Deck 14: Project Planning and Scheduling

ملء الشاشة (f)
exit full mode
سؤال
Estimating the time required for each task is an example of a ______ management decision in project management.

A)planning
B)scheduling
C)control
D)a and b
E)b and c
استخدم زر المسافة أو
up arrow
down arrow
لقلب البطاقة.
سؤال
Project management requires:

A)Scheduling,planning,and controlling
B)Quantitative skills
C)Behavioral skills
D)All of the above
سؤال
Which of the following statements is incorrect about the PERT method of project scheduling?

A)PERT requires three time estimates for scheduling a given activity.
B)PERT assumes that the actual activity times are distributed according to the beta probability distribution.
C)PERT assumes that the statistical variation in total project completion times can be computed by multiplying variances along the critical path.
D)None of the above
سؤال
The advantage(s)of the network method over the Gantt chart is (are)that:

A)The network method is easy to use and quite widely understood.
B)The network method shows precedence relationships explicitly when compared to Gantt charts.
C)Network methods are less costly to use.
D)a and b
E)b and c
سؤال
CPM network scheduling assumes a second order (non-linear)time-cost tradeoff exists.
سؤال
Which of the following statements about CPM is true?

A)CPM is an example of a variable time project scheduling method.
B)The CPM method is well suited when activity times are expected to vary a lot.
C)The CPM method is well suited when activity times are fairly constant and can be reduced by spending more money.
D)The CPM method is well suited for R&D projects and for scheduling computer systems.
E)None of the above
سؤال
A network-based project scheduling method that requires three time estimates for each activity is:

A)PERT
B)CPM
C)Gantt chart
D)a and b
E)None of the above
سؤال
The project management concept that can be best applied to situations such as R&D,computer systems design,and military invasions is:

A)PERT
B)CPM
C)Gantt chart
D)a and c
E)None of the above
سؤال
Multiple critical paths can exist under CPM because:

A)There is more than one way to complete the project
B)Different network paths exist,each with the same total time
C)Great flexibility of activity sequences is available
D)None of the above
سؤال
Controlling a project does NOT entail:

A)Monitoring costs,time,and performance
B)Adhering to the budget
C)Correcting the plan as necessary
D)None of the above
سؤال
"Slack" refers to the difference between:

A)Late and early times
B)Finish and start times
C)Observed and predicted times
D)Optimistic and pessimistic times
E)None of the above
سؤال
A forward pass of the above network indicates that the early start time of activity 4-5 is:

A)4
B)5
C)3
D)None of the above
سؤال
An assumption of PERT is:

A)Activity times are constant.
B)Uncertainty of individual time estimates exists.
C)Distribution of project completion times and probability that each activity is on the critical path can be computed.
D)b and c
سؤال
A forward pass is required while computing the early start and early finish times of activities.
سؤال
Which of the following statements is true about a critical path?

A)A critical path consists of activities for which early start time equals late start time.
B)The activities along the critical path take the longest time.
C)A critical path consists of activities for which early finish time equals late finish time.
D)There is no slack in the activities along the critical path.
E)All of the above
سؤال
The early start and late start times are equal for an activity on the critical path of a network.
سؤال
The purpose of performing a forward pass is to:

A)Identify the critical path
B)Determine the early start and the early finish times
C)Determine the late start and the late finish times
D)Determine the slack available in the process
E)All of the above
سؤال
The job of the project manager is to:

A)Control all costs
B)Control those costs directly controllable by the project organization
C)Control costs,schedule,and performance of the project
D)Keep within the budget,no matter what
E)b and c
سؤال
Gantt charts are effective if:

A)Activities are highly interconnected
B)Activity times are random
C)The project contains simple activity sequences
D)All of the above
سؤال
The advantage(s)that Gantt chart has over the network method is (are):

A)A Gantt chart is easy to use and quite widely understood.
B)Gantt charts show precedence relationships explicitly when compared to network scheduling.
C)Gantt charts are less costly to use.
D)a and b
E)a and c
سؤال
A work-breakdown structure is used in the scheduling activity of project management.
سؤال
PERT assumes that the statistical variation in total project completion times can be computed by adding the standard deviations along the critical path.
فتح الحزمة
قم بالتسجيل لفتح البطاقات في هذه المجموعة!
Unlock Deck
Unlock Deck
1/22
auto play flashcards
العب
simple tutorial
ملء الشاشة (f)
exit full mode
Deck 14: Project Planning and Scheduling
1
Estimating the time required for each task is an example of a ______ management decision in project management.

A)planning
B)scheduling
C)control
D)a and b
E)b and c
B
2
Project management requires:

A)Scheduling,planning,and controlling
B)Quantitative skills
C)Behavioral skills
D)All of the above
D
3
Which of the following statements is incorrect about the PERT method of project scheduling?

A)PERT requires three time estimates for scheduling a given activity.
B)PERT assumes that the actual activity times are distributed according to the beta probability distribution.
C)PERT assumes that the statistical variation in total project completion times can be computed by multiplying variances along the critical path.
D)None of the above
C
4
The advantage(s)of the network method over the Gantt chart is (are)that:

A)The network method is easy to use and quite widely understood.
B)The network method shows precedence relationships explicitly when compared to Gantt charts.
C)Network methods are less costly to use.
D)a and b
E)b and c
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 22 في هذه المجموعة.
فتح الحزمة
k this deck
5
CPM network scheduling assumes a second order (non-linear)time-cost tradeoff exists.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 22 في هذه المجموعة.
فتح الحزمة
k this deck
6
Which of the following statements about CPM is true?

A)CPM is an example of a variable time project scheduling method.
B)The CPM method is well suited when activity times are expected to vary a lot.
C)The CPM method is well suited when activity times are fairly constant and can be reduced by spending more money.
D)The CPM method is well suited for R&D projects and for scheduling computer systems.
E)None of the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 22 في هذه المجموعة.
فتح الحزمة
k this deck
7
A network-based project scheduling method that requires three time estimates for each activity is:

A)PERT
B)CPM
C)Gantt chart
D)a and b
E)None of the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 22 في هذه المجموعة.
فتح الحزمة
k this deck
8
The project management concept that can be best applied to situations such as R&D,computer systems design,and military invasions is:

A)PERT
B)CPM
C)Gantt chart
D)a and c
E)None of the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 22 في هذه المجموعة.
فتح الحزمة
k this deck
9
Multiple critical paths can exist under CPM because:

A)There is more than one way to complete the project
B)Different network paths exist,each with the same total time
C)Great flexibility of activity sequences is available
D)None of the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 22 في هذه المجموعة.
فتح الحزمة
k this deck
10
Controlling a project does NOT entail:

A)Monitoring costs,time,and performance
B)Adhering to the budget
C)Correcting the plan as necessary
D)None of the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 22 في هذه المجموعة.
فتح الحزمة
k this deck
11
"Slack" refers to the difference between:

A)Late and early times
B)Finish and start times
C)Observed and predicted times
D)Optimistic and pessimistic times
E)None of the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 22 في هذه المجموعة.
فتح الحزمة
k this deck
12
A forward pass of the above network indicates that the early start time of activity 4-5 is:

A)4
B)5
C)3
D)None of the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 22 في هذه المجموعة.
فتح الحزمة
k this deck
13
An assumption of PERT is:

A)Activity times are constant.
B)Uncertainty of individual time estimates exists.
C)Distribution of project completion times and probability that each activity is on the critical path can be computed.
D)b and c
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 22 في هذه المجموعة.
فتح الحزمة
k this deck
14
A forward pass is required while computing the early start and early finish times of activities.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 22 في هذه المجموعة.
فتح الحزمة
k this deck
15
Which of the following statements is true about a critical path?

A)A critical path consists of activities for which early start time equals late start time.
B)The activities along the critical path take the longest time.
C)A critical path consists of activities for which early finish time equals late finish time.
D)There is no slack in the activities along the critical path.
E)All of the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 22 في هذه المجموعة.
فتح الحزمة
k this deck
16
The early start and late start times are equal for an activity on the critical path of a network.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 22 في هذه المجموعة.
فتح الحزمة
k this deck
17
The purpose of performing a forward pass is to:

A)Identify the critical path
B)Determine the early start and the early finish times
C)Determine the late start and the late finish times
D)Determine the slack available in the process
E)All of the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 22 في هذه المجموعة.
فتح الحزمة
k this deck
18
The job of the project manager is to:

A)Control all costs
B)Control those costs directly controllable by the project organization
C)Control costs,schedule,and performance of the project
D)Keep within the budget,no matter what
E)b and c
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 22 في هذه المجموعة.
فتح الحزمة
k this deck
19
Gantt charts are effective if:

A)Activities are highly interconnected
B)Activity times are random
C)The project contains simple activity sequences
D)All of the above
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 22 في هذه المجموعة.
فتح الحزمة
k this deck
20
The advantage(s)that Gantt chart has over the network method is (are):

A)A Gantt chart is easy to use and quite widely understood.
B)Gantt charts show precedence relationships explicitly when compared to network scheduling.
C)Gantt charts are less costly to use.
D)a and b
E)a and c
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 22 في هذه المجموعة.
فتح الحزمة
k this deck
21
A work-breakdown structure is used in the scheduling activity of project management.
فتح الحزمة
افتح القفل للوصول البطاقات البالغ عددها 22 في هذه المجموعة.
فتح الحزمة
k this deck
22
PERT assumes that the statistical variation in total project completion times can be computed by adding the standard deviations along the critical path.