Develop a solution for the following line balancing problem, allowing a cycle time of 5 minutes.
a. Draw the precedence diagram for the set of tasks.
b. Calculate the theoretical minimum number of workstations.
c. Balance this line using the longest task time heuristic.
d. What tasks are assigned to which stations?
e. Does the solution have the minimum number of stations? Explain.
f. How much idle time is there, summed over all workstations?
g. What is the efficiency of this line?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q124: A facilities manager at a company headquarters
Q127: "Having a focused work center is like
Q131: Departments A, B, C, and D need
Q134: Briefly explain what "slotting" is. Why is
Q137: Consider the five ideas for determining the
Q139: What is the role of heuristics in
Q140: Define the following terms that occur in
Q213: What design guidelines help retail layouts to
Q261: Identify the four requirements for cellular production.
Q307: Assembly line balancing has just been used
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents