Hemo-tech,Inc. ,a biomedical technology and research laboratory,produces a standard blood filtering device on an assembly-line basis.Six basic tasks are performed along the assembly line.The time to perform each task and the tasks that must immediately precede each task are in the table below.Twenty pumps per 450-minute day must be produced by the assembly line.
(a)Draw the network diagram of the precedence relationships.
(b)Identify the absolute minimum and maximum cycle times.
(c)What is the cycle time required to meet demand?
(d)What is the minimum number of workstations required to meet the schedule?
(e)Balance this line using the most following tasks heuristic.
(f)What is the efficiency of the line obtained in part (e)?
(g)Can the efficiency of this solution be improved? Explain.
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q123: An assembly line has been designed to
Q126: Cyclone Appliances has developed a new European-style
Q127: You have been asked to balance a
Q129: Develop a solution for the following line
Q132: An assembly line consists of 21 tasks
Q135: An assembly line consists of 158 tasks
Q283: If a layout problem is solved by
Q287: A product-oriented layout would be MOST appropriate
Q301: Explain what the purpose of assembly-line balancing
Q315: Identify the formulas for the following terms
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents