Solved

A Company Is Trying to Balance Production Between 3 Workstations

Question 158

Essay

A company is trying to balance production between 3 workstations on an assembly line. Currently there are 5 tasks that need to be performed. These tasks, ABCDE, have required times of 2 minutes, 4 minutes, 1 minutes, 3 minutes, and 10 minutes respectively. The assembly line needs to produce 40 units per day to meet demand and can work for up to 8 hours each day.
A. What is the required cycle time?
B. What is the theoretical minimum # of workstations?
C. Assign the tasks according to shortest task time.
D. Is there a better way to divide the work than in Part C?

Correct Answer:

verifed

Verified

Required cycle time = Production time av...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents