The time an activity will take assuming very unfavorable conditions is:
A) the optimistic time.
B) the pessimistic time.
C) the activity variance.
D) the minimum time.
E) exactly twice as long as the expected time.
Correct Answer:
Verified
Q91: The bell curve is often appropriate for
Q92: The beta distribution is used in project
Q93: Variation in activities that are not on
Q94: A local project being analyzed by PERT
Q95: Which of the following statements regarding PERT
Q97: An activity on a PERT network has
Q98: An activity on a PERT network has
Q99: A PERT project has 45 activities, 19
Q100: Which of the following statements regarding PERT
Q101: A project whose critical path has an
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents