Deck 20: Plug IT In 6 Project Management
1
The traditional approach to project management divides every project into _____ distinct phases.
A) three
B) four
C) five
D) six
A) three
B) four
C) five
D) six
C
2
Which of the following activities is NOT a step in the project monitoring and control phase?
A) Monitoring ongoing project activities
B) Allocating a budget
C) Comparing project variables to the actual plan
D) Identifying corrective actions
A) Monitoring ongoing project activities
B) Allocating a budget
C) Comparing project variables to the actual plan
D) Identifying corrective actions
B
3
Scope creep can only be addressed in the monitoring and control phase of the project management process.
False
4
Quantity is one of the triple constraints of project management.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 6 في هذه المجموعة.
فتح الحزمة
k this deck
5
Runaway projects are those that are so far over budget and past deadline that they must be abandoned, typically with large monetary loss
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 6 في هذه المجموعة.
فتح الحزمة
k this deck
6
Which of the following constraints of project management involves the processes that ensure that the project includes all the work required-and only the work required-to complete the project successfully?
A) Time
B) Cost
C) Deliverable
D) Scope
A) Time
B) Cost
C) Deliverable
D) Scope