The president of a consulting firm wants to minimize the total number of hours it will take to complete four projects for a new client. Accordingly, she has estimated the time it should take for each of her top consultants -- Charlie, Gerald, Johnny, and Rick -- to complete any of the four projects, as follows:
a. In how many different ways can she assign these consultants to these projects?
b. What is the total number of hours required by the following arbitrary assignment?
Charlie→B; Gerald→A; Johnny→D; Rick→C
c. What is the optimal assignment of consultants to projects? (Use the assignment method; SHOW YOUR WORK!)
d. For the optimal schedule, what is the total number of hours it will take these consultants to complete these projects?
e. What is the significance, if any, of the fact that Gerald is the best performer at all four projects?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q100: In retail outlets, customers are usually processed
Q121: Find the sequence for the priority rules
Q122: There are 5 jobs (A, B, C,
Q123: Given the following chart of jobs assigned
Q124: At Morgan's Transformer Rebuilding, five jobs are
Q126: Bob Dresser operates a major appliance warranty
Q127: Lockport Marine Services, Inc. wishes to assign
Q128: The emergency room at a hospital estimates
Q129: Given the following chart of jobs assigned
Q130: A firm that specializes in desktop publishing
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents