A defense contractor has just started producing engines for a new government contract. The first engine took 800 hours to produce. If the learning curve is 80%, how long will it take to produce the first 20 engines? (Use at least three decimals in the exponent if you use the logarithmic approach, or use Table E.3 cumulative coefficient)
A) less than or equal to 1000 hours
B) from 1000 to 8000 hours
C) from 8000 to 8500 hours
D) from 8500 to 10000 hours
E) 10,000 or more hours
Correct Answer:
Verified
Q41: The first unit of a product took
Q42: The first product took 10 hours to
Q42: The second unit of production took 9
Q47: A company negotiates a price for two
Q49: It took 60 hours to make the
Q50: The first unit took 10 hours and
Q52: A manager is trying to estimate the
Q55: It took 18 hours to complete the
Q56: The first unit took 10 hours and
Q73: The first unit of a product took
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents