Which of the following statements regarding PERT times is true?
A) The expected time is an estimate of the time an activity will require if everything goes as planned.
B) The optimistic time estimate is an estimate of the maximum time an activity will require.
C) The expected time estimate is calculated as t = (a + 4m + b) /6.
D) The pessimistic time estimate is an estimate of the minimum time an activity will require.
E) The most likely time estimate is an estimate of the maximum time an activity will require.
Correct Answer:
Verified
Q95: Which of the following statements regarding PERT
Q96: The time an activity will take assuming
Q97: An activity on a PERT network has
Q98: An activity on a PERT network has
Q99: A PERT project has 45 activities, 19
Q101: A project whose critical path has an
Q102: A project manager determined that the project
Q103: A network consists of the following list.
Q104: Two activities on the same critical path
Q105: The _ distribution is appropriate for calculating
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents