The operations manager of a body and paint shop has five cars to schedule for repair. He would like to minimize the throughput time (makespan) to complete all work on these cars. Each car requires body work prior to painting. The estimates of the times required to do the body and paint work on each are as follows:
a. Chart the progress of these five jobs through the two centers on the basis of the arbitrary order
A→B→C→D→E.
b. After how many hours will all jobs be completed?
c. Use Johnson's rule to sequence these five jobs for minimum total duration. Show your work in
determining the job sequence.
d. The optimal sequence is __________.
e. Chart the progress of the five jobs in this optimal sequence.
f. After how many hours will all jobs be completed?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q129: Given the following chart of jobs assigned
Q130: A firm that specializes in desktop publishing
Q131: Use Johnson's rule to determine the optimal
Q132: Complete the table, find average lateness, find
Q133: At Morgan's Transformer Rebuilding, a set of
Q135: Use Johnson's rule to determine the optimal
Q136: A manufacturer has the following jobs waiting
Q137: Jack's Refrigeration Repair is under contract to
Q138: The following jobs are waiting to be
Q139: Machines A, B, C, and D have
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents