 units 1/3 complete.Raw materials are issued at the end of the production process.Using the weighted average method,the equivalent units as to conversion cost for the period are:

A)53,000 units
B)50,000 units
C)54,000 units
D)57,000 units
سؤال
Direct materials are issued to work in process upon receipt of a properly prepared and authorised m___________ r______________.
سؤال
The applied factory overhead is debited/credited ____________________ to the factory overhead account.
سؤال
The statement concerning Activity-based costing ABC)that is not true is:

A)It has been introduced to overcome distortions in costing multiple products which occur when a single base is used to apply overhead to products
B)ABC is cheaper and less time consuming to implement than traditional costing systems
C)Overhead costs are accumulated by activities and then assigned to cost objects using a different cost driver for each activity.
D)ABC can be applied in service businesses as well as in manufacturing businesses
سؤال
It is true that Just-in-time JIT)processing:

A)Is most suitable for small businesses
B)Reflects a 'push' approach to manufacturing
C)Runs the risk of interruptions in supply
D)Applies to inputs of materials rather than outputs of products
سؤال
Factory overhead is charged to jobs by means of a predetermined o______________ rate.
سؤال
The statement concerning cost drivers that is incorrect is:

A)As direct labour shrinks as a proportion of manufacturing costs it becomes a more accurate factor by which to apply overhead to products
B)A cost driver is a measure of the activity that causes overhead costs
C)In modern day manufacturing there has been a decline in labour costs and an increase in factory overheads as a percentage of product costs
D)Inaccurate application of overhead to products can lead to wrong conclusions about which products are profitable
سؤال
The control document used in job order costing is the j_____ c_______ order.
سؤال
The method of calculating equivalent units where the costs assigned to the beginning inventory of work-in-process are combined with the current periods costs of production and the degree of completion of the beginning units is ignored is the:

A)first-in-first-out method
B)last-in-last-out method
C)last-in-first-out method
D)weighted average method
سؤال
P___________ costing is used by firms with continuous production flows which are usually found in industries which mass produce.
سؤال
A________-________ costing is a system in which overhead costs are accumulated by activities and the cost pools for each activity are assigned to the cost object by means of individual cost drivers.
سؤال
E____________ u___________ are a measure of how many whole units of production are represented by the units finished,plus the units partially finished,in a process costing operation.
سؤال
The usual treatment for under-applied overhead at year-end is to add it to ___________ __ ________ sold.
فتح الحزمة
قم بالتسجيل لفتح البطاقات في هذه المجموعة!
Unlock Deck
Unlock Deck
1/44
auto play flashcards
العب
simple tutorial
ملء الشاشة (f)
exit full mode
Deck 9: Cost Accounting Systems
1
Which of these is not a source document for job costing?

A)Materials requisition record
B)Labour hours/time sheets record
C)Invoice for factory expense
D)The marketing manager's expense sheet
D
2
Predetermined overhead rates are necessary for how many of the following reasons?
.Actual overheads are not incurred evenly over the period
.Product costs need to be calculated promptly for decision- making
.Overhead cannot be traced directly to products because of its indirect nature

A)0
B)1
C)2
D)3
3
3
Magenta Ltd uses a job order costing system and applies factory overhead,based on direct labour hours,at a rate of $2 per direct labour hour.The data relating to production for last period is: Magenta Ltd uses a job order costing system and applies factory overhead,based on direct labour hours,at a rate of $2 per direct labour hour.The data relating to production for last period is:
A
4
The Pike Supply Company distributes overhead based on direct labour dollars.The estimated manufacturing overhead for the year was $484,000 and the estimated direct labour dollars for the year were $110,000.Indicate the amount of underapplied or overapplied overhead if actual direct labour was $118,000 and actual manufacturing overhead was $497,400:

A)$21,800 underapplied
B)$21,800 overapplied
C)$15,000 overapplied
D)$15,000 underapplied
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 44 في هذه المجموعة.
فتح الحزمة
k this deck
5
G Repair Services uses job order costing.At the end of the month the following information was available:  Job X-1  Job X-2  Job X-3  Direct materials $50$60$30 Direct labour $20$30$10\begin{array} { l l l l } & \text { Job X-1 } & \text { Job X-2 } & \text { Job X-3 } \\\text { Direct materials } & \$ 50 & \$ 60 & \$ 30 \\\text { Direct labour } & \$ 20 & \$ 30 & \$ 10\end{array} Actual overhead costs are $100.Overhead is applied on the basis of 200% of direct labour costs.Jobs X-1 and X-2 have been completed and sold.Job X-3 is not yet complete.At month-end the work in process inventory balance is:

A)$320
B)$260
C)$60
D)$40
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 44 في هذه المجموعة.
فتح الحزمة
k this deck
6
Which of these is not a section of a cost of production report?

A)Physical flow schedule
B)Costs to be accounted for
C)Costs accounted for
D)GST summary
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 44 في هذه المجموعة.
فتح الحزمة
k this deck
7
Port Manufacturing uses the weighted-average method of computing equivalent units of production.For beginning work in process there were 9000 units 30% complete as to materials and conversion costs.For ending work in process there were 5000 units 60% complete as to materials and conversion costs.13 000 units were completed during the year.Determine the equivalent units of production.

A)16 000
B)19 300
C)20 000
D)22 300
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 44 في هذه المجموعة.
فتح الحزمة
k this deck
8
Equivalent units are:

A)The number of whole units represented by the finished units plus the partly completed units
B)The number of whole units represented by the finished units
C)The units represented by the total manufacturing costs for the period
D)The units that would have been produced under optimum circumstances
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 44 في هذه المجموعة.
فتح الحزمة
k this deck
9
Smith Co started 40 000 units into production during the current period and completed 28 000.The other 12 000 units were 30% complete as to conversion costs at the end of the period.Total costs were $60 000 for material and $36 000 for conversion costs.
Material is added at the beginning of the production process.Unit raw material and conversion costs for the period were: Smith Co started 40 000 units into production during the current period and completed 28 000.The other 12 000 units were 30% complete as to conversion costs at the end of the period.Total costs were $60 000 for material and $36 000 for conversion costs. Material is added at the beginning of the production process.Unit raw material and conversion costs for the period were:
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 44 في هذه المجموعة.
فتح الحزمة
k this deck
10
In 2011,Brunswick Plumbing Supplies planned the following:
Factory overhead costs $180,000
Direct labour costs 15,000 hours at $8.00 per hour) $120,000
Machine Hours 48,000
Direct material costs $108,000
The predetermined overhead rate is based on direct labour hours and planned production during 2011 is 12,000 units.The estimated cost per unit produced is:

A)$24.00
B)$44.00
C)$34.00
D)$26.00
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 44 في هذه المجموعة.
فتح الحزمة
k this deck
11
 Beginning balance Job No 58$18,800 Direct Materials issued to job in the current period $30,600 Direct Labour charged to job in the current period $24,500 Manufacturing overhead applied in the current period $40,100 Total number of units produced by Job 58 30,000 What is the unit cost for Job 58?\begin{array}{l}\begin{array} { l c } \text { Beginning balance Job No } 58 \quad \mid & \$ 18,800 \\\text { Direct Materials issued to job in the current period } & \$ 30,600 \\\text { Direct Labour charged to job in the current period } & \$ 24,500 \\\text { Manufacturing overhead applied in the current period } & \$ 40,100 \\\text { Total number of units produced by Job 58 } & 30,000\end{array}\\\text { What is the unit cost for Job } 58 ?\end{array}

A)$3.85
B)$3.80
C)$4.00
D)$3.91
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 44 في هذه المجموعة.
فتح الحزمة
k this deck
12
Manufacturing costs assigned to inventory should appear on the income statement in the period in which:

A)The goods are completed
B)Cash is collected for the goods sold
C)The sale of goods is recorded
D)The purchase order to manufacture the goods is received
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 44 في هذه المجموعة.
فتح الحزمة
k this deck
13
The statement concerning the job cost order that is incorrect is:

A)It provides an itemised list of all costs charged to a particular job
B)Orders for incomplete jobs serve as a subsidiary ledger for the work in process account
C)It traces all costs to jobs
D)The control number assigned to each job is recorded on the job order
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 44 في هذه المجموعة.
فتح الحزمة
k this deck
14
Black Cat Limited supplies the following information.Manufacturing overhead is applied on the basis of direct labour hours.
 on the basis of direct labour hours.  Estimated manufacturing overhead costs $2,295,000 Estimated direct labour hours 340,000 Actual direct labour hours 348,000 Actual manufacturing overhead costs $2,357,000\begin{array}{l}\text { on the basis of direct labour hours. }\\\begin{array} { l r } \text { Estimated manufacturing overhead costs } & \$ 2,295,000 \\\text { Estimated direct labour hours } & 340,000 \\\text { Actual direct labour hours } & 348,000 \\\text { Actual manufacturing overhead costs } & \$ 2,357,000\end{array}\end{array}
Compute the amount of overapplied or underapplied overhead.

A)$8,800 underapplied
B)$8,000 overapplied
C)$8,000 underapplied
D)$8 800 overapplied
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 44 في هذه المجموعة.
فتح الحزمة
k this deck
15
Which most accurately describes the flow of costs through the accounting system?

A)Purchases,to Finished Goods,to Work in Process
B)Work in Process,to Cost of sales
C)Factory overhead applied,to Work in Process,to Finished Goods
D)Purchases,to Factory overhead,to Cost of sales
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 44 في هذه المجموعة.
فتح الحزمة
k this deck
16
For 2011 The Iron Works planned the following: For 2011 The Iron Works planned the following:
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 44 في هذه المجموعة.
فتح الحزمة
k this deck
17
Petlyn Pty Ltd applies overhead to completed jobs using a predetermined rate of 60% of direct labour costs.If Job No 22 shows $9,000 of factory overhead applied,how much was the direct labour cost of the job?

A)$5,400
B)$12,000
C)$15,000
D)$14,400
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 44 في هذه المجموعة.
فتح الحزمة
k this deck
18
The Work in Process account of Village Manufacturing shows a balance of $42 000 at the end of an accounting period.The job cost orders of the two uncompleted jobs show charges of $15 000 and $7000 for materials used and charges of $10 000 and $5000 for direct labour used.From this information it appears that the company is using a predetermined overhead rate as a percentage of direct labour costs,of:

A)13.5%
B)50.0%
C)33.3%
D)300%
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 44 في هذه المجموعة.
فتح الحزمة
k this deck
19
Small Budget Production uses a predetermined overhead rate based upon direct labour hours.The firm has the following budgeted and actual data for the current year: Small Budget Production uses a predetermined overhead rate based upon direct labour hours.The firm has the following budgeted and actual data for the current year:
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 44 في هذه المجموعة.
فتح الحزمة
k this deck
20
Which best describes the set of costs that are debited directly to work in process inventory?

A)Actual direct materials,actual direct labour,actual overhead
B)Actual indirect materials,actual direct labour,applied overhead
C)Actual indirect materials,actual indirect labour,actual overhead
D)Actual direct materials,actual direct labour,applied overhead
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 44 في هذه المجموعة.
فتح الحزمة
k this deck
21
When a job is completed,the costs recorded on its job cost order are totalled and the amount debited/credite d__________ to finished goods inventory.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 44 في هذه المجموعة.
فتح الحزمة
k this deck
22
The correct statement concerning cost accounting for service type businesses is:

A)Cost information is needed for different reasons in a service business than in a manufacturing business
B)The cost object is normally activities
C)Actual costs rather than budgeted costs are used to determine overhead application rates
D)To determine the rate at which direct labour costs are applied to a particular job a labour cost per hour is developed for each employee.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 44 في هذه المجموعة.
فتح الحزمة
k this deck
23
The two types of cost accounting systems are j______ costing and p________ costing.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 44 في هذه المجموعة.
فتح الحزمة
k this deck
24
The combined cost of direct labour and factory overhead incurred in converting raw materials into finished goods is known as c________________ cost.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 44 في هذه المجموعة.
فتح الحزمة
k this deck
25
In an 'ideal' just-in-time processing plant,the inventories held are:

A)Direct materials
B)Work in process
C)Finished goods
D)Supplies of packaging
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 44 في هذه المجموعة.
فتح الحزمة
k this deck
26
It is incorrect concerning Activity-Based Costing [ABC] that:

A)Production processes are broken down into activities
B)Cost drivers are used to assign costs between activities
C)The use of cost drivers allows management to apply overhead more accurately to products with different production requirements
D)It is now used by firms much more commonly than traditional costing
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 44 في هذه المجموعة.
فتح الحزمة
k this deck
27
Which of these inputs are debited to a work -in-process account with a process costing system?

A)Direct materials and direct labour
B)Direct labour and factory overhead applied
C)Direct materials,direct labour and factory overhead applied
D)Direct materials and factory overhead applied
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 44 في هذه المجموعة.
فتح الحزمة
k this deck
28
Equivalent units of production measures:

A)The number of partial jobs completed in the period
B)The production level which could have been achieved under optimum circumstances
C)The number of full units that could have been completely produced with the effort expended
D)The number of jobs started but not completed in the period
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 44 في هذه المجموعة.
فتح الحزمة
k this deck
29
Which of these differs between job order and process costing?

A)Basic purpose
B)Focal point for cost accumulation
C)Tracing of direct costs and allocation of indirect costs
D)Cost flows
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 44 في هذه المجموعة.
فتح الحزمة
k this deck
30
The correct statement concerning process costing is:

A)The type of production is heterogeneous
B)The flow of products is separated by jobs
C)The control document is a cost of production report
D)Record keeping is more detailed than for job costing
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 44 في هذه المجموعة.
فتح الحزمة
k this deck
31
Something that is not a feature of just-in-time processing is:

A)Strict quality control
B)A steady,reliable supply of raw materials and labour
C)A variable demand from customers
D)Efficiency in the production process
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 44 في هذه المجموعة.
فتح الحزمة
k this deck
32
The flow of goods in a firm that uses process costing is,work in process at the start 5000 units ½ complete,units started 54,000,units finished 50,000,work in process end of period 9000 units 1/3 complete.Raw materials are issued at the end of the production process.Using the weighted average method,the equivalent units as to conversion cost for the period are:

A)53,000 units
B)50,000 units
C)54,000 units
D)57,000 units
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 44 في هذه المجموعة.
فتح الحزمة
k this deck
33
Direct materials are issued to work in process upon receipt of a properly prepared and authorised m___________ r______________.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 44 في هذه المجموعة.
فتح الحزمة
k this deck
34
The applied factory overhead is debited/credited ____________________ to the factory overhead account.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 44 في هذه المجموعة.
فتح الحزمة
k this deck
35
The statement concerning Activity-based costing ABC)that is not true is:

A)It has been introduced to overcome distortions in costing multiple products which occur when a single base is used to apply overhead to products
B)ABC is cheaper and less time consuming to implement than traditional costing systems
C)Overhead costs are accumulated by activities and then assigned to cost objects using a different cost driver for each activity.
D)ABC can be applied in service businesses as well as in manufacturing businesses
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 44 في هذه المجموعة.
فتح الحزمة
k this deck
36
It is true that Just-in-time JIT)processing:

A)Is most suitable for small businesses
B)Reflects a 'push' approach to manufacturing
C)Runs the risk of interruptions in supply
D)Applies to inputs of materials rather than outputs of products
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 44 في هذه المجموعة.
فتح الحزمة
k this deck
37
Factory overhead is charged to jobs by means of a predetermined o______________ rate.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 44 في هذه المجموعة.
فتح الحزمة
k this deck
38
The statement concerning cost drivers that is incorrect is:

A)As direct labour shrinks as a proportion of manufacturing costs it becomes a more accurate factor by which to apply overhead to products
B)A cost driver is a measure of the activity that causes overhead costs
C)In modern day manufacturing there has been a decline in labour costs and an increase in factory overheads as a percentage of product costs
D)Inaccurate application of overhead to products can lead to wrong conclusions about which products are profitable
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 44 في هذه المجموعة.
فتح الحزمة
k this deck
39
The control document used in job order costing is the j_____ c_______ order.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 44 في هذه المجموعة.
فتح الحزمة
k this deck
40
The method of calculating equivalent units where the costs assigned to the beginning inventory of work-in-process are combined with the current periods costs of production and the degree of completion of the beginning units is ignored is the:

A)first-in-first-out method
B)last-in-last-out method
C)last-in-first-out method
D)weighted average method
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 44 في هذه المجموعة.
فتح الحزمة
k this deck
41
P___________ costing is used by firms with continuous production flows which are usually found in industries which mass produce.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 44 في هذه المجموعة.
فتح الحزمة
k this deck
42
A________-________ costing is a system in which overhead costs are accumulated by activities and the cost pools for each activity are assigned to the cost object by means of individual cost drivers.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 44 في هذه المجموعة.
فتح الحزمة
k this deck
43
E____________ u___________ are a measure of how many whole units of production are represented by the units finished,plus the units partially finished,in a process costing operation.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 44 في هذه المجموعة.
فتح الحزمة
k this deck
44
The usual treatment for under-applied overhead at year-end is to add it to ___________ __ ________ sold.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 44 في هذه المجموعة.
فتح الحزمة
k this deck
locked card icon
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 44 في هذه المجموعة.