The feasible region in the diagram below is consistent with which one of the following constraints?
A) 8X1 + 4X2 ≤ 160
B) 8X1 + 4X2 ≥ 160
C) 4X1 + 8X2 ≤ 160
D) 8X1 - 4X2 ≤ 160
E) 4X1 - 8X2 ≤ 160
Correct Answer:
Verified